montrose community centerupdate& mrd outdoor facility...
TRANSCRIPT
Montrose Community Recreation Center Update & MRD Outdoor Facility Plan
September 23rd, 2015
Montrose CRC and Park
Trails, Pickleball Courts, Playgrounds, Natural Areas, Picnic Areas, Water Play, Tennis, Softball Fields, Handball Courts, Outdoor Pool, Outdoor Basketball Courts, Open Space, Multi‐Purpose Artificial Turf Field
CONSTRUCTION PROGRESS
CONSTRUCTION PROGRESS
CONSTRUCTION PROGRESS
CONSTRUCTION PROGRESS
CONSTRUCTION PROGRESS
MRD’s Priority, CRC ‐ Phase One WoodgateCONSTRUCTION PROGRESS• Guaranteed Maximum Price Executed, Which Is Within The Budget MRD Has
Secured
• Enhanced Plan Is Nearly Fully Funded By Meeting Capital Campaign Goal CRC will be 80K+ Square Feet, the largest on the western slope
• Foundation Near Complete: Earthwork By Haynes And 400 Piles By Colorado Piling
• Pile Caps, Grade Beams And Tilt Concrete Panel Walls In Progress by Mayes Concrete
• Most Subcontractors Secured 14 bids on 60 subcontracts from locals; 11 likely awarded. 28 from western
slope.
• Woodgate Road Widening Planned From The Roundabout South To Oxbow Drive
• GOCO Grant Being Pursued Now, Which Would Enable Outdoor Facilities Prior to CRC Opening
MRD’s Priority, CRC ‐ Phase One WoodgateFACILITY RENDERINGS
MRD’s Priority, CRC ‐ Phase One WoodgateFACILITY RENDERINGS
MRD’s Priority, CRC ‐ Phase One WoodgatePUBLIC INPUT: OUTDOOR FACILITIES
2005 Needs Assessment Survey, Statistically Valid Survey of 2,500 households:#1 Trails at 72% (out of 26 parks and recreation facilities rated)
2011 Community Survey, 709 responses, most needed facilities, indoor/outdoor: #1 Indoor Swimming Pools at 54%. #2 Trails at 51%
8.21.13 CRC Master Plan Community Meeting, 96 responses, most needed outdoor facilities at CRC#1 Outdoor Walking Trails at 68%. #2 Picnic Areas at 30%. #3 Multi‐Use Sports Fields at 27%
8.20.15 CRC Design workshop, 71 responses, most needed outdoor facilities at CRC:#1 Trails. #2 Outdoor Fields. #3 Natural Areas, #4 Picnic Areas, #5 Pickleball
9.23.15 GOCO workshop for CRC phase II, xx responses, most needed outdoor facilities given budget at CRC:#1. #2. #3. #4. #5.
MRD’s Priority, CRC ‐ Phase One Woodgate2013 MASTER PLAN
PHASE II: GOCO GRANT APPLICATION
NEW 10 FT. SIDE PERIMETER TRAIL TO COMPLETE WALKING LOOP AND CONNECTS TO CITY TRAIL SYSTEM AT WOODGATE ROAD
6 PICKLEBALL COURTS COMPLEX
YOUTH WATER PLAY FEATURE:WATER JOURNEY “RACE”
(2) YOUTH CLIMBING BOULDERS
EXPAND GRASS OPEN SPACE AND MULTI‐PURPOSE FIELDS. INCLUDE PERIMETER AND STREET FRONTAGE TREES
MONTROSECOMMUNITYRECREATIONCENTER
ARROYO
UNDEVELOPED OPEN SPACE
UNDEVELOPED OPEN SPACE
UNDEVELOPED OPEN SPACE
MRD’s Priority, CRC ‐ Phase One WoodgatePICKLEBALL COURT COMPLEX
PICKLEBALL COURT:20’ WIDE44’ LONG10’ PERIMETER ZONE
MRD’s Priority, CRC ‐ Phase One Woodgate10 FT. WIDE PERIMETER TRAIL
THE 10 FT. WIDE PERIMETER TRAIL PROVIDES VARIOUS WALKING LOOPS AND CONNECTS TO THE CITY TRAIL SYSTEM AT WOODGATE ROAD.
1 MILE “FIGURE 8” LOOP
1/4 MILE
1/2 MILE
‐0‐ BEGIN
1 MILE = 1.5 TIMES AROUND PERIMETER, OR FIGURE “8” PATTERN FROM BLDG ENTRY
MRD’s Priority, CRC ‐ Phase One WoodgateCLIMBING BOULDERS: OPTION A
“EROSION BOULDER”8’WIDE X 13’ LONG X 8’ TALL
“THE MIGHTY FIN”3’WIDE X 14’ LONG X 9’ TALL
MRD’s Priority, CRC ‐ Phase One WoodgateWATER JOURNEY: OPTION B
WATER JOURNEY“RACE” SERIES:16’ WIDE26’ LONG
UPDATED FULL BUILD-OUT PLAN
MONTROSECOMMUNITYRECREATIONCENTER
ARROYO
ARTIFICIAL TURF MULTI‐PURPOSE FIELDS
EXPAND PARKING LOT
PICNIC SHELTERS & PLAYGROUND COMPLEX
TENNIS COURT COMPLEX
PICNIC SHELTER, PLAYGROUND, TOT LOT, & YOUTH FIELD
UNDEVELOPED OPEN SPACE
TRAILHEAD, PARKING, & BRIDGE
OUTDOOR POOL COMPLEX WITH POOLS, SPLASH PADS, PICNIC AREAS, & PLAY STRUCTURES
HANDBALL COURTS & 2 MORE PICKLEBALL EXPAND
MAINTENANCE BLDG
(2) BASKETBALL COURTS
HOLLY PARK RENOVATION IN 2017
NEW DUGOUTS & BLEACHERS
ADD BIKE LANES ON BOTH SIDES OF ROAD
EXPAND SOFTBALL FIELD & ADD MULTI‐PURPOSE FIELDS
ADD PARKING TO NORTH SIDE OF RIVERBOTTOM DRIVE
REMOVE OLD TENNIS COURTS & ADD PARKING
EXPAND BASKETBALL COURT
ADD RIGHT & LEFT TURN LANES
BEAUTIFY STREET FRONTAGE
ADD BIKE LANES ON BOTH SIDES OF ROAD
MRD’s Priority, CRC ‐ Phase One WoodgateOUTDOOR FACILITY BUDGET INTO 17
MRD’s Priority, CRC ‐ Phase One WoodgateGOCO OUTDOOR FACILITY BUDGET
MRD’s Priority, CRC ‐ Phase One WoodgateCONSTRUCTION TIMELINE ESTIMATETimeline for Outdoor Facility Components in Bold
Summer-Fall 2015: Construct CRC building foundation systems, drive 400 piles
Fall 2015: Erect exterior concrete tilt panel walls & begin steel roof structure
Fall-Winter 2015: Start roofing and exterior windows
Winter 2016: Begin pool excavations
March 2016: Notification of Potential GOCO Grant Award
May 2016: Complete Design of Outdoor Recreation Components
Summer 2016: Install gym wood floor
Late 2016: Complete Outdoor Facility Construction
Late 2016: CRC Grand Opening
Early 2017: Complete Field House Construction (Renovation of current Aquatic Center)