    Companion LineKaizen Event

  • 8/9/2019 Manufacturing Kaizen

    2/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    LOT SIZE RULE

    Make One

    Move One

    Companion Line Flow

    INDIVIDUAL EFFICIENCY VS. SYSTEM EFFICIENCYINDIVIDUAL EFFICIENCY VS. SYSTEM EFFICIENCY

    We are committed to overall system efficiency rather than just the

    efficiency of individual processes. We are a TEAM!

  • 8/9/2019 Manufacturing Kaizen

    3/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    Kaizen Mandate

    Eliminate waste

    Create a more efficient layout

    Implement and sustain 5SCreate a tracking and reporting system

  • 8/9/2019 Manufacturing Kaizen

    4/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    Project Scope

    5S the work area

    Redesign the work areaFlow and flexibility

    Visual workspace, point of use tools

    Cost effective

    Define/ implement min/ max inventory levels

    Eliminate waste

    Create Communications Board with measuresDocument Non-conformance issues

    Standardize work (SOP)

  • 8/9/2019 Manufacturing Kaizen

    5/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    Kaizen DeliverablesCreating Shorter, Simpler and Smoother Processes

    Establish ground rules Create a team charter

    (scope, boundaries, expectations, deliverables, ROI)

    Develop a current state map Identify necessary data, people, resources

    Determine Metrics and Indicators

    Incorporate data and metrics into currentstate map

  • 8/9/2019 Manufacturing Kaizen

    6/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    Kaizen DeliverablesCreating Shorter, Simpler and Smoother Processes

    Create detailed future state map Perform Gap analysis

    Assign teams for immediate process changes

    Assign teams for long term system changes Implement immediate changes

    Document and quantify improvements

    Create time-lines and follow-through plans

    Prepare and present report-out

  • 8/9/2019 Manufacturing Kaizen

    7/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    Lean in Action

  • 8/9/2019 Manufacturing Kaizen

    8/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    Lean in Action

  • 8/9/2019 Manufacturing Kaizen

    9/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    Old Layout of Work Area

  • 8/9/2019 Manufacturing Kaizen

    10/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    Old Process Flow Map

  • 8/9/2019 Manufacturing Kaizen

    11/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    Original Spaghetti Diagram 1Pull Order Flow

  • 8/9/2019 Manufacturing Kaizen

    12/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    Original Spaghetti Diagram 3Companion Unit Flow

  • 8/9/2019 Manufacturing Kaizen

    13/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    Original Time and DistanceTotal Time = 2253 min

    Total Distance = 8908 ft

    Total VA Time = 690 min

    Total Steps = 54Total VA Steps = 19

  • 8/9/2019 Manufacturing Kaizen

    14/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    BEFORE Pictures

  • 8/9/2019 Manufacturing Kaizen

    15/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    BEFORE Pictures

  • 8/9/2019 Manufacturing Kaizen

    16/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    BEFORE Pictures

  • 8/9/2019 Manufacturing Kaizen

    17/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    Non-ConformanceService Calls

    2 Methods to Resolve

    Phone

    3rd party service provider @$95/hour

    Average Service Call = $800Total Companion Service Calls = 756

    Total Cost of Service Calls = $604,800

    16 Out of Box Failures

  • 8/9/2019 Manufacturing Kaizen

    18/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    Non-ConformanceCompanion PARsand Deviations

    59 PARs since March 2003

    45 Deviations in last 3 months

    Estimated cost of $100 per deviation

    Cost of deviations last 3 months = $4,500

    Companion communicator spends 8 hours per

    week sorting and tracking documentation forthe area

  • 8/9/2019 Manufacturing Kaizen

    19/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    Non-ConformanceCompanion Rework

    Time/Labor Cost

    67% of rework time is due to engineering changes25% is due to bad parts

    Cost for week of June 13, 2005 = $2,800

    Annual Cost = $145,600

    Vendor errors(vendor errors of fabricated items are generally fixed by assembly personnel and nocost is captured. Items not able to be repaired by assembly are sent to the machineshop. Samples are:

    Side panels: broken welds (30), 6 hrs, $259Stud and paint: 196 parts, 5.25 hrs, $218

  • 8/9/2019 Manufacturing Kaizen

    20/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    Non-ConformanceCompanion Rework

    Samples of items returned to vendor

    Mother board, 27 bad out of 349 (7.7%) sinceFebruary 2005

    Pump board, 97 bad out of 504 (19.2%) since

    January 2005

    Cable set D, 39 bad out of 340 (11.5%) sinceDecember 2005

    Display cable for touch screen, 82 bad out of 254(32.3%) since December 2004

  • 8/9/2019 Manufacturing Kaizen

    21/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    Non-ConformanceSummary

    We do not track nonconformance very well.

    A lot of rework is done by assembly personneland the cost is not captured. However, fromthe data we do have, it is easy to see that

    vendors are hurting the Companion assemblydepartment.

    92% of the rework is generated outside of the

    department, but it cost the department anannual average of $145,000 to fix it.

  • 8/9/2019 Manufacturing Kaizen

    22/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    New Layout and Flow of Work Area

  • 8/9/2019 Manufacturing Kaizen

    23/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    AFTER Pictures

  • 8/9/2019 Manufacturing Kaizen

    24/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    AFTER Pictures

  • 8/9/2019 Manufacturing Kaizen

    25/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    New Time and DistanceTotal Time = 822 min

    Total Distance = 190 ft

    Total VA Time = 578 min

    Total Steps = 31Total VA Steps = 7

  • 8/9/2019 Manufacturing Kaizen

    26/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    Return On InvestmentReduction of overall time by 36% (1431

    minutes)Reduced movement by 7908 feet

    Total steps reduced from 54 to 31Value added increased from 31% to 70%

    Expenditures for the event = $7,500 (see30/ 60 day action plan for details)

  • 8/9/2019 Manufacturing Kaizen

    27/27

    Lean & Six Sigma Integration Specialistswww.wyrickenterprises.com 949-461-0279

    Return On Investment

    Overall benefit is an increase in capacity torun at 4 units per day from 2.1 units per day.

    This translates to a cost savings of $5400 perunit.