  • 7/27/2019 MAINTENANCE EXERCISES.PPT

    1/19

    Maintenance Exercises

  • 7/27/2019 MAINTENANCE EXERCISES.PPT

    2/19

    Master/Basic Data

    Hierarchy

    System Data

    Master Data for IFS Applications

    General Data for Application Area

    Basic Data for Components

  • 7/27/2019 MAINTENANCE EXERCISES.PPT

    3/19

    Equipment Management

    Process Steps

    1. Create a Functional Object (\Equipment\Functional

    Object\Functional Object Information)

    2. Enter the General Tab >> Object Id, Site, Object Level, ObjectType, Category, Belongs to Object, Manufacturing Date,

    Installation Date, Criticality, Manufacturer, Supplier

    3. Enter the Spare Parts >> Site, Part No, Quantity

    4. Enter Test Points >> Test Point ID, Location

    5. Enter Parameters >> Test Point ID, Parameter

    6. Enter Parties >> Supplier, Owner, Manufacturer

  • 7/27/2019 MAINTENANCE EXERCISES.PPT

    4/19

    Equipment Management

    Process Steps

    1. Create a Serial Object (\Equipment\Serial Object\Serial Object

    Information)

    2. Enter the General Tab >> Object Id, Site, Object Type, PartNumber, Serial Number, Category, Belongs to Object,

    Manufacturing Date, Installation Date, Criticality, Manufacturer,

    Supplier

    3. Enter the Spare Parts >> Site, Part No, Quantity

    4. Enter Test Points >> Test Point ID, Location

    5. Enter Parameters >> Test Point ID, Parameter

    6. Enter Parties >> Supplier, Owner, Manufacturer

  • 7/27/2019 MAINTENANCE EXERCISES.PPT

    5/19

    Breakdown Maintenance

    Process Steps

    1. Register a Fault (\Work Order Management\Fault Report)

    2. Select the Directive, Maint Org, Object ID, Description, Required

    start and Latest completion, Discovery, Symptom and Priority3. Save the Fault Registry and note down the WO No.

    4. RMBPrepare. Work Order opens

    5. Select the Work Type

    6. RMBReport In Work Order7. Enter Actual Start and Actual Completion Dates

    8. RMB > Work Order Status >Finish

  • 7/27/2019 MAINTENANCE EXERCISES.PPT

    6/19

    Exercise - Fault Report

    Register a Fault on Unit 2 for your site

    Select the Discovery as 002

    Enter the symptom as 001

    Enter the Required Start & Latest CompletionDate

    Save the Fault

    Check the report O&M Breakdown Report

  • 7/27/2019 MAINTENANCE EXERCISES.PPT

    7/19

    Exercise - Fault Report RMBPrepare (Work Order)

    Enter the Planning Schedule and PlanningInformation

    Enter the Work Type as REPBRK

    Enter the Required Start & Latest CompletionDate

    Change the Work Order status to Released

    Enter the Actual Start Date and ActualCompletion Date

    Change the Work Order status to Finished

  • 7/27/2019 MAINTENANCE EXERCISES.PPT

    8/19

    ExercisePM Calendar Based

    Register a PM action for your

    Motor(Functional)

    Register a Calendar Based generation for

    the motor - 6-jun-09, every 2 months

    Plan crafts and material for the PM action

    Do a calendar Generation for the week 0023

    Register an Event Give an event plan for your PM action

    Register that the event has happened and

    notice the WO that is formed

  • 7/27/2019 MAINTENANCE EXERCISES.PPT

    9/19

    Exercise - PM - Condition Based

    Make sure that motor(functional) hastemperature registered as one of the parameters

    For your PM action mention temperature as a

    criteria for generation with limits as 50-100 Register temperature for the functional

    object(motor) as 150 and perform a condition

    based generation. Notice the WO that gets

    formed

    Perform the above by registering a temperature

    of 80

  • 7/27/2019 MAINTENANCE EXERCISES.PPT

    10/19

    ExercisePM Event Based

    Register a PM action for your

    Motor(Functional)

    Plan crafts and material for the PM action

    Register an Event Give an event plan for your PM action

    Register that the event has happened and

    notice the WO that is formed

  • 7/27/2019 MAINTENANCE EXERCISES.PPT

    11/19

    Exercise - PM - Standard Jobs

    Create a Standard Job for Changing Bearings

    with crafts and material demands

    Create a PM action for the motor (serial) using

    this standard job id and notice that the craft and

    the material tabs get updated automatically

  • 7/27/2019 MAINTENANCE EXERCISES.PPT

    12/19

    Exercise - Route PM actions

    For the Route Monthly Maintenance, register a PMaction for Radial Gate and Under Sluice Gate (find out

    the Object ID in the Functional Object)

    Register the Start Value as 0905 and Interval as 1 month

    Register the planned men and planned hours

    Enter the Jobs in the Job tab

    Enter the Consumables / parts required in Materials tab

    Note down the Maintenance Plan

    Carryout the Calendar Generation & Note down the

    Work Order Number

  • 7/27/2019 MAINTENANCE EXERCISES.PPT

    13/19

    Exercise - Work Order Flow Choose one of your work orders created during previous

    exercises. Complete the Craft and Material planning for the WO

    Release the WO

    In the /Requisition tab of WO raise a PR for one of theparts . Release the requisition

  • 7/27/2019 MAINTENANCE EXERCISES.PPT

    14/19

    Exercise - Work Order Flow (Contd.) Retrieve the requisition in Purchasing and convert it into

    a PO

    Plan and confirm the PO

    Do arrival registration for the PO

    Raise an invoice for the PO and post the invoice. Youwould notice that the cost of the invoice gets updated as

    the actual values in WO

    Open Report In WO and retrieve your WO

    Reserve and issue the materials

    In /Time Report, report a few hours for a few employees

    Notice the changes that are happening in the /Postings

    tab

  • 7/27/2019 MAINTENANCE EXERCISES.PPT

    15/19

    Exercise - Work Order Flow (Contd.) Once all material and time reporting are over, Go to

    /General tab and fill in all the relevant data

    Authorize all the unauthorized postings

    Finish the WO and notice that it appears in the

    Historical WO. Also notice the appearance of the data in the /Cost/year

    tab of the object

  • 7/27/2019 MAINTENANCE EXERCISES.PPT

    16/19

    Exercise - Work Order Flow (Contd.) Pick up any of your round WO

    Report time and material for it

    Create a fault report for an object from here

    Authorize postings and finish the WO

  • 7/27/2019 MAINTENANCE EXERCISES.PPT

    17/19

    External Repair Process

    Register a Repair Order by creating a RepairOrder for Serial Object

    Enter the Repair Workshop as REPAIR-WORKSHOP

    Select the Work Type that belongs to externalrepair

    Move the serial into Inventory Location at the WOSite.

    Create a Service Purchase Requisition (No PartOrder Lines with Purchase Group for ExternalRepair Maintenance)

    Release the PR and convert it into PO

  • 7/27/2019 MAINTENANCE EXERCISES.PPT

    18/19

    External Repair Process

    Send the material to the supplier throughGate Pass by registering a RMGP

    Send the material by Gate Out

    Once the material is repaired, return thematerial back to Inventory

    Issue the material in the WO

    Complete the Purchasing process

    Place the Serial back in the EquipmentStructure

    Finish the Work order process

    E i R i W k O d Fl

  • 7/27/2019 MAINTENANCE EXERCISES.PPT

    19/19

    ExerciseRepair Work Order Flow

    (Contd.) Create a fault report & WO for your functional motor

    with spare part requirement as your serial motor.

    Report the WO by issuing a motor of a different serial

    no. from the inventory and place the serial object under

    the functional motor. Notice in the graphical object structure that the new

    motor is included in the equipment structure

    Create a new object RWSX - repair workshop

    Create a repair WO for your older serial motor and

    move it to the RWSX. Prepare and report the WO and

    move the serial object to inventory. Notice the change in

    the position of the serial object