modernizammodernizamodernization electric substaodernization electric ... ·...
TRANSCRIPT
MODERNIZATION ELECTRIC SUBSTATIONS 110/20 KV
Buletinul AGIR nr. 4/2012 ● octombrie-decembrie 1
MODERNIZAMODERNIZAMODERNIZAMODERNIZATION ELECTRIC SUBSTATION ELECTRIC SUBSTATION ELECTRIC SUBSTATION ELECTRIC SUBSTATIONSTIONSTIONSTIONS 110/20 KV110/20 KV110/20 KV110/20 KV
Eng. Florin DRACEANU PhD, Assoc. Prof. Eng. Cezar Dumitru POPA PhD,
Assoc. Prof. Eng. Dumitru Radu PENTIUC PhD, Assoc. Prof. Eng. Leon MANDICI PhD
University „Stefan cel Mare” from Suceava
Faculty of Electrical Engineering and Computer Science,
.
ABSTRACTABSTRACTABSTRACTABSTRACT. . . . The subjectsThe subjectsThe subjectsThe subjects ””””connection to theconnection to theconnection to theconnection to the national energy systemnational energy systemnational energy systemnational energy system installationsinstallationsinstallationsinstallations producingproducingproducingproducing renewable electricityrenewable electricityrenewable electricityrenewable electricity """" is topical is topical is topical is topical andandandand of of of of great great great great importanceimportanceimportanceimportance for futurefor futurefor futurefor future managers ofmanagers ofmanagers ofmanagers of wind powerwind powerwind powerwind power, , , , photovoltaicphotovoltaicphotovoltaicphotovoltaic, , , , biomassbiomassbiomassbiomass cogenerationcogenerationcogenerationcogeneration. . . . Economic situationEconomic situationEconomic situationEconomic situation inininin RomanRomanRomanRomaniaiaiaia alsoalsoalsoalso influenceinfluenceinfluenceinfluence thethethethe choice ofchoice ofchoice ofchoice of the final solutionthe final solutionthe final solutionthe final solution. . . . Whatever the solutionWhatever the solutionWhatever the solutionWhatever the solution chosenchosenchosenchosen safety and security ofsafety and security ofsafety and security ofsafety and security of SENSENSENSEN are those are those are those are those thatthatthatthat prevailprevailprevailprevail in the final decisionin the final decisionin the final decisionin the final decision. . . . InInInIn the followingthe followingthe followingthe following I will presentI will presentI will presentI will present a solutiona solutiona solutiona solution to upgrade anto upgrade anto upgrade anto upgrade an existingexistingexistingexisting connectionconnectionconnectionconnection stationsstationsstationsstations SENSENSENSEN in in in in order toorder toorder toorder to connectconnectconnectconnect a winda winda winda wind.... Keywords:Keywords:Keywords:Keywords: station, tehnology, AIS, GIS, SEN (the national energy system),
1. INTRODUCTION
Power System consists of the set of all
interconnected power plants located in the territory of a
country by which the manufacture, transportation,
distribution and use of electricity.
Connection to National Energy System NES all
electricity producers are particularly important for the
performance of the obligations assumed by Romania in
Directive 77/2001/CE Strategy for renewable energy
approved by GD 535/2003 and Roadmap energy, part
of the EU accession agreement.
The main objectives for connection to NPS
park wind power or solar are:
• LES MT and MT connection points;
• MT/110 kV transformer substation;
• LES / 110 kV;
• Extending substation 110/20 kV connection existing
in the national energy system (NES).
Developed by geographical area is as follows:
in total, about 60% of EC are located in Dobrogea, 30%
in Moldova and only 10% in the rest of the country.
There is currently an installed capacity of about 1,400
MW in operation CEE and CEE 14,000 MW have been
awarded contracts for connection
2. CONSIDERATION TEHNOLOGIES FOR WORKSTATION IN THE NES
The performance of a transformer station
110/20 kV is mainly given by:
- The quality of functional assemblies
- Type of single line diagram
- Operating system adopted.
The performance must consider: its importance
in SEN (for interconnection of power evacuation from
plants etc.), The nature of consumers with the risk
assumed by the owner and environmental impacts
including population.
As functionality for power plants renewable
energy sources are:
a) collecting the medium voltage substations for
distributed sources;
b) transforming power stations (the most common being
MT/110 kV) to adjust parameters generated energy
optimal technical and economic conditions of transport
to the point of coupling to the network;
c) power stations connecting to the transmission /
distribution as specified in the technical connection of
the operator product of the transmission, the following:
Buletinul AGIR nr. 3/2013 ● iulie-septembrie_____________________________________________________________________________________
319
INT. SYMPOSIUM ON ELECTRICAL ENGINEERING AND ENERGY CONVERTERS – ELS 2013
Buletinul AGIR nr. 4/2012 ● octombrie-decembrie 2
• extension of existing power stations, with a scheme
to minimize disruption during the installation operation
during extension works;
• Building a power station with an input-output
scheme in an existing power line, the 110 kV network
application;
d) power stations directly connected to the user with
NES in the airline, LES-LEA (underground electric
line - overhead line ) connection.
For grid connection of renewable energy
sources have identified two specific conditions:
- Making enlargements with minimizing freezing
facilities
- Values for nominal currents of devices / busbar 4000
A and the threshold currents of 40 kA short circuit.
Analyzing all the above we can identify two
types of transformer substations:
- User station, the station that belongs to the producer of
renewable electricity;
- Station record, being the state where they connect
with NES.
2.1 User stations 110 kV electric
Maximum power generated within wind farms /
PV are 20-100 MW so that schema used is the line-
transformer block.
In most cases these stations are of the AIS (air-
insulated stations) and more rarely of GIS (Gas
Insulated stations). Both types of stations in terms of
economic costs (construction + equipment +
installation) so close that it is time to achieve decisive,
all customers without exception, are interested in an
operation in the shortest time possible.
An example of a stop used with a single step-up
transformer can be seen in Figure 2.1, and an example
of a user station with two transformers elevated in
figure 2.2 and 2.3.
In Figure 2.1 and 2.3 are classical stations with
modern equipment and figure 2.2 we have a compact
docking station.
Fig. 2.1 AIS station with a single-up transformer consists of a single
cell
Fig. 2.3 AIS station with two transformers lifts
Fig. 2.3 AIS station consists of two step-up transformers two cells
_____________________________________________________________________________________INT. SYMPOSIUM ON ELECTRICAL ENGINEERING AND ENERGY CONVERTERS – ELS 2013
320 _____________________________________________________________________________________
Buletinul AGIR nr. 3/2013 ● iulie-septembrie
MODERNIZATION ELECTRIC SUBSTATIONS 110/20 KV
Buletinul AGIR nr. 4/2012 ● octombrie-decembrie 3
2.2 110 kV substation connection
If the connection state is changed stations
generally operators of distribution networks, E-on and
ENEL, impose strict mode, type of connection and the
system solution.
For substations connecting with input-output
scheme in existing power line they use compact
modules required in a scheme to switch to H line,
without hitch and dividers to users.
For connection to existing 110 kV substation
design becomes a real challenge being atypical
situations on a case by case:
• connection to the existing roof, available in a field;
• Connection to existing roof, extended by 1-2 fields for
the new cell;
• installing a breaker in an existing cell,
• adapt the new airline starting cells or cord, if
applicable;
• location of new construction on existing surface
station;
• modernization of relay protection.
• Enhancing the metering and power quality
monitoring,
• integration of new cells in the network operator's
SCADA system.
The following are two types of connection stations,
One in Figure 2.4 is one stop scheme input - output, and
in Figure 2.5 is shown a refurbished stations with
compact modular SF6.
Fig. 2.5 GIS station with two line cells connected to the National
Grid via overhead line
Fig. 2.6 GIS station with two cell line cable entry - exit air
2.3 Technical-economic study of 110 kV substations
The apparatus of existing stations composition
insulating medium is air, SF6 and insulating oil and
carcasses and support insulators are porcelain or
composite materials.
As time passes and technology development
has moved from AIS GIS technology, these stations are
located Insulated especially in urban areas and areas
heavily polluted.
Currently upgrading stations within transport
networks is achieved through SF6 equipment with a
higher reliability than the domestic. Operating costs are
lower, and the average number of interruptions is
order of 0.2 interruptions / year. One can obtain a size
of less than about 10%.
The table below shows the values of 110 kV
primary equipment most commonly used in substations
of 110/20 kV. Value primare110kV equipment
Domeniul de cheltuieli per bucată Unitatea monetară € lei
Modul hibrid pt celula LEA 170000 765000
Modul hibrid pt celula LES 145000 652500
Modul hibrid pt celula TRAFO 155000 697500
Transformator de 25 MVA 305000 1372500
Intreruptor 1600A 29500 132750
Separator de cupla cu doua CLP 9100 40950
Separator tripolar delinie sau bară 8650 28925
Separator monopolar cu un CLP 4000 18000
Transf. de tensiune capacitiv 5200 23400
Transformator de tensiune inductiv 5800 26100
Transformator de curent 5850 26325
Descarcator Zn-O 1250 5625
Descărcător de nul 1000 4500
Izolatori dubli 900 4050
_____________________________________________________________________________________MODERNIZATION ELECTRIC SUBSTATIONS 110/20 KV
Buletinul AGIR nr. 3/2013 ● iulie-septembrie_____________________________________________________________________________________
321
INT. SYMPOSIUM ON ELECTRICAL ENGINEERING AND ENERGY CONVERTERS – ELS 2013
Buletinul AGIR nr. 4/2012 ● octombrie-decembrie 4
Information a user station, belonging to EC 20
MVA, AIS type cell equipped with a transformer as in
Figure 2.1. has a value of about 1.042 million euros and
a connecting station as in Figure 2.5 equipped with two
GIS cell line with a simple busbar sectioned
longitudinally with a three-phase separator coupling has
a value of about 1.280. 000.
3. SOLUTIONS FOR CONNECTION TO NES
Consider a wind power plant with a capacity of 70 MVA consists of 23 wind turbines, a substation MT/110 kV and 110 kV underground transmission line, which requires distribution network manager to connect to the National Grid through a station the 110 kV as in Figure 3.1a, b.
The station is currently Connection type H configuration, simple bar 110 kV sectioned longitudinally through a coupling cell being connected to two stations, one 400/110 kV and two 220/110 kV.
On the station has two 110 kV tie line - transformer, equipped with one switch IO 110 kV 1600 A, acted with a oleopneumatic, MOP 1 second transformer 25 MVA, 110/20 kV Type TTU-FS , placed on concrete foundations, equipped with oil collection tank, filled with.
SL SL
I I
I I
SB SB
SB SB
BC
110
TTTT
TTTT
Tr Tr
TCTC
TCTC
DD
Ic
TSI
PP
TSI
ScSc
BC
110
Fig 3.1.a overview
1
1
2
2
Sa2220/110 kV
110kV
110kV
Sa1400/220/110kV
Btr
LEA 110kV
OL Al 240/40mm L=20km
2
L
EA
110
kV
OL
Al
240
/40
mm
L
=13
km
Bc
S S
I
I I
I
TC TC
TC TC
TT TT
D D
T1T2 25 MVA25 MVA
S
Sc Sc
S
D D
CLP CLP
Ic
ST 110/20kV
Fig. 3.1b wiring diagram monifilară
The following are considered four solutions to expand and modernize the existing station SEN, in order to connect the wind farm to farm. Using electric line cable solution is preferred because the manufacturing technology has developed a lot of cables that allowed carrying a higher power safer (insulation performance, cooling, oil-free alloys improved and enlarged sections) , also reducing manufacturing costs. Solution -1 - consists of: Creating a new cell
line of 110 kV underground alpha1 CEED with modern
air-insulated equipment, in accordance with the
requirements of network management. Step cell will be
16 m and requires expansion stops outline an area of 9 x
30 m to the right or left of the control room.
Demarcation point and patrimonial
management facility is across the line for the cell
separator new 110 kV station.
_____________________________________________________________________________________INT. SYMPOSIUM ON ELECTRICAL ENGINEERING AND ENERGY CONVERTERS – ELS 2013
322 _____________________________________________________________________________________
Buletinul AGIR nr. 3/2013 ● iulie-septembrie
MODERNIZATION ELECTRIC SUBSTATIONS 110/20 KV
Buletinul AGIR nr. 4/2012 ● octombrie-decembrie 5
SL
SL
I I
SB SB
TT TT
TT
TC TC
D
D
CT
Ic ScSc
SL
I
SB
TT
TC
D
BC
110
BC 110
I I
SB SB
TTTT
Tr Tr
TCTC
TSI
PP
TSI 9000
300
00
Fig 3.2 Solution -1-
LES 110 kV connection to the cell terminals
will be designed outdoor dry type insulation composite
joint backing surge.
Disposition chosen design architecture retains
the existing line of the other two cells.
Busbar extension is made with aluminum bar AL
following the same section.
Cell line 110 kV project will be equipped with:
- An outdoor circuit breaker, SF6 (Um = 123 kV, In =
1600 A);
- Three current transformers, single-phase type support
(100/5/5/5/5 A);
- Three capacitive voltage transformers (110 / √ 3 / 0.1 /
√ 3 / 0,1 kV);
- 3 ZnO surge arresters and insulation composite
(meters downloads included) mounted to protect the
cables of 110 kV;
- A rotating separating two knives pole grounding at
each breaker and one for LES;
- A pole rotary separator, single CLP to breaker.
At 110 kV bar will connect a new measuring
cell made with 3x TT 110 / √ 3 / 0.1 / √ 3/0, 1 kV.
Installation of earthing station will be completed by
extending the surface with boundary extension (at 1 m
from fence enclosure) tubular electrode OL-Zn Φ 2
"1/2, l = 3m, 6m place between them and connected to a
strip 50x5 mm Zn OL. Potential distribution routing
socket will be extended by extending the main earthing
conductor electrodes OL Zn horizontal strip 50x5 mm.
Equalization distance between bands will be the same
as the current distance, where one or more of the main
earthing conductor will be affected by the work of the
foundation for bearing equipment designed, then it will
be replaced, taking into account the average distance
between bands of equalization of 5m.
Fig 3.3 Sample cell type underground line departing AIS
The cell design shall be provided with
terminals numerical protection and remote control
functions, which will be mounted in cabinet for
protection tomandă-cell and panel designed for
transformers.
Protection scheme based on the line will be
composed of:
- Longitudinal differential protection provided to
support tactical
- Maximum current protection delay;
- Directional homopolar current maximum protection;
- Subsidiary protection;
As complementary terminal will mount an IED
with PLC functions, it will retrieve and monitor current
in CT secondary sites of cell line when transmitting Sa1
confinement exceeding the maximum current value
deconecatrea of strength produced by dispatchable wind
power plant CEED.
Solution -2- solution contains 1 total refurbishment
with modern equipment plus air-insulated.
Is the most inconvenient due to land costs for
new cell for the cost of new equipment.
Solution -3- consists of: Creating a new cell line EEC
110 kV underground way through a 110 kV compact
multifunctional complex type DY 107/10 R0-A
encapsulated in SF6 Figure 3.4.
The module will be placed under the existing
110 kV bar and will encompass the following functions:
_____________________________________________________________________________________MODERNIZATION ELECTRIC SUBSTATIONS 110/20 KV
Buletinul AGIR nr. 3/2013 ● iulie-septembrie_____________________________________________________________________________________
323
INT. SYMPOSIUM ON ELECTRICAL ENGINEERING AND ENERGY CONVERTERS – ELS 2013
Buletinul AGIR nr. 4/2012 ● octombrie-decembrie 6
The module will be placed under the existing
110 kV bar and will encompass the following functions:
Cell line: - 2x SEP 123 kV + CLP;
- breaker 2500 A;
- 3xTC 100/5/5/5 A,
- 3xTT 110/√3 / 0,1/√3 / 0,1 kV;
- SF6 cable terminal pole;
- Terminal connection bars 110 kV.
Additionally compact module is essential to
measuring cell and measuring group ready for
implementation in remote management system
implemented at NPS;
SL
I
SB
TT
TC
D
BC
11
0
SL
I
SB
TT
TC
D
Ic ScSc
TSI TSI
I
SB
TT
Tr
TC
PASS
I
SB
TT
Tr
TC
PP
Fig 3.4 solution - 3 –
The point of separation of facilities
management and property is LES connection terminals
SF6 compact module.
The overall dimensions allow the installation
GIS module between the pillars of the existing bar
crossmember, respecting and protecting electrical
distances acc on 101/85.
Atmospheric surge protection and / or
switching will be performed with ZnO arresters
mounted composite insulated 110 kV bar.
Arresters are connected in ways distinct from
existing installation earthing band, OL
Zn 50x5 mm or according to equipment
supplier's instructions.
Monitoring and diagnosis module is compact
multifunctional local device panel (HMI - Human-
Machine Interface).
Solution -4- consist of: Complete refurbishment of the
existing substation with SF6 insulated compact
modules.
Teren disponibilizat - 40%
PASS PASS
PASS PASS PASS
Sc
BC
110
BC
110
Tr
DD
Tr
P P
TSIT SITT
410
00
270
00
46000
Fig 3.5 solution -4-
4. CONCLUSIONS
The level of technology used in the creation,
development or upgrading substations is more advanced
the greater reliability, it provides enhanced Mentana
during life of stations increases.
Economic situation in Romania also influence
the choice of the final solution. Whatever the solution
chosen safety and security of SEN are those that prevail
in the final decision.
To increase safety RPS will create all the
conditions required by developers electricity markets
using highly reliable gear for systems monitoring,
command and control parameters evolution functional
assemblies.
BIBLIOGRAPHI
[1] Ghid privind accesul la RET a noilor solicitanţi sau
dezvoltări ale utilizatorilor existenţi, Transelectrica 2011 [2] ABB, Switchear manual 10th edition 2004
[3] ABB, Gas Insulated Switchear modular and flexible, 2009
_____________________________________________________________________________________INT. SYMPOSIUM ON ELECTRICAL ENGINEERING AND ENERGY CONVERTERS – ELS 2013
324 _____________________________________________________________________________________
Buletinul AGIR nr. 3/2013 ● iulie-septembrie