mm ztk 1a onep qua pln 0027_itp for civil construction rev c

17
ZAWTIKA DEVELOPMENT PROJECT PHASE 1A EPCIC OF ZAWTIKA ONSHORE PIPELINE CONTRACT NO.: IMO-EMP-CT-10-0018 INSPECTION AND TEST PLAN FOR CIVIL CONSTRUCTION dl . VV --:YK " LYX 26-Jul-12 Approved for Construction C1 DWC ZZG "'" TH A1 13-Jul-12 Issued for Review LYX DWC ZZG YK TH CHECK APPR. CHECK APPR REV cpp COMPANY APPROVAL DATE BY DESCRIPTION APPROVAL REVISION CODE: A = Issued for Review (IFR); B =Issued for Approval (IFA); C =Approved for Construction (AFC) TOTAL OR PARTIAL AND / OR UTILIZATION OF THIS DOCUMENT ARE FORBIDDEN WITHOUT PRIOR WRITTEN AUTHORIZATION OF THE OWNER PTTEP INTERNATIONAL LIMITED ZAWTIKA DEVELOPMENT PROJECT PHASE 1A EPCIC OF ZAWTIKA ONSHORE PIPELINE MM-ZTK-1A·ONEP-QUA-PLN·0027 I C1 CPP i

Upload: ntah84

Post on 15-Apr-2017

221 views

Category:

Documents


2 download

TRANSCRIPT

ZAWTIKA DEVELOPMENT PROJECT PHASE 1A

EPCIC OF ZAWTIKA ONSHORE PIPELINE

CONTRACT NO.: IMO-EMP-CT-10-0018

INSPECTION AND TEST PLAN FOR CIVIL CONSTRUCTION

k~1~ ~~ dl~~j~ . ~~ VV --:YK ~" LYX26-Jul-12 Approved for Construction C1 DWC ZZG "'" TH

A1 13-Jul-12 Issued for Review LYXDWC ZZG YK TH

CHECK APPR. CHECK APPR

REV cpp COMPANY

APPROVAL

DATE BY DESCRIPTION APPROVAL

REVISION CODE: A =Issued for Review (IFR); B =Issued for Approval (IFA); C =Approved for Construction (AFC)

TOTAL OR PARTIAL AND / OR UTILIZATION OF THIS DOCUMENT ARE FORBIDDEN WITHOUT PRIOR WRITTEN

AUTHORIZATION OF THE OWNER

• PTTEP INTERNATIONAL LIMITED

ZAWTIKA DEVELOPMENT PROJECT PHASE 1A

EPCIC OF ZAWTIKA ONSHORE PIPELINE

MM-ZTK-1A·ONEP-QUA-PLN·0027 I C1 CPP

i

PTTEP International Limited Page 2 / 17

Zawtika Development Project Phase 1A Document : MM-ZTK-1A-ONEP-QUA-PLN-0027

EPCIC of Zawtika Onshore Pipeline Revision :C1

Date : 26- Jul-2012

Inspection and Test Plan for Civil Construction Remark:

S.N QUALITY RELATED ACTIVITY

REFERENCE DOCUMENT

CHARACTERISTICS TO BE VERIFIED

ACCEPTANCE CRITERIA

VERIFYING DOCUMENT CONTRACTOR COMPANY

1 Permit MM-ZTK-1A-ONEP-CIV

-PRC-0005

Permit All necessary permits obtained from Company.

Permit H R

2

Earthworks MM-ZTK-1A-ONEP-CIV-PRC-0005

Removal of garbage, topsoil, etc. Excavation Backfill Grading

Removal of any structures and obstructions on the surface or underground hindering construction Ensure locations and elevations of pipe trenches and equipment foundations confirmed as per the design drawings. Ensure grading below subgrade of the designed foundation completed for foundations, underground pipe networks and utilities. Ensure manual excavation within the range of two meters adopted instead of mechanical excavation to the existing facilities. Ensure excavations more than 1500mm in depth shored or cut back at an angle or stabilized by a combination of shoring and cutting. Ensure appropriate bedding or suitable temporary support installed to prevent damage to pipe prior to any below ground pipe work. Ensure the soil backfilled compacted by required thickness of layer mentioned in design drawing and required density achieved. Ensure ground levels graded to their required elevations indicated in the AFC drawings.

Inspection Report for Clearing Removal Inspection Report for Excavation Inspection Report for Backfilling Record of Foundation Survey

H R

PTTEP International Limited Page 3 / 17

Zawtika Development Project Phase 1A Document : MM-ZTK-1A-ONEP-QUA-PLN-0027

EPCIC of Zawtika Onshore Pipeline Revision :C1

Date : 26- Jul-2012

Inspection and Test Plan for Civil Construction Remark:

S.N QUALITY RELATED ACTIVITY

REFERENCE DOCUMENT

CHARACTERISTICS TO BE VERIFIED

ACCEPTANCE CRITERIA

VERIFYING DOCUMENT CONTRACTOR COMPANY

Verify elevation, slope and ize of drain ditches. During grading, ensure water spraying implemented in accordance with design requirements Ensure removal of excess and unsuitable materials.

3

Concrete Work MM-ZTK-1A-ONEP-CIV-PRC-0005

Material Installation of reinforcing steel

Ensure all material meet the specification requirement Ensure all materials properly stored and protected. Cement conform to all requirements of the latest edition of ASTM C-150 and design drawing requirements All aggregate conform as close as practical to ASTM C-33. Ensure the water for mixing concrete meet specification requirements Admixtures, when approved, used in accordance with ASTM C-494 and the manufacturer's written instructions Ensure all reinforcing bars cold bent to conform accurately to the drawings with all longitudinal plane bars for slabs and beams terminating in standard hooks. Check tie wires bent to prevent ends of ties from

Record of Concrete Work Inspection Report for Steel Bar Installation Inspection Report for Formwork Curing record of precast concrete

H W

PTTEP International Limited Page 4 / 17

Zawtika Development Project Phase 1A Document : MM-ZTK-1A-ONEP-QUA-PLN-0027

EPCIC of Zawtika Onshore Pipeline Revision :C1

Date : 26- Jul-2012

Inspection and Test Plan for Civil Construction Remark:

S.N QUALITY RELATED ACTIVITY

REFERENCE DOCUMENT

CHARACTERISTICS TO BE VERIFIED

ACCEPTANCE CRITERIA

VERIFYING DOCUMENT CONTRACTOR COMPANY

Formwork Samples of aggregate and sand sieve analysis

protrusion from exposed surfaces to the concrete. Ensure formworks plane and straight, of correct geometric dimension and free from warps and defects so as not to create blemishes on concrete surface Before concrete grouting, ensure formwork surface wetted to prevent extraction of water from the concrete Rough face plywood, or equal, used as formwork for unexposed surfaces. Construction tolerances in accordance with ACI 117 Standard Tolerances for Concrete Construction and Materials. Ensure formwork not disturbed until the concrete has cured. Removal of forms and supports in accordance with Paragraph 3.7 of ACI 347 Removal of formwork when the surface temperature of the concrete is 60 degree C or above.

- Sides of beams, walls, columns, pile caps and piles = 2 days

- Soffits of slabs (props left in) = 4 days - Soffits of beams (props left in) = 8 days - Props-beams, and slabs, props concrete

frames and cantilever structures = 14 days Prior to the commencement of concrete trial mixes, Ensure submit samples of aggregate and sand together with their full sieve analysis to COMPANY for

PTTEP International Limited Page 5 / 17

Zawtika Development Project Phase 1A Document : MM-ZTK-1A-ONEP-QUA-PLN-0027

EPCIC of Zawtika Onshore Pipeline Revision :C1

Date : 26- Jul-2012

Inspection and Test Plan for Civil Construction Remark:

S.N QUALITY RELATED ACTIVITY

REFERENCE DOCUMENT

CHARACTERISTICS TO BE VERIFIED

ACCEPTANCE CRITERIA

VERIFYING DOCUMENT CONTRACTOR COMPANY

Slump test Mixing ratio Concrete cubic Concrete Mixing Concrete Grouting

approval, indicating their source of supply. Coarse aggregate size : 25mm nominal maximum Slum: 75 + 5mm Slump test obtained in according with ASTM C143 and witness by COMPANY representative prior to construction Ensure concrete mixing ratio as per approved Mix Design. Ensure concrete cubic tested by CONTRACTOR’s site laboratory during construction period Ensure mixture good plastic consistency and flow sluggishly without crumbling or segregating. Ensure concrete mixed in a batch as recommended by manufacturer Ensure the grouting of all types of concrete a continuous operation without interruption and uniformity of mix maintained and segregation of aggregated is prevented. Check all formwork thoroughly cleaned before grouting. Ensure the recommendations of ACI 305R - Hot Weather Concreting strictly followed for grouting of concrete.

PTTEP International Limited Page 6 / 17

Zawtika Development Project Phase 1A Document : MM-ZTK-1A-ONEP-QUA-PLN-0027

EPCIC of Zawtika Onshore Pipeline Revision :C1

Date : 26- Jul-2012

Inspection and Test Plan for Civil Construction Remark:

S.N QUALITY RELATED ACTIVITY

REFERENCE DOCUMENT

CHARACTERISTICS TO BE VERIFIED

ACCEPTANCE CRITERIA

VERIFYING DOCUMENT CONTRACTOR COMPANY

Vibrators Float finish Curing Repair

Ensure concrete grouting temperature shall be as per specification and standard When grouting, concrete compacted by vibration. Check the distance between two vibrators inserts is approx 300mm to 600mm and in overlapping way to ensure fully vibrated to concrete. Ensure that concrete near formwork faces is sufficiently worked to avoid honeycomb and produce a smooth uniform surface after formworks are removed Float finish applied while the concrete is still plastic. Care taken not to overwork the concrete and avoiding excess of water and mortar being brought to the surface Curing in accordance with ACI 308 – Standard Practice for Curing Concrete. Care shall be taken to prevent drying of the concrete surfaces by applications of water. The surfaces shall be kept covered and moist for a minimum of 5 days. Repair of voids, honeycombs, sand pockets and other similar gross imperfections, completed within 24 hours after removal of formworks Dry mortar of 1 part cement and 2.5 parts of sand passing mesh 16 sieve used to fill cleaned out voids

PTTEP International Limited Page 7 / 17

Zawtika Development Project Phase 1A Document : MM-ZTK-1A-ONEP-QUA-PLN-0027

EPCIC of Zawtika Onshore Pipeline Revision :C1

Date : 26- Jul-2012

Inspection and Test Plan for Civil Construction Remark:

S.N QUALITY RELATED ACTIVITY

REFERENCE DOCUMENT

CHARACTERISTICS TO BE VERIFIED

ACCEPTANCE CRITERIA

VERIFYING DOCUMENT CONTRACTOR COMPANY

Field Tests

and not exceeding 150mm in depth or 0.03 cubic meters in volume. Ensure smooth finish on faces of exposed concrete, and smooth steel travel finish on floors. Ensure sidewalks given a broom finish. Ensure carried out by using calibrated equipments, and as per standard methods of ASTM.

4

Fencing and gates

MM-ZTK-1A-ONEP-CIV-PRC-0005

Installation of all posts, wire mesh fabric, gates, bracing, and all related fastening hardware.

Ensure all posts plumb and securely braced to prevent movement. Ensure that all gates are properly installed to allow gates to open quietly without constraining. Install all earthing wires at each gate as required. ensure that all connections are securely made so that a good earth connection is obtained

Inspection Report for Installation of Steel Fencing

R

R

5

Underground Facilities

MM-ZTK-1A-ONEP-CIV-PRC-0005

Material Installation

Reinforced concrete pipe conform to the requirements of ASTM C76M. Flexible packing conforms to the requirements of ASTM C443. Cement for mortar conform to ASTM C150. Plastic pipe conform to ASTM F714. Ensure Pipe carefully lay in route as per AFC

Installation record

R R

PTTEP International Limited Page 8 / 17

Zawtika Development Project Phase 1A Document : MM-ZTK-1A-ONEP-QUA-PLN-0027

EPCIC of Zawtika Onshore Pipeline Revision :C1

Date : 26- Jul-2012

Inspection and Test Plan for Civil Construction Remark:

S.N QUALITY RELATED ACTIVITY

REFERENCE DOCUMENT

CHARACTERISTICS TO BE VERIFIED

ACCEPTANCE CRITERIA

VERIFYING DOCUMENT CONTRACTOR COMPANY

drawing, and the pipeline kept clean at all times during construction. Ensure all services such as concrete, and clay ware sewers and drains inspected and tested Where sewer lines are below the ground water level, infiltration tests done for measure the rate of infiltration water quantity Ensure the line is straight.

6

Heating, ventilation and air conditioning works

MM-ZTK-1A-ONEP-CIV-PRC-0005

Material and Equipment Construction

All materials and equipment shall conform to design drawings, specification, standards and Recommended practices. Installation shall conform to design drawing, specification, standards and recommended practices as well as manufacturer’s instructions. Ensure air conditioner quantity and capacity checked carefully before installation ,ensure each air conditioner take their correct position, and the installation performed as per vendor’s manual Check all the connections and fixing parts of whole systems after complete testing of equipment.

Installation record

W M/R

7

Prefabrication and Assembly of Buildings and Structures

MM-ZTK-1A-ONEP-CIV-PRC-0005

Materials and Equipment Installation

Quality certificates and introductions for installation and operation of materials and equipment available Ensure all equipment and utility piping systems installed strictly in accordance with the design drawings and manufacturer's instructions.

Installation record

R R

PTTEP International Limited Page 9 / 17

Zawtika Development Project Phase 1A Document : MM-ZTK-1A-ONEP-QUA-PLN-0027

EPCIC of Zawtika Onshore Pipeline Revision :C1

Date : 26- Jul-2012

Inspection and Test Plan for Civil Construction Remark:

S.N QUALITY RELATED ACTIVITY

REFERENCE DOCUMENT

CHARACTERISTICS TO BE VERIFIED

ACCEPTANCE CRITERIA

VERIFYING DOCUMENT CONTRACTOR COMPANY

8

Roofing MM-ZTK-1A-ONEP-CIV-PRC-0005

Waterproof material Waterways Leakage

Ensure waterproof material employed on building roof and the installation method as per vendor’s recommendation and AFC drawings. Ensure adequate waterways available on building roof, and proper lope made as per AFC drawing Test roof with water for leakages to ensure waterproof work executed properly

Installation record

H W

9

Block work MM-ZTK-1A-ONEP-CIV-PRC-0005

Concrete Blocks Cement Sand Lime Water Construction

Ensure quality equal to ASTM C-90 and reasonably smooth and uniform in texture. Ensure samples of proposed concrete blocks submitted for approval at least seven days prior to the start of concrete block work The cement conform to all requirements of the latest edition of ASTM C-150 Ensure the sand clean, sharp sand meet ASTM C-144 The lime hydrated lime for masonry purposes in accordance with ASTM C-207 Use potable water or fine river water Ensure mortar thoroughly mixed and kept mix round on the mortar boards. The mortar has a high water retaining capacity and plasticity. Ensure block lay controlled vertically by plumb, and

Inspection Report for Block work

H W

PTTEP International Limited Page 10 / 17

Zawtika Development Project Phase 1A Document : MM-ZTK-1A-ONEP-QUA-PLN-0027

EPCIC of Zawtika Onshore Pipeline Revision :C1

Date : 26- Jul-2012

Inspection and Test Plan for Civil Construction Remark:

S.N QUALITY RELATED ACTIVITY

REFERENCE DOCUMENT

CHARACTERISTICS TO BE VERIFIED

ACCEPTANCE CRITERIA

VERIFYING DOCUMENT CONTRACTOR COMPANY

level to be controlled by level gauge. Ensure mortar joints 1cm thick with full mortar sealed along the entire length of joints and properly bonded. All partitions horizontally and vertically reinforced with reinforcing steel bars as indicated in the drawings Ensure all interspaces between block and utility lines fully sealed.

10

Wall Finishes MM-ZTK-1A-ONEP-CIV-PRC-0005

External Rendering Internal Plastering

The coarse stuff for undercoats made of cement, lime ,and sand in the proportions of 1:6 in volume The undercoat laid uniformly to an average thickness of 10mm Ensure the undercoat thoroughly dry before application of the final coat. Ensure materials for the finish coat coloured Portland cement accordance with the manufacturer's recommendations and approved by COMPANY Mixing proportions verified by trial mixing at the job site acceptable to COMPANY’s representative Ensure dried and lump plaster discarded and not re-mixed with a new batch

Inspection Record of Plaster

H W

11 Ceiling MM-ZTK-1A-ONEP-CIV

-PRC-0005 Acoustical Tile

Install all acoustical tiles as required in AFC drawings Ensure acoustical tiles carefully handled to prevent being deformed in the course of installation any dirty

Installation record

H W

PTTEP International Limited Page 11 / 17

Zawtika Development Project Phase 1A Document : MM-ZTK-1A-ONEP-QUA-PLN-0027

EPCIC of Zawtika Onshore Pipeline Revision :C1

Date : 26- Jul-2012

Inspection and Test Plan for Civil Construction Remark:

S.N QUALITY RELATED ACTIVITY

REFERENCE DOCUMENT

CHARACTERISTICS TO BE VERIFIED

ACCEPTANCE CRITERIA

VERIFYING DOCUMENT CONTRACTOR COMPANY

Suspended Ceiling Installation

cleaned off. Ensure all edge strips installed straight with all corners, junctions and cuts to be made neatly Ceiling joist properly installed prior to plasterboard/aluminium board mounting, ensure the level of joist strictly controlled Ensure ceiling level, shape not be collided with lighting location, locale ducts, cable and equipments where concealed above the ceiling

12

Painting and Decoration

MM-ZTK-1A-ONEP-CIV-PRC-0005

Painting and Decoration

Ensure the paint kept well stirred and shall not be used when a thick sediment is found Samples for testing taken from the sealed containers or from the workmen's kettles on the works Ensure all surfaces thoroughly prepared and clean, free from loose and powdery material and sufficiently dry Ensure each layer of paint thoroughly dry before the next layer is applied and inspected by Company. Ensure the coating even and adequate and the finish free from orange-peel appearance, runs, sags, curtaining and other defects

Inspection Record of Plaster

H W

13 Windows and Doors and Furniture Installation

MM-ZTK-1A-ONEP-CIV-PRC-0005

Windows and Doors and Furniture

Windows and doors installed with strict attention to detail and dimension, and set plumb and true in the openings, securely anchored and held in alignment

Installation report

R R

PTTEP International Limited Page 12 / 17

Zawtika Development Project Phase 1A Document : MM-ZTK-1A-ONEP-QUA-PLN-0027

EPCIC of Zawtika Onshore Pipeline Revision :C1

Date : 26- Jul-2012

Inspection and Test Plan for Civil Construction Remark:

S.N QUALITY RELATED ACTIVITY

REFERENCE DOCUMENT

CHARACTERISTICS TO BE VERIFIED

ACCEPTANCE CRITERIA

VERIFYING DOCUMENT CONTRACTOR COMPANY

14

Floor Finish MM-ZTK-1A-ONEP-CIV-PRC-0005

Cement Aggregate Support Base Watering Pouring fine stone concrete Surface finish

Ensure cement conform to all requirements of the latest edition of ASTM C-150 and design drawing requirements, and supplied by vendors approved by COMPANY Ensure all aggregate conform as close as practical to ASTM C-33 Ensure the support of raised floor is galvanized steel raised support Ensure the surface of base layer surface, mortar and other debris clean and free of oil, grease and foreign matters Ensure the day before the construction of floor to sprinkle wet. The second day when construction to ensure that the ground wet, no water As concrete is being grouted, ensure the top surface properly levelled to bring the top surface to the elevations required in drawings. To ensure that at least 6 cm thickness reach Ensure float finish applied while the concrete is still plastic. Care taken not to overwork the concrete and avoiding excess of water and mortar being brought to the surface Ensure trowel finish employed until the concrete has hardened enough so that water and mortar are not worked to the surface. Excessive trowelling which

Record of Concrete Work

W R

PTTEP International Limited Page 13 / 17

Zawtika Development Project Phase 1A Document : MM-ZTK-1A-ONEP-QUA-PLN-0027

EPCIC of Zawtika Onshore Pipeline Revision :C1

Date : 26- Jul-2012

Inspection and Test Plan for Civil Construction Remark:

S.N QUALITY RELATED ACTIVITY

REFERENCE DOCUMENT

CHARACTERISTICS TO BE VERIFIED

ACCEPTANCE CRITERIA

VERIFYING DOCUMENT CONTRACTOR COMPANY

Raised floor

produces crazing avoided Ensure the floor smooth, clean, dry, no impurities, no dust Arrangement in the floor of the cable, ensure electrical appliances, air ducts and air conditioning system in the installation of the floor before the completion of construction. Floor installation height on the wall marked, the floor is at the same level. Ensure Installation support adjusted to the same height required, and the support is placed into the ground grid line intersections Ensure screws securing cross member to the support, and that in the same plane and perpendicular to each other Ensure the floor is smooth on the finished beam, with the level of instrument control the height of the floor

15

Tilling MM-ZTK-1A-ONEP-CIV-PRC-0005

Cement Lime

Mixed Portland cement conforming to ASRM C91 Ensure lime hydrated lime, commercially available product, the total unhydrated calcium oxide (CaO) and magnesium oxide (MgO) in the hydrated product not exceed 8% by weight, calculated on as received basis. Ensure floor and wall tiles manufacturer and the color of tile selected and approved by COMPANY

Inspection Report for Tilling

W W

PTTEP International Limited Page 14 / 17

Zawtika Development Project Phase 1A Document : MM-ZTK-1A-ONEP-QUA-PLN-0027

EPCIC of Zawtika Onshore Pipeline Revision :C1

Date : 26- Jul-2012

Inspection and Test Plan for Civil Construction Remark:

S.N QUALITY RELATED ACTIVITY

REFERENCE DOCUMENT

CHARACTERISTICS TO BE VERIFIED

ACCEPTANCE CRITERIA

VERIFYING DOCUMENT CONTRACTOR COMPANY

Tiles Ceramic wall tiles Ceramic floor tiles Samples Installation of Wall Tiles/ Scratch Coats Mortar Beds

Ceramic wall tiles for wall 12”x12”, ensure not less than 5mm thick and have a non-vitreous body, the surface with a high gloss finish, conform to the requirements of Thai Industrial Standard TIS613 and TIS614 Ensure size of ceramic 8”x8” and 12”x12” not less than 9mm thick, conform to the requirements of Thai Industrial Standard TIS38 Ensure surfaces to receive applications of tiles clean and free of oil, grease and foreign matters Ensure scratch coats applied as foundation coats not less than 6 mm thick and composed by volume of 1 part port-land cement to 5 parts damp sand to1/5 part hydrated lime, and mixed with the minimum amount of water necessary to produce a workable mass Ensure mortar for scratch coats used within 1 hour after mixing Ensure scratch coats kept moist, and an interval of at least 48 hours provided between application of scratch coats a-id application of wall tiles Ensure mortar beds composed by volume of 1 part cement to 1/2 part hydrated lime to 5 parts damp sand, and mixed with the minimum amount of water necessary to produce a workable mass

PTTEP International Limited Page 15 / 17

Zawtika Development Project Phase 1A Document : MM-ZTK-1A-ONEP-QUA-PLN-0027

EPCIC of Zawtika Onshore Pipeline Revision :C1

Date : 26- Jul-2012

Inspection and Test Plan for Civil Construction Remark:

S.N QUALITY RELATED ACTIVITY

REFERENCE DOCUMENT

CHARACTERISTICS TO BE VERIFIED

ACCEPTANCE CRITERIA

VERIFYING DOCUMENT CONTRACTOR COMPANY

Tiles Grouting Installation of floor tiles/ Setting beds

Ensure mortar beds brought out flush with temporary screeds or guide strips so placed as to give true even surface at the proper distance from the finished face of tile, and shall have a finish suitable for setting tiles Ensure joints straight, level, perpendicular, and of even width not exceeding 1.5 mm Ensure vertical joints maintained plumb for the entire height of the tile work Before setting, ensure tiles thoroughly soaked in clean water and drained so that no free moisture remains on the back of tile Ensure the joints tooled slightly concave, and the excess mortar cut off and wiped from the face of the tile Ensure setting beds composed by volume of 1 part cement to 6 parts damp sand, and mixed with the minimum amount of water necessary to produce a workable mass Ensure setting beds, screeded to a true plane, and sloped to drains or levelled to the drain pipe Ensure the average thickness of setting bed in any space 25 mm but in no case the setting beds less than 20 mm or more than 30mm thick Ensure the joints between the tiles uniform and not

PTTEP International Limited Page 16 / 17

Zawtika Development Project Phase 1A Document : MM-ZTK-1A-ONEP-QUA-PLN-0027

EPCIC of Zawtika Onshore Pipeline Revision :C1

Date : 26- Jul-2012

Inspection and Test Plan for Civil Construction Remark:

S.N QUALITY RELATED ACTIVITY

REFERENCE DOCUMENT

CHARACTERISTICS TO BE VERIFIED

ACCEPTANCE CRITERIA

VERIFYING DOCUMENT CONTRACTOR COMPANY

Ceramic floor tiles Grout Mixture

less than 6 mm nor more than 9 mm in width Ensure grout mixture for joints of ceramic floor tiles a slurry of white cement and fine screened sand of equal parts mixed with a Minimum amount of water Ensure neat white cement applied to the floor and forced into the joints with the edge of a wood block or trowel. Ensure excess grout removed at once by use of a sponge, squeegee, or burlap to finish the joints and surface clean.

16

Curing MM-ZTK-1A-ONEP-CIV-PRC-0005

waterproof paper Ensure floors covered with waterproof paper with joints lapped at least 10 cm and tape sealed or held down with planks or other weights. Floors allowed to damp-cure for at least 72 hours before foot traffic is permitted thereon

Record of Concrete Work

W R

17

Documentation MM-ZTK-1A-ONEP-CIV-PRC-0005

Inspection Report for Clearing Removal Inspection Report for Excavation Inspection Report for Backfilling Record of Foundation Survey Record of Concrete Work Inspection Report for

Inspection Report for Clearing Removal Inspection Report for Excavation Inspection Report for Backfilling Record of Foundation Survey Record of Concrete Work Inspection Report for Steel Bar Installation Inspection Report for Formwork Curing record of precast concrete Inspection Report for Installation of Steel Fencing Inspection Report for Block work

Inspection Report for Clearing Removal Inspection Report for Excavation Inspection

H R

PTTEP International Limited Page 17 / 17

Zawtika Development Project Phase 1A Document : MM-ZTK-1A-ONEP-QUA-PLN-0027

EPCIC of Zawtika Onshore Pipeline Revision :C1

Date : 26- Jul-2012

Inspection and Test Plan for Civil Construction Remark:

S.N QUALITY RELATED ACTIVITY

REFERENCE DOCUMENT

CHARACTERISTICS TO BE VERIFIED

ACCEPTANCE CRITERIA

VERIFYING DOCUMENT CONTRACTOR COMPANY

Steel Bar Installation Inspection Report for Formwork etc

Inspection Record of Plaster Inspection Report for Tilling etc prepared/verified approved by Contractor QC and submitted to Company.

Report for Backfilling etc

Legends : H – Hold, W – Witness, M – Monitoring, R- Review.