Change House
Environmental
Enclosure #1
Environmental
Enclosure #3
Laboratory
PCAPP EDS Site Overview
5
PCAPP EDS Safety
As of April 30, the PCAPP EDS project staff has accomplished:
20 Safe Work Days
2,497 Safe Work Hours
6
Workers smooth concrete on May 8 after the first concrete slab pour for Environmental Enclosure #1.
PCAPP EDS ConstructionStaffing –26 employees
Construction
Workers: 6
–Subcontractor personnel – 20
A worker sets screws for the forms in preparation for the concrete slab pour for Environmental Enclosure #2
7
NOT STARTED
IN PROGRESS (POTENTIAL ISSUES)
IN PROGRESS (NO ISSUES)
COMPLETE
Key Milestone
DESIGN START (DEC 2013)
SITE DESIGN COMPLETE (MAR 2014)
CONSTRUCTION STARTS (27 MAR 2014)
CONSTRUCTION COMPLETE (OCT 2014)
E-DAY – EDS START OF
AGENT OPERATIONS (OCT 2014)
CONSTRUCTION CONTRACT AWARD (NOV 2013)
PEO ACWA PROGRAMMATIC DECISION TO SELECT EDS TECHNOLOGY (APR 2013)
PCAPP EDS Schedule(JPME-P Working Schedule)
CONCRETE POURS BEGIN (17 APR 2014)
MODULES (COMMAND POST, CHANGE HOUSE, TREATY TRAILER, ETC.)
BEGIN TO ARRIVE (MAY 2014)
MILITARY FABRIC STRUCTURES FOR EDS ENVIRONMENTAL
ENCLOSURES ARRIVE (JUN 2014)
ARRIVAL OF FIRST EDS UNIT (AUGUST 2014)
8
PCAPP EDS Permitting Progress
NOT STARTED
IN PROGRESS (POTENTIAL ISSUES)
IN PROGRESS (NO ISSUES)
COMPLETE
Key Milestone
CLASS III PERMIT MODIFICATION SUBMITTED TO CDPHE (24 OCT 2013)
STATE APPROVAL OF TEMPORARY AUTHORIZATION
FOR CONSTRUCTION (7 MAR 2014)
SITE CONSTRUCTION START (27MAR 2014)
APPROVAL OF CLASS III MODIFICATION
FOR OPERATIONS (SEP 2014)
E-DAY – EDS START OF AGENT
OPERATIONS (OCT 2014)
PCD RCRA PERMIT RENEWED (JAN 2014)
SUBMIT CERTIFICATE OF DESIGNATION (CD) (DEC 2013)
PEO ACWA PROGRAMMATIC DECISION TO SELECT EDS TECHNOLOGY (APR 2013)
APPROVAL OF CD FOR OPERATIONS
(OCT 2014)
COUNTY APPROVAL OF TEMPORARY AUTHORIZATION
FOR CONSTRUCTION (26 MAR 2014)
RECORD OF ENVIRONMENTAL CONSIDERATION (DEC 2013)
9
Site Progress
10
Processing dirt, the job of mixing the fill with water under the weight of heavy equipment, makes for better compaction when it’s later moved into the enclosures as a base for the slabs that will be poured.
Site Progress
11
Measure twice, dig once. A worker confirms the depth of the trench being carved out. This for the pipes that will be part of the fire line that will serve the EDS site when complete.