Make to Stock
Creation of production order CO01
Click on enter
Maintain quantity
Start date
End date
Click on release
Schedule order
![Page 2: Make to stock po](https://reader036.vdocument.in/reader036/viewer/2022070518/58d19cc41a28ab6f6b8b505f/html5/thumbnails/2.jpg)
Make to Stock
Save
Issue the material to PO
T.code MIGO
Give the order no.
![Page 3: Make to stock po](https://reader036.vdocument.in/reader036/viewer/2022070518/58d19cc41a28ab6f6b8b505f/html5/thumbnails/3.jpg)
Make to Stock
Click on check and
Post
t.code co02
Enter
![Page 4: Make to stock po](https://reader036.vdocument.in/reader036/viewer/2022070518/58d19cc41a28ab6f6b8b505f/html5/thumbnails/4.jpg)
Make to Stock
From menu bar click select goto – costs—analysis
Activity confirmation T.code CO11N
![Page 5: Make to stock po](https://reader036.vdocument.in/reader036/viewer/2022070518/58d19cc41a28ab6f6b8b505f/html5/thumbnails/5.jpg)
Make to Stock
Give order no click enter
![Page 6: Make to stock po](https://reader036.vdocument.in/reader036/viewer/2022070518/58d19cc41a28ab6f6b8b505f/html5/thumbnails/6.jpg)
Make to Stock
Maintain yield Quantity
Machine hours
Labour hours
Save
Observe production order cost
T.code:CO03
Give po order
Click enter
![Page 7: Make to stock po](https://reader036.vdocument.in/reader036/viewer/2022070518/58d19cc41a28ab6f6b8b505f/html5/thumbnails/7.jpg)
Make to Stock
From menu bar select goto – costs – analysis
Activity cost loaded on PO
Calculation of WIP
T.code KKAX
![Page 8: Make to stock po](https://reader036.vdocument.in/reader036/viewer/2022070518/58d19cc41a28ab6f6b8b505f/html5/thumbnails/8.jpg)
Make to Stock
Click enter
Compare WIP balance with Production order total actual cost
Balance is match than select back arrow
Remove test run and execute
![Page 9: Make to stock po](https://reader036.vdocument.in/reader036/viewer/2022070518/58d19cc41a28ab6f6b8b505f/html5/thumbnails/9.jpg)
Make to Stock
Partial GR from production order
t.code MIGO
Give Production order no
Execute
![Page 10: Make to stock po](https://reader036.vdocument.in/reader036/viewer/2022070518/58d19cc41a28ab6f6b8b505f/html5/thumbnails/10.jpg)
Make to Stock
Give the quantity 5
Check and save
T.code:CO03
Give po order
Click enter
From menu bar select goto – costs – analysis
![Page 11: Make to stock po](https://reader036.vdocument.in/reader036/viewer/2022070518/58d19cc41a28ab6f6b8b505f/html5/thumbnails/11.jpg)
Make to Stock
GR happened with planned value
Complete GR from production order (remaining 5 pc)
t.code MIGO
Give Production order no
Execute
![Page 12: Make to stock po](https://reader036.vdocument.in/reader036/viewer/2022070518/58d19cc41a28ab6f6b8b505f/html5/thumbnails/12.jpg)
Make to Stock
Check and save
Observe production order cost
T.code:CO03
Give po order
Click enter
From menu bar select goto – costs – analysis
![Page 13: Make to stock po](https://reader036.vdocument.in/reader036/viewer/2022070518/58d19cc41a28ab6f6b8b505f/html5/thumbnails/13.jpg)
Make to Stock
To make production order technically complete (TECO)
Path0: Logistics –Production –shop floor control –Order –Change (T-code is CO02)
Give the order no.800046
Enter
From the menu select Functions –Restrict processing –Technically complete
Save
Calculation of variance ERROR In Variance Calculation
Path :Accounting –Controlling-Product cost controlling –Cost object controlling –Product cost by order - period ending closing –single functions- Variances –Individual processing (T-code is KKS2)
Give the order no.800046
Select execute button
![Page 14: Make to stock po](https://reader036.vdocument.in/reader036/viewer/2022070518/58d19cc41a28ab6f6b8b505f/html5/thumbnails/14.jpg)
Make to Stock
Select back arrow
Deselect test run check box
Execute
Double click on variance amount
Variance not calculated
![Page 15: Make to stock po](https://reader036.vdocument.in/reader036/viewer/2022070518/58d19cc41a28ab6f6b8b505f/html5/thumbnails/15.jpg)
Make to Stock