new england 10 2016
DESCRIPTION
New England 10 2016TRANSCRIPT
![Page 1: New England 10 2016](https://reader030.vdocument.in/reader030/viewer/2022020202/579078d81a28ab6874c455a9/html5/thumbnails/1.jpg)
By Brenda ruggieroceG coRResPoNdeNt
the construction of a30-megawatt, five-turbineoffshore wind farm, thefirst of its kind in theUnited states, is on sched-ule for completion laterthis year, at a reported costof $290 million. theBlock Island Wind Farmwill reportedly supplymost of Block Island,R.I.’s power while reduc-ing air pollution acrosssouthern New england foryears into the future.
When fully completed,the wind farm will consistof five, 6-megawatt windturbine generators, a submarine cable interconnecting theturbines, and a submarine cable from the northernmost tur-bine to an interconnection point on Block Island.
the farm is located approximately 3 mi. (4.8 km) south-east of Block Island. the first offshore construction seasonwas completed at the end of 2015, when all five steel jacketfoundations were fully installed at site.
during the winter andinto the spring, onshorework was under way,including turbine assem-bly and submarine cableinstallation. submarinecable installation also wasscheduled for spring, anderection of the five off-shore wind turbines is setfor this summer.
Project ownerdeepwater Wind is led bya veteran managementteam with experience indeveloping complex ener-gy projects worldwide.Headquartered inProvidence, R.I., the com-pany reports that it isactively planning offshore
wind projects to serve multiple east coast markets located15 or more mi. (24 km) offshore, including New York,Massachusetts, Rhode Island and New Jersey.
“From the first ‘steel in the water’ in July to the last decklift in November, we’ve completed a season of firsts — notonly for the Block Island Wind Farm but also for the launch
Nation’s First Offshore Wind Farmon Schedule for Late 2016 Completion
By Philip MarceloAssocIAted PRess
BostoN (AP) this time last year, MGM officials andstate and city leaders were reveling in a confetti-filledgroundbreaking at the future site of a resort casino in thewestern Massachusetts city of springfield.
But what had been projected to be the state’s first Las
Vegas-style gambling destination has faced a series of set-backs. Now MGM springfield is gearing up for its first fullseason of construction, one year later than hoped.
“It’s had a serious number of twists and turns, but thoseare finally behind us,” said Kevin Kennedy, springfieldMayor domenic sarno’s chief development officer.“We’re pleased we’re on course for a september 2018
Better Late Than Never: MGM CasinoFinally Ready to Roll in Springfield
THE NEW ENGLAND EDITION A Supplement to:
Your New England States Connection • Amanda Hogeboom-Merritt 1-800-988-1203
“The Nation’s Best Read Construction Newspaper… Founded in 1957.”
1
1
1
11
2
16
201
3
9
1
95
95
495
95
9
16
3
26
2
202
89
93
93 95
2
7
4
7
2
89
89
91
91
37
22
6
90
90
495
9593
195
95
6
95
7
6395
95
8491
91
84
95
E q u I P M E N t g u I d E
F o r m e r l y
May 182016
Vol. XlIX • No.10
®
see MgM page 18
Deepwater Wind photoThe construction of a 30-megawatt, five-turbine offshorewind farm, the first of its kind in the United States, is onschedule for completion later this year, at a reported costof $290 million.
see WINd page 4Other Screeners AvailableArguS INduStrIAl CO.www.ez-screen.com866-745-5828
6’x5’ ScreenboxWorks with 1/2 to 1 3/4Yd. Loaders, 25 H.P.
Kohler Diesel Engine, 24”Conveyor Dumps
Screened Product 9’ High
$41,900 plus freight.
2016 EZ-Screen1200XLS
New Option Separate3 Products
Specializing in:
Demolition, Portable Crushing, Material Sales, C & D Recycling,
Land Clearing & 30-115 Yd. Trailers2208 Plainfield Pike • Johnston, RI 02919401-943-7100 • Fax: 401-647-5041
www.jrvinagrocorp.comCall for Pricing
LEED Accredited in Waste Management
CAT 325LFOR SALE!
M.G. EquipmentCall Phil (413) 427-7171
www.foleyengines.com
w
• HIGH QUALITY• FAST SHIPPING• GUARANTEED TO FIT• UNDERCARRIAGE PARTS• FLATPROOF SKIDSTEER TIRES• RUBBER PADS FOR STEEL TRACKS
888-888-1248
NJ, TX, WA
WAREHOUSES
WE STOCK RUBBER TRACKSfor Over 6,000 Models!
Some Used TracksAvailable.
GIVE USYOUR
HAMMER!
GIVE USYOUR
HAMMER!
61 Silva Lane • Dracut, MA 01826
30% off same class Ramfos hammer with competitor’s trade in
Call Today (978) 454-3320
• Repairs
• Rebuilds
• ReplacementParts in
Stock
CALL 888-81-GORILLA(46745)*Some restrictions apply
New Hydraulic Hammers.Remanufactured Hammers.Hammer repairs/rebuilding
with free area pickup.Hammer toolbits delivered
to your site!
YOUR ONE-STOP HYDRAULIC HAMMER SHOP™
![Page 2: New England 10 2016](https://reader030.vdocument.in/reader030/viewer/2022020202/579078d81a28ab6874c455a9/html5/thumbnails/2.jpg)
Page 2 • May 18, 2016 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide
THE W.I. CLARK COMPANYBrookfield, CT • Wallingford, CT • Plainfield, CT
Call Mark Doty @ 203-823-2316
See Our Complete Inventory at www.wiclark.com
C/air, 4x4, Ext. Hoe, Front & Rear Couplers,12 & 24” Buckets, Wobble Sticks, GreatCondition, stk#22910 ..........................$42,500
2002 John Deere 310SG 2011 Deere 310SJ
Tier 4 Cummins Power, Dealer Maintained,Excellent Condition, stk#23023 ..........$69,000
2012 Ingersoll Rand XP825WCU
Cummins Power, Dealer Maintained SinceNew, Great Condition, stk#20097......$109,000
2008 Ingersoll Rand HP1600WCU
C/air, Front Loader & Hydraulics, Rear Hitch,400 Hrs, Great Condition, stk#22459 ..$35,000
2008 Kubota L5740HST Tractor
950 Hours, Kubota Diesel, 8-15’ LegendScreed, stk#22923 ............................$105,500
2013 LeeBoy 8510B
C/air, JRB Coupler, 3 Spool Hyds, RideControl, 1.4 Yd Bkt, Great Condition,stk#23139 ..........................................$125,000
2014 Deere 344K
8-15’ Propane/Electric Screed, Steel Tracks,1190 Hrs, Good Condition, stk#23151 $26,500
2010 Mauldin 1750C
2010 John Deere 410J
1861 Hrs, C/air, Pilots, Ext Hoe, Front & RearHyds, Great Rubber, stk#22596 ..........$80,000
C/air, 1890 Hrs, 4x4, Ext. Hoe, Front & RearHyds, 4-1 Bkt, stk#22846 ....................$79,500
![Page 3: New England 10 2016](https://reader030.vdocument.in/reader030/viewer/2022020202/579078d81a28ab6874c455a9/html5/thumbnails/3.jpg)
Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • May 18, 2016 • Page 3
E. LONGMEADOW, MA251 Shaker Road • East Longmeadow, MA 01028
(800) 292-6351
BERLIN, CT1980 Berlin Turnpike • Berlin, CT 06037
(800) 352-4473www.tylerequipment.com
TWO FULL SERVICE LOCATIONS!
Featuring Leading BrandsSince 1922
![Page 4: New England 10 2016](https://reader030.vdocument.in/reader030/viewer/2022020202/579078d81a28ab6874c455a9/html5/thumbnails/4.jpg)
Page 4 • May 18, 2016 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide
of a new American offshore wind industry,” saidJeffrey Grybowski, Deepwater Wind CEO. “Weare proud of the work we’ve accomplished so far,but we’ve only just begun — and 2016 will be ayear to remember.”R.I. Gov. Gina M. Raimonda noted that Rhode
Island is proud to be home to the nation’s first off-shore wind farm.“With this project, we’re putting hundreds of
our local workers to work at-sea and at our world-class ports to build a project that will help diversi-fy Rhode Island’s energy mix and protect ourenvironment. I applaud Deepwater Wind for theirsuccessful first offshore construction season, and Ilook forward to seeing the project fully opera-tional and generating renewable energy in 2016.”During the 18-week construction period last
year, approximately 200 workers (100 of themlocal) and a dozen construction and transportbarges, tugboats, crew ships and monitoring ves-sels were active at the project’s port.In all, more than 300 local workers will be
involved with building the Block Island Wind Farm.Deepwater Wind is utilizing four Rhode Island ports, BlockIsland, Galilee, Quonset Point and the Port of Providence, tocomplete construction and staging.According to Deepwater Wind, all construction activities
have been completed in accordance with strict environmen-tal rules set by state and federal government agencies. In
2013, Deepwater Wind voluntarily agreed to a series of pro-tective measures to minimize potential underwater noiseimpacts on North Atlantic right whales during wind farmconstruction.“We are especially proud that our work was done while
upholding very high environmental standards,” Grybowskisaid.
Deepwater Wind and General Electric established a newtemporary manufacturing facility at the Port of Providencefor the assembly of turbine components. GE (which recent-ly completed its acquisition of Alstom’s offshore wind unit)is supplying the 6-megawatt Haliade 150 offshore wind tur-bines for the Block Island Wind Farm. Approximately 60local workers will be involved in this aspect of the project.GE’s work will include the installation of the electrical,
mechanical, and safety equipment within the bottom towersections now at ProvPort, with the remaining tower sectionsarriving in Rhode Island next year. Each turbine tower consists of three sections, with a total
height of approximately 270 ft. (82.3 m), and a total weightof approximately 440 tons (399 t), once assembled.Some construction and staging work also is being com-
pleted at Quonset Point, in North Kingstown, R.I.Fabrication of some of the foundation components was com-pleted by local welders at Quonset’s Specialty DivingServices in early 2015, and the port continues to host con-struction work and vessel staging for the wind farm. Quonsetalso will host the project’s long-term operations and mainte-nance facility.The project is scheduled to be in-service and generating
power in the fourth quarter of 2016.A joint venture between Weeks Marine and Manson
Construction is serving as Deepwater Wind’s offshore foun-dation installation contractor. Local contractors assistingwith this work include Aladdin Electric; Bay Crane NewEngland; Essex Newbury; E.W. Audet & Sons; AeroMechanical Inc.; Waterson Terminal Services; GZAGeoEnvironmental; VHB; and Fuss & O’Neill. Workersfrom the laborers, carpenters, elevator constructors, IBEW,ironworkers, plumbers and pipefitters, cement masons, oper-ating engineers and stevedoring unions will be involved.“Building an offshore wind industry in the U.S. will cre-
ate thousands of American jobs,” states Deepwater Wind’swebsite “Today, the offshore wind industry in Europeemploys nearly 60,000 workers. There are approximately2,500 wind turbines spinning in the ocean off the coast ofEurope today, but none yet in the United States. Developingan offshore wind industry right here in America will increaseour nation’s competitiveness in energy sector, revitalizeindustrial ports, bolster the manufacturing sector, and creategood, high paying, jobs in the years to come.”
(This story also can be found on ConstructionEquipment Guide’s Web site at www.constructionequip-mentguide.com.)
Rhode’s Island’s Wind Farm Marks Start of New Industry
For advertising rates: Contact Edwin M. McKeon Jr.
215/885-2900Toll Free 800/523-2200
Fax 215/885-2910e-mail [email protected]
Contact Amanda Hogeboom-Merritt• New England 518/396-7659
Toll Free 800/988-1203Fax 315/866-1379
e-mail [email protected]
Contact Kent Hogeboom• New York • New England 315/866-1379
Toll Free 800/988-1203Fax 315/823-4136
e-mail [email protected]
Construction Equipment Guide NortheastEdition (ISSN 1081-7034) is published bi-weekly by Construction Equipment GuideLtd. Advertising and Editorial Offices arelocated at 470 Maryland Dr., Ft. Washington, PA 19034. Toll Free800/523-2200 or Fax 215/885-2910.Annual Subscription Rate $65.00. Call forCanadian and foreign rates.
Periodicals postage paid at Ft. Washington,PA and at additional mailing offices. POSTMASTER: Send address changes toConstruction Equipment Guide NortheastEdition, 470 Maryland Dr, Ft. Washington, PA19034.
Contents Copyrighted ©2016, byConstruction Equipment Guide, which is aRegistered Trademark, registered in the U.S.Patent Office. Registration number 0957323.All rights reserved, nothing may be reprintedor reproduced(including framing) in whole or part without writtenpermission from the publisher. All editorialmaterial, photographs, drawings, letters, and other material will be treated as unconditionally assigned for publication andcopyright purposes and are subject toConstruction Equipment Guide's unrestrictedright to edit and comment editorially.Contributor articles do not necessarily reflectthe policy or opinions of this publication.
Call or write for advertising rates, publicationschedule and media kit. The ConstructionEquipment Guide is not responsible for cleri-cal or printer's errors, every care is taken toavoid mistakes. Photographs of equipmentused in advertisements are not necessarilyactual photographs of the specific machine.Similar photographs are used occasionallyand every effort is taken to depict the actualequipment advertised. The right is reservedto reject any advertising.
Founder, Publisher & CEO Edwin M. McKeon Sr. Northeast Publisher Edwin M. McKeon Jr.
Editor In Chief Craig Mongeau Associate Editor Christine Allen
Editorial Consultant Pete Sigmund Production Mgr. John Pinkerton
Controller Judith NixonCirculation Mgr. Cathy Printz
Main office 470 Maryland Drive Fort Washington, PA 19034
215/885-2900 Toll Free 800/523-2200
Fax 215/885-2910
Web site www.constructionequipmentguide.comEditorial e-mail [email protected]
Advertising e-mail [email protected]
NEW ENGLAND EDitioN
Deepwater Wind photoDeepwater Wind and General Electric established anew temporary manufacturing facility at the Port ofProvidence for the assembly of turbine components.
Deepwater Wind photoWhen fully completed, the wind farm will consist of five, 6-megawatt wind turbine generators, a submarine cableinterconnecting the turbines, and a submarine cable fromthe northernmost turbine to an interconnection point onBlock Island.
WIND from page 1
![Page 5: New England 10 2016](https://reader030.vdocument.in/reader030/viewer/2022020202/579078d81a28ab6874c455a9/html5/thumbnails/5.jpg)
Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • May 18, 2016 • Page 5
©2016 Hyundai Construction Equipment Americas, Inc. All Rights Reserved.
Hyundai HX Series Excavators
To learn more about the HX series excavators, call your Hyundai dealer today.
BUILT TO PERFORM
PACKED WITH VALUE Faster cycle times, greater productivity Standard rear camera; All-Around View Monitoring option Spacious, quiet cab with Bluetooth and wireless Standard air-suspension seat 3-year Hi-Mate remote management system 3-year, full-machine warranty plus 5-year / 5000-hour
structural guarantee
160 Elm St. Unit 1 • Walpole, MA 02081(508) 660-7600
Fax: (508) 660-7614
www.lhequip.com
![Page 6: New England 10 2016](https://reader030.vdocument.in/reader030/viewer/2022020202/579078d81a28ab6874c455a9/html5/thumbnails/6.jpg)
Page 6 • May 18, 2016 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide
Doosan crawler excavators are packed with comfort features. A wide-open view of the work area. Low noise levels. Adjustable joystick control stands. Reduced dust and dirt levels. Of course, performance and productivity are key, and your Doosan crawler excavator delivers fast, class-leading cycle times, increased flotation in so� soil and precision controls for outstanding e�ciency. It’s a di�erence operators can see, hear and feel.
Get a closer look. Stop in and visit us today.
Doosan and the Doosan logo are registered trademarks of Doosan Corp. in the United States and various other countries around the world. 16-D026
Equipment East61 Silva Lane • Dracut, MA 01826978-454-3320 • www.equipmenteast.com
Authorized Doosan Dealer
Strong enough to handle the ups and downs
r eelwarn casDooein vepo-ediA wl sortnok ccitysojne acnamroforepeviler dotavacxe
� son sn ioitatolf
ed wkcae prs arotavacxr ew noa. Lerk aroe whf tw oe
nt asued dcued. Rsdnatl s, ayee kry ativitcudord pn
cyg cnidael-ssal, ctsas freortnon coisiecrd pnl aio� s
.serutaet f erofomoh ctied welbatsujd. Aslevee lsiow n
e,sruof c. Oslevet lrid dnrelwarn casr Doouod yn
edsaercn, isemie tlcgnidnatstur oos flo
pmeuiqEreal Deanoso DdzeirohtAu
tsa Etn
� son sotatos a d’t. Iycneic�e
oor lesolt a ceG
on lasooe Dhd tnn aasooDors aeirtnuor cehts ouoirav
otoosd pl ao� sn sas crotarepe ocnere�is a d
s tt uisid vnn ap iot. Skoo
on Casoof Ds okramedard teretsigee rro ag620D-6. 1dlroe whd tnuo
gatstur oos fo.leed fnr aaeee, hn s
.yy.aod o
d ns aetatd Setine Uhn t. ipro
pmeuiqEe naa Lvli1 S6 •
0233-454-879
tsa Etn6281A 0, Mtucar D
• .tsatenempiuqe.ww w
mco.
![Page 7: New England 10 2016](https://reader030.vdocument.in/reader030/viewer/2022020202/579078d81a28ab6874c455a9/html5/thumbnails/7.jpg)
Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • May 18, 2016 • Page 7
Go to www.acecrushers.comfor a complete listing and description of our new and used equipment.
Ace Equipment Sales, Inc. and Milroy and Company LLC171 Tolland Turnpike (Route 74) • PO Box 535 • Willington, CT 06279
(860) 429-2793 • Fax: (860) 429-0542
John Patton • (860) 614-3426
WE HAVE ALL THE PARTS YOU NEED:Manganese, Conveyor Belts, Idlers, Head Pulleys, Tail Pulleys and Much More!
Quality Service Guaranteed!
CRUSHING EQUIPMENT, PARTS & SERVICE
• Largest Screen Deck in its Class• Longer Conveyors at 16’8” Stockpile Height• Standard 14’ Wide 12 CY Hopper
ENGINE 129-horsepower CAT® C4.4 (Tier 3)HOPPER CAPACITY 12-cubic yardsSTOCKPILE HEIGHT 16-feet 8-inches
TOP DECK 22-feet by 5-feetMIDDLE DECK 22-feet by 5-feetBOTTOM DECK 20-feet by 5-feet
TS-522 TD
![Page 8: New England 10 2016](https://reader030.vdocument.in/reader030/viewer/2022020202/579078d81a28ab6874c455a9/html5/thumbnails/8.jpg)
Page 8 • May 18, 2016 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide
RIDOT Hosts Nation’s DOTs to Share Winter Storm PracticesImproved winter storm operations and
dramatically reduced pothole claims wereamong the messages being delivered as theRhode Island Department of Transportation(RIDOT) hosted officials from Departmentsof Transportation from across the country.The Clear Roads Spring Meeting took
place the week of April 14 at the RadissonHotel Providence Airport in Warwick, R.I.The conference, featured representationfrom 33 states, afforded an opportunity fortransportation professionals to learn fromeach other about uses of innovative technol-ogy and equipment and other steps taken tomore effectively and efficiently keep roadsclear of snow and ice. This is the first timeRhode Island has hosted this conference,which occurs twice each year, and providedRIDOT an opportunity to learn from bestpractices employed elsewhere in the coun-try.Peter Alviti Jr., RIDOT director, opened
the conference by discussing managementchanges in the past year, including the con-version of 40 unfilled administrative posi-tions, and eliminating such positions as pho-tographer, to bolster its maintenance work-
force to provide additional personnel forwinter storms and maintenance operationsyear round.Also at the conference, RIDOT
announced that both calls from citizensreporting potholes and claims filed with theDepartment dropped significantly this win-ter season. In the past five years, RIDOT hasaveraged approximately 560 pothole claimsper year. This past winter, RIDOT onlyreceived 148 claims — a drop of 75 percent.A similar sharp decline was observed in pot-hole calls, with the total number of callsreceived in March 2016 to date is less thana quarter of the pothole calls received inMarch 2015.“While most people think we had a
milder than usual winter, our records showwe actually experienced a typical winterseason,” Alviti said. “The drop in calls andcomplaints is evidence of the many steps wehave taken to bring about change at RIDOTand improve the quality of our roads for thetraveling public.”RIDOT credits the drop in potholes to the
use of automated pothole patchingmachines, brought into service to help
restore roads following the harsh winter of2014-15. The machines operated through-out the summer and fall months, providinga more durable and longer lasting patch ascompared with traditional methods. Thepothole patching services utilize the latestspray-injection technology to repair pot-holes more efficiently and safely whileensuring a longer-lasting fix. The patchers(which are controlled by a single operatorfrom the cab of a truck) are capable ofcleaning away debris and filling a pothole inonly a few minutes. The pothole patchingmachines were on duty this past winter, pro-viding a reliable hot-mix equivalent (typi-cally unavailable from December throughMarch) for fixing potholes all season.RIDOT in 2015 also placed a high prior-
ity on resurfacing roads that had generatednumerous pothole complaints for severalyears, such as Routes 37, 102, 116,Cumberland Hill Road and sections of I-95.The past winter also saw the debut of the
state’s first-ever strategic salt reserve, meantto protect against national road salt short-ages experienced in previous winters.RIDOT purchased an additional 20,000 tons
(18,143.7 t) of salt and stockpiled it at itsJefferson Boulevard salt facility to be usedto supplement its normal inventory of30,000 tons (27,215.5 t) should the needarise.RIDOT continues to grow its winter fleet
as well, adding 13 new plow trucks for thispast season, bringing its total to 115 trucks.A larger fleet allows the state to more effec-tively manage storms and reduces the needfor private vendors to assist with winteroperations.Launched in 2004 by experienced winter
maintenance professionals, Clear Roads is aresearch program aimed at rigorous testingof winter maintenance materials, equip-ment, and methods for use by highwaymaintenance crews. RIDOT joined the peerexchange group in 2012 to take full advan-tage of the depth of research for wintermaintenance operations as well as the directrelationship with its DOT partners acrossthe country.
(This story also can be found onConstruction Equipment Guide’s Website at www.constructionequipment-guide.com.)
Visit CEG’s Web Site at www.constructionequipmentguide.com
The Maine Department of Transportation received bids fortransportation-related improvement projects.Following is a list of some of the projects let.
Counties: OxfordContract ID: 019290.00Location: Rumford — Haverhill Bridge on River Streetover Mill Yard approximately 0.1 mi. north of PortlandStreet.Project: Bridge strengthening and rehabilitation.Contractors and Bid Amounts:
• T Buck Construction, Inc. — $364,922• Scott Construction Corporation — $393,635• CPM Constructors — $462,170• Wyman & Simpson Inc. — $544,486
County: SomersetContract ID: 020483.00Location: Fairfield — Western Avenue Bridge located onRoute 139/Western Avenue over Interstate 95 approximate-ly 1 mi. west of Route 201 junction. Interstate 95 over 201Bridge is located approximately 2 miles north of the townline.Project: Bridge deck replacement.Contractors and Bid Amounts:
• T Buck Construction, Inc. — $4,321,000• CPM Constructors — $5,337,389• Wyman & Simpson Inc. — $6,104,527
County: WashingtonContract ID: 019194.00Location: Eastport — on the County Road beginning atthe intersection of Route 190 and extending approximately0.88 mi. southerly to Barron Road.Project:Highway reconstruction.Contractors and Bid Amounts:
• Federal Program Integrators — $1,544,952• Fundy Contractors Inc. — $1,843,149• Ed Pelletier & Sons Company — $1,899,692• T Buck Construction Inc. — $1,922,000• Sargent Corporation — $2,124,270• CPM Constructors — $2,325,003• Lane Construction Corporation (The) — $2,354,322
County: CumberlandContract ID: 018229.00Location: Scarborough — Pine Point Crossing Bridgelocated on Bickford Street, Holly Street, Snow CanningRoad and Route 9/Pine Point Road over B&M Railroadand Depot Street extension.Project: Bridge replacement.
Contractors and Bid Amounts:• Reed & Reed Inc. — $3,607,158• CPM Constructors — $3,951,807• Wyman & Simpson Inc. — $4,044,100• T Buck Construction Inc. — $4,426,000• Scott Construction Corporation — $4,470,210• Cianbro Corporation — $4,485,494
County: YorkContract ID: 020474.00Location:Kennebunk and Wells — Pumping Stationlocated on U.S. Route 1/Post Road/ York Street town lineover Branch Brook.Project: Bridge replacement.Contractors and Bid Amounts:
• CPM Constructors — $1,042,345• Reed & Reed Inc. — $1,082,272• Wyman & Simpson Inc. — $1,154,000• Scott Construction Corporation — $1,168,839• T Buck Construction, Inc. — $1,717,726
County: PenobscotContract ID: 020411.00Location:Orono — at the I-95 exit 193 NB off ramp at
Androscoggin • Aroostook • Cumberland • Franklin • Hancock • Kennebec • Knox • Lincoln • Oxford • Penobscot • Piscataquis • Sagadahoc• Somerset • Waldo • Washington • York • Androscoggin • Aroostook • Cumberland • Franklin • Hancock • Kennebec • Knox • Lincoln • Oxford• Penobscot • Piscataquis • Sagadahoc • Somerset • Waldo • Washington • York • Androscoggin • Aroostook • Cumberland • Franklin •Hancock • Kennebec • Knox • Lincoln • Oxford • Penobscot • Piscataquis • Sagadahoc • Somerset • Waldo • Washington • York •Androscoggin • Aroostook • Cumberland • Franklin • Hancock • Kennebec • Knox • Lincoln • Oxford • Penobscot • Piscataquis • Sagadahoc
Maine...
‘Pine Tree State’ Highway Projects Let
see MAINE page 14
![Page 9: New England 10 2016](https://reader030.vdocument.in/reader030/viewer/2022020202/579078d81a28ab6874c455a9/html5/thumbnails/9.jpg)
Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • May 18, 2016 • Page 9
EW Sleeper Co., Inc.391 Loudon Rd.
Concord, NH 03302391 Loudon Rd.
Concord, NH 03802603.225.3361800.358.6007
www.ewsleeper.com
391 Loudon Rd.
Concord, NH 03302
603.225.3361
800.358.6007
www.ewsleeper.com
![Page 10: New England 10 2016](https://reader030.vdocument.in/reader030/viewer/2022020202/579078d81a28ab6874c455a9/html5/thumbnails/10.jpg)
Page 10 • May 18, 2016 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide
Equipment East AnnouncesProduct Line Expansion
Equipment East has expanded and nowcarries the following brands:
• Gorman-Rupp — trash pumps; electricsubmersibles; and prime assisted pumps.Parts and service also are available for theseitems.
• Sullivan Palatek — Portable 90 to 375CFM high-pressure units; utility mounts;and electric compressors.
• Chicago Pneumatic— pneumatic breakers;chipping guns; rivetbusters; and compactionequipment,
• Yanmar — excava-tors from 1,800 to 20,000lbs. (816.5 to 9,072 kg);mini wheel loaders; rubbertire and track skid steers;and track dumps.Attachments also areavailable, includinghydraulic hammers; palletforks; cold planers; andsweepers.
• Multiquip — ram-mers; FWD and REVplate compactors; trenchrollers; walk behindrollers; and road andmasonry saws.
• MQ Power — smallgenerators; large towablegenerators; welder genera-tors; and light towers.
• Stihl — cut-off saws;chainsaws; brooms; lithi-um-ion tools; diamondblades; chainsaw blades; and abrasive blades
Equipment East is located in Dracut,Mass., five minutes south of the NewHampshire border and 10 minutes fromRoute 93 on Route 113. Territories includethe Eastern Massachusetts to the Cape, NewHampshire, Vermont and the southern tip ofMaine. Customers can pick up the equip-ment or Equipment East can deliver to cus-tomers’ specified location.
Until recently, Equipment East carriedmostly heavy construction and screeningequipment from Doosan, Keestrack,Yanmar, Liugong, Ramfos, Felling and AtlasCopco.
According to Giovanni Albanese,founder of Equipment East, “I wanted toexpand into the small tool/compact linebecause I think it’s important to be able tofully support our customers. Contractorsnot only need the large excavators, loadersand dump trucks, but all job sites require the
use of the smaller tools and parts as well,”he said. “[Customers can] come toEquipment East for all of their equipmentand service needs.
“Our staff and technicians are formallytrained and certified to work on all of ournew lines, so that we are able to provide ourcustomers with the supreme customer sup-
port and turnaround they’re used to receiv-ing. Our new line of equipment not onlyappeals to the everyday contractor, but alsoto our neighbors. Anyone in need of pur-chasing a small tool for yard work, homerepair, or project can come to EquipmentEast. Not only can we provide them with ahigh-quality product, but we can back it willa full-service, maintenance and repair foryears to come.”
Equipment East works with its customersto provide them with the right equipmentand construction attachment appropriate fortheir application. Its goal is to help increasethe customer’s productivity and profitability,according to the company.
For more information, call 978/697-3505or visit www.equipmenteast.com.
(This story also can be found onConstruction Equipment Guide’s Website at www.constructionequipment-guide.com.) CEG
THE N.I.C.E. COMPANY9 Rosenfeld Drive, Hopedale, MAToll Free# 888-717-8096 • www.theniceco.com
We sell NICE machines!
WE R
EN
T •
WE R
EN
T •
WE R
EN
T •
WE R
EN
T •
WE R
EN
T •
WE R
EN
T •
WE R
EN
T •
WE R
EN
T •
WE R
EN
T •
WE R
EN
T •
WE R
EN
T •
WE R
EN
T •
WE R
EN
T •
WE R
EN
T •
WE R
EN
T •
WE R
EN
T •
WE R
EN
T •
WE R
EN
T •
WE R
EN
T
WE R
EN
T • W
E R
EN
T • W
E R
EN
T • W
E R
EN
T • W
E R
EN
T • W
E R
EN
T • W
E R
EN
T • W
E R
EN
T • W
E R
EN
T • W
E R
EN
T • W
E R
EN
T • W
E R
EN
T • W
E R
EN
T • W
E R
EN
T • W
E R
EN
T • W
E R
EN
T • W
E R
EN
T • W
E R
EN
T • W
E R
EN
T2012 KOBELCO SK260: A/C,
Pattern Control, Reach Boom, 2-WayAux. Hydraulics, 31.5” Pads, 48” Bkt, Long U/C, Hyd. Thumb $129,000
2007 KOMATSU PC158: Plumbed,QC, Fairly Low Hours $69,000
NEW DOOSAN 225LC:with Factory Plumbing.
Only $149,000 $129,000
NEW 2014 Hyundai Robex R140LC-9A EXCAVATOR: Brand New, Equippedw/Factory Plumbing, AC, Bucket w/Teeth,Quick Coupler $115,000 $99,000
2010 JOHN DEERE 220W: 3700 Hrs, Angle/Tilt Coupler, Outriggers,
Aux. Hydraulics $119,0002014 HYUNDAI 145: has Blade,
1600 Hrs, QC $109,000
2012 VOLVO EC380DL:Coupler, 3500 Hrs, 9000 Ft/Lb Hammer
$189,000
2012 VOLVO EC340:4000 Hrs, Plumbed
$149,000
RENT ME!! RENT ME!!
RENT ME!!RENT ME!!
2014 CAT 303.5E: 350 Hrs, Hydraulic Thumb $49,000
2008 CAT 324D: 5200 hours $99,000 $79,000
RENT ME!! RENT ME!!
RENT ME!!RENT ME!!
RENT ME!! RENT ME!!
![Page 11: New England 10 2016](https://reader030.vdocument.in/reader030/viewer/2022020202/579078d81a28ab6874c455a9/html5/thumbnails/11.jpg)
Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • May 18, 2016 • Page 11
SOLID PERFORMANCE
STARTS AT $99,500.
sdlgna.com/na
LG938L: 2.5 yd 3 / 160 hp
$99,500*LG948L: 3.0 yd 3 / 173 hp
$118,500*LG958L: 4.0 yd 3 / 224 hp
$137,500*LG959: 4.0 yd 3 / 224 hp
$147,500*
When price and reliability are deciding factors,
easy to maintain,te,operafour wheel loader models a
When price and reliability are deciding factors,
and a perfect fit for your day-to-day jobs. easy to maintain,y-leading prices — they’re simple tot industrfour wheel loader models a
e offerW.werr. SDLG is your ansWhen price and reliability are deciding factors,
and a perfect fit for your day-to-day jobs.y-leading prices — they’re simple to
e offer
* Prices are subject to change without notice.
sdlgna.com/nat ay to support you ant's readtha
our loaders are sold through an experienced,Plus,
Visit sdlgna.com for details.* Prices are subject to change without notice.
.sdlgna.com/nay time you need them.y to support you an
our loaders are sold through an experienced,
Visit sdlgna.com for details.
Make the simple choicey time you need them. top-tier dealer network our loaders are sold through an experienced,
Make the simple choice top-tier dealer network
A P PALionville,
(856) 227-6400 NJDeptford,
(610) 363-9200
.comypennjerseymachiner
(718) 448-2444ten Island,Sta
(908) Frenchtown,
.com
(718) 448-2444 NYten Island,
NJFrenchtown,
�����$�&",��*�!��-.��*)#("�!*1��
� ������������������
������",'%)��/,)+%&"�",'%)�������������������
�����",,2��*�!��)#*,���������������������
������%)��.,"".��,%�*/��������
����������
����$""+���0%-��!��*) *,!����������
���������
�����,,")� 0")/"�"-.�,**&���������
����������
���$/)��%&"�*$)-.*)�����������
������������
������'"-� 0")/" 0*)��� ����������������
����*,.$���+'"��.,"".�*�/,)��� �������
���������
�����,-$�''� 0"��%''%-.*)�����������
����������
www.tylerequipment.com
444t d,
444 NYt d,
� �� �
� �
� �� �
� �� � �
� �� � �
� � �� � �
� �� �
� �� � �
� �� � �
� � �� � �
�����,-$�''� 0"��%''%-.*)�����������
����������
![Page 12: New England 10 2016](https://reader030.vdocument.in/reader030/viewer/2022020202/579078d81a28ab6874c455a9/html5/thumbnails/12.jpg)
Page 12 • May 18, 2016 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide
By Dave GramAssociAted Press
MoNtPeLier, Vt. (AP) A frag-mented Vermont supreme court sidedwith developers of a major solar powerproject in rutland town against thewishes of the town and its neighbors.
the five-member court split threeways before ruling 3-2 in support ofallowing construction of the rutlandtown project. the three-membermajority was split 2-1 on one of the bigissues in the case.
the court upheld a ruling by thestate Public service Board that gavethe 2.3 megawatt rutland renewableenergy project a green light. in doingso, it rehashed arguments heard at theLegislature over who should havegreater say — the state or local com-munities — when developers come toa town looking to build solar and wind-power projects.
the town spent a year developinglocal solar siting standards, only to seethem rejected by the Public serviceBoard as carrying sufficient weight in
its consideration of the project at hand.town officials then authored a resolu-tion, demanding greater local say overthe projects. More than 150 ofVermont’s 251 municipalities signedon.
the town and neighbors objectedthat the rutland renewable energyproject would have undue aestheticand historic impacts and would useprime agricultural land. they alsosought to use an addendum to the townplan to slow the project or scale it back.
But the court majority upheld theboard’s findings that the opponents’concerns did not outweigh the greatergood of the state. it said it generallygrants great deference to decisions bythe board, which has expertise in ener-gy issues.
the “Legislature can change thebalance between state and local regula-tion as it deems appropriate,” themajority opinion said. “in the absenceof such a statutory change, the Boardhas the final policy decision. Under thedeferential standard of review, wemust uphold that policy choice.”
the court decision came as a senate
committee was considering Housechanges to a senate-passed bill thatwould give towns and regional plan-ning commissions more clout but callon them to develop energy plans com-porting with a state goal of getting 90percent of Vermont’s energy fromrenewables by 2050.
Associate Justices John dooley iiiand Marilyn skoglund wrote themajority opinion; Associate JusticeBeth robinson wrote a concurrencethat split in one respect from the major-ity, saying it didn’t grapple enoughwith the question of whether the boardhad given “due consideration” to thetown’s concerns.
chief Justice Paul reiber, who prac-ticed law in rutland before formerGov. Jim douglas appointed him to thecourt, joined by Associate JusticeHarold eaton, wrote a stinging dissentthat called the Public service Boarddecision “self-serving” and “disingen-uous at best.”
(This story also can be found onConstruction Equipment Guide’s Website at www.constructionequipment-guide.com.)
Vermont High Court Sides With Developers
Place Your Business Card for...
3 months $300* only $50 an issue6 months $585* only $45 an issue1212 months $1040* only $40 an issue
Call now to reserve your space! 800-225-8448* pre-payment required
200 Codman Hill Rd., Boxborough, MA 01719978-429-8666
Hydraulic Cranes 8 to 600 Ton
Daily & HourlyServices
Fully Insuredwww.astrocrane.com
2012 CAT 980K, 3800hrs, GP Bucket (7.8 yd), 90% L-5 Tires, LightPackage, Power/Heated Mirrors, Axle Cooler Option, Auto-Shift, RideControl ........................................................................................CALL2012 CAT 966K, 3780 hrs, GP Bucket w/Edge, Ride Control, Light Package, New L-3 Radial Tires....................................$255,0002003 CAT 966G II, GP Bucket w/ Teeth, 70% Tires, New Paint, 3rd Valve option, Ride Control....................................................SOLD2008 CAT D8T Waste Handler, Factory Spec, New CAT U/C......SOLD
208 Holland RoadBrimfield, MA 01010
Sales Contact: R.J. [email protected]
413-245-3882Fax: 413-245-3522
www.rjpoirier.com
Repair Services:Complete Machine Rebuilding, Engine,
Transmission, Undercarriage, Bucket Rebuilding,Computer Diagnostics, Software Enhancements,Hydraulic Cylinder Repair, Custom Products.
2011 CAT 972K,3300 Hrs, GP Bucketw/Edge, RideControl, LightPackage, 85% Tires..........................CALL
AIR COMPRESSORS
2015 DryAIR 250FS, Classic,
Free standing, Portable
Aftercooler, New ............$2995.
Trask-Decrow Machinery
207-799-1538
ASPHALT EQUIPMENT
Asphalt Pavers
2006 LeeBoy Pathmaster
5000, Paves 5’ to 9’. One
owner. Must sell! Good operat-
ing condition, 900 hrs $39,000.
Elliott & Frantz, Inc.
610-279-5200
EXCAVATORS
Doosan DX480 s/n 5217, 11’Stick, JRB Powerlatch, QC,Bucket, Grapple, Runs well!3,687 hours ..............$227,800.
Gibson Machinery440-439-4000
Classified Rates: 30 Words or Less for $40.00. EachAdditional Word is $1.16. For just an additional $20 your adcan be posted on our online searchable database for 30 days.Ad runs for 2 (two) insertions - no changes in second insertion.
PLEASE ENCLOSE PAYMENT WITH ORDER and mail to:470 Maryland Drive• Fort Washington, PA 19034
215/885-2900 • Fax 215/885-2910Toll Free 1-800/523-2200
DISPLAY ADS/CLASSIFIEDS
DAILY AND WEEKLYEQUIPMENT RENTALS
CLOSE TO YOUR JOB SITE
CATERPILLAR®
GENIE®
CHALLENGER®
SCREEN MACHINE®
RENTMACHINES.COM
![Page 13: New England 10 2016](https://reader030.vdocument.in/reader030/viewer/2022020202/579078d81a28ab6874c455a9/html5/thumbnails/13.jpg)
Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • May 18, 2016 • Page 13
Chappell Tractor Sales, Inc.
454 Route 13 SouthMilford, NH 03055800/698-2640
www.chappelltractor.com
Chappell Tractor East, LLC
251 Route 125Brentwood, NH 03833
800/616-5666www.chappelltractor.com
Kahn Tractor & Equipment, Inc.
520 Pond RoadNorth Franklin, CT 06254
860/642-7596www.kahntractor.com
Lorusso HeavyEquipment, LLC
160 Elm StreetP.O. Box 857
Walpole, MA 02801508/660-7600
www.lhequip.com
![Page 14: New England 10 2016](https://reader030.vdocument.in/reader030/viewer/2022020202/579078d81a28ab6874c455a9/html5/thumbnails/14.jpg)
Page 14 • May 18, 2016 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide
RIDOT Using Accelerated Method for East Bay BridgesGov. Gina M. Raimondo joined with
Rhode Island Department of Transportation(RIDOT) officials to tour RIDOT’s acceler-ated bridge reconstruction project for theEast Shore Expressway and McCormickQuarry bridges in East Providence, twoexamples of the many deficient bridgeswhich RIDOT is going to fix as it moves for-ward with its RhodeWorks program.The bridges serve as a vital link in Rhode
Island’s highway system, providing directaccess for the East Shore Expressway (onebridge for each direction of travel) overWarren Avenue and connecting all of RhodeIsland’s East Bay communities (EastProvidence, Barrington, Warren and Bristol)with I-195. Both bridges have structuraldeficiencies that cannot be addressed with-out a complete replacement. Already, areabusinesses and residents have been disruptedby a 17-ton (15.4 t) weight limit for thebridge carrying off-ramp traffic from I-195East onto Route 114 South. The weight limithas been in effect for more than four years,requiring trucks to detour onto EastProvidence city streets.“When we took action to rebuild Rhode
Island’s crumbling roads and bridges, wealso committed to rebuilding RIDOT to beready to manage these projects and deliverresults on time and on budget,” said
Raimondo. “Today’s project update was agood opportunity to see firsthand the newmethods RIDOT is putting in place to inno-vate in the department, move more quickly,and get the job done. We’re going to keepfixing bridges like this that are so importantto the communities they serve, and we’regoing to keep putting Rhode Islanders backto work in the process.”RIDOT will reconstruct the bridges by
using precast foundation elements and byconstructing the new bridge decks on largesupports adjacent to the current bridges.When the new bridge decks are finished thisfall, RIDOT will temporarily close the firststructure (East Shore Expressway Bridge)and the road underneath and in one 80-hourextended weekend closure, will remove theold bridge and install the new one. Theprocess will be repeated in approximatelytwo weeks for the second structure, theMcCormick Quarry Bridge.Using accelerated bridge construction
methods, RIDOT will dramatically shortenthe overall construction timeframe, complet-ing the bridge one year earlier than would bepossible using conventional constructionmethods. Additionally, if RIDOT had nottaken this approach, the travelling publicwould have been impacted over the courseof a year with each ramp only opened at half
capacity.“Rhode Island has the worst bridges in the
country, and with a great sense of urgencywe are exploring all options, including inno-vative accelerated bridge construction meth-ods like we’re using on this project,” PeterAlviti Jr., RIDOT director said. “With care-ful and diligent oversight through our newproject management approach, we are com-mitted to delivering the project on time, onbudget and with the highest quality.”These two bridges, originally built back in
1959, are being replaced through a $16.7million project with a $663,000 budget con-tingency. The East Shore ExpresswayBridge, which carries traffic from I-195 Eastto Route 114 South, carries 20,600 vehiclesper day. The McCormick Quarry Bridgeservices 17,000 vehicles per day making thereturn trip from Route 114 North to I-195West.The East Shore Expressway Bridge is
classified as functionally obsolete, with sig-nificant concrete cracking that limits its abil-ity to service large vehicles, resulting in thebridge’s 17-ton weight limit. The supportson the McCormick Quarry Bridge areseverely deteriorated, and are supplementedwith large wooden timbers to carry thebridge’s structural load.Pre-construction activities to relocate util-
ities and minor drainage work began last fall,with full construction resuming last month.Ongoing operations include excavation ofthe soil behind the bridge’s current support-ing columns to make room for the construc-tion of foundations for the new bridges.RIDOT also is making use of geosyntheticreinforced soil walls for the bridge’s abut-ments, which utilize layers of crushed stoneand reinforcing fabric to quickly assemblethe these foundation elements.In the coming weeks, motorists will see
construction begin on the supporting struc-tures for the new bridge decks, followedshortly by the delivery of large steel beamsfor the decks. Work will progress throughthe summer in completing the decks to thepoint where they can be installed using self-propelled modular transporters — multi-wheel dollies capable of lifting the bridgedecks off their temporary supports, drivingthem toward the bridge’s foundations andsetting them into place. Once installed,RIDOT will pave the bridge and approachesand open the road to traffic.For more information, visit
www.dot.ri.gov.(This story also can be found on
Construction Equipment Guide’s Website at www.constructionequipment-guide.com.)
Stillwater Avenue.Project:Highway safety improvements.Contractors and Bid Amounts:
• Lane Construction Corporation (The) —$709,969
• Maine Earth — $778,516• Sargent Corporation — $814,816• R F Jordan & Sons Construction Inc. —
$910,069
County: PenobscotContract ID: 019311.00Location: Bangor — Webster Ave. Bridge onInterstate 395 eastbound and westbound overWebster Avenue.Project: Bridge replacement.Contractors and Bid Amounts:
• S E Macmillan — $2,617,000• Lane Construction Corporation (The) — $2,987,065• Wyman & Simpson Inc. — $3,063,467• Sargent Corporation — $3,242,389• CPM Constructors — $3,431,904• T Buck Construction, Inc. — $3,759,000
County: LincolnContract ID: 020527.00Location:Wiscasset — at the intersection of U.S. Route 1& Route 27.Project:New sidewalk construction.Contractors and Bid Amounts:
• DDI Earthworks LLC — $389,010• Crooker Construction LLC aka Harry C Crooker &
Sons Inc. — $523,618• Sargent Corporation —
$572,965• T Buck Construction, Inc. —
$610,359• St. Laurent & Son Inc. aka
Maine Heavy Equipment Rental Inc. —$697,991
• Enterprise Trenchless Technology Inc. —$806,112
• CPM Constructors — Irregular
County: AroostookContract ID: 018813.00Location:Millinocket — on Route 11(Central Street) from Millinocket Streamextending easterly to the intersection withMedway Road.
Project:Drainage improvements.Contractors and Bid Amounts:
• Lane Construction Corporation (The) — $351,678• Lee’s General Trucking aka Emery Lee & Sons Inc. —
$380,358• Brown Developments LLC — $382,925• Sargent Corporation — $415,914• Stetson & Watson, J. V. — Irregular
Androscoggin • Aroostook • Cumberland • Franklin • Hancock • Kennebec • Knox • Lincoln • Oxford • Penobscot • Piscataquis • Sagadahoc• Somerset • Waldo • Washington • York • Androscoggin • Aroostook • Cumberland • Franklin • Hancock • Kennebec • Knox • Lincoln • Oxford• Penobscot • Piscataquis • Sagadahoc • Somerset • Waldo • Washington • York • Androscoggin • Aroostook • Cumberland • Franklin •Hancock • Kennebec • Knox • Lincoln • Oxford • Penobscot • Piscataquis • Sagadahoc • Somerset • Waldo • Washington • York •Androscoggin • Aroostook • Cumberland • Franklin • Hancock • Kennebec • Knox • Lincoln • Oxford • Penobscot • Piscataquis • Sagadahoc
Maine...
‘Pine Tree State’ Highway Projects Let
MAINE from page 8
![Page 15: New England 10 2016](https://reader030.vdocument.in/reader030/viewer/2022020202/579078d81a28ab6874c455a9/html5/thumbnails/15.jpg)
Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • May 18, 2016 • Page 15
A Company
CARIBOU, ME314 Main Street
Caribou, ME 04736
CHELMSFORD, MA15 Katrina Road
Chelmsford, MA 01824
BANGOR, ME188 Perry Road
Bangor, ME 04401
WESTBROOK, ME160 Warren Avenue
Westbrook, ME 04092
CONCORD, NH237 Sheep Davis Road
Concord, NH 03301
WE PROUDLY REPRESENT THE TEREX FINLAY LINE OF AGGREGATE EQUIP-
MENT THROUGHOUT NEW ENGLAND.
PLEASE FEEL FREE TO CONTACT US FOR YOUR SALES, RENTAL, PARTS AND SERVICE (NEW AND USED) NEEDS!
CALL TODAY!
978-987-2793
SALES * SERVICE* RENTALS
- - NorthlandJCB.com
Our Newest Location
150 N. Plains Industrial Road
Wallingford, Connecticut
![Page 16: New England 10 2016](https://reader030.vdocument.in/reader030/viewer/2022020202/579078d81a28ab6874c455a9/html5/thumbnails/16.jpg)
Page 16 • May 18, 2016 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide
MassHighway received bids for transportation-relatedimprovement projects.Following is a list of some of the projects let.
County/District: District 3Proposal Number: 607002-90315Project:Drainage repairs and improvements.Location:At three locations — Routes 2A- 146 and 122.(Shirley, Uxbridge and Worcester).Contractors and Bid Amounts:
• Onyx Corporation — $769,562• Ricciardi Bros Inc. — $772,602• David G Roach & Sons Inc. — $828,046• Newport Construction Corporation — $891,809• JBL Construction Company Inc. — $897,261• Ludlow Construction Company Inc. — $987,667• J H Lynch & Sons Inc. — $997,189• Caracas Construction Corporation — $1,067,371• A F Amorello & Sons Inc. — $1,072,452
County/District: District 4Proposal Number: 607209-90025Project: Roadway reconstruction and related work (includ-ing signals).Location:Along a section of Beacon Street. (Cambridgeand Somerville).Contractors and Bid Amounts:
• Newport Construction Corporation — $9,550,337• McCourt Construction Company Inc. — $10,058,840• Dallessandro Corporation — $10,256,180• J H Lynch & Sons Inc. — $11,786,049• J Tropeano Inc. — $12,081,117
County/District: District 5Proposal Number: 605848-89911Project: Roadway reconstruction and related work (includ-ing signals).Location:Along a section of Faunce Corner Mall Roadand Route 6 (Grand Army of the Republic Highway)(Dartmouth).Contractors and Bid Amounts:
• J H Lynch & Sons Inc. — $3,747,747• PJ Keating Company — $3,984,597• P A Landers Inc. — $4,074,357• Lal Construction Company Inc. — $4,212,989• Cardi Corporation — $4,279,143• UEL Contractors Inc. — $4,392,064• Wes Construction Corporation — $4,619,845
County/District: District 5Proposal Number: 604589-90404Project: Bridge replacement.Location: Bridge No. N-23-017 (concrete) Plain Streetover the Canoe River. (Norton).Contractors and Bid Amounts:
• Cardi Corporation — $1,839,313• E T & L Corporation — $1,868,064• New England Infrastructure — $1,949,150• Aetna Bridge Company — $2,133,200
• SPS New England Inc. — $2,263,022• UEL Contractors Inc. — $2,264,670• Northern Construction Services LLC — $2,279,930• A A Will Corporation — $2,721,220• Wes Construction Corporation — $2,809,486
County/District: District 2Proposal Number: 605559-90475Project: Roadway reconstruction and related work.Location:Along sections of Routes 67 and 19 (Main andMaple Streets) and adjacent Streets (Warren).Contractors and Bid Amounts:
• Ludlow Construction Company Inc. _ $1,571,411• Baltazar Contractors Inc. — $1,665,869• Jack Goncalves & Sons Inc. — $1,673,857• A F Amorello & Sons Inc. — $1,696,630• Northern Construction Services LLC — $1,723,749• JBL Construction Company Inc. — $1,725,491• Caracas Construction Corporation — $1,770,878• E T & L Corporation — $1,770,981• C & A Construction Company — $1,799,440• Palmer Paving Corporation — $1,940,131
County/District: District 3Proposal Number: 606485-90406Project: Resurfacing, median barrier replacement andrelated work.Location:Along sections of Route 146 (Worcester-Providence Turnpike). (Millbury and Sutton).Contractors and Bid Amounts:
• J H Lynch & Sons Inc. — $5,794,360• Cardi Corporation — $5,816,852• Aggregate Industries NE Region Inc. — $6,483,660• A F Amorello & Sons Inc . — $6,687,81
County/District: District 4Proposal Number: 603682-90407
Project: Bridge replacement.Location: Bridge No. A-07-026 (precast concrete arch)Interstate 495 (NB&SB) over Amesbury Riverwalk bike-way. (Amesbury).Contractors and Bid Amounts:
• SPS New England Inc. — $6,515,258• Kodiak Corporation — $6,698,712• McCourt Construction Company Inc. — $6,982,532• MIG Corporation — $7,037,757• Northern Construction Services LLC — $7,373,948• S&R Corporation — $7,593,867• John Rocchio Corporation — $7,625,421• E T & L Corporation — $8,460,930• J F White Contracting Company — $8,490,57
County/District: District 3Proposal Number: 606347-90472Project: Resurfacing and related work.Location:Along a section of Route 20 (Charlton Road)(Sturbridge).Contractors and Bid Amounts:
• J H Lynch & Sons Inc. — $2,434,773• A F Amorello & Sons Inc . — $2,607,285• PJ Keating Company — $2,633,883• Palmer Paving Corporation — $2,832,322
County/District: District 2Proposal Number: 606597-86888Project: Bridge rehabilitation and related work (includingpainting).Location: Three bridges along Interstate 90 (Bridge Nos.P-01-046-P-01-047 and P-01-049) (Palmer).Contractors and Bid Amounts:
• Aetna Bridge Company — $6,876,990• Northern Construction Services LLC — $7,777,200• N E L Corporation — $7,860,012• SPS New England Inc. — $7,987,355
Essex • Bristol • Franklin • Plymouth • Worcester • Middlesex • Norfolk • Dukes • Barnstable • Suffolk • Hampshire • Chilmark • Amherst •Monterey • Nantucket • Hampden • North Adams • Essex • Bristol • Franklin • Plymouth • Worcester • Middlesex • Norfolk • Dukes •Barnstable • Suffolk • Hampshire • Chilmark • Amherst • West • Monterey • Nantucket • Hampden • North Adams • Essex • Bristol • Franklin• Plymouth • Worcester • Middlesex • Norfolk • Dukes • Barnstable • Suffolk • Hampshire • Chilmark • Amherst • West • Monterey •Nantucket • Hampden • North Adams • Essex • Bristol • Franklin • Plymouth • Bristol • Franklin • Plymouth • Worcester • Middlesex
Massachusetts...
‘Bay State’ Highway Projects Let
![Page 17: New England 10 2016](https://reader030.vdocument.in/reader030/viewer/2022020202/579078d81a28ab6874c455a9/html5/thumbnails/17.jpg)
Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • May 18, 2016 • Page 17
1-800-53-CRUSH
Call for Instock Parts
284 North StreetWindsor Locks, CT 06096
51 Veterans DriveLoudon, NH 03307
1-800-53-CRUSH or 860-627-6596www.powerscreen-ne.com
Davis Auctions, Inc., will be conducting our next auction of utility and construction equipment andrelated supplies on June 18, 2016. This auction will consist of excess equipment from the powercompanies, municipalities and others to be sold in absolute.
Early Consignments:EQUIPMENT
Excavators: IHI 28N Mini, w/blade, aux hyd, swing boom;Skid Steer Loader: 2012 JOHN DEERE 320D, EROPS, heat & air, 815 +/- hrs; Loaders: CAT 931B Track Loader, EROPS; FIAT-ALLIS 545B Wheel Loader;Manlift: JLG 260MRT Scissor, 4x4; STRATO-LIFT 25’ Scissor, new batteries;Cable Plow: VERMEER Flex Trak 75;Wheel Tractors: FORD 445D, w/loader, forks, enc. cab w/heat, 3PtH, 4x4; JOHN DEERE 1010,3PtH, PTO, 2WD; FERGUSON, 3PtH, PTO, 2WD;Forklift: BIG-JOE PDR-20-106 Walk Behind, 2000lb cap.; KOMATSU FG25, propane;Attachments: Skid Steer Buckets & Forks;3 PtH Attachment: 4’, 5’, 6’, & 7’ Brush Hogs; Fertilizer Spreaders; Disc Harrow; York Rake;Rotary Tiller;Miscellaneous: Heavy Duty-All Steel 60”x120” Workbench w/vise; Lincoln Welder (6 mth old);Buckets: Assorted New JOHN DEERE & KOMATSU Buckets;
VEHICLESTractor: 2011 INT’L ProStar Premium T/A, MaxxForce 13, 430hp, eng. brake, Eaton Fuller10spd, A/R suspension, 14K front, 40K rears;Box Truck: 2000 INT’L 4000 Series, 26’ box w/peak, rebuilt DT466E, auto;Dump Truck: 1987 FORD F800 w/STETCO Series 950 Catch Basin Cleaner Crane, plow, diesel;Derrick Truck: 1986 INT’L 1900 w/Telelect C130 Derrick, DT466, auto, utility body, outriggers;Flatbed Trucks: 2008 INT’L 4400 26’, MaxxForce DT, 7.6L L6 diesel; 2007 CHEV T8500 24’ T/A,w/locking rear axle, auto; FORD 700, gas;Cars: 2007 FORD Crown Victoria;SUV: 2002 NISSAN Xterra, 4x4; Vans: 2009 CHEV Express Cargo; 2005 DODGE Sprinter 2500, diesel; (2) 2003-2002 GMCSafari Cargo; (3) 2001-1998 FORD E350 Cargo, V8;Trucks: 2007 DODGE Dakota Ext Cab, 4x4, (2) 2009-2007 CHEV Silverado 3500, w/EagleLift liftgate, 4x4; 1997 FORD F450 SD; w/utility body, V8, diesel;Trailers: 1998 FONTAINE 50Ton Detach Lowbed; 2016 TOPLINE TLU-16, 6’4” x 16’ Utility, w/2’dovetail, slide in ramps, brakes, & (2)3500# axles; 2016 TOPLINE JTW-12, 6’4” x 12’ Utility,w/side & tail gates, & 3,500# axle; 2007 INT. 20DT Equipment, elec. brakes; 2003 EAGERBEAVER 12HA-PT Pintle Hitch Equipment,(new deck, brakes & drums in 2015); 2000 KENSING-TON K3URE Utility; Miscellaneous: Assorted Truck Parts (New & Used- Mack, Freightliner, International)
This is our early tentative list. We accept consignments up thru SATURDAY, JUNE 11, 2016 at2:00 P.M. We never know what will be consigned at the last minute – so come to our inspection
and find out!
INSPECTION: FRIDAY, JUNE 17,
2016
This is when/whereyou find out what
is really here!!!9:00 A.M. – 5:00 P.M.
TERMS: CASH OR GOOD CHECKS WITH IDENTIFICATION. ABSENTEE BIDS ACCEPTED.
Website list frequently updated. If you don't see what you want here,
visit www.davisauctionsinc.com for updates.
For Online Bidding, Visit Realtimebid.com
Call for more information:
DAVIS AUCTIONS, INC.
(203) 758-4087 or 1-800-201-4368
www.davisauctionsinc.com
Auctioneer:
Reginald Lussier
Lyndonville, VT 05851
NH License# 2413
CONSTRUCTION AUCTIONDAVIS AUCTIONS, INC.
SATURDAY, JUNE 18, 2016 • 9:00 A.M.LOCATION: 210 CHESHIRE ROAD, RT. 68
PROSPECT, CTTHINK SUNSHINE!!!
![Page 18: New England 10 2016](https://reader030.vdocument.in/reader030/viewer/2022020202/579078d81a28ab6874c455a9/html5/thumbnails/18.jpg)
Page 18 • May 18, 2016 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide
opening.”The project endured a lengthy review by
historic preservation authorities over theplanned demolition of downtown buildingsin the months after last year’s March 24groundbreaking.
Then MGM asked the state and city forpermission to open a year later in September2018, on account of a major interstate high-way project happening nearby that it fearedwould impact the first year of operation.
The company followed that request up byproposing cost saving design changes,including the controversial elimination of a25-story glass hotel tower (in favor of a six-story structure with the same 250 rooms) anda reduction in total square footage of thecomplex by about 10 percent.
Even with the changes, the project hasballooned from $800 million to $950 millionbecause of updated labor, material andadministrative cost estimates.
“Things happen on a complex project. Itisn’t unique,” said Michael Mathis, MGMSpringfield president. “It was less active thanwe planned. But it’s such a sprawling sitethat we were able to do some work all alongthe way.”
Since the groundbreaking, Mathis said,underground utility work has been done andmany downtown buildings have been razedor partly demolished to clear the 14.5-acredevelopment site.
Preparations are now under way for thefirst major new structure — a roughly 3,400-space parking garage.
Mathis said 700 construction workershave been employed to date. The project isrequired to provide a minimum of 2,000temporary jobs during construction and3,000 permanent ones when it opens.
But Springfield and other governmentagencies will have to wait longer for their bigpayouts.
The Las Vegas-based company is requiredto pay Springfield over $16 million beforethe casino opens and $25 million annuallythereafter.
Kennedy, of the Sarno administration,said MGM has so far met its financial obli-gations. It has paid the city about $8 millionof the pre-opening payments, as scheduled.Another $4.5 million is due later this year,and the final $4 million comes in 2017.
Massachusetts also claims a share ofannual gambling revenues, and 10 surround-ing cities and towns get more modest upfrontand annual payments from the casino.
Michael Fenton, Springfield City Councilpresident said he’ll be watching the project
isn’t “further watered down” without faircompensation to the city.
One open question, he said, is whereMGM places a promised apartment complexeliminated in the new designs. The companyhas said the roughly 50 market-rate units bebuilt within a half mile of the casino but noton site.
MGM’s involvement in the casino debatein nearby Connecticut is also worrying,
Fenton said.Connecticut lawmakers have authorized
the two tribes that separately own Foxwoodsand Mohegan Sun to seek a new site for ajointly-run casino, likely in the Hartford-areanear Springfield.
But MGM has sued in federal court, argu-ing the law violates the U.S. constitution bygiving the two tribes an unfair advantageover other would-be developers. It’s alsohelping finance another federal complaint bythe Schaghticoke Tribal Nation that makessimilar arguments.
“I have no issues with MGM trying tostop the expansion of Connecticut gaming,”Fenton said. “But if they’re teaming up withanother tribe to compete with the Springfieldcasino, I have a real big problem with that.”
Mathis declined to discuss theConnecticut lawsuits in detail.
“It has nothing to do with our day-to-dayjob here,” he said. “We’re focused on gettingthis project built. There’s a separate part ofthe company that’s pursuing opportunities inConnecticut and other parts of the countryand the rest of the world.”
Meanwhile, Wynn Resorts is hoping toopen a $1.7 billion Boston-area resort in late2018 and the Mashpee Wampanoag tribesaid it’ll break ground in April on a resortnear Cape Cod that could open as soon asnext year.
Plainridge Park, a slots parlor inPlainville, opened last summer.
(This story also can be found onConstruction Equipment Guide’s Website at www.constructionequipment-guide.com.)
Work on Massachusetts MGMCasino Kicking Into Full Gear
MGM from page 1
“Things happen ona complex project. Itisn’t unique.”
Michael MathisMGM Springfield
NEW ENGLAND SUPPLEMENTADVERTISER INDEX
The Advertisers Index is printed as a free editorial service to ouradvertisers and readership. Construction Equipment Guide is not
responsible for errors or omissions.
ACE EQUIPMENT SALES INC ........................................7
ARGUS INDUSTRIAL COMPANY ....................................1
ASTRO CRANE ..............................................................12
BULLETIN BOARD ........................................................12
CHADWICK BAROSS MA ..............................................15
CLASSIFIED ..................................................................12
DAVIS AUCTIONS INC ..................................................17
E W SLEEPER CO............................................................9
EQUIPMENT EAST........................................................1,6
FOLEY MARINE & INDUSTRIAL ENGINE ......................1
GORILLA HAMMERS........................................................1
HYUNDAI CONSTRUCTION EQUIPMENT....................13
J R VINAGRO CORPORATION........................................1
LORUSSO HEAVY EQUIPMENT LLC..............................5
M G EQUIPMENT ............................................................1
MILTON CAT....................................................................12
NORTHLAND JCB ..........................................................15
POWERSCREEN NEW ENGLAND................................17
R J POIRIER HEAVY EQUIPMENT REP ......................12
ROGERS BROTHERS ....................................................19
SDLG DEALER GROUP ................................................11
SUMMIT SUPPLY LLC/MULTI MACHINE ........................1
THE N.I.C.E. COMPANY ................................................10
THE W I CLARK CO ........................................................2
TYLER EQUIPMENT CO ..................................................3
WOODCO MACHINERY ................................................20
![Page 19: New England 10 2016](https://reader030.vdocument.in/reader030/viewer/2022020202/579078d81a28ab6874c455a9/html5/thumbnails/19.jpg)
Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • May 18, 2016 • Page 19
Tyler Equipment251 Shaker Road
East Longmeadow, MA 01028(413) 525-6351(800) 292-6351
Parts: (877) 255-6351
1980 Berlin TurnpikeBerlin, CT 06037(860) 356-0840(800) 352-4473
Parts: (860) 356-0848
www.tylerequipment.com
C.N. Wood Co., Inc.200 Merrimac St.
Woburn, MA 01801(781) 935-1919
Avon, MA (508) 584-8484
Johnston, RI(401) 942-9191
www.cn-wood.com
![Page 20: New England 10 2016](https://reader030.vdocument.in/reader030/viewer/2022020202/579078d81a28ab6874c455a9/html5/thumbnails/20.jpg)
Page 20 • May 18, 2016 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide
Some companies have you choose power or fuel efficiency. You chose both.
DEALER LOGO
Contact your localdealer:
Dealer Name
T, SCity123.456.7890
T, SCity123.456.7890
T, SCity123.456.7890
T, SCity123.456.7890
T, SCity123.456.7890
T, SCity123.456.7890
T, SCity123.456.7890
T, SCity123.456.7890
T, SCity123.456.7890
eloped the industrvo deolvVVolv
st fuel efficiency guary’s fireloped the industr
ever ha avvantee so you nest fuel efficiency guar
e
ALERDELOGO
omise on perto comprmonitoring, you can f
owing your business. Get the details at gr
And with Car. oductivitye or prormancfomise on pere imporocus your attention on mormonitoring, you can f
owing your business. Get the details at ocolvv
ack machinereTTrAnd with Caretant things — like impor
tfuelom/smare.coc .
Contact your local dealer:
WoodCo MaChinery
140 Wales AvenueAvon, MA 02322508.584.8484
22 North Maple StreetWoburn, MA 01801781.935.3377
60 Shun PikeJohnson, RI 02919401.942.9191
www.woodcomachinery.com