![Page 2: PCAPP Update 18 September 2013](https://reader033.vdocument.in/reader033/viewer/2022052606/58f2e4ec1a28ab6f678b461b/html5/thumbnails/2.jpg)
Safety
As of August 31, 2013PCAPP staff has accomplished:
492 Safe Work Days 2,562,303 Safe Work Hours
2
![Page 3: PCAPP Update 18 September 2013](https://reader033.vdocument.in/reader033/viewer/2022052606/58f2e4ec1a28ab6f678b461b/html5/thumbnails/3.jpg)
Staffing – 1,002 employees
Bechtel Pueblo Team non-manual: 808
Pueblo – 806
– (191 Pueblo County hires ~ 24%) (49 Colorado hires ~ 6%)
– Off-project locations—2
Construction Workers: 194
– Bechtel direct-hire – 118
– Subcontractor personnel – 76
3
![Page 4: PCAPP Update 18 September 2013](https://reader033.vdocument.in/reader033/viewer/2022052606/58f2e4ec1a28ab6f678b461b/html5/thumbnails/4.jpg)
Facilities Construction Certification Metrics
July 2013 Progress of 178
packagesas of August 15,
2013
Current Snap Shot
App'd Matric
es
Summary
Shee
ts Ava
ilable
Summary
Shee
ts in Pro
gress
SS to
HGSP
SS to
HGSA
HGSA Certi
fied
CDPHE Concurre
nce
169
106
1836
0 7 6
Summary Sheet Progress - 179 Total
4
![Page 5: PCAPP Update 18 September 2013](https://reader033.vdocument.in/reader033/viewer/2022052606/58f2e4ec1a28ab6f678b461b/html5/thumbnails/5.jpg)
Systemization (Plant) – cont’d
5
S1 - Turnover S2-PreComm S3-Comm S4-Startup S5-Sys Demo/Perf Testing
94%
86%84%
24%
77%73%
53%
0%
91%
78%75%
12%
58%
39%
48%
0%
Commissioning & Startup Activity Status(APB, ERB, BTA, HVAC, UTIL, FAC)
% Planned Commenced % Commenced % Planned Completed % Completed
![Page 6: PCAPP Update 18 September 2013](https://reader033.vdocument.in/reader033/viewer/2022052606/58f2e4ec1a28ab6f678b461b/html5/thumbnails/6.jpg)
Staffing Plan
6
During the next 13 months, 306 new positions (an average of 23 positions per month) will be added
Maintenance: 74 Operations: 125 Operations Support: 73 Laboratory: 93
Staffing will be completed in 2014A second PCAPP Job Symposium will be held in November
![Page 7: PCAPP Update 18 September 2013](https://reader033.vdocument.in/reader033/viewer/2022052606/58f2e4ec1a28ab6f678b461b/html5/thumbnails/7.jpg)
Training Highlights (since January)
7
First-Of-A-Kind equipment has been installed at the Training Facility, and is awaiting training by maintenance and operations personnel.
Implemented the following training programs:
HAZWOPER Operator Leadership Entry Support Area Operator Maintenance Simulator First-Of-A-Kind Emergency Response Incident Command
Initial Training by Employees 175 completed NEOST or Vendor
Orientation 361 completed Site Worker Training
Completed 14,321 training items
![Page 8: PCAPP Update 18 September 2013](https://reader033.vdocument.in/reader033/viewer/2022052606/58f2e4ec1a28ab6f678b461b/html5/thumbnails/8.jpg)
Job Workstations
8
Two new workstations are available for PCAPP job seekers at the Pueblo Chemical Stockpile Outreach Office, allowing for easy submittal of on-line applications.
![Page 9: PCAPP Update 18 September 2013](https://reader033.vdocument.in/reader033/viewer/2022052606/58f2e4ec1a28ab6f678b461b/html5/thumbnails/9.jpg)
Employee Volunteerism
9
More than 70 PCAPP employees painted five houses on Sept. 7, as part of Operation Paintbrush, an annual community-wide event.
![Page 10: PCAPP Update 18 September 2013](https://reader033.vdocument.in/reader033/viewer/2022052606/58f2e4ec1a28ab6f678b461b/html5/thumbnails/10.jpg)