main aspects and results of level 2 psa for knpp wwer … aspects and results of level... ·...

15
Proceedings of the 10 th International Conference on Nuclear Option in Countries with Small and Medium Electricity Grids Zadar, Croatia, 1-4 June 2014 Paper No. 146 146-1 Main Aspects And Results Of Level 2 PSA For KNPP WWER-1000/B320 Kaliopa Mancheva, Kiril Tzenkov, Evgeni Borisov “Risk Engineering” Ltd 10 Vihren Street, Sofia, Bulgaria [email protected], Kiril.Tzenkov@ riskeng.bg, Evgeni. [email protected] ABSTRACT The PSA Level 2 for Kozloduy NPP (KNPP) is an update of a previous study with wider scope of analysis. The previous study represented the status of the units up to 2001. The current PSA Level 2 is based on the PSA Level 1 and represents the status of the units up to 2007 year concerning the systems and procedures included in PSA level 1 and status up to 2011 for the systems and procedures (e.g. SAMG) related to containment and severe accident aspects. The study is performed after the PSA level 1 has been finished and approved by the customer. Compare to the older analysis all modes of operation for analyzed in PSA level 1 event groups as well Spent Fuel Pool accidents are investigated. The analysis consists of both deterministic and probabilistic analysis. As part of deterministic analysis a contemporary containment strength analysis and accident progression deterministic analysis using the last version of MELCOR are performed. The probabilistic analysis contains of two parts: Interface PSA and CET are calculated using Riskspectrum program code. Two types of models for CET have been developed: one for conditional probabilities calculations and a set of simplified CET’s for each PDS group – for integral model. The purpose of the first model is to be able to perform quick calculations and for sensitivity analyses as well. The simplified CET’s are used for integral calculation of the model. Source Term analysis is mainly based on the MELCOR analyses results. All characteristics of the releases have been defined, i.e. location, mass, energy of radionuclide groups and activity of the released isotopes (most important are reported only). The main goals of the study are to analyze the status of the containment, systems designed to prevent containment failure and operator action required under the severe accident and to give quantitative assessment of the risk parameter LERF (Large Early Release Frequency). This report will present main results, finding and conclusions of the analysis. Based on the results, the effectiveness of the current means and SAMG are assessed qualitatively. 1 INTRODUCTION Units 5 and 6 of Kozloduy are of VVER-1000/B320 type of reactors. These are pressurized light water reactors with four loops, horizontal SG and with 3 independent and of 100 % capacity safety systems trains. The PSA Level 2 analysis is partially an update of the currently available PSA L2 study for Units 5 and 6 of Kozloduy NPP (KNPP) and partially entirely new analysis. The new study includes in addition to the previous one all low power and shutdown modes and Spent Fuel Pool (SFP) analysis. The scope of the new study covers: Internal IE’s Internal Flooding; Internal Fires;

Upload: truonglien

Post on 01-Mar-2018

215 views

Category:

Documents


2 download

TRANSCRIPT

Proceedings of the 10th International Conference on Nuclear Option in Countries with Small and Medium Electricity Grids Zadar, Croatia, 1-4 June 2014 Paper No. 146

146-1

Main Aspects And Results Of Level 2 PSA For KNPP WWER-1000/B320

Kaliopa Mancheva, Kiril Tzenkov, Evgeni Borisov “Risk Engineering” Ltd

10 Vihren Street, Sofia, Bulgaria [email protected], Kiril.Tzenkov@ riskeng.bg, Evgeni. [email protected]

ABSTRACT

The PSA Level 2 for Kozloduy NPP (KNPP) is an update of a previous study with wider scope of analysis. The previous study represented the status of the units up to 2001. The current PSA Level 2 is based on the PSA Level 1 and represents the status of the units up to 2007 year concerning the systems and procedures included in PSA level 1 and status up to 2011 for the systems and procedures (e.g. SAMG) related to containment and severe accident aspects. The study is performed after the PSA level 1 has been finished and approved by the customer. Compare to the older analysis all modes of operation for analyzed in PSA level 1 event groups as well Spent Fuel Pool accidents are investigated.

The analysis consists of both deterministic and probabilistic analysis. As part of deterministic analysis a contemporary containment strength analysis and accident progression deterministic analysis using the last version of MELCOR are performed. The probabilistic analysis contains of two parts: Interface PSA and CET are calculated using Riskspectrum program code. Two types of models for CET have been developed: one for conditional probabilities calculations and a set of simplified CET’s for each PDS group – for integral model. The purpose of the first model is to be able to perform quick calculations and for sensitivity analyses as well. The simplified CET’s are used for integral calculation of the model.

Source Term analysis is mainly based on the MELCOR analyses results. All characteristics of the releases have been defined, i.e. location, mass, energy of radionuclide groups and activity of the released isotopes (most important are reported only).

The main goals of the study are to analyze the status of the containment, systems designed to prevent containment failure and operator action required under the severe accident and to give quantitative assessment of the risk parameter LERF (Large Early Release Frequency).

This report will present main results, finding and conclusions of the analysis. Based on the results, the effectiveness of the current means and SAMG are assessed qualitatively.

1 INTRODUCTION

Units 5 and 6 of Kozloduy are of VVER-1000/B320 type of reactors. These are pressurized light water reactors with four loops, horizontal SG and with 3 independent and of 100 % capacity safety systems trains.

The PSA Level 2 analysis is partially an update of the currently available PSA L2 study for Units 5 and 6 of Kozloduy NPP (KNPP) and partially entirely new analysis. The new study includes in addition to the previous one all low power and shutdown modes and Spent Fuel Pool (SFP) analysis. The scope of the new study covers:

• Internal IE’s • Internal Flooding; • Internal Fires;

146-2

• Seismic Hazard, All power levels and shutdown of the reactor installation and SFP (full power mode is

excluded from the analysis of SFP) are analyzed. Moreover, the new study is based on different PSA tools and the latest MELCOR version is

used for accident progression analysis. The old study is developed using SAPHIRE for interface part and EVNTRE code for Containment Event Tree analysis. The current study is performed using RiskSpectrum for interface and CET part of the analysis, i.e. the PSA part of the modeling. In this sense, the current study can be treated as an entirely new study.

The analysis structure is shown on Figure 1. The figure pictures the different tasks performed in the study and relations between them.

PSA L1$L2 Interface

MELCOR’s Models Development (Reactor

and SFP)

Melcor Calc

Containment Structural model development

Containment Event Trees

Melcor Clacs

Melcor CalcsSource Term Analysis

Phenomenon Analysis

Primary Side structural model development

Containment Structural Analysis

Conclusions and Insights

Quantitative Assessment

Recomendations

Additional Assessments

System & Human Error Analysis

Sensitivity, Uncertainty and Importance

Analysis

Primary Side Structural Analysis

Input Data Analysis

Figure 1: PSA Level 2 Analysis structure Goals of the study are in compliance with the recommendations given in IAEA SSG-4

document (reference).

2 INTERFACE BETWEEN PSA LEVEL 1 AND LEVEL 2

The interface analysis links PSA L1 and L2 models in way that all of the sequences in PSA L1 are grouped in so called Plant Damage States (PDS), which further are analyzed in CET model. The analysis groups sequences based on their similar characteristics in order CET model can treat particular PDS as one severe accident scenario. This means that the severe accident progression for all of the sequences grouped in one PDS are expected to be identical or similar. Therefore, grouping process is performed using so called attributes or characteristics of the sequences, which are identical or similar for all the sequences in the PDS and are important considering the severe accident progression.

For the sequences with no bypass of Containment, the following attributes are used: • IE’s class – Large LOCA, Small Small LOCA, Transient, TBO and ATWS classes are

analyzed; • Primary Side Pressure at core damage moment:

- Pressure is above 110 kgf/cm2 – only make up system can be used; - Between 21 kgf/cm2 and 110 kgf/cm2 – HPIS can be used; - Bellow 21 kgf/cm2 – LPIS can be used;

146-3

• Containment Status – isolated, not isolated or opened; • Spray System Status – available in recirculation mode or failed; • AC Power Supply availability – At least 1 out 3 Safety 6 kV Switchgears is available

or TBO; • ECCS availability – 1 out of 3 HPIP or LPIP is available, 1 out of 3 Make-up pumps is

available, all systems are failed ; • Time to Core damage:

- Core damage occurs before 12-th hour after EP is onset; - Core damage occurs after 12-th and before 24-th hour after EP is onset; - Core damage occurs after 24-th and before 48-th hour after EP is onset; - Core damage occurs after 48-th hour after EP is onset.

For the bypass events the attributes are as follows; • IE’s Class – Medium or Large Break, SGTR and Interface LOCA; • SDA status – failed in open position or operate in cycling mode; • SGSV status – failed in open position or operate in cycling mode; • Primary Side Pressure – Bellow or above SDA (72 kgf/cm2) set point for opening;

For Spent fuel Pool, the attributes are similar, although, systems for injection into the SFP are not the same and some of the attributes used for reactor installation are skipped (e.g. pressure at fuel damage moment).

The distribution of different major PDS groups for reactor installation and SFP are shown on Figure 2.

RI analysis SFP analysis

Figure 2: PDS distribution

3 ACCIDENT PROGRESSION ANALYSIS – MELCOR CALCULATIONS

Deterministic part of accident progression analysis has been performed using the last version of MELCOR code, i.e. version 2.1. The results of the analysis are used for containment event tree construction, bases of conditional probabilities assignment for most of the phenomena, quantitative analysis of the source term.

Several models are developed to envelope different POS (Plant Operating State) for reactor installation and SFP. The choice of the POS’s is done based on the PSA level 1 and respectively PSA L1&L2 interface results. The models that are used consequently in the analysis are:

• Full power (POS0) model for reactor installation; • Cold state (POS06) model for reactor installation; • Shutdown state with open reactor (POS08) model for reactor installation; • Shutdown state with unloaded reactor (POS10) model for Spent fuel pool.

146-4

3.1 Reactor installation modeling

Two different nodalizations have been used – simple one for LBLOCA sequences and the detailed one for all others (which includes Small Small LOCA, Transients and ATWS).

Generally, the differences between two nodalizations is in the core region, where a number of 30 control volumes (CV) has been used for detailed nodalizations and 5 CV for simplified one. The detailed nodalization gives more sophisticated behavior of internal flows and consequently more realistic simulation of the slow core degradation. The control volume model for Primary Side is represented by 112 volumes in detailed nodalization and by 87 in the simple one. The nodalizations for the current study are shown on Figure 3.

010-020010-020020-034

020-035 020-033

040-050

033-050032-050

031-050034-050

035-050

CV0

34

CV0

60

020-033

CV0

10

030-060

CV0

32

020-031

CV0

35

031-032034-035

033-034

035-040

24.930

CV0

33

CV0

31

020-032

032-050

020-040 020-035020-034

031-050

040-050040-060

035-050 033-050034-050

032-033

CV0

33

CV0

34

CV0

40

CV070

CV0

6002

0-06

0

CV020

CV0

10

032-033

CV0

32

033-034

040-060

CV0

35

031-032034-035

CV0

31

035-040

020-031

29,440

030-060

18.419

22.928

16.899

070-050

060-070

16.899

26.953

060-070

CV070

020-

060

CV020

CV050

CV0

40

18.419

070-050

22.928

24.930

18.519

020-040

CV050

020-03218.519

26.953

29,440

010-020

CV032

CV016

CV047

CV014 CV024

CV052

CV037

CV042

CV056

CV012

CV023

CV045

CV036

CV057

CV046

CV054

CV055CV025

CV044

CV022

CV043

CV034

CV035CV015

CV050

CV027

CV013 CV053

CV017

CV033

CV026

25.275

24.647

22.928

16.899

070-092

24.930

26.753

CV092091-092

23.728CV091

020-040

040-060

CV01

0

CV04

0

CV020

18.519 18.419

29,440

060-070

X=1,2,3,4109-458

CV458 CV458

29.5545

28.7565

28,0395

21,065

x02-x20

CV110

x02-x03

20,640

CVx24

CVx22CVx21

x08-x09

23.900

CVx07

CVx26x02-x23

CVx20

CVx28x25-x05

27,938 27,938

CVx09

CVx0

4

29.140

CVx

06

20,21520,215

x28-x05

29.140

30,128

24.000

CVx27

CVx0

8

CVx25

109-110*

x27-x28

x21-x22CVx0

2

x20-x21

CVx23

22,18

x23-x24

x07-x08

x26-x27

x24-x25

32,17

CVx0

5

x00-x04

x05-x06

CVx0

1

x06-x07

CVx0

3

x04-x05

CVx00

32,17

30,128

x01-x02

x02-x26

25.700

x22-x05

110-458

CV070

CV0

60

035-040

020-

060

050-091

26.125

047-050 057-050037-050027-050017-050040-050

057-060047-060037-060027-060017-060

020-052020-042

020-032020-022

020-012

050-x00 25.700

x09-010 (110-010*) 23.900

24.325

23.475

Simple Nodalization Detailed Nodalization

Figure 3: Primary Side Nodalizations For open reactor modes, the nodalization is changed to account for absence of some of the

internal structure and reactor cover. Additionally, the connections between different parts of Primary side (SG, Pressurizer and Reactor) and gas removal system are simulated. The nodalization of the model is shown on Figure 4.

144-811

811-813

x03-811

010-020

x04-811

034-035

x00-x04

CVx20

CV050

x27-x28

25.275

040-050

27.55

18.419

x01-x02

x08-x09

020-032

16.899

x04-x05

x07-x08

CV01

0

033-034

CVx0

4

CVx0

8

24.000

32,17

x05-x06

CVx28x23-x24

x06-x07

22.928

24.930

x09-010 (110-010*)

x24-x25

CVx0

3

x21-x22

25.700

29.140

CVx0

1

CVx

05

22,18

x26-x27

031-032

CVx27

x20-x21CVx

02

27,938

x25-x05

24.325

CVx0026.125

109-110*

23.475

20,215

x28-x05

x02-x23CVx25

x02-x20

30,128

32,17

30,128

29.140

020-031

20,215

CVx0

6

CVx09

020-040

CVx24

23.900

CVx21

CVx26

CVx07 20,640

x02-x26

CVx22x22-x05

x02-x03

CV110

CV04

0

21,065

23.900

CV0

34

050-x00

CV0

33

25.700

032-033

020-

060

CV020

CV03

2

28,0395

28.7565

033-050

CV03

5

29.5545

035-040

CV03

1

034-050

020-035020-034

020-033

031-050032-050

X=1,2,3,4

035-050

140-14322.64

CV463

20.113

CV400

19.767

CV140

CV81134.323

23.475

FL142 FL141

32.15

463-050

19.94

CV143

FL143-144

CV144

400-140

TQn2đĺ ě î í ňí î đŕ çőëŕ ćäŕ í ĺ(î ňâĺ ćäŕ í ĺ í ŕ ňî ďëî í î ńčňĺ ë)CV407

25.70

CV140

CV813

CV140

813-463

31.353

TQn2đĺ ě î í ňí î đŕ çőëŕ ćäŕ í ĺ(ďî äŕ âŕ í ĺ í ŕ ňî ďëî í î ńčňĺ ë)CV100

27,938

18.519

CVx23

31.353

CV140

CV140

25.70400-140

CV144

FL143-144

CV143

19.94

32.15

FL141FL142

23.475

34.323

CV140

19.767

CV400

20.113

22.64

140-143

Figure 4: Primary Side Nodalization for open reactor

More simplified nodalization is used for the secondary side. Two different nodalizations of secondary side of steam generator have been tested in order to choose the most appropriate, first one with one control volume and second one with three control volumes per SG (riser, downcomer and steam part). The results for 5 different transients showed that the more detailed nodalization slows down calculations significantly, about 2 times, without any significant change in the behavior

146-5

of SG model. Therefore, the simple one has been used for all the analyzed scenarios. The two nodalizations are shown on Figure 5.

Steam Generators Steam Generators

CVx10

x00-

x10

CVx10

x00-

x10

FLX08

CVX02

DowncomerFLX03

CVX00

CVX00FLX04

30.380

X=5,6,7,8

FLX05

CVX01

31.930

35.275

29.155

31.930

Riser

34.695

35.275

34.695

27.930

30.380

FLX07

27.930

Figure 5: Secondary Side Nodalizations

The containment nodalization is shown on Figure 6. As it is seen from the picture, the so

called central hall compartment (which is about 30 000 m3 out of 60 000 m3 in total) is divided into 10 control volumes on 4 different levels. The idea of the division is to account for possible gas stratification and to account for spray system inability to spray all over the entire central hall volume directly.

(n17,19-24)

(n57)

(n93,95)

ĂŔ304ĂŔ312ĂŔ502/1ĂŔ503ĂŔ504/2ĂŔ504/3ĂŔ507/2ĂŔ601ĂŔ603/1ĂŔ603/3ĂŔ604

ĂŔ301(2)***, ĂŔ407/2ĂŔ506/2, ĂŔ606/1

(nn73,88-92)

(n96,97,99)

ĂŔ301(1)

(n59)

(n42,47-49)

ĂŔ701

ĂŔ701

ĂŔ301(3)ĂŔ312ĂŔ313ĂŔ501

ĂŔ301(2)***, ĂŔ407/1ĂŔ506/1, ĂŔ606/2

(n31,33)A336

ĂŔ311 ĂŔ306/3

ĂŔ302ĂŔ303ĂŔ304**ĂŔ305ĂŔ309/2ĂŔ310ĂŔ315/3ĂŔ308*

ĂŔ304**ĂŔ405/4ĂŔ405/5ĂŔ405/6ĂŔ406(2)

(n44,56)

(n55,58)

ĂŔ701

n54

(n118)

ĂŔ701

(n34,36n37-40)

ĂŔ403

(n64-67,69)ENVIROMENT

(n106,107)

(n14-18)

(n25

-28)

ĂŔ401ĂŔ402

ĂŔ405/1ĂŔ405/2ĂŔ405/3ĂŔ406(1)ĂŔ505

ĂŔ701

( n31,80,81)

(n70-72)

ĂŔ306/2

(n115)

(n103,108,109,111-114)

ĂŔ201

(n100)

(n31,33)

(n51)

ENVIROMENT

(n41)

n46

(n87)

ĂŔ701

(n117,n119)

(n60,62)

ĂŔ701ĂŔ701

ĂŔ701

(n82-86)

ĂŔ302

ĂŔ101

ĂŔ306/1

(n101,102,104,105,110)

ĂŔ701

ĂŔ502/2ĂŔ504/1ĂŔ504/4ĂŔ507/1ĂŔ603/2ĂŔ605

ĂŔ307/1,2,3ĂŔ309/1,3,4ĂŔ314ĂŔ315/1ĂŔ315/2ĂŔ308*

460-455

466-469

465-462

456-455

453-454

453-456

460-452

459-466461-466

477-470

478-471

465-467

458-469

462-469

455-453

475-

984

469-464

461-459

471-472

455-451

485-456

464-469

458-459

458-

462

456-453

468-477

455-451

458-465

473-470

477-473470-471

466-468

469-470

461-456

478-472

468-469

462-460

472-986

020-457

485-

486

458-457457-459

457-

485

478-474

473-474

454-453

459-461

452-450

467-473

463-469

451-450

464-463

460-462

458-451

465-466

453-450

458-460

467-469

458-452

451-452

465-469

460-465

460-458

455-452

468-467

477-478

452-455

458-451

474-472

459-453

451-455

460-451

459-469

460-986

469-463

472-985

457-

475

460-461

î ň ĐĹŔĘŇÎ ĐŔ

474-471

CV456

CV458

CV452 CV454

CV450

CV468

CV465

CV469

CV472

CV470CV473

CV485

CV463

CV986 CV985

CV475

ENVI

RONM

ENT

CV987

ENVI

RONM

ENT

CV462

CV984

CV466

CV464

CV467

CV474 CV471 CV478

CV477

CV453

CV459

CV461

CV455

CV451

CV460

CV486

CV457

6.9

13.7

6.96.9

II

I

33.6 m2

15.78 m2

Heavy door

III

CAV10

77.75 m2

IV

GA310GA302GA308GA301

CAV30

Transport hatch

Containment nodalization Cavities in containment Figure 6: Containment Nodalization

The cavities in the lower containment compartments are modeled in a way to account for heavy door, which is between room GA301 and GA302 and to account for possible interaction between metal structure of transport hatch cover and core melt (corium) that will be spread into GA302 and GA308 rooms after heavy door failure.

146-6

3.2 Spent Fuel Pool modeling

Spent Fuel Pool for VVER-1000 is of high density rack type. In total, a 563 fuel assemblies can be arranged in three partially separated pools or so called sections of the SFP. The spent fuel pool is located in the containment. The model nodalization and SFP rack view are shown on Figure 7. The core model is based on SFP-BWR type and accounts for channel (through the rack flow) part and bypass part (the flows between racks).

28.83

CV092CV091

CV021

CV090

36.9

CV 056

086-090

CV 075

CV 085CV 083

CV 047

CV 061

CV 033

CO

RE R

ING

2

CV 042

CV 085

CV 031

CV 081 CV 082

CV 045

CO

RE

BYPA

SS R

ING

1 CV 075

CV 087

CV 070CV 071

COR

E BY

PASS

RIN

G3

CV 086

CV 066

CV 074

CV 084

CV 034

CV 055

CV 086

CV 050

CV 076CV 076

CV 087

CV 076

CO

RE R

ING

4

CV020

CV 086

CV 066

CV 046CV 047 CV 046

CV 066

CV 056

CV 036

020-033 020-035020-032 020-034

083-090 084-090082-090 109-090

062-063

CV 046

COR

E BY

PASS

RIN

G4

080-090

CV 030

060-061

036-037

081-090

037-100

084-085080-081

032-033 CV 034

052-053

084-085

020-100

CV 064

056-057

CV 067

046-047

034-035

CV 044

CV 065

074-075

086-087

054-055

CV 062

CV 040 044-045

CV 080

CV 100

076-077

CV 064

047-102

CV 057C

ORE

BYP

ASS

CV 035

CV 060 066-067

CV 102

CV 104

CV 106C

ORE

RIN

G 3

CV 041

CV 072

CV 045

CV 055

CV 035

CV 053

CV 066

CV 084

CV 074 CV 076CV 076

CV 036CV 036 21.44

CV 066

CV 056

24.933

CV 037

CV 056

CV 066

CV 076

CV 066

CV 036

CV 066

22.815

23.521

24.227

CV 046 22.109

20.7

25.725

25.725

CV 077

CV 109

CV 054

077-108

020-037

067-106

CV 076

020-030

057-104

020-031

CV 076

21.44

CV 086

CV 037030-031

087-109

CV 108

CV 054

087-090

020-036

CV 077CV 073

085-090

CORE

RIN

G 1

CV 052

072-073

050-051

070-071

064-065

CV 043

COR

E BY

PASS

RIN

G2

042-043

CV 032

CV 065CV 063

CV 051

CV 044040-041

28.83

Spent fuel pool nodalization View of SFP Rack

Figure 7: Spent Fuel Pool Nodalization

4 CONTAINMENT STRUCTURAL ANALYSIS

The approach of containment structural analysis accounts for contemporary regulatory standards given in [4]÷[6] and methodical approach given in [3]. Additionally, the results and conclusions given in [7]÷[9] are accounted in the analysis. Several possible failure modes are studied due to high internal pressure:

• barrel or o-ring failure – in the middle of the cylindrical part; • blade failure– at the basement part; • failure due to hatches or penetration failure; • failure due to flying objects.

Additionally, two types of pressure behavior are analyzed – quasi static pressure increase and dynamic (explosion or detonation) pressure increase.

The assessment of the structural integrity of the containment during severe accident is done using finite element analysis of detailed 3D models of containment. Three different models are used. The code SOLVIA is used for the modeling and analyzing the containment ultimate capacity. For the flying object vulnerability analysis an empirical equations are used. The models are shown on Figure 9.

All performed analyses with three different model (see Figure 8) in the current study and analytical and experimental results for similar type of constructions, confirms that main failure mode of the construction is failure of the cylindrical containment part in between or around the hatches caused by annular ring strains. Then, the obtained results are in qualitative and quantitative agreement with the contemporary understanding of the containment structure behavior.

Main failure mode (the most probable one) is shear (failure) of the cylindrical containment part between hatches and penetrations due to high annular ring strains. Deterministically assessed ultimate capacity for this failure mode is 1080 kPa (abs) for unit 5 and 1100 kPa (abs) for unit 6. The median value of the absolute containment failure pressure for unit 5 is 1430 kPa and 1450 kPa for unit 6.

On Figure 9 are shown two out of numerous fragility curves for different failure modes.

146-7

barrel or o-ring failure model – Model 2 blade failure model - – Model 3 Figure 8: Structural models

Static pressure Dynamic pressure – impulse 0.1 s

Figure 9: Fragility curves

5 CONTAINMENT EVENT TREES

Generally, there are several approaches for CET or APET development. In this particular study, it was a ToR requirement to be used RiskSpectrum code for entire probabilistic model. This requirement predestines the approach to be used for CET development, i.e. ET/FT approach.

Accident progression in reactor installation is divided into three main phases – early phase (in-vessel accident progression), middle phase (vessel breach time) and late phase (about 0.5 hours after vessel breach up to the end of the analysis). For SFP accident progression similar phases are defined. The differences is in middle phase, which for SFP covers the period from the melt interaction with SFP concrete structures beginning up to failure of SFP concrete structures and relocation of the melt in the lower containment compartments.

All known phenomena were analyzed for their applicability before CET development and only flying object, rocket mode failure and corium re-criticality were found as inapplicable. The phenomena that are included explicitly in the CET are hydrogen burning (for all three phases), high temperature creep rupture, PORV stuck open, HPME and DCH, in-vessel and ex-vessel steam explosion, static overpressure, MCCI. The conditional probabilities for occurrences and impact of the different phenomena are mainly based on the MELCOR analyses and contemporary understanding of phenomena behavior.

146-8

Apparently, some of the phenomena, which are typical or possible for reactor installation, are inapplicable for SFP (e.g. HPME and DCH). Moreover, based on MELCOR analyses, in-vessel and ex-vessel steam explosion for SFP was found to be not applicable.

System availability and their effect on the accident progression included in the model are LPIS, HPIS, Spay System, Make-up system (the make-up system injection effect is temporary and influences mainly release onset) and Passive Filter Ventilation system. Modeling approach of the systems has two aspects: system unavailability or conditional failure probability is done in a same approach as in PSA L1 and interface analysis and qualitative analysis for equipment located in containment is performed based on MELCOR results. The qualitative analysis determine whether system components in the containment status (failed or not due to beyond basis environment conditions) and system unavailability analysis analyses the stochastic nature of system failure possibility.

As an example of CET structure, the early phase for high pressure sequences is shown on Figure 10.

CET - tight Primary Side

P-EARLY-PHASE

PORV stuck open

YP-STUCK

High temp. creep rupture - hot legs or SL

HTRCS

High temp. creep rupture - SGTR

HTSGTR

AC power recovery

R-EL-I

In vessel corium coolability

IVR-COOL

In-vessel steam explosion

IVR-SE

Spray System operation

SS-I

Hydrogen burning

BUR-I

Containment failure - early

CONT-FE

Time of failure

CONT-T1

1 RC0

2 RC03 IVR-COOL

3 P-MID-PHA IVR-COOL-IVR-SE

4 RC03 IVR-COOL-IVR-SE-CONT-FE

5 P-MID-PHA IVR-COOL-IVR-SE-BUR-I

6 RC01 IVR-COOL-IVR-SE-BUR-I-CONT-T1

7 RC02 IVR-COOL-IVR-SE-BUR-I-CONT-T1(3)

8 RC03 IVR-COOL-IVR-SE-BUR-I-CONT-T1(4)

9 P-MID-PHA IVR-COOL-IVR-SE-SS-I

10 RC03 IVR-COOL-IVR-SE-SS-I-CONT-FE

11 8.02E-02 P-MID-PHA IVR-COOL-IVR-SE-SS-I-BUR-I

12 RC01 IVR-COOL-IVR-SE-SS-I-BUR-I-CONT-T1

13 RC02 IVR-COOL-IVR-SE-SS-I-BUR-I-CONT-T1(3)

14 RC03 IVR-COOL-IVR-SE-SS-I-BUR-I-CONT-T1(4)

15 RC03 R-EL-I

16 P-MID-PHA R-EL-I-IVR-SE

17 RC03 R-EL-I-IVR-SE-CONT-FE

18 8.27E-04 P-MID-PHA R-EL-I-IVR-SE-BUR-I

19 RC01 R-EL-I-IVR-SE-BUR-I-CONT-T1

20 RC02 R-EL-I-IVR-SE-BUR-I-CONT-T1(3)

21 RC03 R-EL-I-IVR-SE-BUR-I-CONT-T1(4)

22 P-BYPASS HTSGTR

23 P-EARLY-P HTRCS

24 9.19E-01 P-EARLY-P YP-STUCK

1

1

1

21

5

1

2

3

2

1

1

21

5

1

2

3

2

2

2

2

1

1

1

21

5

1

2

3

2

2

2

1

2

1

2

1

2

21

No. Freq. Conseq. Code

Figure 10: Containment Event Tree for Early phase

6 SOURCE TERM

The release categories are determined based on the following main attributes:

• Containment status (isolation failure, isolated – considering the expected lack tightness or bypassed);

• Time of release onset – 4 time periods are distinguished (before 12 hours, between 12 h and 24 h, between 24 h and 48 h and after 48 hours);

• Mitigation features – spray system and Filter Venting System;

• Containment failure location or Release location – failure through containment basement, containment structure failure, isolation failure (releases are through vent stack);

• Activity [Bq] of 137Cs – division is made based on the regulation normative bases, i.e. 3.0E13 Bq. Then, there are two possibilities – below the normative basis considered as small releases and higher than normative basis considered as large releases.

Example of the represented results is given on Table 1.

146-9

Table 1 Activity of Release categories

Release Category PDS

Activity [Bq] Sr-90 Ru-103 Te*-131 I-131 Xe-133 Cs-137 Ba-140 La-140 Ce-141

RC0

Sc1 2,20E+04 4,68E+05 1,54E+04 1,47E+08 3,43E+08 8,26E+05 2,95E+05 2,35E+04 5,04E+04 Sc2 4,99E+04 5,14E+04 1,29E+04 4,48E+06 1,14E+07 8,33E+04 1,02E+06 6,13E+04 1,55E+05 Sc3 2,62E+03 2,47E+04 1,29E+05 7,53E+07 2,77E+08 2,58E+05 5,10E+04 3,05E+02 5,27E+03 Sc4 3,42E+04 1,30E+04 1,65E+06 1,77E+08 4,42E+08 1,41E+05 7,02E+05 2,24E+02 7,99E+02 Sc5 3,83E+05 1,52E+05 3,18E+07 1,91E+09 4,28E+09 3,98E+06 7,84E+06 6,18E+03 1,42E+04

RC1 Sc6 2,94E+16 3,05E+16 1,21E+16 2,90E+18 5,36E+18 7,00E+16 5,27E+17 3,11E+16 1,63E+17 Sc7 5,40E+15 2,48E+16 8,68E+16 3,22E+18 6,45E+18 1,37E+17 1,05E+17 1,04E+15 1,65E+16 Sc8 2,87E+16 2,87E+17 2,41E+16 2,68E+18 4,68E+18 1,85E+17 4,75E+17 3,00E+17 4,22E+17

RC2 Sc9 1,79E+16 1,05E+16 9,89E+14 1,30E+18 1,94E+18 7,26E+16 2,69E+17 3,44E+15 7,32E+16

7 MAIN RESULTS

Based on the definitions given in Bulgarian nuclear Agency regulatory guide for probabilistic analyses, risk parameters that need to be assessed in PSA L2 are:

• LERF – Large Early Release Frequency – frequency of accident sequences that lead to significant, not mitigated releases from the containment at a moment before the evacuation procedure of nearby local people has been finished, i.e. early fatalities or health troubles are possible, [1/y];

• LRF – Large Release Frequency - frequency of large releases from NPP, [1/y]; • TRAR – Total Risk of Activity Release – total releases for particular release category,

[Bq/y]. There are 21 release categories (RC) defined for reactor installation and 5 RC’s for spent fuel

pool. Only one RC, named RC0, is assigned to the sequences with successful severe accident termination and releases, which are maintained bellow normative bases (i.e. activity of CS-137 bellow 3.10E13 Bq). For all of the rest RC, releases are higher or are expected to become higher compare to normative bases in time. In Table 2 are given all the defined RC for reactor installation and SFP. As it can be seen from the table there several attributes that are used for RC division:

• Containment status; • Type of containment failure; • Time of containment failure; • Release path – direct or not direct releases to the Environment; • Spray system and or Filter Venting system status.

Table 2 Release categories

Release Category

Frequency [y-1]

Description

Reactor Installation RC0 9.40E-06 Successful cooling of damaged core. Isolated containment - releases are less than normative

bases. RC1 8.08E-07 Not isolated containment or early failure. Releases starts before 12th hour to RB. RC2 7.45E-08 Not isolated containment or early failure. Releases starts between 12th÷24th hour to RB. RC3 7.53E-07 Not isolated containment or early failure. Releases starts before 12th hour to Environment RC4 2.86E-07 Open reactor. Not isolated containment or early failure. Releases starts between 12th÷24th hour to

Environment RC5 1.98E-07 Open reactor. Not isolated containment or early failure. Releases starts before 12th hour to

Environment RC6 8.29E-07 Isolated containment. Releases are to RB due to basement failure. Activity of Cs-137 is less than

146-10

Release Category

Frequency [y-1]

Description

3.0Е13 Bq up to the end of calculation RC7 6.13E-08 Isolated containment. Sprays are in operation. Late containment failure due to hydrogen burning.

Releases starts between 24th÷48th hour to Environment RC8 2.90E-11 Isolated containment. Sprays are in operation. Containment failure after vessel breach due to

hydrogen burning, HPME or ex-vessel steam explosion. Late containment failure due to hydrogen burning. Releases starts between 12th÷24th hour to Environment

RC9 4.02E-09 Isolated containment. Sprays and Filter system are failed. Containment failure after vessel breach due to hydrogen burning, HPME or ex-vessel steam explosion. Late containment failure due to hydrogen burning. Releases starts between 12th÷24th hour to Environment.

RC10 8.65E-08 Isolated containment. Sprays and Filter system are failed. Late containment failure due to basement failure. Releases starts between 24th÷48th hour to RB.

RC11 8.13E-08 Isolated containment. Sprays are failed. Containment failure after vessel breach due to hydrogen burning, overpressure or Filter system isolation failure. Releases starts between 24th÷48th hour to Environment.

RC12 3.35E-06 Isolated containment. Sprays are failed. Containment failure after vessel breach due to hydrogen burning, overpressure or Filter system isolation failure. Releases starts after 48th hour to Environment.

RC13 4.22E-06 Isolated containment. Sprays are failed. Containment failure after vessel breach due to hydrogen burning, overpressure or Filter system isolation failure. Releases starts after 48th hour to RB.

RC14 3.53E-06 Open reactor. Isolated containment. Sprays are failed. Late containment failure due to basement failure. Releases starts after 48th hour to RB. Activity of Cs-137 is less than 3.0Е13 Bq up to the end of calculation.

RC15 4.06E-06 Open reactor. Isolated containment. Sprays are failed. . Late containment failure due to basement failure. Releases starts after 48th hour to RB. Activity of Cs-137 is higher than 3.0Е13 Bq.

RC16 4.32E-06 Isolated containment. Sprays are failed. Filter system is in operation. Releases from Filter system are less than normative bases. In late phase, after 48th hour, containment failed due to basement failure and releases to the RB goes beyond normative bases.

RC17 1.73E-06 Containment bypass. IE is Primary to Secondary LOCA. SDA is stuck open. Early releases to the Environment.

RC18 2.64E-07 Containment bypass. IE is Primary to Secondary LOCA. SDA operates in cycling mode. Early releases to the Environment.

RC19 1.93E-07 Containment bypass. IE is Interface LOCA. Early releases to the RB. RC20 1.98E-08 Containment bypass due to HT SGTR. Releases to the Environment.

Spent Fuel Pool SFP-RC0 4.14E-08 Successful cooling of damaged core. Isolated containment - releases are less than normative

bases. SFP-RC1 1.83E-06 Isolated containment. Late containment failure due to overpressure. Releases to the Environment

starts after 9 days from the accident beginning. SFP-RC2 3.21E-07 Not isolated containment or early failure. Releases starts between 12th÷24th hour to the

Environment. SFP-RC3 5.37E-07 Not isolated containment or early failure. Releases starts after 72th hour to the Environment. SFP-RC4 1.64E-09 Isolated containment. Late containment failure due to basement failure. Releases to the RB starts

after 10 days from the accident beginning. On Figure 11 are shown distributions for Release categories (excluding RC0) for all modes of

Reactor Installation (RI), closed and open reactor. The results states that dominating categories are RC13÷RC16, which actually represents

accident sequences with basement failure in the late phase of the accident progression. The common characteristic between these 3 categories is that releases onset after 48-th hour from the emergency evacuation start point. The other significant dominant category is again a late failure (after 48-th hour) of the containment (RC12) but the failure is caused by containment overpressure or Filter venting system isolation failure. The results for open and closed reactor confirm already made conclusions.

146-11

Reactor Installation – all modes

Closed reactor Open Reactor

Figure 11: Release Category Distribution for Reactor Installation

Looking at the aspects of the accident for SFP, one can conclude that here the differences between early and late releases are even more outlined compare to RI. As it is shown on Figure 12, the only one RC that can be considered as early release (release onset starts between 12th÷24th hours ) is RC2, which has only 12 % of contribution.

Figure 12: Release Category Distribution for SFP

The risk from releases is divided into two main groups, based on the interpretations for LERF and LRF given in the above. The main problem of assigning of different categories to LERF or LRF is the time after the emergency evacuation start point. The emergency evacuation start point is defined very clearly in the KNPP Emergency plan based on the IE, safety systems state and core state (e.g. temperature at core exit is above 650 ͦC). Unfortunately, there are no normative bases or regulations or any other source of information that says what is the time duration of the evacuation procedure. Therefore, three different time intervals are assumed based on engineering judgment and other countries experiences. For LERF and respectively for LRF, the three time thresholds are 12-th

146-12

hour, 24-th hour and 48-th hour. In that sense based on different groupings of RC’s, three different numbers for LERF and LRF has been obtained:

• The evacuation finishes before 12-th hour – LERF is 3,92E-06 [1/y] and LRF is 2,05E-05 [1/y];

• The evacuation finishes before 24-th hour – LERF is 4,43E-06 [1/y] and LRF is 2,01E-05 [1/y];

• The evacuation finishes before 48-th hour – LERF is 4,67E-06 [1/y] and LRF is 1,98E-05 [1/y].

Apparently, the results shows that the assumptions for different evacuation duration do not impact significantly the final results for LERF and LRF parameters. Moreover, LERF in all three cases is significantly less than target criterion, which is 1.0E-05 [1/y].

On Figure 13 is shown LRF and LERF distribution for different states of reactor installation and SFP. Both figures shows that main contributor to the risk of releases is closed reactor. The result is expected considering the frequency of the PDS’s for closed reactor and power level. The power level (full power is the representative power level) causes significantly faster core degradation and consequently earlier releases. Moreover, containment bypass events as primary to secondary LOCA are typical only for closed and are dominant release categories for LERF.

The contribution of accident sequences for open reactor and SFP is determined exclusively by not isolated containment, as in these sequences a direct releases onset right after CD. For SFP, accident sequences with releases before 12-th hour are not realistic, due to slow water evaporation and low decay heat in SFP, regardless of the conservative assumption made for MELCOR analyses.

A.Risk distribution based on Reactor state and SFP B.LERF distribution based on Reactor state and SFP

Figure 13: Risk parameters LERF and LRF for different state of reactor and SFP

On Figure 14A is shown risk distribution based on different types of IE’s. The results show outlined domination of the IE’s, which confirms the picture from PSA L1. Generally, the distribution follows or is closed to the one obtained in PSA L1. The main reason for this is that no system recovery is credited, except for power supply. Obviously, the credited sequences are not dominant one. Safety systems recovery is not credited mainly because of the lack of procedures for it, which determines too long time window for execution of the actions.

The distribution of different containment failure modes that goes into LERF are shown on Figure 14B. The results are exclusively determined by the PDS with attribute not isolated containment. Therefore, the gathering of the sequences with containment failure in the early phase due to any other reason is acceptable.

146-13

A.Risk distribution based on IE group B. Containment failure distribution based on phenomena types

Figure 14: Risk distribution based on type of IE and LERF based on containment failure mode

8 CONCLUSIONS

Based on the Bulgarian regulations for existing plants (currently in operation) the target risk parameters for severe accidents are:

Art10 (3) For severe accidents, the limit of cesium-137 release in the atmosphere is 30 TBq that does not impose long-term restrictions for soil and water use in the monitored area. Combined release of other radionuclides different from cesium isotopes shall not in a long-term perspective, starting three months after the accident, provoke a greater hazard than the one identified for cesium release within the indicated limit.

Art10 (4) The frequency of a large radioactive release into the environment that requires undertaking of immediate protective measures for the population shall not exceed 1.10-6 events per NPP per year.

Since the last paragraph is considered for new plants, for the existing one as is KNPP, the requirement of interest is given in Transitional and Final Provisions:

§ 3 (3) The frequency of a large radioactive release into the environment that requires undertaking of immediate protective measures for the population shall not exceed 1.10-5 events per NPP per year.

The last risk parameter is considered as LERF in the analysis.

Comparison of the obtained values for LERF against normative requirements for existing plants shows that the current safety level of unit 5 and 6 of KNPP meets the criteria for all three estimated LERF’s. The results completely meets the international requirements for plants, which design is not performed based on the last contemporary safety standards. Therefore, one can conclude that safety level of KNPP is acceptable.

Considering the requirement given in article 10 (3), which determines the maximum allowed magnitude of releases of Cs-137, only RC0 for Reactor installation and SFP-RC0 for SFP, meet this criterion. For all other release categories, this criterion is violated. That means that the releases in these categories should be always considered as large.

Analysis of the results (main results and sensitivity analyses results) shows that:

• Major risk for radionuclide products releases to the environment in the early phase of the accident is dominated by primary to Secondary LOCA events, i.e. containment bypass;

• Major challenge to the containment integrity is basement melt through (concrete ablation). This could be explained with lack of severe accident management strategies directed to the MCCI management;

146-14

• Operator actions for containment isolation are of high significance considering the LERF. In case of guaranteed isolation the LERF is lowered twice. Note, that all these actions need to be performed before severe accident onset;

• Operator action for Primary pressure decrease lowers the risk of early containment failures with about 22 %, which shows the significance of this action;

• The HPME and DCH phenomena do not represent significant risk to the containment integrity. The main reasons for this results are lower compartments layout (lack of direct path to the upper containment volume), reactor cavity construction (closed cavity) and the high containment free volume that allows to accumulate the heat transferred from the corium to containment atmosphere;

• The in and ex-vessel steam explosion phenomena have negligible contribution to the LERF and LRF due to lack of conditions for occurrence for most of the scenarios and very low probability of containment failure in case of occurrence;

• Dynamic loads and consequent failure of the containment structure due to hydrogen and/or carbon monoxide burning are probable only in the late phase of the severe accident progression. The burning modes that are expected are flame acceleration or detonation. Note, that main source of flammable gas at this phase of the accident is MCCI phenomenon;

• Significant contribution to the SFP risk decrease would have an implementation of SAMG for SFP severe accidents. Considering the slower accident progression and available time, restoration of systems would decrease the risk several times;

• Unequal decay heat distribution of the fuel assemblies in SFP (loading of FA with high decay heat in one of the SFP pools) leads to significant decreasing of time to fuel damage and faster severe accident progression.

Based on the conclusions different corrective measures are proposed to the plant staff. For most of the proposed measures additional analyses are required.

146-15

REFERENCES

[1] Probabilistic Safety Analysis for NPP, Safety Guide, BNRA, 2010

[2] Development and Application of Level 2 Probabilistic Safety Assessment for Nuclear Power Plants, specific Safety Guide No. SSG-4, IAEA, Vienna 2010;

[3] ASAMPSA2, 2010, BEST-PRACTICES GUIDELINES FOR L2PSA DEVELOPMENT AND APPLICATIONS, Volume 2 - Best practices for the Gen II PWR, Gen II BWR L2PSAs. Extension to Gen III reactors, ASAMPSA2/WP2&3/ 2010-28

[4] U.S. NRC, REGULATORY GUIDE 1.216, CONTAINMENT STRUCTURAL INTEGRITY EVALUATION FOR INTERNAL PRESSURE LOADINGS ABOVE DESIGN BASIS PRESSURE

[5] U.S. NRC, DRAFT REGULATORY GUIDE DG -1203, CONTAINMENT PERFORMANCE FOR PRESSURE LOADS, December 2008,

[6] U.S. NRC, REGULATORY GUIDE 1.136, DESIGN LIMITS, LOADING COMBINATIONS, MATERIALS, CONSTRUCTION, AND TESTING OF CONCRETE CONTAINMENTS, December 2008

[7] Rizkalla, Sami H., Simmonds, Sydney H., MacGregor, James G., Pre-stressed Concrete Containment Model, Journal of Structural Engineering, Vol.11, No. 4, April 1984, pp.730-743

[8] International Standard Problem No.48 Containment Capacity, Synthesis Report, NEA/CSNI/R(2005)5, OECD Nuclear Energy Agency, Committee on the Safety of Nuclear Installations, France, September, 2005

[9] NUREG / CR-6906, “Containment Integrity Research at Sandia National Laboratories – An overview”, Washington DC, July 2006.