mammoet world 12
DESCRIPTION
Mammoet helps clients improve construction efficiency and optimize the uptime of plants and installations. For that purpose, we provide solutions for lifting, transporting, installing and decommissioning large and heavy structures. Our services are focused on the petrochemical and mining industries, civil engineering, power generation and offshore projects. The logistic challenges in these industries are growing daily. Factors such as remote locations, harsh climates and a strong emphasis on the environment are constantly driving us towards smarter and safer solutions. In this publication you can read how.TRANSCRIPT
Mammoet World12
How do you add value in markets where customers are faced with mounting challenges?
Find out on page 22.
Worldwide specialists
in heavy lifting and transport
Salvagepage 38
Powerpage 16
Offshorepage 24
Petrochemicalpage 6
Mining & Metalspage 12
Civil page 32
New Generation PTC at work for QUIP in Brazil
QUIP is currently building two large FPSOs for Petrobras, Brazil’s leading oil and gas
company. The PTC is being used to install components weighing as much as 1,700 tons
on the FPSO hulls. Because of its flexibility and efficiency, the new generation PTC is the
perfect crane for this sort of project.
2 3
Corporate Marketing & Communication
This magazine is a publication of
Mammoet Holding B.V., Corporate
Marketing & Communication Department,
P.O. Box 10000, 3505 AA Utrecht,
The Netherlands.
E-mail: [email protected]
Text & photography: Mammoet
Employees, Clients, Andrew Walkinshaw,
Chris Hoefsmit, Ads&Strats, TechTrans,
The English Center
Layout & printing: Badoux BV,
Houten - The Netherlands
Copyright: Text and photos may only be
reproduced with permission from the
Corporate Marketing & Communication
Department of Mammoet Holding B.V.
www.mammoet.com © 2013
“Building
collaborative
relationships with
clients.”
Last year, Mammoet professionals traveled the world, sailed several oceans,
and worked in far-flung locations. Meanwhile, closer to home, we created new
collaborative structures to ensure that our clients always receive optimal
solutions. In this edition of the World, we’d like to share our vision.
Expertise and Imagination
Introduction from The Board
Moving a Caterpillar front-end loader in South Africa
Mammoet moved a Caterpillar
994H front-end loader from
Middelburg SA to a mine, a 30-
kilometer route.
Conversion factors
1 meter = 3.28 feet
1 metric ton = 0.984 long tons (UK ton)
1 metric ton = 1.102 short tons (US ton)
1 metric ton = 2205 pounds
1 foot = 0.305 meters
1 long ton = 1.016 metric tons = 2240 pounds
1 short ton = 0.907 metric tons = 2000 pounds
We begin with a simple belief: The added
value of Mammoet is actually realized in the
work of its professionals. As CEO Jan Kleijn
observes: “Our equipment base is
exceptional, but it is the expertise and
imagination of my colleagues that really
makes us extraordinary.” In the “Mammoet
moves me” article, Jan Kleijn discusses the
role of the new Solutions team in a global
market.
Sometimes, great clients make great
partners. In “Meeting the client”, Heerema
Fabrication Group COO Wim Matthijssen
explains why his company has recently
signed an exclusive long-term agreement
with Mammoet. We also interview
Matthijsen’s counterpart at Mammoet
Europe, Sander Splinter, who echoes the
idea of building collaborative relationships
with clients, saying, “by forming a team
with our customers, we reach new frontiers
together.”
In the “Sharing Innovation” interview,
Directors Maurits Croon and Pieter Jacobs
shed some light on the start of Mammoet
Solutions in 2012. This global team of
engineers and sales professionals is
responsible for delivering innovative
solutions and sharing expertise with our
clients worldwide. In the “Case of the
crane”, we learn how a Solutions dialogue
resulted in the development of our new
MTC 15 crane. Based on a modern
interpretation of an ancient design, this
innovation allows for more time & cost
efficient logistics solutions in ports with
limited facilities.
In the article “Optimizing safety
performance”, Corporate Safety Director
Koos van Tol discusses the importance of
regional and cultural awareness and the
new SHE-Q structures that were developed
over the last year. Continuous
development, decentralization and
refinement of the organizational structure
are key elements of the Mammoet plan.
Mammoet Salvage is known for “United
experience, smart solutions.” In “Thinking
outside the box”, Managing Director Fokko
Ringersma discusses the value of
engineering capacity, asset base and
“outside the box thinking” for delivering
optimal solutions for salvage and oil
industry projects.
In this issue of the World, we’ll take you
inside our “sharing innovation think-tank
meetings” and across the globe to far-flung
locations. Along the way, you will encounter
flying roofs, traveling railway stations,
underwater tunnels, cold boxes in hot
places and some big jobs in very cold
places. We hope you enjoy the journey.
Jan Kleijn
President and CEO
Erik Rave
CFO
Herman Smit
COO
Just In ’t Velt
Head of Human
Capital
LOCATION: INGLESIDE, TEXAS, USA
JOB: HEAVY LIFTING
CHALLENGE: WEIGHT OF THE LOADS
First PTC lift in
the USA
You may have read about our New
Generation PTC (Platform, Twin
Ring, Containerized) Cranes in the
previous issue of Mammoet World.
The first New Generation lift in the
USA took place when our crane
lifted a large spar section for an off-
shore structure. The PTC installed
13 of these spar sections. Other
lifts for this project ranged from 800
to 2,800 tons.
Segments
6 Petrochemical
12 Mining & Metals
16 Power
24 Offshore
32 Civil
38 Salvage
Contents
Close up
4 Message from the CEO
14 Meeting the client
22 Mammoet Solutions
30 SHE-Q
“Lifting with power and versatility:
the New Generation Cranes.”
“The combined weight of a spar section and
rigging was almost 1,200 tons.”
4 5
“ Mammoet moves me”
Message from the CEO
At the forefront“I joined Mammoet in 1997 as an engi-
neer. What most attracted me was the
Mammoet mentality, that virtually anything
is possible.” This mentality stems from the
company’s roots, established in 1807. At
this time Jan Goedkoop was one of the
first entrepreneurs to begin offering large-
scale transportation services, in the form
of a 140-ton sailing barge. Ever since
then, visionary entrepreneurs like
Goedkoop have led the companies from
which present-day Mammoet has
emerged. Kleijn: “Goedkoop foresaw the
ever-growing need for transportation ser-
vices in an expanding and industrializing
society, and he set the tone for a compa-
ny that’s always been at the forefront of
market developments. The motto of one
of Mammoet’s former owners was:
‘Challenges, be welcome.’ This has
become ingrained in our DNA.”
Soon after Kleijn was hired, he would
encounter this mentality first-hand while
working on one of the most challenging
and renowned projects in Mammoet his-
tory: salvaging the Kursk. This Russian
submarine, powered by two nuclear reac-
tors, had sunk in the Barents Sea on
August 12th, 2000, following an explo-
sion. Mammoet took on the job, which
required innovation along with meticulous
planning and execution, all in difficult and
unpredictable conditions. Kleijn: “What
really struck me throughout the entire pro-
ject was how everyone on the Mammoet
team was absolutely convinced that we
would succeed. In spite of the risks and
unforeseen obstacles, that common belief
was always present. Since then I’ve
worked on many projects throughout the
world, and I’ve learned that what hap-
pened on the Kursk project is typical of
the Mammoet approach to work. We
always find solutions, no matter the situa-
tion. The combination of imagination and
expertise always gets us there, without
making any concessions for safety. It’s a
great privilege to work with so many tal-
ented professionals – both with my col-
leagues at Mammoet and with our clients
worldwide.”
Expertise and imaginationKleijn shares this passion with many long-
term members of the Mammoet team. But
the direction in which this passion drives
Mammoet is changing. “For our clients,
the exploration of energy resources and
raw materials is more difficult than ever. In
the construction and process industries,
projects are now being completed on ever
larger scales and are constantly growing
in complexity. To solve these challenges,
our clients need smart solutions that min-
imize downtime, optimize costs of owner-
ship and guarantee safety. They must,
therefore, rely more on technology and
innovation. Our equipment base, the larg-
est and most advanced available, enables
us to realize such solutions. But it is the
expertise and imagination of the
Mammoet people that makes it possible
for us to find these solutions.”
Global presence based on local strengthThis change in focus has led to changes
in Mammoet’s corporate structure. For
example, Europe now functions as a
separate region with its own local man-
agement. This enables it to respond more
quickly to the needs of its European
clients, emphasizing Mammoet’s position
as a global operator with its head office in
the Netherlands. This local presence gives
greater responsibility to regional manage-
ment, allowing them to respond to local
conditions. At the same time, they benefit
from Mammoet’s global fleet, which can
be deployed anywhere at any moment.
Kleijn: “If you compare our business now
with what it was ten years ago, you’ll
notice how much stronger we’ve become
in many regions. From a strong head
office managing projects worldwide, we
have now developed into a global opera-
tor with strong hubs in the U.S., Canada,
Europe, Singapore, Australia and the
Middle East, and a growing presence in
developing regions including Africa and
South America. Mammoet is unique in this
approach, and we are grateful that our
clients recognize this fact and continue to
entrust us with more work every year.”
Solutions teamMammoet has a long tradition of
industry-leading technology with its
strong equipment base. Kleijn: “We
recognize that our equipment alone,
though unique in its scale and
capabilities, is no longer the most
important thing to our clients. It’s
how we use it that truly matters.
Our focus is on thoroughly under-
standing our clients’ processes and
challenges in order to provide the
best possible solutions. These solu-
tions require a great deal of innova-
tion in equipment and processes.
We’ve therefore combined our
expertise, knowledge and creativity
to form a global Solutions team.
Jan Kleijn was appointed CEO of Mammoet in July 2011. Like most senior
managers, he’s been with the company for a long time and is passionate
about Mammoet’s clients, professionals and equipment. In this interview, he
shares with us his passion and strategic vision: “Our equipment base is
exceptional, but it is the expertise and imagination of my colleagues that
really makes us extraordinary.”
“Our focus is on
thoroughly
understanding
our clients’ processes
and challenges
in order to provide
the best possible
solutions.”
“ It’s a great privilege to work with so many talented
professionals – both with my colleagues at Mammoet
and with our clients worldwide.”
This team is now responsible for
devising and implementing new,
smart solutions. We are increasingly
focused on adding value through
time savings, improved safety and
cost efficiency. Large modular con-
struction projects, in mining, oil &
gas and power industries, provide
excellent examples. We work with
our clients from the very start to
help them design and build modules
which can be transported around the
globe and installed in the most cost-
efficient way, without the need for a large
workforce at the installation site. One
example is the gantry system we provided
to a yard in Brazil, allowing them to install
the huge deck box of a semi-submersible
platform on its hull. This solution allowed
the client to build the two halves at the
same time and avoid the need for special
barges, saving both time and money.”
At the conclusion of the interview, Kleijn
reiterated how he feels about his work:
“Like all of my 5,000 colleagues, I am at
the service of Mammoet. But Mammoet
feels like our business, like an extension
of our lives. When I go out on my moun-
tain bike, I put on a Mammoet T-shirt.
When I do jobs around the house, I
wear Mammoet safety gear. It’s a
characteristic that many of my
Mammoet colleagues share: we
eat, drink and sleep Mammoet, a
demonstration of the pride and
passion that makes this a wonderful
company to work for. Few people
realize just how essential this is to
our brand.”
LOCATION: USA AND CANADA
JOB: MODULE TRANSPORT
CHALLENGE: NUMBER OF LOADS
6 7
Petrochemical
North American long haul
In remote locations, modular construction is
often an ideal solution offering both time
and cost efficiency. In this case, our client
was building a large oil facility in a remote
location in Canada and had therefore
selected a modular construction method.
Starting in the US port of Lewiston, Idaho,
Mammoet transported more than 300
modular units overland to Fort McMurray in
Alberta - a journey of about 2,000
kilometers. Although poor weather and
rough terrain presented some difficulties, the
project was completed safely and efficiently.
“ Modular construction was well suited for this remote location.”
LOCATION: KROTZ SPRINGS,
LOUISIANA, USA
JOB: INSTALLING VESSELS
CHALLENGE: WORKING IN A LIVE
PLANT
LOCATION: WILLEMSTAD, CURAÇAO
JOB: CAT CRACKER HEAD
REPLACEMENT
CHALLENGE: LIMITED SPACE
Petrochemical
Hurricane Isaac interrupts work
Crane in the Caribbean
Mammoet was asked to install several
units – including a 154-ton reformate
splitter – at a refinery in Louisiana. The
crane lifted the top of the splitter while the
bottom was supported using an SPMT
and tailing frame. Unfortunately, after
placing the first unit - the splitter - the
work had to be interrupted due to serious
weather conditions. The team had no
choice but to lower the crane boom to the
ground and leave the site because of the
approaching hurricane. After Hurricane
Isaac passed, the work was completed.
In 2011, Mammoet headed to the
Caribbean to deliver a cat cracker head
for a petrochemical refinery in Curaçao. In
2012 the team returned for the head
installation. Usually this is quite a
straightforward job but in this case the
workspace was very limited. Nonetheless,
Mammoet provided the right equipment
and the head replacement was executed
on schedule. Two and a half days later, the
rigging was removed and within another
four days, all remaining items were
reinstalled and the crane was ready. This
project is a good example of our Factory-
to-Foundation service.
“Handling the
unexpected is just
part of the job.”
“The cracker head had to be installed in a
very confined workspace.”
LOCATION: RUSSIAN FEDERATION
JOB: VESSEL INSTALLATION
CHALLENGE: SCHEDULE CHANGES
8 9
Petrochemical
Time challenges in Russia
On this project in the Russian Federation,
professionals from Mammoet Russia and
Mammoet Europe worked together to install
38 vessels at a petrochemical facility. The
variable vessel delivery schedule presented a
complex challenge, which was compounded
by an accelerated deadline request from the
client. The team efficiently managed all
aspects and completed the work one month
ahead of schedule. The tasks included, among
others, the installation of a 70-meter column
weighing 354 tons, which was installed on a
27-meter high pedestal. Also, Mammoet found
a solution for eleven heat exchangers, which
lacked suitable lifting points and required the
fabrication of special lifting beams and
saddles.
“Despite a variable
schedule, the work
was completed
early.”
LOCATION: JUBAIL, SAUDI ARABIA
JOB: TRANSPORT AND INSTALLATION
CHALLENGE: HOT WEATHER,
CROWDED SITE
LOCATION: JUBAIL, SAUDI ARABIA
JOB: HEAVY VESSEL INSTALLATION
CHALLENGE: TIGHT TOLERANCE
LOCATION: SAUDI ARABIA
JOB: TRANSPORTING COLUMNS
CHALLENGE: TIGHT TURN ON A ROAD
Petrochemical
For this petrochemical plant in Saudi Arabia, Mammoet used conventional trailers and prime
movers to transport two columns from the port to the site.
The requirements for this air
separation plant included a cold
box plus 20 other units. The largest
unit weighed 571 tons and
measured 72 x 8 x 8 meters. The
work site was crowded and
afforded little space for the
positioning of equipment, making
detailed advance planning an
important part of the process.
In Jubail, Saudi Arabia, Mammoet installed a 950-ton emergency surge bullet for a
gas plant. It was the first heavy item installation at the site. Using SPMTs provided
the most efficient solution – as compared to heavy jacking equipment - to lift the
vessel up step-by-step while simultaneously increasing the thickness of the jacking
timbers on the temporary supports and on the SPMTs. This approach proved to be
the most economical option. Finally, SPMTs were used to place the vessel on the
5.8-meter high pedestal. Notably, the position of the anchor bolts meant that the
clearance allowed just six millimeter tolerance.
“ The extensive advance
planning was invaluable.”
“ SPMTs provided
the best solution.”
“Using conventional
trailers and prime
movers.”
Transportation from port to site
Desert project in Saudi Arabia
Step-by-step
LOCATION: CHAYVO, SAKHALIN
ISLAND, RUSSIAN FEDERATION
JOB: INSTALLATION OF LARGE
MODULES
CHALLENGE: WEATHER CONDITIONS
10 11
Petrochemical
This project required the extension of an oil processing facility in the Russian Federation. For
the most efficient approach, Mammoet had designed a solution that enabled modular
construction. Mammoet handled the load-out, transport and installation of 12 oversize plant
modules, and used a ballasting system for the barges. The remote location and difficult
weather conditions were the key challenges on this job. The range of modules and road
conditions required several SPMT configurations and our utmost concentration, particularly for
the crossing of a kilometer-long bridge. This was our second project on this site, we also
helped build the original facility, in 2005 - 2006.
Modular components for Russian facility
“The most efficient approach.”
LOCATION: WHITING, INDIANA, USA
JOB: TOWER INSTALLATION
CHALLENGE: CONGESTED SITE
LOCATION: MARINA DI CARRARA, ITALY
JOB: MODULE TRANSPORT
CHALLENGE: WEIGHT AND SIZE
Petrochemical
One of Mammoet’s stateside jobs in 2012 required the installation of a sour
water stripper at a facility in Indiana. Despite the size and weight of this sort of
sour water stripper tower, the job would normally have been quite
straightforward. However, the working area was very congested and the team
had to work around tight corners and obstructions. Mammoet professionals
used SPMTs to bring the tower onto the site and fitted both rigging to the top
and a tailing unit to the bottom. A crawler crane then lifted the tower into
vertical position, after which the tailing unit was removed and the tower was
placed on its foundations.
Our Italian client built a huge module weighing 2,300 tons and measuring 27 meters high,
23 meters wide and 54 meters long for a large gas plant in Australia. Mammoet
transported it over the public roads to the local port where we loaded it onto a ship. The
module was then shipped to Australia for installation at the gas plant. This was the largest
transport ever made on Italy’s public roads.
Despite the relatively short distance - only 1,500 meters - the journey required two years
of planning due to necessary road alterations. Extensive communication with the local
authorities resulted in a route suited to Mammoet vehicles and load. The total weight
(including 144 SPMT axle lines) was 3,000 tons with a length of 60 meters, a width of 23
meters and a height of 30 meters. En route, we jacked-up the module by as much as
three meters to clear fences and other obstructions. Once in port, the module was
lowered to load it onto the heavy lift ship.
Sour water stripper in the American Midwest
The journey begins in Italy
“ This congested
site provided some
challenges.”
“ The largest transport on
Italy’s public roads.”
LOCATION: TIMMINS, ONTARIO,
CANADA
JOB: RELOCATION OF A MINING
SHOVEL
CHALLENGE: ICE AND STEEP SLOPES
LOCATION: PORT HEDLAND,
AUSTRALIA
JOB: ASSEMBLING A RECLAIMER
CHALLENGE: INNOVATIVE APPROACH
1312
Mining &
Metals
Saving months in Ontario
Australian ore reclaimer
This client operates two open pit mines located a few kilometers apart, and wished to
relocate a huge shovel from one mine to the other. Mammoet proposed a solution that
would complete the job in two weeks rather than several months. In the past, the client
had disassembled the shovel, transported the components on trucks and then
reassembled it. This process usually took months to complete. When asked to provide
a better solution, Mammoet suggested moving the whole unit on 36 axle lines of SPMTs.
The client accepted the proposal and gave us two weeks to complete the job. At each
mine site, we used gravel and crane mats to create ramps so that the shovel could drive
on and off the SPMTs. While the icy roads and steep slopes proved to be a challenge,
our experienced crews completed the job on time.
By masterminding a new approach, Mammoet was able to realize a safer and more cost
efficient installation of an ore reclaimer’s 250-ton boom at an iron ore handling port.
Normally such booms are fitted in a dual lift operation with two cranes. This time,
however, the client wanted to reduce the footprint of the operation and avoid dual lifts
for safety reasons. Mammoet’s suggestion was to rest the bucket wheel end of the boom
on SPMTs, while a crane would lift the other end. The equipment owner, equipment
manufacturer and the main contractor all approved of the approach. The SPMTs were
fitted with a large turntable, equipped with a specially designed wedge, in order to
support the boom and to accommodate the required tilt range. At the start of the
operation, we checked the weight and center of gravity of the components and made
some necessary adjustments of the rigging. After checks and adjustments, the operation
went smoothly as planned.
“ Mammoet moved
the shovel in two
weeks without
disassembling.”
“A time-saving new
approach increased
safety while
reducing
installation costs.”
LOCATION: MA’ADEN, SAUDI ARABIA
JOB: ROOF INSTALLATION
CHALLENGE: CONGESTED SITE,
SPECIAL RIGGING
LOCATION: LONG HARBOUR, NEWFOUNDLAND,
CANADA
JOB: MODULE TRANSPORT AND INSTALLATION
CHALLENGE: SCALE OF THE PROJECT
Saudi roof placement
Long haul in Long Harbour
Mammoet used a heavy crawler
crane to lift and place roofs on
four silos for this client’s large
aluminum facility in Saudi Arabia.
The silos’ roofs, which had been
assembled on the ground, each
had a diameter of 42 meters and
a weight of 235 tons. Because
the permissible deflection of the
roofs was very small, a special
rigging system was designed.
Other challenges included the
congested site and the tight
schedule.
Our client is building a large
nickel processing plant, and
Mammoet has been involved in
the project for over two years.
One of our key responsibilities is
the unloading of large plant
modules from barges and
transporting them to the site on
SPMTs. With a route of three
kilometers and slopes as high as
6%, we have now handled over
200 modules, tanks and other
pieces of equipment, sometimes
using over 300 axle lines of
SPMTs. Other Mammoet
equipment on site includes
cranes, conventional trailers,
jacks, and weighing equipment.
On average, we maintain a crew
of 55 at this site.
“We used special rigging to lift
and place the silo roofs.”
“ On average, we
maintain a crew
of 55 at this large
scale project site.”
Mining & Metals
14 15
We visited Matthijssen at Heerema
Fabrication Group’s offices in Zwijndrecht.
The adjacent yard displays impressive
fabrication halls. A large number of plat-
forms have been built here, in addition to
specialized structures such as bridges
(e.g. Erasmus Bridge Rotterdam) and steel
structures for buildings (like the head
offices of Mammoet Europe, ‘De Bolder’).
Heerema provided a sheltered construc-
tion area in Zwijndrecht where De Bolder
was constructed concurrently with its
foundations in Schiedam. Mammoet
transported the whole building to
Schiedam with a large pontoon, installing
it in a spectacular operation. The two
businesses have much in common: they
are both internationally acclaimed in their
respective fields, and they are both known
for daring projects that shift the bounda-
ries of what is considered possible.
Heerema doesn’t want to do everything
in-house, therefore it works with partners.
Why are you working with Mammoet on
the basis of an LTA rather than on a sepa-
rate contract for each project?
Matthijssen: “The advantage to working
on the basis of an LTA is that you don’t
always have to focus on the commercial
aspects of a project. First and foremost,
it’s our job to focus on the best solution
for any given project. We draw up a
“shopping list” of all the equipment we
will need and how much it will cost, so we
don’t have to waste time negotiating pric-
es. By cooperating, we gain access to
specialist expertise that we don’t have in-
house. When bidding for a new project,
we work with Mammoet during the tender
stage to see how we can best do the job.
But not all of our joint efforts are related to
projects. Currently we are studying solu-
tions for lifting platforms, which continue
to grow larger and can weigh upwards of
15,000 tons. We also recently discussed
how we could get the fabrication of a plat-
form back on schedule, despite a delay
during the design stage. Together we con-
sider the options, based on each party’s
expertise. We can always find a solution.
Splinter: “I call this making the impossible
possible. By bringing the best people
together, you can develop the best solu-
tions. And that’s one of Mammoet’s key
objectives. We want to provide our clients
with smart solutions in order to give them
a competitive advantage. The best way to
achieve this is by working closely with the
client and by contributing expertise and
skills early on, while the client is still work-
ing on their tender. A solution can have a
major influence on the price of a project.
For example, we once jointly developed a
solution for installing lock gates in the
Panama Canal, reducing installation time
by six months.”
Are other clients also working with LTAs?
Splinter: “Yes, particularly with mainte-
nance projects for some of the world’s
largest companies, where the barrier to
entry is high. These clients appreciate that
we’re familiar with their sites and proce-
dures, and that our people know exactly
what to do on their sites. Companies that
place importance on these factors won’t
put every project out to tender. Mammoet
aims to excel in these areas, so we always
become intimately familiar with our cli-
ent’s culture, providing good service over
a long period of time. It’s a well-known
fact that a client who opts for the lowest
hourly rate won’t necessarily get the best
deal overall. The total cost of the project
also depends on how long the work takes,
and to what extent you can optimize the
client’s processes. This is where our smart
solutions have a real impact on signifi-
cantly reducing the overall project cost
and, ultimately, the total cost of owner-
ship. That’s how Mammoet provides
added value.”
Matthijssen: “That’s right. It’s not just
about the price, it’s about the package.
We want Mammoet to work with us to
develop optimal solutions, to consider
savings in certain key areas, and to
achieve better results by doing things dif-
ferently. We are constantly thinking about
how we can deliver the highest added
value to our clients, and we expect our
partners to do the same. This form
of cooperation also eliminates a
certain amount of work for us. In
the past we handled routine opera-
tions and standard load-outs our-
selves. We organized everything
from A to Z. We now have a regular
partner for that. We keep an eye on
the work, but we no longer design
and manage everything in-house.
Instead we leave that to Mammoet.
We know each other well by now,
and we trust each other’s expertise.
Our coordination is ongoing and
ever-evolving; we are always com-
ing up with new developments and
designs, so we must always con-
front the newest challenges. We
discuss these challenges and we
find the best possible solution.”
Splinter: “Yes, we always find a
solution. As Matthijssen mentioned,
we don’t only work together on
high-end projects, but also on rou-
tine jobs. As a partner you can opti-
mize the work-flow, because you
Heerema Fabrication Group specializes in the engineering and fabrication of
large and complex structures, mainly for offshore oil & gas and energy related
industries. Heerema has been working with Mammoet for decades, delivering
lifting and transport operations at their yards in Zwijndrecht and Vlissingen
(NL) and in Hartlepool (UK). Previously every project went out to tender, but
today the company prefers to work on the basis of an exclusive Long-Term
Agreement (LTA). Wim Matthijssen, Heerema’s COO, told us more about this
cooperative way of doing business in a dual interview with his professional
counterpart, Managing Director Europe, Sander Splinter.
“A partnership based on inspiration and challenge”
Meeting the client: Heerema Fabrication Group
Sander Splinter
are familiar with the rules and pro-
cedures on a site. We also share
the same safety standards.
Agreement in this area of coopera-
tion is essential, as different
approaches simply don’t work
when it comes to safety.”
Matthijssen: “Another key element
is the exchange of know-how and
complementing each other. We
both have a certain knowledge and
expertise, and we’re happy to share
these with one another. You know
more about lifting than we do, so
we can learn from you. Mammoet
also gains experience from their
other projects, and we discuss our
findings together. Both parties
benefit from that kind of coopera-
tion. It’s crucial we keep challeng-
ing and inspiring each other to stay
focused on the big issues.
Ultimately, the most important thing
is to achieve our shared objectives.
We have to complement each other
and be able to offer one another
worthwhile expertise. The relationship has
to provide us with more than just another
supplier, otherwise it has no point.”
You mentioned shifting boundaries. Could
you give some key developments in the
market?
Matthijssen: “One example is that plat-
forms are getting bigger, especially in the
wind power industry. In fact, they’re get-
ting much bigger, meaning we need to
think about how we’ll build them in the
future. Are we going to continue using
single platforms, or divide them into
sections? Will the modules become so
large that you can’t install them with the
available heavy lift vessels, and have to
use float-overs instead? Or modules
assembled at sea? There’s a whole range
of potential solutions. We are currently
studying them together with Mammoet.”
Splinter: “Of course we are always devel-
oping new methods. We have often mated
platform sections onshore, and are now
quite familiar with the technique. But off-
shore mating is new to us. In Brazil, we
recently did a semi-offshore mating of a
deck weighing 16,000 tons. We lifted the
deck up in a dry dock, the base was float-
ed over, and we lowered the deck. That
was another step forward.”
Returning to entrepreneurship and innova-
tion, it seems you broadly share the same
background.
Splinter: “If you look back at the roots of
our businesses, you can see there has
been quite a lot of synergy because of our
shared experience. Here’s a princi-
ple I cherish deeply: deliver what
you promise. By sticking to this, we
have been able to build relation-
ships with our clients based on
trust and mutual respect. By form-
ing a team with our customers, we
reach new frontiers together.
Wim Matthijssen
“We want Mammoet to work with us to develop optimal solutions, to consider savings in certain
key areas, and to achieve better results by doing things differently.”
LOCATION: CHOOZ, FRANCE
JOB: SPECIALIST HEAVY LIFTING
CHALLENGE: CONFINED, RADIOACTIVE
ENVIRONMENT
16 17
Power
One of the reactors at this nuclear site in the north of France is being decommissioned. As
it was an early prototype for this sort of facility, there was little consideration in the original
design regarding eventual decommissioning. Notably, this reactor is housed in an unusual
location - a cavern in a hill - and it’s also the first pressurized water reactor in France to be
decommissioned. Mammoet was contracted to extract four steam generators from the plant,
each weighing 120 tons. Although the loads were not particularly heavy or large by
Mammoet standards, the project was a challenge, as the limited space inside the building
required us to design a custom tilt unit and undertake extensive engineering. Given the
nature of the job, our work was scrutinized in detail by the client’s engineers and the
authorities. Our tilt unit - with four hydraulic cylinders - was suspended from the overhead
crane and gave us full control of the movement of the steam generators. These were first
lifted vertically, then tilted to a horizontal position, and then moved sideways. Next, they were
moved to an initial decontamination area, after which we jacked them up and transported
them to temporary storage on SPMTs. Our project team started working on this job three
years before the actual lifts were undertaken, and greatly benefited from the nuclear industry
specialists in our engineering department.
Tailor-made solutions in a French cavern
“ We designed a custom
tilt unit with four
hydraulic cylinders.”
LOCATION: JÜLICH, GERMANY
JOB: NUCLEAR REACTOR LIFT
CHALLENGE: STRICT REGULATIONS,
LIMITED SPACE
Power
This nuclear research reactor in Germany was shut down in 2006 after 44 years of operation.
Mammoet’s involvement in the decommissioning project began in 2007 and is scheduled for
completion in 2014. The task includes lifting the reactor, skidding it out of the building, and
transporting it to a storage facility. A complex lifting and skidding unit fitted with strand jacks
was built specifically for this job. Installing the two 53-ton crane girders of this unit in the
reactor building presented an interesting challenge, as there was very little operating space.
The system was tested with a 138-ton mock-up of the relevant parts of the reactor, and was
approved by the authorities and the client. Because of the delicate nature of the load,
Mammoet is working closely with the client, authorities, other contractors and the regular
inspectors for safe and efficient completion.
Seven-year relationship
“Our involvement in
this decommissioning
project began in
2007.”
LOCATION: THYBORN, DENMARK
JOB: WIND TURBINE TRANSPORT AND
INSTALLATION
CHALLENGE: NEW TURBINE DESIGN
LOCATION: ST-RÉMI, QUÉBEC, CANADA
JOB: WIND TURBINE INSTALLATION
CHALLENGE: STRONG WINDS
LOCATION: MACARTHUR, VICTORIA,
AUSTRALIA
JOB: INSTALLING 140 TURBINES
CHALLENGE: SCALE OF THE PROJECT
18 19
Power
The client developed a wind turbine with an innovative two-blade rotor using a partial
pitch system, and commissioned Mammoet to install the prototype at a test site.
Mammoet engineers devised the best lifting solution for this new model turbine in
close cooperation with the engineers of the client. The advantage of this two-blade
system is that the load on the turbine can be reduced during a storm. The job began
in the workshop, with jacking up the nacelle (220 tons, 13 x 6 x 8 meters) and then
using our SPMTs to bring it to the quay for loading onto a vessel that took it to
Thyborn, near the west coast of Jutland. In the meantime, Mammoet prepared for its
arrival by installing a heavy foundation ring, electrical containers and the turbine tower.
When the nacelle arrived in Thyborn, it was transported 300 meters to the site - again
on SPMTs - and fitted with its two blades, each 63-meters long. The overall weight of
the nacelle and rotor was 260 tons.
This Canadian wind turbine project required 15 cranes and a crew of almost 100.
Mammoet was awarded a contract for the installation of 44 large wind turbines in Saint
Rémi, Quebec. One of the main challenges was using wind-restricted lifts in an area that
is naturally windy. For this assignment, Mammoet delivered a turnkey solution that
included post-tensioning, mechanical and electrical work. A narrow track crane was used
that is specifically designed for wind turbine projects and does not demand the use of
wide site roads. This led to considerable time and cost savings.
When the installation of all 140 wind turbines has been completed, this wind farm
will be the largest in the Southern Hemisphere. Our involvement is covered by two
contracts, one with the main contractor (provision of cranes and other equipment),
and one with the turbine manufacturer (installation of the turbines). The advantage
for the clients is that they deal with just one heavy lifting contractor for the duration
of the project - leading to significant efficiency gains. The turbines, which use a new
model, have a capacity of three MW each. Mammoet installed them using a heavy
mobile crane and a special narrow track crawler crane. As explained in the previous
case, this narrow track unit helps save time and costs in wind turbine projects as
compared to the use of a conventional crawler crane.
“Specifically
designed for
wind turbine
projects.”
“ Saving time in
the Southern
Hemisphere.”
“Close cooperation
between Mammoet
and the client’s
engineers helped
us devise the best
lifting solution.”
Innovative two-blade turbine in Denmark
Forty-four Canadian turbines
Southern Hemisphere’s largest wind farm
LOCATION: RIGA, LATVIA
JOB: TRANSPORT, LIFTING AND
INSTALLATION
CHALLENGE: LACK OF PORT
FACILITIES, BRIDGE CLEARANCES
Power
Multidisciplinary power project
Our client built a gas-fired power station in Riga, Latvia and awarded Mammoet the
transport, lifting and installation contract. Because Riga’s port normally handles only bulk
cargo, we began by transforming one of their berths into a goods and RoRo quay. We
offloaded, stored and reloaded 26 Super Over Dimensional Cargo items (SODC), 126 Over
Dimensional items and over 500 general cargo items. The SODC loads had to be transported
to the other side of Riga on a special barge over the Daugava River, which took over nine
trips. The journey required us to sail under five bridges, sometimes with little clearance. At
the destination, we built a RoRo facility to drive the loads off on SPMTs, and then
transported the SODCs 12 kilometers through town.
Once at the site, Mammoet installed the gas turbine, generator and rotor with a special lifting
system. We also installed three condenser vessels and two transformers with our jacking and
skidding system, plus a generator and two turbines with the containerized winch system.
Finally, we used our heavy cranes to install 15 sizeable heat-recovery steam generator
modules and several other items.
“ Offering comprehensive solutions.”
LOCATION: CALGARY, ALBERTA,
CANADA
JOB: POWER TRAIN TRANSPORT AND
INSTALLATION
CHALLENGE: COMPLEXITY OF THE
PROJECT
LOCATION: IQALUIT, NUNAVUT, CANADA
JOB: TRANSPORTING ENGINES
CHALLENGE: ICEBERGS, NO PORT
20 21
Power
The client was responsible for the construction of a large new power station in Calgary,
Canada. They arranged to have two gas turbines (333 tons each) and three generators
(255–298 tons) shipped to Duluth, Minnesota, in the USA. The cargo was then offloaded onto
our SPMTs, moved to the rail yard and transferred onto specialized railcars for the journey
to Calgary.
In Calgary, we offloaded the cargo, transported it to the site and then installed it. In addition,
we installed 36 heat-recovery steam generators, steam drums, a 500-ton condenser unit,
and other heavy items. We used a range of gantries, strand jacks and hydraulic jacks. For
this international project, a dedicated team of Mammoet professionals from Canada and the
USA was utilized.
Nunavut is Canada’s newest, largest and
least densely populated territory. This arctic
region has no roads linking it to the rest of
Canada and is only accessible by air and
water. Mammoet Canada Eastern was
contracted to deliver two diesel engines to
Iqaluit (Place of Many Fish), which is the
rapidly growing capital of the territory. Harsh
weather, icebergs and the lack of a port made
this job quite challenging. The engines were
transferred from the ship onto a barge that
was towed close to the shore. Once the
12-meter tide had beached the barge, there
was a small window of time in which to set up
our ramps and drive the engines off the barge
on our SPMTs. The route to the power station
was challenging, including some steep
inclines. Additionally, the power company had
to lift some power cables to enable us to
pass underneath. As a result of the two new
5MW units, our client was able to double its
capacity.
North American power plant
Power in the far north
“A dedicated team
of Mammoet
professionals from
Canada and the
USA worked
together.”
“ Harsh weather,
icebergs and the
lack of a port made
this Arctic job quite
challenging.”
LOCATION: SELLAFIELD, UK
JOB: MODULAR CONSTRUCTION
CHALLENGE: SPECIAL SITE
CONSTRAINTS, SMALL CLEARANCES
Power
For reasons of time efficiency, Evaporator D at the
Sellafield site in the UK is being built using modu-
lar construction. The main contractor pours most
of the concrete structure for the entire building,
Mammoet inserts the modules, and then the con-
tractor pours the last wall. Most of the ten mod-
ules weigh 100-480 tons and measure about 10
meters high, 7.5 meters wide and almost 10
meters long. The main contractor wanted to avoid
the use of conventional cranes due to the special
nature of the site and the surrounding structures.
Therefore, Mammoet undertook a feasibility study
for an alternative method, and our solution won
the contract. Most of the modules were installed
in 2012, and the project will be completed in 2013.
For this project, we developed a dedicated strand
jack gantry (34 meters high, 38 meters long and
18 meters wide), which moves between the build-
ing sections on skids.
The modules are built at Ellesmere Port, then
transported 1.5 kilometers to the quay on our
SPMTs and loaded onto a pontoon. The pontoon
is towed to a beach near Sellafield, where the
modules are driven off on the SPMTs. We then
cross the beach, a bridge specially built for this
project, a railway, and a 10% incline in order to
arrive at a temporary storage area. The modules
are then transported to the installation site one at
a time. Once positioned under the lifting gantry,
each module is lifted off the SPMTs and placed on
the lifting table. The table lifts the module up to
the required level where it is skidded into the
building shell. To complete the installation, the
modules are lifted slightly, the skid tracks are
removed, and the modules are lowered into their
final position.
Sellafield Evaporator D project
“ Mammoet undertook a feasibility study for an alternative to conventional cranes.”
22 23
That’s the purpose of Mammoet
Solutions. This new business unit oper-
ates globally and has strong ties with all
regions. Solutions supports local
Mammoet sales staff by providing clients
with global expertise and innovative
strength. At Mammoet, we know that
when we listen carefully and offer smart
solutions, our clients benefit. At its best,
our logistical insights and smart solutions
can have a widespread positive effect,
transforming all kinds of client practices
and often, the bottom line. By optimizing
the Mammoet-client conversation, and
therefore, our performance, we can help
clients achieve significant improvements
that influence the big picture, well beyond
the boundaries of our part in the whole.
Recently, Mammoet World interviewed
two people central to the new business.
Here’s a look behind the scenes.
Mammoet Solutions Director Pieter
Jacobs studied mechanical engineering
and has worked in various roles at
Mammoet. Strategy Director Maurits
Croon is an economist and has a back-
ground in strategy and business develop-
ment.
Croon: “Essentially, we want to develop
better solutions to the challenges our
clients face as identified by our sales
teams. They engage in dialogue with our
clients to get an in-depth understanding
of their projects. So, if a client asks for a
crane which can lift X tons at a radius of Y
meters, we want to know more about the
details of the project and why they want
to move the load that way. That may
enable us to come up with a different
approach that can bring benefits in terms
of reduced overall project costs,
timesaving and risk reduction. Sometimes
a better solution requires the development
of new equipment, but significant gains
are often made by simply using a different
lifting and transport method, or by using
existing equipment in a different manner.
Obviously, it helps if we get involved in a
project at an early stage.”
Our clients are responsible for some of the world’s toughest jobs - dealing
with supersized challenges in circumstances that grow more demanding
every day. Factors such as remote locations, harsh climates and emphasis on
environmental care raise the bar. They put pressure on productivity, safety
measures and timeframes. In such situations, insightful, creative approaches
to transport and installation can significantly impact the timing, safety and
cost-efficiency of the overall project. But coming up with innovations is just
one part of the story. How do we ensure that best practices and smart
solutions are shared with clients, wherever and whenever they need them?
Sharing innovation
Nowadays, power stations and similar
plants are more and more often built at
remote locations. However, bringing
heavy components such as large diesel
Innovation in action: T
Jacobs: “Mammoet has always
been able to serve clients with
technological developments and
process innovations. Imaginative
salespeople and creative engineers
team up with clients and come up
with new approaches. A recent
project for a mining company in
Canada is a good example. The
client requested crane assistance
and trailers for disassembling a
large shovel, transporting the com-
ponents and then reassembling it at
another mine site. That was going
to take weeks. Instead of just giving
them a quote for the cranes and
trailers, our salespeople discussed
the project in greater detail. It
turned out that transporting the
shovel without disassembling it was
actually a much better solution. We
managed to engineer the project
and bring our equipment to the site
in two weeks and then only needed
four days to relocate the shovel.
That saved the client significant
downtime and avoided the risks
associated with dismantling and
assembling heavy equipment. With
Mammoet Solutions, we share our
clients’ questions with a global
team that consists of salespeople
and engineers from all regions and
backgrounds. This ensures access
to as much technical expertise and
creativity as possible, and helps us
to serve our clients with smart solu-
tions wherever they are needed.
This approach also helps us identify
engines and generators to these
sites can be difficult and costly due
to poor roads. Transport over water
is potentially more attractive, but
there is rarely a nearby harbor with
large cranes for unloading ships.
Some heavy-lift vessels do have
cranes, but such vessels are costly,
their availability is limited, and they
cannot reach small harbors.
Bringing in a crawler crane is also
unattractive, as cranes with
adequate capacity are themselves
very large and heavy and need to
be assembled using a fairly large
mobile crane. In short, conventional
methods involve significant costs
and the use of very heavy equip-
ment.
“Smart solutions
can help clients
achieve signifi cant
improvements.”
The case of the crane
trends across industries and define
our long term innovation agenda.”
Sharing expertise worldwide Mammoet Solutions has numerous
specialists in disciplines including
mechanical and electrical engineer-
ing, structural engineering, naval
architecture, offshore dynamics and
software development. Bringing
them together in one team means
that our innovative strength is now
more concentrated, more focused
and more accessible to all
Mammoet regional operations and
clients. To facilitate a good interface
between regional Mammoet
Solut ions and Sales and
Operations, we have set up regional
Solutions think-tank meetings
where representatives can regularly
exchange information with their col-
leagues. The meetings foster a cul-
ture of connectivity, enabling us to
share expertise and best practices
throughout the company and make
smart, innovative solutions readily
available to our clients.
Question: What does the client really need? Answer: The MTC 15
To help clients operating at such
remote sites, Mammoet Solutions
talked to clients, and then decided
to go back to square one and care-
fully analyze the clients’ lifting
needs. In many cases, all that’s
needed in a port is the ability to lift
a component from a ship onto a
trailer or SPMTs for further trans-
port to the construction site. In
other words, there may be no need
for all the functions provided by
heavy crawler cranes, such as
slewing (crane rotation) or the abil-
ity to move the crane once it’s on
site. This insight led to the design of
Mammoet Terminal Crane 15 (MTC 15).
Essentially, it’s a derrick crane, a form of
machinery that’s been known for at least
2000 years. It has a lifting capacity of 500
tons at a radius of 30 meters, comparable
with a 1,200-ton crawler crane (which is
much heavier, larger and costlier). The
whole crane is packed into shipping con-
tainers, which can be transported to the
site by ordinary trucks. The MTC 15 only
needs a relatively modest mobile crane for
assembly, and its ground bearing pressure
is low enough to operate close to most
quay edges with no need for civil works.
The MTC 15 is also a good solution for
projects where a crane needs to be on
site for a long time, but only needs to
make occasional lifts. This is quite com-
mon in ports serving modular construction
projects. The MTC 15 has been the right
answer for several Mammoet clients.
The development of the MTC 15 is just
one example of how adding extra value
for our clients demands dialogue, creative
thinking, internal networking and innova-
tive solutions. Having great hardware is
just part of the Mammoet story. Working
for the best interests of our clients is what
really moves us.
“Sometimes innovation means lots of dialogue…
and then going back 2000 years.”
Maurits Croon Pieter Jacobs
LOCATION: RIO GRANDE, BRAZIL
JOB: DECK LIFT
CHALLENGE: SIZE AND WEIGHT OF
THE LOAD
24 25
OffshoreOffshore
Seventeen thousand tons in Brazil
The P-55 is Brazil’s largest semi-submersi-
ble offshore platform. It has been built in
two parts: the deck box and the lower hull.
For lifting and installing the huge deck box,
Mammoet engineered, built and installed a
special lifting system – which requires 160
containers for transportation.
The P-55 deck box was constructed inside
a dry dock on five meter high temporary
supports. Mammoet erected the Mammoet
Gantry System on two sides of the dock.
The system included 12 lifting towers (MSG
and PTC crane mast sections), six gantry
beams (each 23 meters long and 2.5
meters high), and 24 strand jacks, each
with a capacity of 900 tons. The lifting
started by weighing the deck box, which
set a record for our gantry system – 17,000
tons. The lifting system was then subjected
to a 110% load test, after which the deck
box was raised to an intermediate level,
just above the dry dock. With the box at
this level, the client prepared the dock
blocks to receive the lower hull. The dry
dock was then flooded and the doors
opened. This meant that our gantry towers
were partly under water. Next, the lower
hull of the offshore platform was towed into
the dock. Following that, it was time to lift
the deck box to its top level, 47.2 meters.
The next day, the lower hull was towed
underneath the deck box and positioned.
After that, we slowly lowered the deck box
to mate it with the lower hull, leaving the
whole structure sitting on the dock blocks.
Finally, the two modules were installed on
top of the P-55 platform. The installation of
these modules involved transport, lifting
using a gantry system, skidding, and jack-
ing operations.
“To lift and install the massive offshore platform
deck box, we built a special lifting system.”
LOCATION: HAMRIYAH FREE ZONE, UAE
JOB: VESSEL LOAD-OUT
CHALLENGE: COMPLEX LOAD
INTERACTION
Offshore
Dynamic loads
“The client built an 8,500-ton jack-up vessel and
contracted Mammoet to load it onto the barge.”
In the UAE, one of our clients built an 8,500-ton jack-up vessel for wind turbine
installation operations and contracted Mammoet to load it onto a barge. The client
tested the new jack-up system while the unit was still on our SPMTs and trailers. The first
operation was a sideways load-out with several space restrictions for the SPMTs and
trailers and little allowance for weight or center-of-gravity changes. Next, the vessel’s
legs were jacked down while it was still on our SPMTs and trailers and on the barge. Four
sets of dynamic loads had to be considered, affecting the floating barge, our SPMTs and
trailers, the vessel’s legs, and the tide. Mammoet’s engineering department assessed all
the relevant forces and successfully planned the operation in detail.
LOCATION: VUNG TAU, VIETNAM
JOB: PLATFORM PUSH-UP AND
LOAD-OUT
CHALLENGE: LATE DESIGN CHANGES,
ASYMMETRIC CENTRE OF GRAVITY
26 27
OffshoreOffshore
Offshore in VietnamFor this project in Vung Tau, Mammoet
undertook a major push-up operation and
two load-outs. The yard decided to build
the deck support frame and the deck itself
(approximately 12,000 tons) separately,
both at a low level, making it possible to
construct the two units in parallel.
Mammoet was contracted to push-up the
deck platform so that the frame could be
inserted underneath it. Although there were
some late design changes, close
cooperation between the client and
Mammoet ensured that all nine units of the
2,400-ton push-up system were available
on time and that the operation went
smoothly. The frame was placed under the
platform, which was then lowered down
onto it, resulting in a structure with a total
weight of 14,300 tons.
The next task was to load the resulting
large structure onto a barge. The
combination of tidal conditions and an
asymmetrical center of gravity proved to be
quite a challenge. Mammoet engineers, in
close consultation with the client, decided
to shift the center of gravity towards the
middle of the platform by installing
counterweights on one side and pumping
water and fuel to the tanks on that side.
We also loaded the platform jacket (length
145 meters, weight 11,500 tons) onto a
barge, which required us to pull it across
250 meters using four of our 900-ton strand
jacks. In addition, we provided ballasting
systems (30 pumps with capacities of 500
m3/h and 1000 m3/h) for the barges, and
lastly, we handled the mooring of the
barges.
LOCATION: LAEM CHABANG, THAILAND
AND HAUGESUND, NORWAY
JOB: OFFSHORE MODULE HANDLING
CHALLENGE: HEAVY RAIN, SIZE OF THE
LOAD, SITE LAYOUT
28 29
OffshoreOffshore
Offshore platform module construction in two countries
“Serving the client
through dedicated
collaboration.”
The client, who operates yards in Norway
and Thailand, was building offshore oil and
gas platform modules in both locations.
The upper module (living quarters) was
being built in Thailand and the lower
module was being built in Norway.
Mammoet began in Thailand, weighing the
living quarters module using our jacks and
load cells, and then updated our plans with
the verified weight and center of gravity. We
then loaded the module out onto a vessel
using SPMTs for transport to the yard in
Norway.
At the yard in Norway, we had to combine
the lower platform module with the upper
platform module (including the living
quarters). Again, we first weighed the lower
module using load cells and jacks, and we
then used our SPMTs to move it out of the
assembly hall and set it down on the
quayside. Once the barge with the upper
module arrived, we fitted it with our
ballasting system and then moved the
upper module onto the quay with SPMTs.
The upper module was fitted with rigging
so it could be lifted by our two heavy
crawler cranes and placed on the lower
module. The next step was to move the
combined structure back into the hall,
though now only part of it fit into the
building. Given the site layout, this took
some careful maneuvering with our SPMTs.
Fortunately, our crews and those of the
client benefited from particularly good
weather. Mammoet will return to the site
later to load the completed platform,
weighing 11,600 tons, onto a barge.
LOCATION: MARAGOGIPE, BRAZIL
JOB: LOAD-OUT, LEG INSTALLATION
CHALLENGE: SIZE AND WEIGHT OF THE
LOADS
LOCATION: NEWFOUNDLAND AND
LABRADOR, CANADA
JOB: HEAVY PIPE REEL HANDLING
CHALLENGE: SIX WEEKS TO RELOCATE
AND BUILD A PTC
Offshore
Brazilian big rigs
Saving time on Canadian FPSO
“Two jacks on each
bundle increased
the pulling speed
and reliability of the
system.”
“ The client wanted an
approach to improve
safety while saving time.”
This Mammoet Brazil project
required the loading out of two
jack-up platforms and their canti-
levers. Each rig weighed approxi-
mately 7,000 tons, and the canti-
levers weighed 1,500 tons. We
used two strand bundles and four
strand jacks of 900-ton capacity.
Having two jacks on each bundle
increased the pulling speed and
reliability of the system. After the
load-outs, our CC-6800 crane
helped assemble the 145-meter
high platform legs. It was config-
ured with a 96-meter main boom
and 72-meter jib.
This project required the replacement of
flow lines and risers of an FPSO (Floating
Production, Storage and Offloading unit).
In the past, the client had used crawler
cranes and transporters for such
operations. This time, they wanted an
approach to improve safety while saving
time. Mammoet offered a solution
involving our unique PTC crane, as it
could perform all lifting and handling
operations required. Given its size and
reach, it would not have to be relocated
between lifts and eliminated the need for
other handling equipment. The client
accepted our proposal, but allowed us a
lead time of just six weeks. In that period,
Mammoet shipped a PTC from India and
assembled it on the job site.
In total, the job represented several
kilometers of pipeline. The harsh climate in
the area meant there was an ice-free
window of only five months. The pipes
were delivered on 42 reels with diameters
of ten meters and weights of 160 to 280
tons. The scope of the project was to
offload the reels from the heavy lift vessel
which delivered them, store them on a
quay, load them onto the pipe-laying
vessels, and eventually load the empty
reels back onto the heavy lift vessel.
This is now the client’s preferred method
for projects of this nature.
WE CARE!
LOOK OUT!
KEEP THINKING!
30 31
Corporate SHE-Q Director Koos van Tol
explains: “Having worldwide operations
means that we have to recognize cultural
differences; you can’t work the same way
everywhere. We have to delegate respon-
sibility and promote flexibility, while still
ensuring that a coordinated approach is
followed worldwide. We’re developing a
new corporate structure to accommodate
that.”
He continues: “Just like our clients, we
are well aware of the basics of SHE-Q, the
hardware, the skills and procedures.
We’re now focusing on our own behavior,
both on an individual and on a team level.
A team of consultants has assessed our
professional culture worldwide, and
following this assessment, each region
has selected two issues to focus on. The
consultants are also helping four regions
foster leadership development programs
for middle management, which will soon
be rolled out throughout Mammoet world-
wide. We want our people to grow, espe-
cially our operational personnel, becom-
ing more aware of what they’re doing and
becoming even better at assessing the
diverse situations that they work in. Most
of all, we want our personnel to stay
sharp and think for themselves. It’s never
enough to simply follow procedures. All of
this ties in perfectly with our new, decen-
tralized SHE-Q structure.”
To ensure that SHE-Q is firmly embedded
throughout Mammoet, everyone attends
safety instruction sessions, including
senior management and office personnel.
Safety toolbox meetings are held at the
head office every other week, just as they
are on the shop floor.
New SHE-Q structureThe new SHE-Q structure was developed
in central and regional management meet-
ings over the past year. We considered
input from our developing business
regions especially important, as these
regions will soon be gaining greater
independence. Quality, safety, health and
environmental protection will be embed-
ded even more firmly within all of our
global processes. Mammoet has an ambi-
tious SHE-Q agenda; Van Tol mentions
several of the many initiatives: “A number
of Mammoet businesses have already
been certified to ISO 9001 (quality
management), ISO 14001 (environmental
management) and OHSAS 18001 (safety
management). Other Mammoet business-
es will quickly follow suit. We are continu-
ously improving our risk management and
updating our Corporate Safety
Requirements. The Safety, Health &
Incident Management System (SHIMS),
introduced in 2011, was updated in 2012
and provides us with invaluable manage-
ment information. It also ensures effective
communication between all parties
involved in the case of a serious incident.
Additionally, a Corporate Quality Manager
has now been appointed and is develop-
ing an action plan. The Training and
Development Program (T&DP) is being
updated and aligned with the new SHE-Q
structure. T&DP coordinators will be
appointed in all regions, with the coordi-
nator in Singapore acting as the global
head for T&DP. We want to give each
region greater autonomy, while still ensur-
ing global coordination.”
Working with clients and other contractorsMammoet works with clients from many
different industries and cultures, often on
projects involving multiple contractors.
Van Tol: “We promote effective safety
practices rather than just concentrating
on paperwork. This is particularly impor-
tant when working in a multiparty setting.
Our people and our organization have
been trained to be highly flexible, and to
adapt quickly to the many working envi-
ronments and approaches to SHE-Q that
they will encounter on the job.”
STOP
RISKS?
Take the Mammoet Minute, daily!
Continuous development, decentralization and refining the organizational
structure: these are key elements of Mammoet’s plan to optimize performance
and deliver greater added value to our clients. These elements also drive our
Safety, Health, Environment and Quality (SHE-Q) efforts.
Optimizing safety performanceKoos van Tol, Corporate SHE-Q Director
“ We aim at
continuous
personal
growth.”
1 2 3 4 5 6
STOP BEFORE YOU START YOUR TASK.
THINK CAREFULLY ABOUT THE TASK AND THE RISKS.
LOOK AROUND, ARE THERE ANY HAZARDS?
ASSESS THE RISKS.
TAKE ACTION: ISOLATE AND CONTROL THE RISKS
SAFELY START YOUR TASK!
LOCATION: ST PAUL, MINNESOTA, USA
JOB: INSTALLING BRIDGE SPANS
CHALLENGE: SLOPE, TIGHT
TOLERANCES
32 33
Civil
The Maryland Avenue Bridge, which crosses over a major road in St. Paul, Minnesota, had
to be replaced. In the past, the client had used conventional construction methods that
required prolonged road closures. This time, the client decided to have the two new bridge
spans (each approximately 40 x 30 meters and 1,200 tons) built on an adjacent site. Once
the old bridge had been demolished, Mammoet used two sets of SPMTs (with a total of 88
axle lines) equipped with jacks to transport the new spans and position them on the site. The
first part of the trip was the most difficult, as we had to negotiate a 9% incline ramp. To
ensure correct alignment of the dowels of each span, the units had to be installed within tight
tolerances. Once the SPMTs had positioned the spans, they were lowered onto the supports
with the jacks. The operation was completed within 12 hours, as requested by the client. The
local residents were pleased with the reduction in area disruption and the minimized bridge
closure time.
Minimizing closure time on a US bridge replacement
“ The operation was
completed within
12 hours.”
LOCATION: LONDON, UK
JOB: TBM TRANSPORT
CHALLENGE: SIZE, HEIGHT
CONSTRAINTS
LOCATION: ALBERTA, CANADA
JOB: RELOCATING A TRAIN STATION
CHALLENGE: SIZE OF THE LOAD
CivilCivil
Crossrail is a major railway expansion project that requires 21 kilometers of twin bore tunnels
under central London, UK. Mammoet provided cranes for the assembly of two 1,000-ton
Tunnel Boring Machines (TBM). Later, we provided SPMTs and other equipment to move
them from the assembly yard to the tunnel portal. The units included a 160-meter long
conveyor system which was transported with the TBMs in one piece. Mammoet also jacked
a pedestrian bridge up several meters to provide clearance for the passage of the TBMs and
SPMTs. Due to height constraints in the tunnel portal (in some places, as little as
20-millimeter clearance), a skidding system was used for the final 150 meters.
The Beiseker Railway Museum (near
Calgary, Alberta, Canada)
purchased the disused 100-year-old
train station of the town of Bassano,
155 kilometers away. The station
weighed around 165 tons and was
51 meters long. The project started
by jacking-up the station up and
placing beams underneath it. We
then transported it to the museum
on conventional trailers. A spokes-
person from the museum comment-
ed, “I just can’t say enough good
things about the crew and their pro-
fessionalism; they were well pre-
pared and executed the entire move
seemingly without a worry.”
Crossrail TBMs for a major railway expansion
A train station goes for a scenic drive
“ Working with
1,000 tons and just
20-millimeters
clearance.”
“ Finding a new home for a
100-year old train station.”
LOCATION: SCHIEDAM,
THE NETHERLANDS
JOB: OFFLOADING BARGE HULLS
CHALLENGE: SPECIAL RIGGING
34 35
Civil
A Dutch shipyard bought 18 large hulls in China. The hulls were stacked 4-high on two
barges that were transported to Rotterdam by a semisubmersible vessel. The barges were
then floated off and towed to the Mammoet Heavy Lift Terminal at Schiedam, just outside
our European head office.
The hulls weighed between 400 and 1,460 tons each, with lengths of 72-135 meters.
Mammoet’s task was to individually unload the barges in a step-by-step procedure. We first
lifted a hull off the stack. Secondly, we ballasted the barge and moved it out of the way.
Thirdly, we lowered the hull into the water and moved it to a mooring. Lastly, we returned the
barge to the quayside to allow the cranes to lift the next hull. One crane stayed in place while
the other one moved along the quay, depending on the length of the hull to be lifted. Special
rigging designed to spread the loads on the hulls was used for this task.
Barge hulls in the Netherlands
LOCATION: AMSTERDAM, THE
NETHERLANDS
JOB: INSTALLING TUNNEL SECTIONS
CHALLENGE: ACCURATELY PLACING
EXTREMELY LARGE UNITS
36 37
Mammoet Maritime installed three tunnel sections for the new north-south metro route in
Amsterdam. The concrete tunnel elements were initially constructed at dock nearby, which
was then flooded in order to move the floating sections to temporary storage. Finally, the
tunnel sections were transported by four tugs and one pusher tug to the location where
they were to be installed. Each section was approximately 140 meters long, 12 meters
wide and 8 meters high.
The installation of each tunnel section began by placing foundation blocks on the riverbed
with our sheerlegs. Next, each floating tunnel section was positioned using tugs, a pusher
tug, and in one case, wire ropes and winches. The ballast tanks were then flooded with
water to submerse the tunnel section. Finally, the section’s position was carefully adjusted
with two sheerlegs to ensure that it connected flawlessly with the previously placed tunnel
section.
Amsterdam metro tunnel installation
“Adjusting with two
sheerlegs.”
Civil
LOCATION: ZUTPHEN,
THE NETHERLANDS
JOB: INSTALLING A BRIDGE
CHALLENGE: WEAK QUAY, SHALLOW
WATER
This bridge, with a length of 117 meters, a
height of 15 meters and a weight of about
1,000 tons, was built in a yard located three
kilometers away from the installation site.
The bridge would provide multiple
improvements, such as better access to an
industrial estate near Zutphen, and reduced
traffic through the town. However, the
asymmetrical design of the bridge (with a
bicycle path on one side), the weak quay
and the shallow waterways posed some
interesting challenges.
The weak quay at the construction yard
meant that Mammoet’s heavy equipment
was required to stay 11 meters from the
water’s edge. Hence, a creative solution
had to be developed in order to move the
bridge from the yard onto the barges. We
decided to use SPMTs to move the bridge
so that one end extended over the canal,
which was then supported by an auxiliary
barge. Next, the SPMTs and auxiliary barge
moved the bridge further across the canal
so that our main barges could be
positioned underneath to pick it up. We
then lifted the bridge seven meters above
the main barge deck, using our JS500
push-up system.
On the way to the installation site, canal
water depth presented another challenge.
In order to reduce the draft, Mammoet
distributed the load between three linked
barges, clearing the canal bottom by as
little as ten centimeters in some places.
Close to the installation site, four winches
were used to turn the bridge to span across
the canal, and then pull it into position.
Finally, the push-up system gently lowered
the bridge onto the abutments.
“Working with ten
centimeters
between the barge
and the bottom.”
Shallow water bridge installation
Civil
38 39
Managing Director Fokko Ringersma is
proud of his division’s success and looks
forward to its continued development.
Ringersma: “Our company is thriving, with
a growing team of dedicated
professionals. In addition to Mammoet’s
long standing network of depots, we now
have dedicated Salvage depots in
Houston, Singapore and Schiedam, and
sales offices in London and Korea. We
have a wide range of emergency response
equipment in a custom-bonded area at
Amsterdam Airport Schiphol, ready for
global dispatch at any time. A network of
subcontractors all around the world helps
support our operations. This global
presence allows us to take on both
emergency response salvage and major
wreck removal projects.”
Salvage projects Mammoet Salvage recently began work
on a wide range of projects. The largest is
the wreck removal of the B. Oceania, a
bulk carrier transporting 67,000 tons of
iron ore that sank in the busy Straits of
Malacca after a collision in 2011.
Ringersma: “The position of the ship in
the channel leading to Singapore was a
critical factor in the bid for work. The
major challenge is that other ships often
pass extremely close by. Safe navigation
requirements are therefore particularly
demanding. In addition to our working
pontoon, we have an observation post
with radar and communications equip-
ment, along with two additional ships
patrolling the area in order to warn
approaching vessels. In 2012, we made
good progress on this wreck removal
project. We recovered the cargo, the
engine room section, and the bow and
accommodation block. Now we are
clearing the double bottom sections
between the engine room and the bow.
The project is well on schedule, and we
hope to have it completed by spring 2013.
Environmental protection is an important
component of this project - we carefully
dispose of all recovered cargo and scrap
while also offsetting our carbon
emissions.” Salvage has also invested in a
customized directional drilling system,
designed by Mammoet Solutions. This is
used to place cutting and lifting chains
under the Oceania wreck.
The Mauritania ships’ graveyard project
was completed in fall 2012 with the
removal of the 74th shipwreck from
Nouadhibou Bay. Ringersma: “We
completed this project well before the
deadline. The wrecks were removed and
dismantled safely. Environmental
protection was an especially important
consideration, as we were dealing with
hazardous materials, including asbestos.
Mammoet runs its business with great
care for the local environment and
community. While working on the
project, we made generous
donations to the Nouadhibou Bay
community, among others to Enfant
du Monde, and we sponsored the
Nouadhibou Marathon two years in
a row. It’s all part of our Corporate
Social Responsibility Program.
Additionally, we improved the local
infrastructure and set up an
education program for Nouadhibou
residents. By hiring personnel
locally, we provided not only
employment, but also practical,
on-the-job training. This project will
have long-term environmental
benefits, as we have prevented
future toxic emissions from harmful
materials.”
Oil industry projects Projects involving offshore oil and
gas platforms are another important
market for Mammoet, given our
petrochemical and offshore experi-
ence and our salvage expertise. We
demonstrated our strength in this
market during our work on the Pico
lift boat, which was positioned in
near proximity to a platform in the
Gulf of Mexico. The lift boat toppled
over, and the topside of the boat
and the top end of the legs broke
Mammoet Salvage has established itself as a leading international salvage
company on the basis of “Smart solutions, united experience.” This means
thinking outside the box and having the engineering capacity and asset base
to support smart solutions. Along with wreck removal projects, this division
of Mammoet undertakes emergency response salvage and decommissioning
jobs.
Thinking outside the box
Fokko Ringersma, Managing Director Mammoet Salvage:
Salvage
24/7 Emergency response
Salvage
off, leaving the bottom leg sections
with spud cans buried in the
seabed. We had to remove these
leg sections with immense care, as
they were only meters away from a
seabed operating platform
containing live high-pressure oil
pipelines. Because of the growing
demand for these kinds of
operat ions, Mammoet has
es tab l i shed a ded icated
Decommissioning business unit as
of January 1, 2013, specialized in
removing end-of-life offshore
structures. Ringersma: “One of our
greatest strengths is that we offer
proven solutions based on united
experience. This is extremely
important when dealing with the oil
and gas industry, where safety is
the top priority.”
Emergency response salvageThe quality of our workmanship
was a decisive factor in Mammoet
Salvage’s successful bid to refloat
the Feruz ferry in Turkey. In a heavy
storm, the captain had found refuge
by grounding his vessel in the small
harbor of an “aqua park.”
Ringersma: “The Feruz is not large,
but it’s an unusual ship, a RoRo
ferry with railway tracks for train
wagons. Therefore, the ship owner
wanted immediate action so as to limit
damage to the ship. We provided
emergency response support, working
with a local diving contractor and a tug
company in our international network in
order to stabilize and inspect the vessel.
At first, this looked like a routine salvage
job, but due to the shallow water it was
difficult to pull the Feruz from the harbor
without damaging the hull. Our naval
architects developed a solid and
innovative refloating plan - that’s why the
project was awarded to us. After refloating
the vessel, we successfully towed it to a
port nearby.”
This project demonstrates the strength of
Mammoet Salvage’s international salvage
network, which enables the company to
provide rapid response support in
emergencies and to minimize further dam-
age to vessels. The advantages of having
a local presence with salvage expertise
are magnified by our global scope and
resource network. Emergency response
salvage is often followed up by complex
wreck removal operations, and Mammoet
Salvage benefits from the larger
Mammoet group’s equipment, know-how
and engineering support, delivering the
smart solut ions that are our
company’s defining strength.
+31 (0)10 204 24 45
“This global presence
allows us to take
on both emergency
response salvage and
major wreck removal
projects.”
“ Smart solutions,
united experience.”
www.mammoet.com
Please visit our website for Mammoet job opportunities and for more information
and addresses all over the world.
Mammoet
Global service, local presence
Mammoet has clients and projects in all
parts of the world. To keep the lines of
communication short and to stay abreast
of the local markets, Mammoet has
operating companies throughout Europe,
the Americas, Africa, the Middle East,
Asia and Australia. Global or highly
complex projects and global logistics are
handled centrally from our home base in
Utrecht, the Netherlands. As much as
possible everything else is handled locally.
This structure enables us to act swiftly,
effectively and cost-efficiently in your local
market, while offering the benefit of a
central knowledge and experience center
for more demanding aspects of your
project.
Worldwide specialists
in heavy lifting and transport
Mammoet helps clients improve construction effi ciency and reduce downtime of plants and installations. For that purpose,
we provide solutions for lifting, transporting, installing and decommissioning large and heavy structures.
Our services are focused on the petrochemical and mining industries, civil engineering, power generation and offshore
projects. The logistic challenges in these industries are growing daily, with factors such as remote location, harsh climate
and emphasis on environmental care raising the bar.
We help clients reduce the cost of ownership and optimize uptime of their plants and installations with the following services:
• Lifting, transportation and installation of modular constructions
• Factory-to-foundation projects
• Plant turnaround logistics
• Lifting and transportation services
• Salvage and wreck removal
• Decommissioning of on and offshore installations
• Trading in new and used equipment worldwide
Mammoet is known for the unique size and capacity of its state of the art equipment. But it is the trust of our clients that
enables 5,000 Mammoet professionals to give their best every day and truly make a difference in projects all over the world.
Offshore
Mammoet’s activities in the
offshore industry include
the accurate and safe
implementation of transport
solutions by land and by
water, load-ins and load-
outs, and the assembly of
extremely large and heavy
items. Mammoet Decom
specialises in the decom-
missioning and removal of
offshore structures such as
platforms, pipelines and
subsea templates.
Civil
Mammoet’s experiences
with multimodal transport
by road, rail and water,
along with its knowledge of
the equipment used for lift-
ing, skidding and jacking
heavy loads, ensure
Mammoet’s position as a
full-service provider in the
market for civil projects and
infrastructure works.
Salvage
Mammoet Salvage provides
worldwide salvage, emer-
gency response and wreck
removal services, at sea, in
ports and on inland water-
ways.
Mining & Metals
Mammoet’s services to the
opencast and deep mining
industry include transport-
ing and installing large
modular plants at remote
mine sites, general lifting
services and supporting
maintenance operations.
Petrochemical
Mammoet’s operations in
the petrochemical and
chemical industries largely
relate to maintenance work,
the replacement of plant
modules, complete over-
hauls and the expansion or
construction of production
sites.
Power
Mammoet has established
a formidable reputation for
itself in all parts of the
power industry, from fossil
fuel and nuclear plants to
facilities using renewable
energy sources.
Mammoet World Missing?
You can order available back issues by
sending an e-mail to
stating which issue you wish to receive,
together with your name and the address to
which the Mammoet World(s) should be sent.
Mammoet World
A long drive in South Africa. Read more about it on page 7.
As the world market for heavy lifting and heavy transport continues to grow, the loads to
be lifted are getting heavier and heavier. To meet this growth opportunity, we have
developed a New Generation of PTC Super Heavy Lift cranes, with a combination of high
lifting capacity and flexibility to set it apart from the rest of the market.
Worldwide specialists
in heavy lifting and transport
A
b
d
li11
Marinepage 40
Powerpage 14
Offshorepage 24
Petrochemicalpage 6
Miningpage 12
Civil page 32