Linac4 Update. 1. Project Meeting 14 March 2013. 1. Updated Schedule 2. EVM (light) rebaselining 3. Linac4 at Open Days. Linac4 – 2012 Progress. Building and Tunnel CV and EL infrastructure installed RF network + 2 klystrons installed Cabling completed. New 2.8MW klystron. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Linac4 Update

1

Linac4 Update

Project Meeting14 March 2013

1

1. Updated Schedule2. EVM (light) rebaselining3. Linac4 at Open Days

Page 2: Linac4 Update

Building and TunnelCV and EL infrastructure installed RF network + 2 klystrons installedCabling completed

Linac4 – 2012 Progress

Machine componentsNew ion source completed RFQ completed and installed DTL 1st segment completed2 CCDTL modules delivered

New 2.8MW klystron

H- source

DTL

CCDTL

RFQ

Page 3: Linac4 Update

3

Linac4 – New Masterplan

Ready for 50 MeV protons as

backup to Linac2 Ready for

connection

2013/16 Masterplan, adapted to limited availability of resources during Long Shutdown 1 (2013/14)

Options for connection to the PS Booster: a) Long Shutdown 2 (2018?) or b) intermediate length shut-down after end 2016

Start high-energy commissioning (12

MeV)

1 year reliability run

End high-energy

commissioning (160 MeV)

Transfer 3 MeV to Linac4 tunnel

Page 4: Linac4 Update

4

Masterplan – What is new

New with respect to the Masterplan of June 2012, adapted to LS1

6 months (3 more) for 3 MeV recommissioning in tunnel

(more time for measurements + match delayed start of LS1)

Better definition of 2 transfer line phases and

activities

Clear separation between beam commissioning phases (red) and

installation/HW commissioning phases (blue)

Beam test time foreseen for eg.

PSB stripper tests

Keep flexibility at the end to adapt to any connection

schedule

Page 5: Linac4 Update

5

Organisation

Only one major change:

Jean-Baptiste Lallement replaces Christian Carli (who has been nominated Project Leader for ELENA) as WP Holder for the Transfer Line Workpackage.

Best wishes of success to Christian, and thanks to Jean-Baptiste for having accepted to extend from the «intertanks» to a quite larger intertank section…

Page 6: Linac4 Update

6

Linac4 – spending profile

- «smooth» curve because of manpower limitations

- new profile (green): end of «normal» budgets in 2015 (extensions to 2016 will be possible) + «bump» for the connection in 2018 (a few budgets will remain active).

- An operation budget from 2016 is being requested by BE (and by the other Departments).

(MCHF)

Page 7: Linac4 Update

7

EVM – where are we ?

- Very good agreement between Earned Value and Actual Cost- Large delays (see previous slide) which are not realistic:

long WUs started longtime in the past with a very low earned value but a high accumulated planned value.

EVM reporting is not too bad, but should improve: 50% of WU are up-to-date, for 15% reporting is late, for 35% is very late (>3 months):

Buzio, Brunner, Lopez-H., Broere, Coupard, Carli, Baudrenghien, Vandoni, Raich, Kozsar

Page 8: Linac4 Update

8

A light EVM rebaselining

ACTIONS 2013:

- Modify only few individual WUs that are obsolete.

- Adjust only the dates in the WUs that show a large delay (for a large cost).

- Organise individual meetings with few critical WPs:

Acc. Structures / HPRF / LLRF / BI / Tr. Line / Magnets / …

and correct the WP on the spot.

Page 9: Linac4 Update

9

Linac4 at the Open Day

Proposal for visits to Linac4 for the CERN Open Days (28-29.9.2013):

1. Free visit of the hall (access only to platform), with an exhibition of equipment and possible conference/slide show

2. Guided tour of tunnel (groups of 12 with a guide, only 2 groups at the same time, ≈100 p/hour) - 3 MeV installed (and running?), some CCDTL, 1 PIMS.

Need about 10 volunteers for the tunnel visits (half a day each on Saturday or Sunday). More is better!

Page 10: Linac4 Update

10

Safety File (from Anne Funken)

• La partie descriptive du safety folder est en révision chez les WP Holders depuis le 8/02.

• Merci à ceux qui l’ont déjà commenté et fourni les informations manquantes (Il y en a peu…).

• Deadline pour ceux qui ne l’ont pas encore fait: sous 8 jours, pour pouvoir intégrer les commentaires et l’envoyer aux chefs de groupes et DSOs avant Pâques, soit d’ici fin mars.

Partie démonstrative en travail, de même que la partie opérationnelle.  Pour la phase commissioning (hardware et beam), il faut connaitre les tests qui sont prévus et le planning, en particulier les dangers additionnels que les tests génèrent (conditions particulières éventuelles lors des tests). Des procédures doivent être rédigées et approuvées au préalable. Pour la source, rien ne m’a encore été communiqué par exemple (documents qui ont du être fournis lors de la réception de HSE notamment).

Page 11: Linac4 Update

11

Conclusions

Thanks to all for this outstanding result !