5/25/18 9:19 AM Page 1 of 3 MGM SPRINGFIELD CONSTRUCTION ACTIVITIES -5/22/17-6/5/18 WORK HOURS: 7:00 AM - 7:00 PM FOR CONSTRUCTION-RELATED INQUIRES PLEASE CONTACT: [email protected] FULL CONSTRUCTION BUILD OUT ZONE LOCATION STATUS 1 95 and 101 State Street Work is anticipated on the exterior facade as well as in the alleyway between 95 and 101 State Street. The alley will be closed while this work is taking place and the entrance to 101 State Street may at times be partially impeded. 2 Hotel Interior fit-out is underway. Exterior façade work is underway. 3 Casino Interior fit-out is underway. Exterior façade work is underway. 4 Da Vinci Park No work anticipated 5 Dave's Furniture No work anticipated 6 Armory Interior fitout is underway. Exterior masonry work is underway. 7 Plaza Landscape/hardscape work is underway. 8 Church Church patio foundations/walls underway. 9 Entertainment Interior fit-out is underway. Exterior façade work is underway. Storefront installation is underway. 10 Parking Garage Garage is now being utilized for craft labor parking. 11 Support Area Landscape and hardscarpe is underway. 12 MGM Way Exterior façade work is underway. Receiving deliveries and staging of material/equipment. Landscape and hardscape work is underway. Utility, sewer, drain structure castings to be jackhammered & reset within milled areas. Road paving scheduled for Saturday 6/2/18 from 4:00 AM until mid-afternoon w/ traffic down to one lane of travel. Individual parking spots to be impacted at limited intervals. Pedestrian access will be rerouted as required. Some noise, dust and vibration may result. A police detail is anticipated w/ lane shifts or alternating one way traffic. Activity will proceed on an intermittent basis due to normal sequencing of work tasks, subcontractors, & coordination of work. Early Childhood Center (off map) Interior fit-out is underway. Exterior façade work is underway.

Upload: others

Post on 04-Sep-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MGM SPRINGFIELD CONSTRUCTION ACTIVITIES -5/22/17-6/5/18 ...€¦ · 6 Armory Interior fitout is underway. Exterior masonry work is underway. 7 Plaza Landscape/hardscape work is underway

5/25/189:19AM Page1of3

MGM SPRINGFIELD CONSTRUCTION ACTIVITIES -5/22/17-6/5/18

WORK HOURS: 7:00 AM - 7:00 PM

FOR CONSTRUCTION-RELATED INQUIRES PLEASE CONTACT: [email protected]

FULL CONSTRUCTION BUILD OUT

ZONE LOCATION STATUS

1 95 and 101 State Street Work is anticipated on the exterior facade as well as in the alleyway between 95 and 101 State Street. The alley will be closed while this work is taking place and the entrance to 101 State Street may at times be partially impeded.

2 Hotel Interior fit-out is underway. Exterior façade work is underway.

3 Casino Interior fit-out is underway. Exterior façade work is underway.

4 Da Vinci Park No work anticipated

5 Dave's Furniture No work anticipated

6 Armory Interior fitout is underway. Exterior masonry work is underway.

7 Plaza Landscape/hardscape work is underway.

8 Church Church patio foundations/walls underway.

9 Entertainment Interior fit-out is underway. Exterior façade work is underway. Storefront installation is underway.

10 Parking Garage Garage is now being utilized for craft labor parking.

11 Support Area Landscape and hardscarpe is underway.

12 MGM Way

Exterior façade work is underway. Receiving deliveries and staging of material/equipment. Landscape and hardscape work is underway.

Utility, sewer, drain structure castings to be jackhammered & reset within milled areas. Road paving scheduled for Saturday 6/2/18 from 4:00 AM until mid-afternoon w/ traffic down to one lane of travel. Individual parking spots to be impacted at limited intervals. Pedestrian access will be rerouted as required. Some noise, dust and vibration may result. A police detail is anticipated w/ lane shifts or alternating one way traffic. Activity will proceed on an intermittent basis due to normal sequencing of work tasks, subcontractors, & coordination of work.

Early Childhood Center (off map) Interior fit-out is underway. Exterior façade work is underway.

Page 2: MGM SPRINGFIELD CONSTRUCTION ACTIVITIES -5/22/17-6/5/18 ...€¦ · 6 Armory Interior fitout is underway. Exterior masonry work is underway. 7 Plaza Landscape/hardscape work is underway

5/25/189:19AM Page2of3

STREET WORK

State Street

Utility, sewer, drain structure castings to be jackhammered & reset within milled areas. Road paving scheduled for Saturday 6/2/18 from 4:00 AM until mid-afternoon w/ traffic down to one lane of travel. Individual parking spots to be impacted at limited intervals. Pedestrian access will be rerouted as required. Some noise, dust and vibration may result. A police detail is anticipated w/ lane shifts or alternating one way traffic. Activity will proceed on an intermittent basis due to normal sequencing of work tasks, subcontractors, & coordination of work.

Main Street

Reflectorized drums will intermittently be placed in the south bound lane to shift traffic from 6am-6pm Monday through Friday to allow for the unloading of certain materials onto the construction site. The barrels will be moved out of the road at the end of each day to allow parking during non-working hours. Two way traffic will be maintained at all times and two police details will be present. This traffic shift is currently underway.

Work is underway to install a secure loading zone for hotel and casino podium equipment. This work will include the removal of scaffold and curbing from the Union Chandler building north along Main Street to 101 State Street. Jersey barriers will be installed along with fencing and gates. Two way traffic will be maintained at all times. Loading Zone is currently receiving deliveries.

Reconstruction of sidewalks, curbing, signs, & installation of wheelchairs ramps. Utility, sewer, drain structure castings to be jackhammered & reset within milled areas. Individual parking spots to be impacted at limited intervals. Pedestrian access will be rerouted as required. Some noise, dust and vibration may result. A police detail is anticipated w/ lane shifts or alternating one way traffic. Activity will proceed on an intermittent basis due to normal sequencing of work tasks, subcontractors, & coordination of work.

Union Street

Traffic signal timing adjustments & line striping expected at the intersection of Union Street and East and West Columbus Avenue. Road paving at the intersection of Union Street and East and West Columbus Avenue scheduled for Saturday 5/26/18 from 4:00 AM until mid-afternoon w/ traffic down to one lane of travel. Utility, sewer, drain structure castings to be jackhammered & reset within milled areas. Individual parking spots to be impacted at limited intervals. Pedestrian access will be rerouted as required. Some noise, dust and vibration may result. A police detail is anticipated w/ lane shifts or alternating one way traffic. Activity will proceed on an intermittent basis due to normal sequencing of work tasks, subcontractors, & coordination of work.

Installation of drive aprons is underway.

East Columbus Avenue

Traffic signal timing adjustments & line striping expected. Road paving scheduled for Saturday 5/26/18 from 4:00 AM until mid-afternoon w/ traffic down to one lane of travel. Utility, sewer, drain structure castings to be jackhammered & reset within milled areas. Individual parking spots to be impacted at limited intervals. Pedestrian access will be rerouted as required. Some noise, dust and vibration may result. A police detail is anticipated w/ lane shifts or alternating one way traffic. Activity will proceed on an intermittent basis due to normal sequencing of work tasks, subcontractors, & coordination of work.

Bliss Street Landscape/hardscape is underway.

Howard Street Turn Around No work anticipated

Howard Street Landscape/hardscape is underway.

UTILITY ACTIVITY

UTILITY PROVIDER WORK TO BE PERFORMED

Eversource No work anticipated

Page 3: MGM SPRINGFIELD CONSTRUCTION ACTIVITIES -5/22/17-6/5/18 ...€¦ · 6 Armory Interior fitout is underway. Exterior masonry work is underway. 7 Plaza Landscape/hardscape work is underway

5/25/189:19AM Page3of3

Verizon No work anticipated

Comcast No work anticipated

Columbia Gas No work anticipated

Springfield Water & Sewer No work anticipated

MISCELLANEOUS ACTIVITY

LOCATION WORK TO BE PERFORMED

York Street Lot Construction material staging is underway.

Zorzi Lot Established as parking for craft labor foreman and superintendents.

Offsite Parking Lots Established for site orientation parking and oversized vehicles.

Page 4: MGM SPRINGFIELD CONSTRUCTION ACTIVITIES -5/22/17-6/5/18 ...€¦ · 6 Armory Interior fitout is underway. Exterior masonry work is underway. 7 Plaza Landscape/hardscape work is underway

195/101 STATE

2HOTEL

3CASINO

12MGM WAY

7PLAZA

6ARMORY

8CHURCH

5DAVE’S

FURNITURE

4DA VINCI

PARK

9ENTERTAINMENT

10PARKING GARAGE

11SUPPORT

AREA

BLIS

S ST

REET

HOW

ARD

STRE

ET

STAT

E ST

REET

UNIO

N ST

REET

MAIN STREET

WORK IS UNDERWAY TO INSTALL A SECURE LOADING ZONE FOR HOTEL AND CASINO PODIUM EQUIPMENT. THIS WORK WILL INCLUDE THE REMOVAL OF SCAFFOLD AND CURBING FROM THE UNION CHANDLER BUILDING NORTH ALONG MAIN STREET TO 101 STATE STREET. JERSEY BARRIERS WILL BE INSTALLED ALONG WITH FENCING AND GATES. TWO WAY TRAFFIC WILL BE MAINTAINED AT ALL TIMES. LOADING ZONE IS CURRENTLY RECEIVING DELIVERIES.

HOW

ARD

TURN

ARO

UND

UTILITY, SEWER, DRAIN STRUCTURE CASTINGS TO BE JACKHAMMERED & RESET WITHIN MILLED AREAS. ROAD PAVING SCHEDULED FOR SATURDAY 6/2/18 FROM 4:00 AM UNTIL MID-AFTERNOON W/ TRAFFIC DOWN TO ONE LANE OF TRAVEL. INDIVIDUAL PARKING SPOTS TO BE IMPACTED AT LIMITED INTERVALS. PEDESTRIAN ACCESS WILL BE REROUTED AS REQUIRED. SOME NOISE, DUST AND VIBRATION MAY RESULT. A POLICE DETAIL IS ANTICIPATED W/ LANE SHIFTS OR ALTERNATING ONE WAY TRAFFIC.

EAST COLUMBUS AVENUE

TRAFFIC SIGNAL TIMING ADJUSTMENTS & LINE STRIPING EXPECTED AT THE INTERSECTION OF UNION STREET AND EAST AND WEST COLUMBUS AVENUE. ROAD PAVING AT THE INTERSECTION OF UNION STREET AND EAST AND WEST COLUMBUS AVENUE SCHEDULED FOR SATURDAY 5/26/18 FROM 4:00 AM UNTIL MID-AFTERNOON W/ TRAFFIC DOWN TO ONE LANE OF TRAVEL. UTILITY, SEWER, DRAIN STRUCTURE CASTINGS TO BE JACKHAMMERED & RESET WITHIN MILLED AREAS. INDIVIDUAL PARKING SPOTS TO BE IMPACTED AT LIMITED INTERVALS. PEDESTRIAN ACCESS WILL BE REROUTED AS REQUIRED. SOME NOISE, DUST AND VIBRATION MAY RESULT. A POLICE DETAIL IS ANTICIPATED W/ LANE SHIFTS OR ALTERNATING ONE WAY TRAFFIC