MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley Draper Trail Project Number: M3‐T003B FINAL PLANS TRIAD DESIGN GROUP November, 2017

Upload: others

Post on 28-May-2020

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley ...€¦ · MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley Draper Trail Project Number: M3‐T003B FINAL PLANS

MAPS 3 Trail ImprovementsPhase 3, Project 3 

Lake Stanley Draper TrailProject Number: M3‐T003B 

FINAL PLANSTRIAD DESIGN GROUP

November, 2017

Page 2: MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley ...€¦ · MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley Draper Trail Project Number: M3‐T003B FINAL PLANS

Phase 3, Project 3 Section Overview

Total Alignment Length: 4.52 miles Alignment begins 1500’ south of I‐240 on Midwest Boulevard Draper Trail will connect to existing Tinker‐Draper Trail Major Intersections :

Midwest Boulevard Douglas Boulevard Post Road Westminster Road S.E. 104th Street

Trail is a minimum of 25 feet from Midwest Boulevard and Stanley Draper Drive with the exception of the creek crossings.

Creek crossings require extension of existing drainage structures and guardrail along the roadway where guardrail has not been installed.

Page 3: MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley ...€¦ · MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley Draper Trail Project Number: M3‐T003B FINAL PLANS

Phase 3, Project 3 Construction Cost Overview

Construction Budget: $3,415,000 Construction Cost Estimate: $3,290,000

Page 4: MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley ...€¦ · MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley Draper Trail Project Number: M3‐T003B FINAL PLANS

Stanley Draper Dr.

I‐240

Midwest B

oulevard

Midwest Blvd. to Stanley Draper Dr.

Page 5: MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley ...€¦ · MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley Draper Trail Project Number: M3‐T003B FINAL PLANS

Stanley Draper Dr.

I‐240

Midwest B

oulevard

Midwest Blvd. to Stanley Draper Dr.

Page 6: MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley ...€¦ · MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley Draper Trail Project Number: M3‐T003B FINAL PLANS

Stanley Draper Dr.

I‐240

Midwest B

oulevard

Midwest Blvd. to Stanley Draper Dr.

Extend 4’ x 4’ RCB 28 feet and install 400 feet of guardrail

Page 7: MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley ...€¦ · MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley Draper Trail Project Number: M3‐T003B FINAL PLANS

Stanley Draper Dr.

I‐240

Midwest B

oulevard

Midwest Blvd. to Stanley Draper Dr.

Connection to Tinker‐Draper Trail

TRAIL LOCATION

Page 8: MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley ...€¦ · MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley Draper Trail Project Number: M3‐T003B FINAL PLANS

I‐240

Stanley Draper Drive

Doug

las B

lvd.

Lake Stanley Draper

Midwest B

oulevard

Midwest Blvd. to Douglas Blvd. along Stanley Draper Dr.

Page 9: MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley ...€¦ · MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley Draper Trail Project Number: M3‐T003B FINAL PLANS

I‐240

Stanley Draper Drive

Doug

las B

lvd.

Lake Stanley Draper

Midwest B

oulevard

Midwest Blvd. to Douglas Blvd. along Stanley Draper Dr.

Extend existing 60’ RCP 14 feet.

Existing guardrail in place.

Page 10: MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley ...€¦ · MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley Draper Trail Project Number: M3‐T003B FINAL PLANS

I‐240

Stanley Draper Drive

Doug

las B

lvd.

Lake Stanley Draper

Midwest B

oulevard

Midwest Blvd. to Douglas Blvd. along Stanley Draper Dr.

Extend existing 72” RCP 40 L.F.

Trail Greater than 25 feet from road, new 

guardrail is not required.

Page 11: MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley ...€¦ · MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley Draper Trail Project Number: M3‐T003B FINAL PLANS

I‐240

Stanley Draper Drive

Doug

las B

lvd.

Lake Stanley Draper

Midwest B

oulevard

Midwest Blvd. to Douglas Blvd. along Stanley Draper Dr.

View from Trail to Lake

Page 12: MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley ...€¦ · MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley Draper Trail Project Number: M3‐T003B FINAL PLANS

I‐240

Stanley Draper Drive

Doug

las B

lvd.

Lake Stanley Draper

Midwest B

oulevard

Midwest Blvd. to Douglas Blvd. along Stanley Draper Dr.

TRAIL LOCATION

Page 13: MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley ...€¦ · MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley Draper Trail Project Number: M3‐T003B FINAL PLANS

I‐240

Stanley Draper Drive

Doug

las B

lvd.

Lake Stanley Draper

Midwest B

oulevard

Midwest Blvd. to Douglas Blvd. along Stanley Draper Dr.

Extend 4 – 72” RCP 20 feet.  Existing guardrail in place.

Page 14: MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley ...€¦ · MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley Draper Trail Project Number: M3‐T003B FINAL PLANS

SE 89th Street

S. Post R

oad

Stanley Draper Drive

Doug

las B

lvd.

Douglas Blvd to Post Rd.

Page 15: MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley ...€¦ · MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley Draper Trail Project Number: M3‐T003B FINAL PLANS

Post Rd. along Stanley Draper Dr. to SW 104th. St.

SW 104th. St.

S. Post R

oad

Page 16: MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley ...€¦ · MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley Draper Trail Project Number: M3‐T003B FINAL PLANS

Post Rd. along Stanley Draper Dr. to SW 104th. St.

SW 104th. St.

S. Post R

oad

Page 17: MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley ...€¦ · MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley Draper Trail Project Number: M3‐T003B FINAL PLANS

Post Rd. along Stanley Draper Dr. to SW 104th. St.

SW 104th. St.

S. Post R

oad

TRAIL LOCATION

Page 18: MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley ...€¦ · MAPS 3 Trail Improvements Phase 3, Project 3 Lake Stanley Draper Trail Project Number: M3‐T003B FINAL PLANS

Phase 3, Project 3 Construction Cost Overview

November 2017: MAPS Board Meeting for recommendation to City Council to advertise for bids

November 8, 2017:  Advertise for Bids November 29, 2017 – Receive Bids December  20, 2017 – Recommendation to Subcommittee December 21, 2017 – Recommendation to Citizens Advisory Board

January 2, 2018 – Award of Construction Contract by City Council

January 3, 2018 – Notice to Proceed for Construction August 2018 – Construction Complete