SUBSIDY REINVESTMENT AND EMPOWERMENT PROGRAMME PROGRESS REPORT MINISTERIAL PLATFORM JULY, 2013 By Nze Akachukwu Nwankpo, Secretary SURE-P

Upload: fminigeria

Post on 05-Dec-2014

1.087 views

Category:

Business


1 download

DESCRIPTION

 

TRANSCRIPT

Page 1: #MP2013 Presentation of SURE-P

SUBSIDY REINVESTMENT

AND EMPOWERMENT

PROGRAMME

PROGRESS REPORT

MINISTERIAL PLATFORM JULY, 2013

By Nze Akachukwu Nwankpo, Secretary SURE-P

Page 2: #MP2013 Presentation of SURE-P

H.E. Dr. Goodluck Ebele Jonathan GCFR

President, Commander-in-Chief of the Armed Forces of the Federal Republic of Nigeria

Page 3: #MP2013 Presentation of SURE-P

H.E. ARC. Mohammed Namadi Sambo GCON

Vice President, Federal Republic of Nigeria

Page 4: #MP2013 Presentation of SURE-P

Dr. Christopher Kolade CON

Chairman, SURE-P

Page 5: #MP2013 Presentation of SURE-P

Gen Martin Luther Agwai (rtd) Deputy Chairman, SURE-P

Page 6: #MP2013 Presentation of SURE-P

Nze Akachukwu Nwankpo ksj Secretary, SURE-P

Special Adviser to President on Tech. Matters

Page 7: #MP2013 Presentation of SURE-P

SURE-P INTERVENTION CATEGORIES • Category 1

– Infrastructure Development Projects • Roads and Bridges • Niger Delta (East – West) Rd • Railway

• Category 2

– Social Safety Net Programmes • Community Service, Women & Youth Empowerment

Programme (Includes Graduate Internship Scheme) • Maternal Child Health (MCH) • Mass Transit • Public Works (Ferma) • Vocational Training • Culture and Tourism

Page 8: #MP2013 Presentation of SURE-P

SURE-P

• 21-member Committee established February 13, 2012,

• Manages the Federal Government’s 41% share of the savings from the partial reduction of subsidies on petroleum products.

• Focused on critical infrastructure projects and social safety net programmes that will directly and positively impact on the people.

• Started receiving funds from July 2012. Project funds housed in CBN, Administrative funds kept in commercial bank.

Page 9: #MP2013 Presentation of SURE-P

SURE-P PROCESS

• Infrastructure Projects • Proper Project Management • Effective contractor supervision • Prompt payment of contractors for certified completed

work

• Social Safety Net Programmes • Project Design and Management

• Supervision of Project Implementation Unit in MDAs

• Prompt Cash Transfer to the PIUs

Page 10: #MP2013 Presentation of SURE-P

Roads, Bridges and Railways Abuja- Lokoja (197km) Benin – Ore road (293km) Kano – Maiduguri road (544km) Onitsha – enugu (157km) 2ND NIGER BRIDGE (2km) Loko – oweto bridge (2km) NIGER DELTA EAST - WEST ROAD SECTIONS I – IV (338km) Railways Lagos-Jebba Rail Line PH – Maiduguri Rail Line Jeba – Kano Rail Line Abuja – Kaduna Rail Line

Infrastructure Development Project

Page 11: #MP2013 Presentation of SURE-P

Financial Information Abuja – Lokoja (SECTION I-IV) Section I (43Km)

Contract 5862 Awarded July 2006

Section II(55Km) Contract 5863 Awarded July 2006

Section III(49Km) Contract 5884 Awarded Sept 2006

Section IV(50Km) Contract 5885 Awarded Sept 2006

Total

Contract Sum (Nbillion)

28.8 (6yrs) 31.2 25.8 31.087 116.887

SURE-P Budget 2012 (Nbillion)

7.5 7.5 5.00 5.000 25.000

SURE-P Amount Paid 2012 (Nbillion)

6.829 7.50 3.29 1.392 19.011

SURE-P Budget 2013 (Nbillion)

5.250

8.00

6.50 5.250

25.000

SURE-P Amount Paid 2013 (Nbillion)

0.987 3.539 1.693 0.839 7.049

Percentage Completion Before SURE-P

38.00% 38.00% 16.06% 16.28% N/A

Percentage Completion to date SURE-P

63.80% 73.72% 30.97% 22.26% N/A 11

Page 12: #MP2013 Presentation of SURE-P

Abuja – Lokoja Road

Gwagwalada Bridge

Page 13: #MP2013 Presentation of SURE-P

Financial Information Kano – Maiduguri (SECTION I-V) Section

I(102km): Contract 5878 Sept 2006

Section II(118): Contract 5879 Sept 2006

Section III(96): Contract 5880 Sept 2006

Section IV(96): Contract 5881

Section V(132): Contract 5869

Contract Sum (Nbillion)

55.122 65.315 45.181 51.903 67.795

SURE-P Budget 2012 (Nbillion)

4.0 4.00 4.00 4.000 4.000

SURE-P Amount Paid 2012 (Nbillion)

3.714 4.00 3.194 4.000 4.000

SURE-P Budget 2013 (Nbillion)

6.000

7.00

6.30 6.000

6.200

SURE-P Amount Paid 2013 (Nbillion)

3.338 1.541 2.655 3.152 3.158

Percentage Completion Before SURE-P

33.33% 51.02% 48.07% 31.82% 36.32%

Percentage Completion to date SURE-P

36.25%

46.88%

53.80%

47.44%

40.62% 13

Page 14: #MP2013 Presentation of SURE-P

Financial Information Benin-Ore -Shagamu(SECTION I-V) Phase I(36km):

Contract 6000 May 2009

Phase II(76km): Contract 5900 Dec 2009

Phase III(83km) Contract 6133 Dec 2012

Sect II(98km) Contract 6012 May 2009

Contract Sum (Nbillion)

12.64(3yrs) 24.266 65.223 2.498

SURE-P Budget 2012 (Nbillion)

6.0 6.00 0.00 10.50

SURE-P Amount Paid 2012 (Nbillion)

1.843 4.510 9.317 0.00

SURE-P Budget 2013 (Nbillion)

7.800 5.20

7.80

-

SURE-P Amount Paid 2013 (Nbillion)

0.00 0.00 3.630 -

Percentage Completion Before SURE-P

75.11%

55.61%

0.00%

98%

Percentage Completion to date SURE-P

98.20%

90.84%

17.00%

98% 14

Page 15: #MP2013 Presentation of SURE-P

Financial Information Onitsha – Enugu (Phase I-II) , 2nd Niger Bridge, Loko-Oweto Bridge

Phase I Sect I (52km): Contract 5929 Awarded April 2009

Phase II Sect I (49km): Contract 5929A Awarded Dec 2009

Section II(56km): Contract 5988 Awarded May 2009

Oju/Loko-Oweto Bridge (2km)C/No.6108 Oct 2011

2nd NIGER BRIDGE AT ONITSHA (2km) Ongoing Bpp process - JB

Contract Sum (Nbillion)

5.092 (3yrs) 4.613 7.251 36.118 -

SURE-P Budget 2012 (Nbillion)

3.0 2.00 3.00 5.00 5

SURE-P Amount Paid 2012 (Nbillion)

0.392 0.434 0.393 0.917 0.00

SURE-P Budget 2013 (Nbillion)

2.000

3.00

2.00 10.00

7

SURE-P Amount Paid 2013 (Nbillion)

0.00 0.00 0.00 5.151 0.00

Percentage Completion Before SURE-P

26.10% 8.61% 33.00% 0.00% -

Percentage Completion to date SURE-P

36.66%

14.66%

45.00%

13.68%

-

Page 16: #MP2013 Presentation of SURE-P

Ongoing Roads and Bridges

Projects Across the Nation

Page 17: #MP2013 Presentation of SURE-P

Financial Information EAST - WEST ROAD (SECTION I-IV) Section I (87km):

Contract 5867 Section II-I(101km): Contract ID/09/03

Section II-II: Contract ID/09/02

Section III(99km): Contract 5882

Section IV (51km): Contract 5883

Contract Sum (Nbillion)

112.166 84.759 48.973 66.459 37.509

SURE-P Budget 2012 (Nbillion)

4.700 5.000 8.000 4.000

SURE-P Amount Paid 2012 (Nbillion)

4.700 2.290 2.385 7.739 0.403

SURE-P Budget 2013 (Nbillion)

11.670

18.00

<- 8.600

4.000

SURE-P Amount Paid 2013 (Nbillion)

6.724 1.918 1.318 4.240 0.879

Percentage Completion Before SURE-P

52.21% 23.17% 18.21%

73.44%

53.55%

Percentage Completion to date SURE-P

66.52% 28.92% 27.31% 86.81% 58.45% 17

Page 18: #MP2013 Presentation of SURE-P

East – West Road

Page 19: #MP2013 Presentation of SURE-P

PROGRESS/OPERATION REPORT FOR RAILWAYS PROJECT S/No PROJECT CONTRACTOR PROGRESS

BEFORE SURE-P INTERVENTION

PROGRESS AS AT JUL 2013

ORIGINAL CONTRACT SUM

AMOUNT PAID TO DATE BY SURE-P

REMARKS

1 Lagos-Jebba Rehabilitation

Costain West Africa

100% N12.293bn N11.6Bn

Funded the completion of Western Line that enabled Train movement from Lagos-Kano

2 PH - Makurdi Railway Rehabilitation Project

Esser W.A 25% 42% N19.165bn N3.482Bn

Contractor fully on-site and achieving significant improvement with steady funding

3

Makurdi - Kanfanchan - Kuru - Jos & Kanfanchan - Kaduna Junction Railway Rehabilitation Project

Messrs CGGC 6% 30% N19.165bn N3.758Bn

Contractor fully on-site and achieving significant improvement with steady funding

4 Kuru - Maiduguri Railway Rehabilitation Project

LINGO 5% 14% N23.720bn N2.522Bn

Contractor fully on-site and achieving significant improvement with steady funding 19

Page 20: #MP2013 Presentation of SURE-P

20

PROGRESS/OPERATION REPORT FOR RAILWAYS PROJECT

S/No PROJECT CONTRACTOR PROGRESS BEFORE SURE-P

INTERVENTION

PROGRESS AS AT JUL

2013

ORIGINAL CONTRACT

SUM

AMOUNT PAID TO DATE BY

SURE-P

REMARKS

5 Abuja (Idu) - Kaduna Railway Modernisation Project

CCECC 35% 65% N136.39bn

N6.457Bn (Contractor)

N794Mn (Consultant)

Project completion fast tracked to present level of 65%

6

Design, Supply and Installation of Signaling on the Eastern Line (Port Harcourt - Maiduguri)

Ansaldo 5% 40% N5.6bn N502,423,809.6

3

7 Jebba- Kano Addendum

Yet to be awarded

20

Page 21: #MP2013 Presentation of SURE-P

Lagos – Kano Rail Line – 100%

Commissioned Dec. 2012

Page 22: #MP2013 Presentation of SURE-P

Abuja – Kaduna Rail line

65%

Page 23: #MP2013 Presentation of SURE-P

Community Service Scheme • CSWYE through the Community Service Scheme (CSS) has

engaged One Hundred and Nineteen thousand (119,000) beneficiaries spread across various communities in the country.

• This number is made up of over Eight Thousand (8000) beneficiaries that were deployed in twelve states during the Pilot stage.

• Three Thousand ( 3, 000) beneficiaries were also deployed in each

of the state of the country and FCT apart from Plateau state which has Two Thousand, Two Hundred and Seventy Two (2,272) beneficiaries. The remaining Seven Hundred and Twenty Eight beneficiaries for Plateau is expected to be deployed by middle of August 2013.

Social Safety Net Programmes

Page 24: #MP2013 Presentation of SURE-P

Community Service Scheme

• These beneficiaries who are deployed in communities where they come from are engaged in different community services thereby helping in maintaining social infrastructure in these communities.

• Each of these beneficiaries is paid monthly stipend of Ten

Thousand (N10,000) naira which is a form of social safety net for the beneficiaries.

• The Scheme spends about N1.2Billion every month to pay the beneficiaries their monthly stipends.

Page 25: #MP2013 Presentation of SURE-P

Graduate Internship Scheme

• This Scheme which hopes to provide mentorship and upgrade the skills of Nigerian graduate has at today engaged One Thousand Eight Hundred and Twenty Three (1,823) Interns.

• These Interns are currently being mentored and provided

some skills by various firms across the country. • The interns presently are being paid a monthly stipend of

N18, 000.

Page 26: #MP2013 Presentation of SURE-P

CSS Stakeholder Engagement

CSS Beneficiaries

At Work

Page 27: #MP2013 Presentation of SURE-P

MCH Infrastructure & Human Resource of Health

• In 2012, in collaboration with State and Local Government authorities, we selected 500 Primary Health Care Centres (PHC) and 125 General Hospitals (GH) across the 36 states of the country and FCT.

• So far, Construction of 313 boreholes are ongoing at the PHCs

• Renovation of 74 PHCs are Ongoing • Contracting Process concluded for 336 PHCs. • Recruited 6,630 health care workers comprising of ;

– 1,304 midwives; – 2,254 community health extension workers (CHEWs); and – 3,072 female village health workers (VHWs)

Page 28: #MP2013 Presentation of SURE-P

• In 2013, We are adding 700 PHCs to the 500 of 2012, and 175 GHs to the 125 of 2012.

• Additional 700 PHCs -> Total = 1,200 PHCs

• Additional 175 GHs -> Total = 300 GHs

• Additional 1,500 midwives -> Total = 2,804

• Additional 2,800 CHEWs -> Total = 5,054

• Additional 4,200 VHWs -> Total = 7,272

Page 29: #MP2013 Presentation of SURE-P

MCH Midwives and CHEWs

Page 30: #MP2013 Presentation of SURE-P

Drugs, Kits and Equipment

• The 500 PHCs and 125 GHs across the country were supplied cumulatively with 1.8Billion naira worth of Drugs, Mama Kits, VHW kits, health commodities and medical equipments.

• 600Million naira worth of Buffer stock for Drugs,

Mama Kits, VHW kits, health commodities have been procured and stored in zonal medical stores to stamp out “out of stock syndrome”.

Page 31: #MP2013 Presentation of SURE-P

MCH Outcome

• Growing number of health workers are now providing quality antenatal, skilled birth delivery and postnatal services to pregnant women and their babies in SURE-P facilities across the country.

• 223,786 pregnant women have received antenatal care services in SURE-P MCH supported facilities

• 28,435 deliveries have been taken by skilled birth attendants in these same facilities

• 19,514 new acceptors of family planning have been recorded in these same facilities

Page 32: #MP2013 Presentation of SURE-P

Conditional Cash Transfer (CCT)

• We have successfully launched the Conditional Cash Transfer (CCT) Pilot Programme in Health Centre FCT. This will pay beneficiaries Five thousand Naira (N5,000)

• In 5 primary health care (PHC) centres in FCT, a total of 2,150

beneficiaries have been enrolled into the programme as at 30th June, 2013 as follows:

• Inauguration of State CCT Steering Committees has occurred in the Federal Capital Territory (FCT) and 8 pilot states namely Anambra, Bauchi, Bayelsa, Ebonyi, Kaduna, Niger, Ogun and Zamfara States

• Beneficiaries are now being enrolled in the pilot PHC facilities in the 8 other pilot states

Page 33: #MP2013 Presentation of SURE-P

MASS TRANSIT

• The SURE-P funds for Mass Transit is managed by The

Infrastructure Bank (TIB), they are responsible for monitoring the

loans and payment to suppliers and operators.

• Total Number of Buses – 809 valued at 9.1Billion Naira

• Total Number of Transport Operators – 19

• Sector – Private from six geo- political zones of Nigeria, including Abuja and Lagos.

• SURE-P released to Infrastructure Bank – 8.9Billion Naira

Page 34: #MP2013 Presentation of SURE-P

FERMA/ PUBLIC WORKS

1. Presently active on 40 Federal Roads :- across all states of the Federation 2. Currently engaging 12,400 (10,000 workmen, 2400 Supervisors) young Nigerians from neighbouring communities of selected roads 4. District (Community)Roads Maintenance Programme –Currently implementing pilot scheme in 3 states (Anambra, Kano, Zamfara) employing 20 Supervisors 500 workmen, 500km of roads in each State 5. Budget: N4 Billion (January – June 2012) N4 Billion (July – December 2013)

Page 35: #MP2013 Presentation of SURE-P
Page 36: #MP2013 Presentation of SURE-P

TECHNICAL VOCATIONAL EDUCATION AND TRAINING (TVET)

Effective Start Date: May 27, 2013 • Annual Budget N8.6billion

Achievements to Date: • Received applications from 44,000 youths for skills training. • Undertook infrastructure assessment visits to 8 FG Institutions •. Plans for 2013: 1. Conclude all rehabilitation works in all the 8 Federal Government Training

Centers 3. Equip and retool the 8 Federal Government training Centers by September, 2013. 4. Conclude training of 6,250 client based Trainees by end of 2013 in the following

client centers including NRC, NAPTIN, FERMA, 5. Commence training of 8000 youth through the citizens based component of the

TVET program by August, 2013

Page 37: #MP2013 Presentation of SURE-P

• CULTURE AND TOURISM

For 2013, SURE-P plans on intervening in Culture and Tourism

Planning Phase – 50%

Social Safety Net Programmes

Page 38: #MP2013 Presentation of SURE-P

MONITORING & EVALUATION OF SURE-P

PROJECTS & PROGRAMMES

SURE-P has a robust institutional framework for ensuring the quality and value for money aspect of its interventions in Infrastructure Projects and Social Safety Net Programmes.

The SURE-P M&E Team works closely with the National Planning Commission (M&E Department) and supported by DFID consultants, to ensure that all SURE-P interventions are accorded the necessary scrutiny to meet required standards of project and programme delivery.

Through this partnership, the Nigerian Taxpayer can be confident that SURE-P is at the fore-front of enabling the transformation of public sector service delivery and maximizing value for money.