mechanical training project

Upload: shubhankar-shukla

Post on 02-Jun-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/11/2019 mechanical training project

    1/46

    Copyright2013-2014

    Training Semester

    Scooters India Limited

    Shubhankar Shukla

    101108102

  • 8/11/2019 mechanical training project

    2/46

    Copyright2013-2014

    Projects

    Analyze and Provide Solution for Reducing

    rejections at different operations on Clutch

    Housing.

    Optimize The post-procurement process.

    Study manufacturing of the drive shaft and

    reduce rejections.

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 2

  • 8/11/2019 mechanical training project

    3/46

    Copyright2013-2014

    Department

    ScootersIndiaLimited

    R & D

    Production

    Engine

    Assembly

    Casting

    Paint

    Weld

    Machine

    Sales and SupplyChain

    Store

    BOF

    BOSF

    Tool

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 3

  • 8/11/2019 mechanical training project

    4/46

    Copyright2013-2014

    Project 1

    Analyze and Provide Solution for Reducing

    rejections at different operations on Clutch

    Housing.

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 4

    Clutch/gear

    Box housing

  • 8/11/2019 mechanical training project

    5/46

    Copyright2013-2014

    Sub Projects

    Study Of Die casting process involved inmanufacturing of Clutch/gear Box Housing andstudy rejections for a month and suggest

    improvements. Study various machining process performed on

    Clutch/gear box housing and identify defects andsuggest ways to eliminate them.

    Study and Validate the complete clutch/gear boxassembly and perform Assembly Line balancing inorder to improve productivity.

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 5

  • 8/11/2019 mechanical training project

    6/46

  • 8/11/2019 mechanical training project

    7/46

    Copyright2013-2014

    Rejection Report (Initial)

    Sno. Total production

    Rejection

    1 75 2

    2

    76

    2

    3 76 3

    4

    72

    2

    5 77 4

    6

    68

    2

    7

    76

    18 74 4

    9 76 0

    10

    74

    2

    11 81 6

    12 76 2

    13 75 1

    14

    75

    3

    15 74 0

    16

    76

    1

    17 76 6

    18 71 5

    19 75 2

    20 76 2

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 7

    Rejection Rate 3.7%

  • 8/11/2019 mechanical training project

    8/46

    Copyright2013-2014

    Defects

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 8

    Thermal cracks- coolant failure, holding furnace.

  • 8/11/2019 mechanical training project

    9/46

    Copyright2013-2014

    Die Wear

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 9

  • 8/11/2019 mechanical training project

    10/46

    Copyright2013-2014

    Countermeasures

    Make a 3mm Radius

    Installation of Temperature Controller

    training of operators

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 10

  • 8/11/2019 mechanical training project

    11/46

    Copyright2013-2014

    Rejections (improved)

    S no.

    Total no. of produce

    Rejections

    1 78 1

    2 76 0

    3 78 2

    4 73 0

    5 51 4(die wear)

    6 72 0

    7 82 1

    8

    78

    1

    9

    75

    0

    10 76 0

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 11

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    1 2 3 4 5 6 7 8 9 10

    total rejections Series 3

    Improved Rejection

    Rate = 1.21%

  • 8/11/2019 mechanical training project

    12/46

    Copyright2013-2014

    Machine Shop (Ln No. 2)

    Operation No. Machine no. Details

    --

    --

    Face milling with a HSS tool with a

    Carbide tip to rectify the height of

    Clutch box housing.

    Operation 20 2602 Drilling and daweling

    Operation 25 4047 Side milling(undercut for diesel

    engines as they have large first gear)

    Operation 50

    3195

    Drilling, counter, chamfering

    Operation 100+90 -- Dawel Pin

    Operation 60 2595 Boring, chamfering

    Operation 20

    --

    Side stab

    Operation 70 3567 Milling for gear pin

    Operation 75

    2155

    Step drilling

    Operation 80 2603 Tapping of all drills

    Operation 120 145 Tapping of drills in operation 50

    Operation 40 3202 Step boring off GB flange

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 12

  • 8/11/2019 mechanical training project

    13/46

    Copyright2013-2014

    Problems

    Unavailable tools

    Machine vibrations

    Machine breakdown Weak Inspection schemes

    Less compression pressure

    Voltage fluctuations (rare)

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 13

  • 8/11/2019 mechanical training project

    14/46

    Copyright2013-2014

    Process Capability

    Process capabilityis the ability of the process

    to meet the design specifications for a service

    or product.

    Cp = Allowable Process Spread / Actual Process Spread

    Cpk= Process capability index that indicates process actual

    performance by accounting for shift in the mean of the

    process within the upper and lower specification limit.

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 14

    Equivalent, Cp value Capability to produce nonconformance

    product, %

    0.50 86.64

    0.62 93.50

    0.68

    96.00

    0.81 98.50

    0.86 99.00

    1.00 99.73

    1.33

    99.994

  • 8/11/2019 mechanical training project

    15/46

    Copyright2013-2014

    Boring Process Capability

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 15

    52mm and 16mm

    4 readings for 15 days(initial)

    4 readings for 19days(improved)

    Analysis on minitab 17

    Improvements

  • 8/11/2019 mechanical training project

    16/46

    Copyright2013-2014

    52mm (Initial)

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 16

  • 8/11/2019 mechanical training project

    17/46

    Copyright2013-2014

    16mm (intial)

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 17

  • 8/11/2019 mechanical training project

    18/46

    Copyright2013-2014

    16mm (initial)

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 18

  • 8/11/2019 mechanical training project

    19/46

    Copyright2013-2014

    Problems

    Old machinery

    High vibrations

    Jammed Oiling Ducts Poor maintainance

    Noise

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 19

  • 8/11/2019 mechanical training project

    20/46

    Copyright2013-2014

    Improvements

    Tool Holder changed

    Shock Absorbers installed

    Internal Oiling Oiling pipes and filters changed

    Worker Training

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 20

    Shock

    absorbers

  • 8/11/2019 mechanical training project

    21/46

    Copyright2013-2014

    52mm (improved)

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 21

  • 8/11/2019 mechanical training project

    22/46

    Copyright2013-2014

    52mm (improved)

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 22

  • 8/11/2019 mechanical training project

    23/46

    Copyright2013-2014

    16mm (improved)

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 23

  • 8/11/2019 mechanical training project

    24/46

    Copyright2013-2014

    16mm (improved)

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 24

  • 8/11/2019 mechanical training project

    25/46

    Copyright2013-2014

    Gear Box Assembly

    Gear box assembly (sequential 4 gear system)

    Clutch assembly

    Reverse gear assembly

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 25

    Clutch/Gear box

  • 8/11/2019 mechanical training project

    26/46

    Copyright2013-2014

    Line Balancing

    Task

    Time

    Description

    Preceed

    A

    43

    Gear box house loading

    B 76 Inner lever + gc shaft A

    C

    75

    Lay shaft, davel pin, lay shaft spacer

    B

    D 88 Cluster gear C

    E 97 Gb flange, sheam clearance D

    F 38 Pt wheel E

    G

    69

    Clutch well, torque nut

    F

    H

    76

    Clutch assembly, lock nut

    G

    I

    61

    Reverse gear 0093, lock nut, needle bearing

    E

    J 48 Push rod, sector A

    K

    36

    TOP shaft

    I, J

    L 88 Spindle rod, reverse gear set K

    M 87 Gasket, top cover, o ring, speed pinion L

    N 93 Companion flange, reverse gear selector M

    O 92 Engine mountings, unloading of clutch box

    housing

    N, H

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 26

    AB C D E

    F G H

    O

    I K L M N

    J

  • 8/11/2019 mechanical training project

    27/46

    Copyright2013-2014

    Line Balancing

    Calculate the theoretical minimum number

    of workstations.

    NUMBER OF WORK STATIONS = ( SUM OF TOTAL

    TASK TIMES) / (CYCLE TIME)

    = 1109 secs / 180 secs = 6.31 = 7(rounded)

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 27

  • 8/11/2019 mechanical training project

    28/46

    Copyright2013-2014

    Line Balancing

    STATION

    TASK

    TIME

    FOLLOWING TIME REMAINING

    1 A

    B

    J

    43

    76

    48+10

    14

    12

    6

    137

    61

    3

    2 C

    D

    75+10

    88

    11

    10

    94

    5

    3

    E

    I

    97

    61+10

    9

    5

    83

    12

    4 F

    G

    K

    38+10

    69

    36+10

    2

    1

    4

    132

    63

    17

    5

    LM

    8887

    32

    925

    6 N

    H

    93

    76+10

    1

    1

    87

    1

    7

    O

    92

    0

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 28

  • 8/11/2019 mechanical training project

    29/46

    Copyright2013-2014

    Line Balancing

    Benefits

    1. Equal Work Load distribution

    2. No idle time3. High efficiency

    4. Less Human resource required

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 29

  • 8/11/2019 mechanical training project

    30/46

    Copyright2013-2014

    Post Procurement

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 30

    Main gate Security Check Store manager

    Quality

    controldepartment

    store manager store

    assembly line/manufacturing

  • 8/11/2019 mechanical training project

    31/46

    Copyright2013-2014

    BOF store

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 31

    Finished Items Glass Store, Tyre store, leaf spring suspension store etc.

    Online database

  • 8/11/2019 mechanical training project

    32/46

    Copyright2013-2014

    Current scenario

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 32

    Area destroyed in fire

    18.6*60 m2

    Used for various BOF stores

    located at the entrance eg.Glass store, Silencer store,

    tyre store etc

  • 8/11/2019 mechanical training project

    33/46

    Copyright2013-2014

    Layout Initial

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 33

  • 8/11/2019 mechanical training project

    34/46

    Copyright2013-2014

    Proposed Layout

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 34

    Bins Added Min path width 3m

    Major BOF stores shifted to

    fire destroyed area

    No ground storage

    Extra storage for extra

    inventory

  • 8/11/2019 mechanical training project

    35/46

    Copyright2013-2014

    Detailed Look

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 35

  • 8/11/2019 mechanical training project

    36/46

    Copyright2013-2014

    BOSF store

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 36

    BOSF- Bought of semi finished

    Unplanned

    High Ground Storage

    No FIFO

    Degradation Slow material flow

  • 8/11/2019 mechanical training project

    37/46

    Copyright2013-2014

    Initial Layout

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 37

  • 8/11/2019 mechanical training project

    38/46

    Copyright2013-2014

    Proposed Layout

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 38

    Min 3.5 mm pathway

    U shaped for quick material flow

    Bins added

    Special area for packaging

    material Ground storage for extra

    inventory

  • 8/11/2019 mechanical training project

    39/46

    Copyright2013-2014

    Detailed Look

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 39

  • 8/11/2019 mechanical training project

    40/46

    Copyright2013-2014

    5s implimentation

    Good layout not enough

    At present no principles to follow for store

    management.

    New products would put more pressure

    5s for sustainable organization maintainence

    suggested

    Special set of instructions

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 40

  • 8/11/2019 mechanical training project

    41/46

    Copyright2013-2014

    Principles

    Sort:

    No useless wrappers, cartons or boxes should be present in the store premises.

    Keeping material on ground not allowed.

    Degraded items should be reported and removed.

    Straighten

    Bins should be arranged properly with no bins blocking others. Strict use of FIFO methodology, so as to minimize wastage due to degradation of

    material.

    Use big bin numbers which are clearly visible. And numbering to be done in such away so that finding a bin becomes easier.

    A manual trolley specifically for store so that in store movement is smooth and fast

    as well. Shine

    Packaging of materials to be moved out of the storage thrice every day.

    Maintain safety is case of dealing with heavier material.

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 41

  • 8/11/2019 mechanical training project

    42/46

    Copyright2013-2014

    Standardize

    Store Manager is to be held accountable for all problems in storage.

    Handle all materials following the instructions especially with handle

    with care items.

    Divide areas for specific materials eg. Shelves for smaller items andbings for bigger ones.

    Sustain

    To keeps check on store workers so the instructions are followed

    Keep the workers updated with rules and regulations.

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 42

  • 8/11/2019 mechanical training project

    43/46

    Copyright2013-2014

    Drive Shaft

    Cutting

    Lathe turning

    Hobbing

    Heat Treatment

    Grinding

    Visual Inspection

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 43

  • 8/11/2019 mechanical training project

    44/46

    Copyright2013-2014

    Month Rejections

    Feb 17

    March 19

    April 22

    May 21

    June 15

    July 12

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 44

    The number of rejections for feb july are recorded and are as follows:

    0

    5

    10

    15

    20

    25

    feb april june

    Rejection

    f ( d)

  • 8/11/2019 mechanical training project

    45/46

    Copyright2013-2014

    Defects (rod)

    Dents

    Material Defect

    Grinding Fault- unbalanced, vibrations

    Rust

    Monday, September 08,THAPAR UNIVERSITY, PATIALA 45

  • 8/11/2019 mechanical training project

    46/46

    Copyright2013-2014

    Improvements

    The unbalanced wheel of the grinding wheelfixed.

    Inspection schedule made.

    Training to workers as visual inspection isdone

    Coolant temperature varied so as the

    abrasives do not get attached to the workpiece. Filters changed.

    Feed maintained