north fulton wastewater capacity analysis and economic ......the jcec is a state-of-the-art facility...
TRANSCRIPT
-
North Fulton Wastewater Capacity Analysis and Economic Assessment
Fulton County Department of Water Resources
Project No. 84426
07/27/2015
-
North Fulton Wastewater Capacity Analysis and Economic
Assessment
prepared for
Fulton County Department of Water Resources
Fulton County, Georgia
Project No. 84426
07/27/2015
prepared by
Burns & McDonnell Engineering Company, Inc. Alpharetta, GA
Engineered Horizons, LLC
Duluth, GA
COPYRIGHT © 2015 BURNS & McDONNELL ENGINEERING COMPANY, INC.
-
North Fulton Wastewater Capacity Analysis Table of Contents
Fulton County Department of Water Resources TOC-1 Burns & McDonnell
TABLE OF CONTENTS
EXECUTIVE SUMMARY ................................................................................................. i
1.0 INTRODUCTION AND OBJECTIVES ................................................................. 1-1 1.1 Objectives ............................................................................................................... 1-2
2.0 COMPLIANCE WITH DISTRICT PLANS ............................................................ 2-1
3.0 POPULATION PROJECTIONS ........................................................................... 3-1 3.1 Historic Population Trends ..................................................................................... 3-1 3.2 Future Population Projections ................................................................................. 3-2 3.3 Sewershed Population Projections .......................................................................... 3-6
4.0 WASTEWATER FLOW FORECASTS ................................................................ 4-1 4.1 North Fulton Sewersheds – Historic Trends and Metrics ....................................... 4-1 4.2 Intergovernmental Agreements ............................................................................... 4-3 4.3 Methodology ........................................................................................................... 4-4 4.2 Wastewater Flow Forecasts through 2035 .............................................................. 4-4
5.0 TREATMENT CAPACITY NEEDS ...................................................................... 5-1 5.1 Treatment Capacity Needs ...................................................................................... 5-1
6.0 ALTERNATIVES EVALUATION ......................................................................... 6-1 6.1 Big Creek Sewershed Alternatives ......................................................................... 6-1
6.1.1 Long-term Alternatives for Big Creek WRF ........................................... 6-1 6.1.2 Short-Term Management Options for Big Creek WRF ........................... 6-2 6.1.3 Big Creek Sewershed – Alternatives Cost Summary .............................. 6-4
6.2 JCEC Sewershed Alternatives ................................................................................ 6-4 6.2.1 Option A: JCEC Expansion to 20 MGD (Long-Term) ............................ 6-5 6.2.2 Option B-1: Cauley Creek WRF Purchase .............................................. 6-5 6.2.3 Option B-2: Cauley Creek WRF Restart (Private Operator) ................... 6-6 6.2.4 JCEC Sewershed – Alternatives Cost Summary ..................................... 6-6
6.3 Little River / Etowah Sewershed Strategy - Expansion to 2.6 MGD ..................... 6-6
7.0 RECOMMENDATIONS ....................................................................................... 7-1 7.1 Big Creek Sewershed Recommendations ............................................................... 7-1 7.2 Johns Creek Sewershed........................................................................................... 7-1 7.3 Little River Sewershed ............................................................................................ 7-2 7.4 Reuse Water Recommendations ............................................................................. 7-2
APPENDIX A - OUTREACH TO CITIES IN NORTH FULTON APPENDIX B – FOLLOW UP MEETINGS WITH CITIES APPENDIX C - COST ESTIMATE CALCULATIONS
-
North Fulton Wastewater Capacity Analysis Table of Contents
Fulton County Department of Water Resources TOC-2 Burns & McDonnell
LIST OF TABLES
Page No.
Table 2-1: Irrigation Customers Rate Implementation Schedule ................................................ 2-1 Table 4-1: Total Flow to North Fulton Wastewater Treatment Facilities ................................... 4-1 Table 4-2: Wastewater Generation Rate ...................................................................................... 4-3 Table 4-3: Wastewater Transfers between Counties ................................................................... 4-3 Table 6-1: Big Creek Sewershed Alternatives Cost Summary – 2015 Dollars ........................... 6-4 Table 6-2: JCEC Sewershed Alternatives Cost Summary – 2015 Dollars .................................. 6-6 Table 6-3: JCEC Sewershed Alternatives Cost Summary – 2015 Dollars .................................. 6-7
-
North Fulton Wastewater Capacity Analysis Table of Contents
Fulton County Department of Water Resources TOC-3 Burns & McDonnell
LIST OF FIGURES
Page No.
Figure 1-1: North Fulton Study Area and Sewersheds ................................................................ 1-1 Figure 3-1: North Fulton Cities.................................................................................................... 3-1 Figure 3-2: Historic City Populations in North Fulton ................................................................ 3-2 Figure 3-3: City of Alpharetta Population Projections ................................................................ 3-3 Figure 3-4: City of Johns Creek Population Projections ............................................................. 3-4 Figure 3-5: City of Milton Population Projections ...................................................................... 3-5 Figure 3-6: City of Mountain Park Population Projections ......................................................... 3-5 Figure 3-7: City of Roswell Population Projections .................................................................... 3-6 Figure 3-8: North Fulton Cities and Sewersheds ......................................................................... 3-7 Figure 3-9: Big Creek Sewershed Population within Chattahoochee Basin ................................ 3-8 Figure 3-10: Big Creek Sewershed Population within Etowah Basin ......................................... 3-9 Figure 3-11: JCEC Sewershed Population ................................................................................... 3-9 Figure 3-12: Little River Sewershed Population ....................................................................... 3-10 Figure 3-13: Etowah Sewershed Population .............................................................................. 3-10 Figure 4-1: Historic Population and Wastewater Flow Trends ................................................... 4-2 Figure 4-2: Big Creek Sewershed Projected Flows ..................................................................... 4-4 Figure 4-3: JCEC Sewershed Projected Flows ............................................................................ 4-5 Figure 4-4: Little River Sewershed Projected Flows ................................................................... 4-5 Figure 4-5: Etowah Sewershed Projected Flows ......................................................................... 4-6 Figure 5-1: Treatment Capacity Needs: Big Creek Sewershed ................................................... 5-2 Figure 5-2: Treatment Capacity Needs: Little River Sewershed ................................................. 5-3 Figure 5-3: Treatment Capacity Needs: JCEC Sewershed ...................................................... 5-4
-
North Fulton Wastewater Capacity Analysis Executive Summary
Fulton County Department of Water Resources i Burns & McDonnell
EXECUTIVE SUMMARY
Fulton County Department of Water Resources (DWR) completed its last round of master planning in
2008, with a Water and Wastewater Master Plan Update. Since that time the County has survived the
drought of record, the 500-year flood, and an economic recession that continues to challenge the view of
“normal”. With development and growth returning in earnest to the North Fulton area, DWR is taking a
careful look at how much wastewater capacity is needed at each of its facilities and assessing strategies to
provide additional capacity. To plan for this need, DWR commissioned this evaluation.
Purpose
This evaluation
accomplishes the
following objectives:
• Develop
wastewater flow
forecasts based on
the most recent
population
forecasts for the
North Fulton
sewersheds
• Assess wastewater
treatment capacity
needs for each
sewershed
• Evaluate and
recommend the most cost effective solution for wastewater treatment capacity in each sewershed,
including the evaluation of proposals regarding the Cauley Creek Water Reclamation Facility (WRF).
Results and Recommendations
• Study area is limited to the North Fulton area that is served by Big Creek WRF, JCEC or Little
River WRF, and the Etowah Basin that is currently unsewered.
• The planning period is 20 years; through year 2035.
JCEC
Big Creek – Chattahoochee Sewershed
Big Creek – Etowah Sewershed
Etowah Sewershed
Little River Sewershed
Figure ES-1. North Fulton Sewersheds
Johns Creek Environmental Campus (JCEC)
Big Creek WRF
Little River WRF
-
North Fulton Wastewater Capacity Analysis Executive Summary
Fulton County Department of Water Resources ii Burns & McDonnell
• Population projections provided by each city’s planning or community development department
indicated the area will grow by 27% over 20 years.
• Wastewater flow forecasts developed for each sewershed; total flow for North Fulton is forecast
to be 50.9 MGD in 2035.
• Treatment capacity assessment and recommendations:
o JCEC, a 15-MGD state-of-the-art facility, has adequate wastewater treatment capacity
through 2035. If additional capacity is required, expanding JCEC by 5 MGD to 20 MGD is
the least cost option for additional capacity. The capital cost of the expansion is estimated to
be $3.2M.
o Under current conditions, Big Creek WRF periodically experiences flows nearing the
permitted maximum month average day limit of 24 MGD, generally during wet months. The
least cost option is to fully utilize the 15.48 MGD of treatment capacity Fulton County DWR
owns in Cobb County Water System’s (CCWS) R.L. Sutton WRF. DWR plans to continue
coordination with CCWS on any collection system modifications to transfer flow to the R.L.
Sutton WRF. This approach provides treatment capacity through the planning period for an
estimated cost of collection system improvements of $30M. Alternatively, DWR can
preserve the owned capacity at R.L. Sutton WRF by moving ahead with the Big Creek
expansion during planning period.
o Little River WRF is currently operating at its permitted capacity. The sewershed is currently
under a development and sewer connection moratorium. This project should soon be clear
from a regulatory perspective to move ahead with an expansion in capacity to 2.6 MGD,
more than sufficient to meet the projected flow of 1.4 MGD by 2035.
• Reuse water recommendations:
o The reasons to implement a water reuse system have changed due to a changing regulatory
landscape. In the early 2000s, the North Fulton reuse system provided a way for wastewater
to be discharged when it a river discharge was not allowed. Now, discharges to rivers are
preferred and encouraged.
o Once a benefit to reuse customers, irrigation with reuse water is no longer allowed during
drought conditions.
o A business case evaluation is recommended for any and all reuse proposals to assess whether
a reuse water system is a viable and cost effective service for Fulton County to provide.
-
North Fulton Wastewater Capacity Analysis Introduction and Objectives
Fulton County Department of Water Resources 1-1 Burns & McDonnell
1.0 INTRODUCTION AND OBJECTIVES
Fulton County Department of Water Resources (DWR) provides wastewater collection and treatment
services to three primary basins, or sewersheds, in North Fulton County: Big Creek, JCEC and Little
River. Figure 1-1 presents the Study Area and sewersheds in North Fulton. The small black lines
represent sewer lines in the Big Creek (Chattahoochee and Etowah), JCEC and Little River Sewersheds.
The Etowah Sewershed currently has no collection system or treatment facilities. The wastewater
generated in this sewershed is treated by on-site systems, such as septic tanks.
Figure 1-1: North Fulton Study Area and Sewersheds
The sewersheds are generally aligned with the watershed basins and include the Johns Creek, Big Creek
Chattahoochee, Big Creek Etowah, Little River and Etowah sewershed. The Big Creek-Etowah
sewershed is located in the Etowah River watershed; the wastewater generated in this area is pumped to
JCEC Sewershed
Big Creek - Chattahoochee Sewershed
Big Creek – Etowah Sewershed
Etowah Sewershed
Little River Sewershed
-
North Fulton Wastewater Capacity Analysis Introduction and Objectives
Fulton County Department of Water Resources 1-2 Burns & McDonnell
the Big Creek Water Reclamation Facility (WRF) for treatment and was separated from the rest of the
Etowah River basin to account for this flow.
Wastewater generated within the sewersheds, except for the Etowah Sewershed, flows to treatment plants
owned and operated by the County including Johns Creek Environmental Campus (JCEC), Big Creek
WRF and the Little River WRF. A brief snapshot of current North Fulton wastewater treatment assets
follows:
The JCEC is a state-of-the-art facility that discharges highly treated effluent into the
Chattahoochee River and has a treatment capacity of 15 MGD on a maximum month average day
(MMAD) basis. This facility replaced the original Johns Creek Water Pollution Control Plant
(WPCP). In 2009, with the capacity and efficiency of the newly commissioned JCEC facility, the
Cauley Creek WRF, which was owned and operated by an private owner, was no longer needed.
The contract for use of the Cauley Creek WRF was terminated early and the owner compensated
as contractually obligated.
The Big Creek WRF has a permitted capacity of 24 MGD-MMAD and also discharges to the
Chattahoochee River. DWR currently diverts 3.5 MGD to Cobb County Water System (CCWS)
from Big Creek WRF for treatment. An additional 2 to 2.5 MGD of wastewater is pumped to
CCWS from Big Creek at three other pump stations, for a total of 5 to 6 MGD of flow. DWR
owns 25.8% reserve capacity, which is currently 15.48 MGD, at the CCWS’s R.L. Sutton WRF.
The 3.5 MGD diversion does not count against that capacity as it is in exchange for treatment of
flow from Cobb County.
The Little River WRF, located in adjacent Cherokee County provides tertiary filtration and
discharges to the Little River within the Etowah River basin. A planned expansion and upgrade of
the facility described in the August 2012 Design Development Report will improve treatment
technology via membranes and expand the treatment from 1.0 MGD-MMAD capacity to 2.6
MGD-MMAD. The Little River basin is currently under a moratorium until the plant expansion
completed. Little River WRF also provides reuse water to the Settindown Creek Golf Course.
1.1 Objectives DWR’s goal is to provide wastewater collection and treatment at the least cost to its customers. To
adequately plan for the next 20 years (through 2035), DWR requested a thorough, independent
assessment of wastewater flow forecasts in the North Fulton sewersheds and the required treatment
capacity needs. Based on treatment needs over the planning horizon, alternatives were developed along
-
North Fulton Wastewater Capacity Analysis Introduction and Objectives
Fulton County Department of Water Resources 1-3 Burns & McDonnell
with a present-worth analysis, including operations and maintenance. The most cost effective option for
each sewershed was identified and recommended.
A related objective that is documented in Section 2.0 of this document is the approach that will be
implemented for Fulton County to be in compliance with the Metropolitan North Georgia Water Planning
District’s (District) Action Item 5.1 – conservation pricing for irrigation customers. With compliance
achieved on this action item, progress can be made on the upgrade and expansion of the Little River
WRF.
-
North Fulton Wastewater Capacity Analysis Compliance with District plans
Fulton County Department of Water Resources 2-1 Burns & McDonnell
2.0 COMPLIANCE WITH DISTRICT PLANS
The Georgia General Assembly created The Metropolitan North Georgia Water Planning District
(District) in 2001. The District prepares stormwater, water supply and wastewater management plans,
which are approved by the Georgia Environmental Protection Division (EPD). The statute creating the
District provides that EPD may not issue a water related permit to any local government in the District
area not in compliance with the Plans. EPD conducts audits of local governments to determine plan
compliance. Therefore, in order to receive EPD permits for future wastewater treatment facilities in north
Fulton County, Fulton County must receive certification from EPD that Fulton County is in compliance
with the District plans.
One of the requirements of the District’s water supply plan is a fee structure for irrigation water supply.
The rate (cost to the customer) of this irrigation water must be greater than or equal to 200% of the first
tier residential water rate.
In December 2013, EPD informed Fulton County that the County cannot be certified as compliant with
the Metro District plan since the County did not employ the District required irrigation rate structure and
that nine customers in north Fulton County were paying irrigation rates less than the District-required
irrigation rate.
In order to comply with the District plan, Fulton County adopted the District irrigation rate structure and
developed a schedule to apply the newly adopted irrigation rate for the nine facilities. The timeline is
presented in Table 2-1.
Table 2-1: Irrigation Customers Rate Implementation Schedule
Customer New Rate Implementation Date
Johns Creek United Methodist Church November 2017 Country Club of the South December 2017
Atlanta Athletic Club January 2018 City of Johns Creek November 2021
River Farm Subdivision November 2021 Perimeter Church April 2022
Standard Club May 2022 River Pine Golf Club May 2022
St. Ives Golf Club January 2023
-
North Fulton Wastewater Capacity Analysis Compliance with District plans
Fulton County Department of Water Resources 2-2 Burns & McDonnell
In November 2014, Fulton County informed EPD of its new compliant irrigation rate ordinance and
committed to move the nine customers onto this rate according to the above schedule. Fulton County
formally requested EPD’s certification of compliance with the District’s plans and the District irrigation
rate. However, in April 2015, EPD denied the certification saying the nine facilities must have the 200%
irrigation rate immediately. EPD did state that there were no other issues to be resolved to achieve
compliance with the District plans.
Subsequently, Fulton County has cooperated with EPD to identify options to quickly and fully implement
its new irrigation rate. Of the several options presented and discussed, EPD and Fulton have agreed upon
the following course of action.
Fulton County will terminate or amend the existing irrigation water contracts for the nine customers.
New or amended contracts will be executed based upon a water rate equal to the established Fulton
County irrigation rate, which is equivalent to the 200% rate adopted by the District. Fulton County will
establish water credits to these customers for payment for easements previously granted to these
customers and/or the outstanding portion of the contract. The credits will be used for future irrigation
water payments and the cost of the irrigation water shall be the 200% irrigation rate.
EPD has tentatively concurred with this proposal, and Fulton County is now implementing this option.
Upon completion, Fulton County will provide the new or amended contracts to EPD who will then issue a
certification that Fulton County is in full compliance with District plans.
-
North Fulton Wastewater Capacity Analysis Population Projections
Fulton County Department of Water Resources 3-1 Burns & McDonnell
3.0 POPULATION PROJECTIONS
The first step to forecast future wastewater flows is to identify population forecasts for the Study Area.
This section documents historic population trends and the population forecasts used for this Study.
3.1 Historic Population Trends North Fulton County is comprised of five cities, as shown on the map in Figure 3-1. With the
incorporation of the cities of Johns Creek and Milton in 2006, there is no unincorporated land in North
Fulton County.
Figure 3-1: North Fulton Cities
As seen in Figure 3-2, the cities within North Fulton have experienced significant growth since 1990 (city
population estimates for years prior to incorporation were developed by the Georgia Office of Planning
and Budget or OPB). The annual growth rate in recent years has been between two percent and six
percent.
-
North Fulton Wastewater Capacity Analysis Population Projections
Fulton County Department of Water Resources 3-2 Burns & McDonnell
Figure 3-2: Historic City Populations in North Fulton
3.2 Future Population Projections Local, state and federal entities develop future population projections to plan for future services, such as
transportation, water, wastewater, parks, etc. Population projection data was obtained from a number of
sources for evaluation, including the following:
• Atlanta Regional Commission (ARC): traffic analysis zones (TAZ) data published in 2012 with
projections through 2040. The TAZ provide small area breakdown of population; typically
smaller than census tracts.
• The Georgia Office of Planning and Budget (OPB): county-level population projections through
2050.
• United States Census Bureau: 2010 census population counts and 2012 population estimates for
each city
• City of Alpharetta Community and Economic Development Departments, City of Johns Creek
Community Development Department, City of Milton Community Development Department,
City of Mountain Park, City of Roswell Community Development Department: each City
Popu
latio
n
-
North Fulton Wastewater Capacity Analysis Population Projections
Fulton County Department of Water Resources 3-3 Burns & McDonnell
provided most current population projections based on land use development vision and rigorous
projection methods
The Burns & McDonnell team met (in person or on the phone) with each City’s development director to
discuss population projections provided, current development patterns and vision for development
through 2035. Documentation of this outreach effort and discussion notes are included in Appendix A. In
general, each City conducted a detailed analysis of their available developable land coupled with future
land use plan, and calculated the population that would result from those future developments.
Comparison to previous Comprehensive Plans and/or ARC data showed that the current population
projections are not significantly different. Future population projections for each of the cities are shown in
Figures 3-3 through 3-7.
The City of Alpharetta uses the slogan “A Technology & Employment Hub” to describe the community.
Alpharetta contains 20 million square feet of office space (nearly equal to Buckhead’s 22 million) plus
four exits along Georgia 400. They do not anticipate significant single-family residential development in
the future, but see most of their development being commercial or mixed-use. Redevelopment is
occurring on a few large parcels that were formerly commercial space.
Figure 3-3: City of Alpharetta Population Projections
The City of Johns Creek anticipates continued single family residential as the preferred style of
development, with commercial development along the major corridors. The City Center initiative is
planned to attract more businesses and mixed use to the downtown area. Most growth is anticipated by
-
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
100,000
110,000
2010 2015 2020 2025 2030 2035
Popu
latio
n
-
North Fulton Wastewater Capacity Analysis Population Projections
Fulton County Department of Water Resources 3-4 Burns & McDonnell
2025 as large tracts of land for development begin to taper. The opportunity for redevelopment is
anticipated to be limited due to the number of single-family home subdivisions, which make it a challenge
to purchase enough homes to convert to new types of development.
Figure 3-4: City of Johns Creek Population Projections
The City of Milton has a strong desire to maintain the rural character of pre-developed Fulton County.
Thus, future development is anticipated to be predominately residential at a minimum density of one unit
per acre, which is the Fulton County minimum requirement for septic service. All commercial
development will be focused on three areas, called development nodes, including Crabapple, Deerfield
and the Arnold Mill Corridor. Currently, the first two have sewer service available; however, the Arnold
Mill Corridor does not. The City desires sewer service extensions to this area to allow for this to be a
commercial development node within the City.
-
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
100,000
110,000
2010 2015 2020 2025 2030 2035
Popu
latio
n
-
North Fulton Wastewater Capacity Analysis Population Projections
Fulton County Department of Water Resources 3-5 Burns & McDonnell
Figure 3-5: City of Milton Population Projections
As seen in Figure 3-6, the City of Mountain Park expects to remain very similar to the way they are today
with very little growth over the planning period.
Figure 3-6: City of Mountain Park Population Projections
The City of Roswell is currently well developed, and therefore does not anticipate significant growth over
the planning period. The growth that is currently happening and expected to continue is higher density
redevelopment near the downtown area, and mixed-use developments in other similar areas.
-
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
100,000
110,000
2010 2015 2020 2025 2030 2035
Popu
latio
n
-
100
200
300
400
500
600
700
800
900
1,000
2010 2015 2020 2025 2030 2035
Popu
latio
n
-
North Fulton Wastewater Capacity Analysis Population Projections
Fulton County Department of Water Resources 3-6 Burns & McDonnell
Figure 3-7: City of Roswell Population Projections
3.3 Sewershed Population Projections North Fulton lies within two major river basins, the Chattahoochee, which serves as the eastern and
southern county boundary in North Fulton, and the Etowah, which bisects the northern portion of North
Fulton. The Chattahoochee River basin contains several tributary creeks, the two largest being Big Creek
and Johns Creek, both of which originate in Forsyth County.
The collection system in North Fulton is comprised primarily of gravity sewers, which generally follow
streams and rivers within a watershed. This is the most economical way to collect wastewater. Pump
stations and force mains are employed to pump wastewater from a topographically low area to a higher
area. Based on the topography, Fulton County developed three facilities to treat wastewater in North
Fulton County:
• The Big Creek Water Reclamation Facility (WRF) is located just west of the confluence of Big
Creek with the Chattahoochee River. In addition, as development moved northward, limited
sewer was constructed in the Etowah basin and is collected and pumped to the Big Creek basin
via pumping stations.
• The Johns Creek Environmental Campus (JCEC) is located adjacent to the Holcomb Bridge Road
crossing of the Chattahoochee River, south of the confluence of Johns Creek.
• The Little River WRF is located outside of Fulton County and serves the Little River basin. Little
River is a tributary to the Etowah River.
-
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
100,000
110,000
2010 2015 2020 2025 2030 2035
Popu
latio
n
-
North Fulton Wastewater Capacity Analysis Population Projections
Fulton County Department of Water Resources 3-7 Burns & McDonnell
The area served by a wastewater treatment facility is commonly referred to as a sewershed, since it may
not conform exactly to hydrologic watersheds. Each sewershed associated with each treatment facility is
presented in Figure 3-8.
Figure 3-8: North Fulton Cities and Sewersheds
Municipal boundaries rarely follow watershed or sewershed boundaries. So the next step in developing
wastewater flows is to use data analysis tools to translate the City population projections to sewershed
populations. Figure 3-8 shows the city boundaries relative to the sewershed boundaries. There is overlap
between portions of the cities between the sewershed boundaries.
A small portion of the City of Sandy Springs (shown in yellow on the Figure 3-8) contributes flow to the
Big Creek WRF and to JCEC. The majority of flow generated in Sandy Springs is treated by the City of
-
North Fulton Wastewater Capacity Analysis Population Projections
Fulton County Department of Water Resources 3-8 Burns & McDonnell
Atlanta. Using the TAZ data, the portion of the Sandy Springs population located within the JCEC and
Big Creek Sewersheds were assigned to those sewersheds.
The ARC-obtained Traffic Analysis Zone GIS data includes residential and employment populations for
5-year increments through 2040. TAZ boundaries are small areas located with county boundaries that are
generally smaller than census tracts. Using GIS, the city boundaries and TAZ boundaries, the sewersheds
were overlain and data joined to create sewershed populations based on TAZ data.
However, the most recent ARC regional TAZ data was published in 2012, and was lower than the local
projections for each City. The resulting sewershed populations were adjusted upward based on the
percent difference between the two data sets. The resulting populations for each sewershed are shown in
Figures 3-9 through 3-13.
Figure 3-9: Big Creek Sewershed Population within Chattahoochee Basin
0
40,000
80,000
120,000
160,000
200,000
240,000
2015 2020 2025 2030 2035
Popu
latio
n
-
North Fulton Wastewater Capacity Analysis Population Projections
Fulton County Department of Water Resources 3-9 Burns & McDonnell
Figure 3-10: Big Creek Sewershed Population within Etowah Basin
Figure 3-11: JCEC Sewershed Population
0
5,000
10,000
15,000
20,000
25,000
30,000
2015 2020 2025 2030 2035
0
20,000
40,000
60,000
80,000
100,000
2015 2020 2025 2030 2035
Popu
latio
n
-
North Fulton Wastewater Capacity Analysis Population Projections
Fulton County Department of Water Resources 3-10 Burns & McDonnell
Figure 3-12: Little River Sewershed Population
Figure 3-13: Etowah Sewershed Population
0
2,000
4,000
6,000
8,000
10,000
12,000
2015 2020 2025 2030 2035
Popu
latio
n
0
10,000
20,000
30,000
40,000
50,000
2015 2020 2025 2030 2035
Popu
latio
n
-
North Fulton Wastewater Capacity Analysis Wastewater Flow Forecasts
Fulton County Department of Water Resources 4-1 Burns & McDonnell
4.0 WASTEWATER FLOW FORECASTS
The population of North Fulton is expected grow by 27% by 2035. As discussed in Section 3, each
sewershed has its own vision for future growth, ranging from Little River’s 13% growth to Etowah’s 47%
growth over the planning period. The increase in population is projected to produce 50.9 million gallons
per day (MGD) of wastewater in North Fulton that will need to be managed in 2035.
4.1 North Fulton Sewersheds – Historic Trends and Metrics Daily wastewater influent flow rates for each facility located in each sewershed (Big Creek, JCEC/Johns
Creek WRF/Cauley Creek WRF, and Little River) for the period 2006 to 2014 were reviewed. From this
data, two important statistical numbers were calculated. Annual average day flow (AAD) rates and
maximum month average day flow (MMAD). The AAD flow is the amount of flow a facility receives on
average over the entire year; the MMAD flow is the average daily flow for the month with the highest
volume of flow. The MMAD flow is of particular importance as it is used to permit wastewater treatment
facilities and this is the capacity for which recommendations for additional capacity are made.
Table 4-1 presents the AAD and MMAD combined flow to all North Fulton facilities for years 2006
through 2014. An important ratio is the MMAD to AAD factor. This factor is applied to AAD flows to
estimate the MMAD. The geometric mean of the ratios is 1.20. There were significant weather events
during this period – the drought of record from 2007 to 2009 followed by the 500-year flood event in late
2009 both of which influence the ratio. Reviewing studies in North Fulton from years prior to 2007, the
average MMAD to AAD ratio used historically is 1.24 and was used for this study.
Table 4-1: Total Flow to North Fulton Wastewater Treatment Facilities
Year AAD MMAD MMAD to AAD Ratio
2006 30.36 35.04 1.15 2007 29.28 33.00 1.13 2008 28.41 32.33 1.14 2009 32.70 42.55 1.30 2010 29.35 41.28 1.41 2011 26.42 32.77 1.24 2012 24.35 26.88 1.10 2013 28.06 32.92 1.17 2014 27.88 33.81 1.21
-
North Fulton Wastewater Capacity Analysis Wastewater Flow Forecasts
Fulton County Department of Water Resources 4-2 Burns & McDonnell
When the average daily flow received at each facility in North Fulton is summed and plotted over time,
an interesting trend becomes apparent. As shown in Figure 4-1, the population increased by 20% and the
wastewater flows decreased by 20% over the period from 2006 to 2012.
Figure 4-1: Historic Population and Wastewater Flow Trends
Water efficient fixtures and changes in water usage behaviors are having an impact on both the regional
and national level. This net 40% reduction in water use and wastewater generation is a success story for
the conservation and stewardship initiatives promoted by the State, Metro Water District and Fulton
County. Similar trends are also being seen as the update-in-progress 2016 Metro Water District Plans
reviews water consumption and population for the 15-County region.
To develop wastewater generation rates, the base year of 2010 was selected, as it was a census year with
actual counts of the population, rather than estimates or projections of the population in each city. The
2010 AAD wastewater flow in each sewershed was divided by the number of people in 2010 in each
sewershed. The AAD wastewater generation rate for the base year is shown in Table 4-1.
-
50,000
100,000
150,000
200,000
250,000
300,000
20.00
25.00
30.00
35.00
40.00
45.00
Jan-06 Jan-07 Jan-08 Jan-09 Jan-10 Jan-11 Jan-12 Jan-13 Jan-14
Popu
latio
n
Was
tew
ater
Flo
w (M
GD)
30-Day Average Flow All Plants
Total Population
Linear (30-Day Average Flow All Plants)
20% Increase in Population
20% Decrease in Flow
-
North Fulton Wastewater Capacity Analysis Wastewater Flow Forecasts
Fulton County Department of Water Resources 4-3 Burns & McDonnell
Table 4-2: Wastewater Generation Rate
Sewershed
Wastewater Generation Rate (gallons per person per day)
AAD MMAD Big Creek 125 155 JCEC 121 150 Little River 100 124
As seen on Table 4-1, the different development patterns for the sewersheds influence the wastewater
generation rate. The Big Creek and JCEC sewersheds have a mix of residential and employment while
the Little River sewershed is primarily residential. The wastewater generation rate includes all
components of flow including inflow and infiltration (groundwater and stormwater that enters the
collection system), and thus represents the flow received at the treatment facility. Compared to the
current Metro District-wide generation rate of 104 gallons per person per day on an AAD basis, these
rates are significantly higher.
4.2 Intergovernmental Agreements An important element of wastewater flows in Fulton County is the receipt and transfer of wastewater from
surrounding counties. Table 4-3 provides a summary of contracted flow allocations and reserved
capacity. Flows into the County are included in the projections for each sewershed.
Table 4-3: Wastewater Transfers between Counties
County
Allocation in Big Creek WRF
(MGD)
Average flow to Big Creek
WRF (12/14-5/15)
(MGD)
Allocation in JCEC (MGD)
Average Flow to JCEC
(12/14-5/15) (MGD)
Reserve Capacity at R.L. Sutton WRF
(MGD)
Annual Average Flow to Cobb’s WRF
(MGD) Forsyth 0.5 1.8 1.37 0.79 DeKalb 1.25 0.6 1.0 0.66 Cobb 0.7 2.6 15.48 5.4
DWR has an agreement with Cobb County that the Big Creek WRF can divert up to 3.5 MGD for
treatment at R.L. Sutton WRF in exchange for treatment of Cobb County flows at Big Creek. This
exchange does not count as part of the total Reserve Capacity that Fulton County owns in CCWS’s R.L.
-
North Fulton Wastewater Capacity Analysis Wastewater Flow Forecasts
Fulton County Department of Water Resources 4-4 Burns & McDonnell
Sutton WRF. In addition to the 3.5 MGD diversion to CCWS, DWR transfers flow from the Big Creek
sewershed to CCWS via three pump stations. With the diversion and pump stations combined, the
average flow transferred to CCWS for the past 12 months was 5.4 MGD.
4.3 Methodology To project wastewater flows for each sewershed in North Fulton the 2010, the wastewater generation rates
presented in Table 4-1 were applied to the population projections for each sewershed over the planning
period. The generation rates for each sewershed were held constant over the planning period, despite the
downward trend in wastewater flows presented in Figure 4-1. This decision essentially builds in a safety
factor for additional development or other unforeseen factors over the planning period.
4.2 Wastewater Flow Forecasts through 2035 The wastewater flow forecasts through 2035 are presented in the following figures. Please note that for
the Big Creek Sewershed, the 3.5 MGD that is currently conveyed to Cobb County Water System’s R.L.
Sutton WRF was subtracted from the flow forecasts at the Big Creek WRF through the planning period.
Figure 4-2: Big Creek Sewershed Projected Flows
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
2015 2020 2025 2030 2035
Was
tew
atr F
low
(MG
D)
Big Creek AAD Total Big Creek MMAD
-
North Fulton Wastewater Capacity Analysis Wastewater Flow Forecasts
Fulton County Department of Water Resources 4-5 Burns & McDonnell
Figure 4-3: JCEC Sewershed Projected Flows
Figure 4-4: Little River Sewershed Projected Flows
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
16.0
2015 2020 2025 2030 2035
Was
tew
ater
Flo
w (M
GD)
JCEC AAD JCEC MMAD
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
2015 2020 2025 2030 2035
Was
tew
ater
Flo
w (M
GD)
Little River AAD Little River MMAD
-
North Fulton Wastewater Capacity Analysis Wastewater Flow Forecasts
Fulton County Department of Water Resources 4-6 Burns & McDonnell
Figure 4-5: Etowah Sewershed Projected Flows
0.0
0.1
0.2
0.3
0.4
0.5
0.6
2015 2020 2025 2030 2035
Was
tew
ater
Flo
ws
(MG
D)
Etowah AAD Etowah MMAD
-
North Fulton Wastewater Capacity Analysis Treatment Capacity Needs
Fulton County Department of Water Resources 5-1 Burns & McDonnell
5.0 TREATMENT CAPACITY NEEDS
This section presents a comparison of the flow forecasts to the permitted treatment capacity in each
sewershed to identify long-term treatment needs in North Fulton. The Big Creek Sewershed has an urgent
need for additional treatment capacity. The Little River Sewershed has a need for additional treatment
capacity. JCEC Sewershed has ample capacity through the planning period.
5.1 Treatment Capacity Needs The wastewater flow forecast for each sewershed presented in Section 4.0 was compared to the permitted
treatment capacity to identify if and where additional capacity may be required. The annual average day
(AAD) flow is the amount of wastewater the treatment facility routinely needs to treat. However, due
primarily to rain events treatment facilities need to be sized to treat flows higher than the average flow.
Treatment capacity is designed and permitted to treat the maximum month average day (MMAD) flow,
which is flow average daily flow for the month with the highest volume of flow. Treatment capacity is
permitted on a MMAD basis.
Figures 5-1 through 5-3 provide an overview of treatment capacity needs for the Big Creek, JCEC and
Little River sewershed. The Big Creek WRF has a permitted treatment capacity of 24 MGD. As noted in
Section 4.0, the Big Creek AAD and MMAD projected wastewater flows were reduced by 3.5 MGD,
which is the amount of flow that Fulton County diverts to CCWS’s R.L. Sutton WRF for treatment. The
amount of flow that Big Creek pumps to CCWS (approximately another 2 MGD on average for the past
12 months) via other pump stations was not removed. This difference in approach is due to the diversion
being taken just prior to the Big Creek WRF while the other pump stations are located at other points in
the sewershed. This approach provides a level of conservatism in the assessment and provides a complete
picture of flows generated in the basin. As seen in Figure 5-1, the Big Creek WRF has an urgent need for
additional capacity by 2020.
-
North Fulton Wastewater Capacity Analysis Treatment Capacity Needs
Fulton County Department of Water Resources 5-2 Burns & McDonnell
Figure 5-1: Treatment Capacity Needs: Big Creek Sewershed
The Etowah sewershed does not currently have wastewater collection or treatment, except for the
southeastern portion that is pumped to Big Creek. The portion of the Etowah that is pumped to Big Creek
WRF is included in the flows presented in Figure 5-1. For the remaining Etowah sewershed, it is
assumed that the flows generated at commercial nodes described in Section 3.0 would be treated at the
Little River WRF. Collection system infrastructure would need to be funded and constructed to convey
the wastewater to the WRF. With the uncertainty over whether these projects will come to fruition, the
Etowah sewershed flows were not included in the Little River WRF projections at this time.
As seen in Figure 5-2, the Little River WRF is also in need of additional capacity. The Little River WRF
has a permitted treatment capacity of 1.0 MGD on a MMAD basis. The sewershed is under a moratorium
for development and connections to the collection system. Approximately 0.2 MGD of treated effluent is
pumped from the effluent discharge to the adjacent Settindown Golf Course.
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
2015 2020 2025 2030 2035
Was
tew
atr F
low
(MG
D)
Big Creek AAD Total Big Creek MMAD Permitted Treatment Capacity
-
North Fulton Wastewater Capacity Analysis Treatment Capacity Needs
Fulton County Department of Water Resources 5-3 Burns & McDonnell
Figure 5-2: Treatment Capacity Needs: Little River Sewershed
Figure 5-3 presents the treatment capacity needs at the JCEC facility. The facility is permitted to treat 15
MGD on a MMAD basis. As seen on Figure 5-3, JCEC has adequate capacity through the planning
period.
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
2015 2020 2025 2030 2035
Was
tew
ater
Flo
w (M
GD)
Little River AAD Little River MMAD Permitted Treatment Capacity
-
North Fulton Wastewater Capacity Analysis Treatment Capacity Needs
Fulton County Department of Water Resources 5-4 Burns & McDonnell
Figure 5-3: Treatment Capacity Needs: JCEC Sewershed
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
16.0
2015 2020 2025 2030 2035
Was
tew
ater
Flo
w (M
GD)
JCEC AAD JCEC MMAD Permitted Treatment Capacity
-
North Fulton Wastewater Capacity Analysis Alternatives Evaluation
Fulton County Department of Water Resources 6-1 Burns & McDonnell
6.0 ALTERNATIVES EVALUATION
To meet the needs forecast in Section 5.0, a number of alternatives were identified and assessed based on
economics, technical feasibility and ability to meet the need within the timeframe required. Alternatives
for short- (5-year), medium- (5-10-year) and long-term (beyond 10 years) time frames are presented
below for each sewershed along with cost comparisons of present worth.
6.1 Big Creek Sewershed Alternatives
The Big Creek sewershed is
projected to experience
flows of 24.3 MGD-MMAD
in 2015. With current
permitted treatment capacity
of 24 MGD, this will leave a
small deficit of 0.3 MGD, as
presented in Figure 5-1. By
2020, the Big Creek WRF is
projected to have flows of
25.8 MGD-MMAD, which
represents a growing deficit. Over the short-term, the Big Creek WRF will be managed to operate within
its permit. Several options exist for short-term and long-term; these alternatives are discussed in the
following sub-sections.
6.1.1 Long-term Alternatives for Big Creek WRF There are two viable opportunities for the long-term capacity needs at the Big Creek WRF. One is the 14
MGD expansion of the facility and the other is to take advantage of capacity Fulton County owns in
CCWS’s R.L. Sutton WRF. Each of these options is discussed in more detail below.
6.1.1.1 Diversion to CCWS Fulton County owns 25.8% reserve capacity, which is currently 15.48 MGD, in CCWS’s R.L. Sutton
WRF. As the facility expands, the capacity that Fulton County owns increases. Big Creek WRF
currently diverts up to 3.5 MGD of flow to Cobb County Water System (CCWS) and has conveyed up to
6 MGD through existing infrastructure without incident. The 2035 deficit in treatment capacity is
projected to be approximately 8 MGD for the Big Creek sewershed. The capacity available at R.L. Sutton
Big Creek WRF
-
North Fulton Wastewater Capacity Analysis Alternatives Evaluation
Fulton County Department of Water Resources 6-2 Burns & McDonnell
is more than adequate to provide treatment capacity to the sewershed through 2035 and beyond.
Modifications to the collection and transmission system may be necessary to utilize the full capacity
owned by Fulton County. The potential cost for these transmission system improvements is $30M,
although a detailed study has not yet been completed.
6.1.1.2 Big Creek WRF Expansion to 38 MGD Expansion of the Big Creek WRF’s treatment capacity by 14 MGD is a long planned and viable
alternative. With construction costs ranging from $173 to $288 Million, depending on the treatment
technology selected, this expansion in capacity would address the long-term basin needs through year
2035 and beyond. It is conceivable that the CCWS diversion might defer the Big Creek expansion some
years while funding is secured.
6.1.2 Short-Term Management Options for Big Creek WRF The best short-term management option should segue into the selected long-term option with the least
amount of operational change and money spent. The options considered include additional diversion to
CCWS, Forsyth County flow reduction plan, and flow diversion to JCEC. Each of these options is
described below.
Big Creek WRF currently conveys up to 3.5 MGD of flow to Cobb County Water System (CCWS)
through an intergovernmental agreement and has conveyed up to 6 MGD through existing infrastructure.
The 3.5 MGD of flow diverted to CCWS is already included in the flow forecasts, but there is additional
flow that can be sent to CCWS with relatively minimal changes to the downstream collection system in
Cobb County.
6.1.2.1 Diversion of additional flows to Cobb County Water System In 2015, DWR diverted from 3.0 to 3.5 MGD of flow from the Big Creek WRF into the Cobb County
Water System (CCWS) under intergovernmental agreement. In addition, there are several pump stations
that convey wastewater to CCWS at other points before it reaches the Big Creek WRF. Records indicate
that Fulton has pumped a total of 5 to 6 MGD to CCWS in previous years.
One tool DWR can use to manage flows into Big Creek WRF during the next 5 years is to increase
pumping during peak flows as needed to meet demands at Big Creek WRF until the additional collection
system capacity is available or Big Creek WRF expansion is on-line by 2020.
-
North Fulton Wastewater Capacity Analysis Alternatives Evaluation
Fulton County Department of Water Resources 6-3 Burns & McDonnell
6.1.2.2 Decrease flows from Forsyth County DWR is receiving a monthly average of 1.80 MGD from Forsyth County in the Big Creek basin for the
first half of 2015. A reduction in the flow from Forsyth County to no more than 1.25 MGD is scheduled
to occur by 2017. Meetings with Forsyth County during the research on this analysis found that Forsyth
is moving in this direction and will certainly not increase flows to Fulton County.
6.1.2.3 Diversion of flows from Big Creek WRF to JCEC (Short Term) As a contingency alternative, DWR completed a feasibility study in 2009 investigating the possible
diversion of flows from Big Creek WRF to JCEC to provide “relief” capacity during peak flows for the
Big Creek sewershed.
This option, while technically feasible may well be practically impossible. The option requires extensive
land acquisition for the pumping and transmission facilities to complete the diversion. The diversion
project, including planning, permitting, engineering, land acquisition and construction, would run parallel
with the time line for other long-term alternatives. With an estimated completion year of 2019 to 2020
for the diversion, the project would essentially become unnecessary with long-term options, such as Big
Creek WRF expansion or conveyance to CCWS facilities, also operational by 2020.
The Big Creek to Johns Creek feasibility study is approximately 6-years old and needs to be updated,
including more robust hydraulic modeling of the sewer transmission and collection system, before it can
be acted upon. The option, with an estimated construction cost of $16.8 Million, which does not include
all easement acquisition, is less attractive as it would divert needed funding away from the primary
objective of increasing capacity inside the Big Creek sewershed. Combined with the projected O&M
costs for the diversion transmission system, the total cost for comparison is $21 Million over the 20-year
planning period of operation, respectively. Existing Fulton County water and sewer ratepayers have and
continue to pay for the existing capacity at both Big Creek and Johns Creek treatment facilities. The
diversion project would effectively cause ratepayers to pay again to utilize capacity they have previously
financed both inside and outside Fulton County (i.e., Cobb County).
Diverting flow from Big Creek WRF to JCEC would tend to drive an earlier expansion of JCEC to treat
the increase in flow. It is projected that the expansion at JCEC would need to begin in 2020 and certainly
be in place by 2025. As discussed below, the estimated cost this expansion is $3.2 Million, with a present
worth of $5.0 Million including O&M for the 10-year window. The total expenditure for this intra-Fulton
County diversion would be approximately $19 Million plus $5.0 Million, or $24 Million for the 10-year
-
North Fulton Wastewater Capacity Analysis Alternatives Evaluation
Fulton County Department of Water Resources 6-4 Burns & McDonnell
window to year 2025. The difficulty in implementing this solution combined with its costs has eliminated
it from further consideration.
6.1.3 Big Creek Sewershed – Alternatives Cost Summary Table 6-1 provides a summary of the Big Creek Sewershed Alternatives in 2015 dollars. Both estimated
capital cost and O&M are presented. Appendix C provides the basis for the cost estimates.
Table 6-1: Big Creek Sewershed Alternatives Cost Summary – 2015 Dollars
Alternatives Capacity Added
Estimated Capital Cost
Estimated O&M Costs
Total Project Cost (Capital
+ O&M) Long-Term Options Over 20-years Diversion to CCWS RL Sutton WRF (10 MGD)
10 MGD $30M $5M $35M
Expand Big Creek to 38 MGD
14 MGD $173M - $288M $13M $186M - $300M
Short-term Options Additional Diversion to CCWS RL Sutton WRF (5-6 MGD)
1.5 to 2.0 MGD
Minimal costs; coordination with CCWS
Minimally different than
current
Forsyth County Flow Reduction 0.55 MGD No cost No change
Diversion to JCEC 3.0 to 8.0 MGD
$16.8M+upgrade JCEC $5M
$2.2M over 10 years
$24M
6.2 JCEC Sewershed Alternatives The JCEC sewershed is projected to receive flows of 11.0 MGD by 2015. JCEC is currently permitted to
treat up to 15 MGD. By 2035, JCEC is projected to have 2.1 MGD
surplus capacity when flows are projected to be 12.9 MGD-MMAD.
DWR is projected to have sufficient capacity at JCEC for the entire 20-
year planning period. Included in these flow projections are flows into
the basin from Forsyth County which comprise approximately 0.76
MGD for the first half of 2015. Under the intergovernmental agreement
with Forsyth County, DWR has agreed to receive up to 1.37 MGD from
Forsyth County.
Based on this analysis, JCEC is forecast to have sufficient capacity to JCEC
-
North Fulton Wastewater Capacity Analysis Alternatives Evaluation
Fulton County Department of Water Resources 6-5 Burns & McDonnell
serve the growth predicted in the basin, which includes the projected growth in the City of Johns Creek,
for the 20-year planning period.
For additional capacity to be needed in JCEC sewershed, one would have to believe the sewershed’s
population would increase by 75% to nearly double the current population (130,000 people). With
130,0000 people in the sewershed, the population density would be similar to Buckhead in Atlanta, where
approximately 7.5 people reside per acre. The Buckhead density compares with current Johns Creek
projections of 17% growth over 20 years which would yield 3.88 people per acre. To manage that
increased flow during or beyond the 20-year window, there are two options:
• Option A: Expand JCEC by 5 MGD to capacity of 20 MGD with a Capital Cost = $3.2M, or
• Option B: Purchase Cauley Creek WRF for additional 5 MGD with a Capital Cost = $15M +
upgrades and operating costs
The options are described in detail below.
6.2.1 Option A: JCEC Expansion to 20 MGD (Long-Term) When constructed, certain design and redundancy features were incorporated into the plant that would
provide an easy and cost effective expansion in treatment capacity when the future need arises. It is
estimated that an increase in treatment capacity to 20 MGD can be achieved for approximately $3.2
Million. This added capacity is the most cost effective solution for additional treatment capacity in the
entire North Fulton system. Appendix C provides documentation on the cost estimate for JCEC
expansion.
For the long term, JCEC is projected to experience flows of 12.9 MGD by 2035, which still remains
under the permitted capacity of 15 MGD.
6.2.2 Option B-1: Cauley Creek WRF Purchase The Owners of the Cauley Creek WRF propose to sell the dormant facility to Fulton County for an
immediate purchase price of $15 Million. As the facility has been effectively out-of-service since
December 2012, the outright purchase of the facility by Fulton County would require due diligence (on-
site condition assessment) to determine what additional improvements would be needed to restore the
facility to Class I reliability status.
Also, with an outright purchase of the facility, Fulton County would incur the annual operation and
maintenance costs for the facility. For comparison with other options for new treatment capacity in the
-
North Fulton Wastewater Capacity Analysis Alternatives Evaluation
Fulton County Department of Water Resources 6-6 Burns & McDonnell
Johns Creek Basin, the present value of the purchase price plus long term operation and maintenance of
the facility over the 20-year planning period is estimated at $27.9 Million. Appendix C provides the basis
for this estimate.
6.2.3 Option B-2: Cauley Creek WRF Restart (Private Operator) As a comparison with the outright purchase, if Fulton County opted to pay for additional treatment only,
the Owners of the Cauley Creek WRF propose to treat up to 5 MGD for $3.25 per thousand gallons
treated. For comparison with other options for treatment in the Johns Creek basin, the present value for
the annual treatment expenditure over the 5, 10, and 20 year planning periods is estimated at
approximately $28, $52, and $100 Million, respectively. Appendix C provides the basis for this estimate.
6.2.4 JCEC Sewershed – Alternatives Cost Summary Table 6-2 provides a summary of the JCEC Sewershed Alternatives in 2015 dollars. As noted in Section
6.2, there is adequate wastewater treatment capacity at JCEC through the planning horizon; however, if
additional capacity were needed, the options and associated costs to meet those needs are provided below.
Appendix C provides the basis for the cost estimates.
Table 6-2: JCEC Sewershed Alternatives Cost Summary – 2015 Dollars
Alternatives Capacity Added
Estimated Capital Cost
Estimated O&M Costs
(over 20 years)
Total Project Cost (Capital +
O&M)
Upgrade JCEC to 20 MGD 5 MGD $3.2M $3.3M $6.5
Purchase Cauley Creek WRF 5 MGD $15M + upgrades $12.9M $27.9M + upgrades
Cauley Creek WRF Private Operator 5 MGD None None $100M
6.3 Little River / Etowah Sewershed Strategy - Expansion to 2.6 MGD The basin is projected to receive flows of 1.2 MGD in 2015.
Little River WRF, located in Cherokee County, is currently
permitted to treat up to 1.0 MGD with approximately 0.2
MGD of treated effluent pumped from the effluent discharge
to the Settindown Golf Course, also in Cherokee County. By
2035, Little River WRF is projected to receive flows in the
Little River WRF
-
North Fulton Wastewater Capacity Analysis Alternatives Evaluation
Fulton County Department of Water Resources 6-7 Burns & McDonnell
1.4 MGD range. At that time, the basin would experience a deficit in available capacity of 0.2 MGD
described in the projection tables.
The sewershed where Little River WRF is located primarily serves the City of Mountain Park and a
portion of the City of Roswell. Currently, there is significant economic development interest in the SR
140 / Arnold Mill Road corridor located in the City of Milton that would require collection system
expansion to provide service to that area.
For the long term, DWR plans to expand Little River WRF’s treatment capacity by 1.6 MGD beginning
in 2017 with completion by 2020. The estimated construction cost of the plant expansion is $25 Million
based on the treatment technology described in the approved Design Development Report. This
expansion in capacity will address the long-term basin needs through year 2035 and beyond. The present
value of the construction plus the long term O&M for the facility is estimated at $27 Million for the 20-
year build out.
If that expansion is not undertaken during the period between 2015 and 2017, DWR can manage the
capacity at Little River WRF by purchasing up to 0.5 MGD of capacity at Cherokee County’s Rose Creek
WRF. DWR has continued ongoing discussions with Cherokee County on this matter although costing
has not been documented at this time. This would increase available treatment capacity up to 1.5 MGD
by 2035 to serve the 20-year projection of 1.4 MGD of need in the sewershed. Appendix C provides the
basis for the cost estimates.
Table 6-3: JCEC Sewershed Alternatives Cost Summary – 2015 Dollars
Alternatives Capacity Added
Estimated Capital Cost
Estimated O&M Costs
(over 20 years)
Total Project Cost (Capital +
O&M)
Purchase 0.5 MGD capacity at Rose Creek WRF 0.5
To Be Determined TBD TBD
Expand Little River WRF to 2.6 MGD 1.6 $25.2M $1.8M $27
-
North Fulton Wastewater Capacity Analysis Recommendations
Fulton County Department of Water Resources 7-1 Burns & McDonnell
7.0 RECOMMENDATIONS
Based on the needs assessment and evaluation of strategies, the following plan of action is recommended
for DWR with points grouped by sewershed or relevant topic.
7.1 Big Creek Sewershed Recommendations Under current conditions, Big Creek WRF periodically experiences flows nearing the permitted
maximum month average day limit of 24 MGD. These occurrences generally fall within wet months.
With Big Creek WRF having maximum month average day flows reaching near permitted capacity, this
sewershed has an urgent need for additional treatment capacity. This need becomes crucial during the
next 5 years as we approach 2020 as projected flows reach 25.8 MGD-MMAD. To meet the projected
needs during the planning period, including the projected flow of 32.2 MGD-MMAD by 2035, it is
recommended that DWR undertake the following:
o Short-term Strategy: Through 2020, wastewater flows to Big Creek WRF can be managed
through continued flow diversion to Cobb County’s R.L. Sutton WRF where Fulton County
owns 15.48 MGD of treatment capacity. Fulton County plans to continue coordination with
CCWS on any collection system modifications necessary to utilize capacity owned at the
plant.
o Long-term Strategy: The least cost option is to fully utilize the capacity Fulton DWR owns in
the R.L. Sutton WRF. Coordination with CCWS on any collection system modifications to
transfer flow to the Sutton WRF. Alternatively, construction of some or all of the planned
additional 14 MGD capacity at Big Creek WRF should be undertaken. We use the term
“alternatively” based on the amount of capacity Fulton County owns at the CCWS facility,
which if fully utilized would allow the deferment of the Big Creek upgrade through the
planning period of 2035. To accomplish the expansion of Big Creek WRF by 2020, one
would assume some form of accelerated alternative procurement might be in order, similar in
nature to the JCEC procurement process.
7.2 Johns Creek Sewershed JCEC has sufficient treatment capacity through 2035 and beyond based on the sewershed’s projected
wastewater flows. We recommend that DWR set a planning level “trigger” benchmark based on
maximum month average daily flow for the JCEC facility (and all facilities) to establish when planning
for capacity expansions should begin.
-
North Fulton Wastewater Capacity Analysis Recommendations
Fulton County Department of Water Resources 7-2 Burns & McDonnell
At the point in time defined by the proposed benchmark and growth in the sewershed dictates, DWR
should upgrade the JCEC by 5 MGD, taking advantage of the pre-planned, modular upgrade attributes
found in JCEC’s membrane system design. In 2015 dollars, the estimated construction cost plus
additional allocated O&M cost has a present value of approximately $6.5 Million under a 20-year life
cycle analysis. This is the least cost option for capacity expansion in the entire North Fulton area and is
recommended for the JCEC sewershed when additional capacity is required.
7.3 Little River Sewershed The Little River WRF is currently operating at capacity. With continued development pressure for sewer
service, it is recommended that DWR proceed with expanding the Little River WRF. The ability to
obtain a permit from EPD for the expansion will soon be cleared by coming into compliance with the
District’s irrigation rate requirements, as described in Section 2.0.
7.4 Reuse Water Recommendations North Fulton County’s reuse system provided a way to allow growth to continue in early 2000s when a
river discharge was not an option. The regulatory climate has changed; discharge to rivers is now
encouraged. Another driver for reuse water was that it was allowed for use during drought conditions.
Per EPD regulations, reuse water is no longer allowed for irrigation during drought conditions. Reuse can
still be considered a tool in overall water management; however, a business case evaluation is
recommended for any and all reuse proposals to assess whether a reuse water system is a viable and cost
effective service for Fulton County.
-
APPENDIX A - OUTREACH TO CITIES IN NORTH FULTON
-
City Technical Lead: Population
Projections Mayor City Manager/
Administrator Notes
Alpharetta Economic Development Director Peter Tokar Phone: 678-297-6075 Fax: 678-802-3293 E-mail: [email protected]
David Belle Isle Phone: (678) 297-6020 (office) E-mail: [email protected]
Robert J. Regus City Administrator Phone: (678) 297-6010 Fax: (678) 802-3293 E-mail: [email protected]
Left vm for Samir Adwahee in Economic Development office – spoke with admin in planning and zoning was told that projections are handled by Economic Development office.
Roswell Alice Wakefield Director of Community Development [email protected] Ph: 770-641-3780 Fx: 770-641-3741
Jere Wood [email protected] Robyn Kenner Executive Assistant to Mayor Ph: 770-594-6288
Kay G. Love City Administrator mailto:[email protected] ph: 770-641-3727
Johns Creek
Sharon Ebert, Director of Community Development [email protected] Thomas Black Director of Public Works [email protected]
Mike Bodker [email protected] Karen Negri, Exec. Assistant: 678-512-3327
Warren Hutmacher City Manager [email protected] Karen Negri, Exec. Assistant: 678-512-3327
Talked with Tom Black to get information for Sharon – he said she’s the one to send to, but is also interested in the projections.
Mountain Park
Jim Stills [email protected]
Karen Segars [email protected]
City hall: 770-993-4231
Milton Kathleen Field Director of Community Development [email protected] 678-242-2555
Joe Lockwood [email protected] 678.242.2484
Chris Lagerbloom City Manager [email protected] 678-242-2488
mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]
-
3650 Mansell Road \ Suite 300 \ Alpharetta, GA 30022 O 770-587-4776 \ F 770-587-4772 \ burnsmcd.com
June 22, 2015 Mr. Peter Tokar Economic Development Director City of Alpharetta 2 Park Plaza Alpharetta, GA 30009 Re: Population Forecasts for Fulton County Department of Water Resources Dear Mr. Tokar: On behalf of the County, we are evaluating long term wastewater treatment capacity needs in North Fulton. As part of the study, we would like to obtain your most up-to-date population projections through year 2035. We understand the City provided population projections to Fulton County Water Resources Department in May 2014. These projections are provided below for your reference. Please review the projections and let us know if revisions are in order based on your latest planning data.
City 2012
Population Estimate
Population Projections
2015 2020 2025 2030 2035
Alpharetta 61,981 60,319 62,904 65,560 68,218 70,858
Johns Creek 82,306 81,050 85,372 89,727 94,304 99,114
Milton 35,015 34,232 40,770 47,308 53,847 60,385
Mountain Park 576 573 606 638 665 703
Roswell 93,692 90,633 92,442 99,774 103,488 107,338 Sources: 2012 Estimate obtained from State of Georgia’s Office of Planning and Budget.
Also, we would appreciate an opportunity to visit with you to discuss the City’s vision for growth. During the next two weeks, we would like to find a convenient time when you could meet with us for this discussion. We will follow up with a call to set this date. In the meantime, please call me if you have questions on this matter. Sincerely, Wayne Haynie, P.E. Project Manager
whayniePencil
whayniePencil
-
City of Alpharetta June 22, 2015 Page 2 cc: Hon. David Belle Isle, Mayor
Mr. Robert J. Regus, City Administrator
-
3650 Mansell Road \ Suite 300 \ Alpharetta, GA 30022 O 770-587-4776 \ F 770-587-4772 \ burnsmcd.com
June 22, 2015 Ms. Alice Wakefield Director of Community Development City of Roswell 38 Hill Street, Suite G-30 Roswell, GA 30075 Re: Population Forecasts for Fulton County Department of Water Resources Dear Ms. Wakefield: On behalf of the County, we are evaluating long term wastewater treatment capacity needs in North Fulton. As part of the study, we would like to obtain your most up-to-date population projections through year 2035. We understand the City provided population projections to Fulton County Water Resources Department in May 2014. These projections are provided below for your reference. Please review the projections and let us know if revisions are in order based on your latest planning data.
City 2012
Population Estimate
Population Projections
2015 2020 2025 2030 2035
Alpharetta 61,981 60,319 62,904 65,560 68,218 70,858
Johns Creek 82,306 81,050 85,372 89,727 94,304 99,114
Milton 35,015 34,232 40,770 47,308 53,847 60,385
Mountain Park 576 573 606 638 665 703
Roswell 93,692 90,633 92,442 99,774 103,488 107,338 Sources: 2012 Estimate obtained from State of Georgia’s Office of Planning and Budget.
Also, we would appreciate an opportunity to visit with you to discuss the City’s vision for growth. During the next two weeks, we would like to find a convenient time when you could meet with us for this discussion. We will follow up with a call to set this date. In the meantime, please call me if you have questions on this matter. Sincerely, Wayne Haynie, P.E. Project Manager
whayniePencil
whayniePencil
whayniePencil
-
City of Roswell June 22, 2015 Page 2 cc: Hon. Jere Wood, Mayor
Ms. Kay G. Love, City Administrator
-
3650 Mansell Road \ Suite 300 \ Alpharetta, GA 30022 O 770-587-4776 \ F 770-587-4772 \ burnsmcd.com
June 22, 2015 Ms. Sharon Ebert, Director of Community Development City of Johns Creek 12000 Findley Road, Suite 400 Johns Creek, GA 30097 Re: Population Forecasts for Fulton County Department of Water Resources Dear Ms. Ebert: On behalf of the County, we are evaluating long term wastewater treatment capacity needs in North Fulton. As part of the study, we would like to obtain your most up-to-date population projections through year 2035. We understand the City provided population projections to Fulton County Water Resources Department in May 2014. These projections are provided below for your reference. Please review the projections and let us know if revisions are in order based on your latest planning data.
City 2012
Population Estimate
Population Projections
2015 2020 2025 2030 2035
Alpharetta 61,981 60,319 62,904 65,560 68,218 70,858
Johns Creek 82,306 81,050 85,372 89,727 94,304 99,114
Milton 35,015 34,232 40,770 47,308 53,847 60,385
Mountain Park 576 573 606 638 665 703
Roswell 93,692 90,633 92,442 99,774 103,488 107,338 Sources: 2012 Estimate obtained from State of Georgia’s Office of Planning and Budget.
Also, we would appreciate an opportunity to visit with you to discuss the City’s vision for growth. During the next two weeks, we would like to find a convenient time when you could meet with us for this discussion. We will follow up with a call to set this date. In the meantime, please call me if you want to discuss. Sincerely, Wayne Haynie, P.E. Project Manager
whayniePencil
-
City of Johns Creek June 22, 2015 Page 2 cc: Hon. Mike Bodker, Mayor
Mr. Warren Hutmacher, City Manager Mr. Thomas Black, Director of Public Works
-
3650 Mansell Road \ Suite 300 \ Alpharetta, GA 30022 O 770-587-4776 \ F 770-587-4772 \ burnsmcd.com
June 22, 2015 Ms. Kathleen Field Director of Community Development City of Milton 13000 Deerfield Parkway, Suite 107 Milton, GA 30004 Re: Population Forecasts for Fulton County Department of Water Resources Dear Ms. Field: On behalf of the County, we are evaluating long term wastewater treatment capacity needs in North Fulton. As part of the study, we would like to obtain your most up-to-date population projections through year 2035. We understand the City provided population projections to Fulton County Water Resources Department in May 2014. These projections are provided below for your reference. Please review the projections and let us know if revisions are in order based on your latest planning data.
City 2012
Population Estimate
Population Projections
2015 2020 2025 2030 2035
Alpharetta 61,981 60,319 62,904 65,560 68,218 70,858
Johns Creek 82,306 81,050 85,372 89,727 94,304 99,114
Milton 35,015 34,232 40,770 47,308 53,847 60,385
Mountain Park 576 573 606 638 665 703
Roswell 93,692 90,633 92,442 99,774 103,488 107,338 Sources: 2012 Estimate obtained from State of Georgia’s Office of Planning and Budget.
Also, we would appreciate an opportunity to visit with you to discuss the City’s vision for growth. During the next two weeks, we would like to find a convenient time when you could meet with us for this discussion. We will follow up with a call to set this date. In the meantime, please call me if you have questions on this matter. Sincerely, Wayne Haynie, P.E. Project Manager
whayniePencil
-
City of Milton June 22, 2015 Page 2 cc: Hon. Joe Lockwood, Mayor
Mr. Chris Lagerbloom, City Manager
-
3650 Mansell Road \ Suite 300 \ Alpharetta, GA 30022 O 770-587-4776 \ F 770-587-4772 \ burnsmcd.com
June 22, 2015 Hon. Jim Stills, Mayor City of Mountain Park 118 Lakeshore Drive Roswell, GA 30075 Re: Population Forecasts for Fulton County Department of Water Resources Dear Mayor Stills: On behalf of the County, we are evaluating long term wastewater treatment capacity needs in North Fulton. As part of the study, we would like to obtain your most up-to-date population projections through year 2035. We understand the City provided population projections to Fulton County Water Resources Department in May 2014. These projections are provided below for your reference. Please review the projections and let us know if revisions are in order based on your latest planning data.
City 2012
Population Estimate
Population Projections
2015 2020 2025 2030 2035
Alpharetta 61,981 60,319 62,904 65,560 68,218 70,858
Johns Creek 82,306 81,050 85,372 89,727 94,304 99,114
Milton 35,015 34,232 40,770 47,308 53,847 60,385
Mountain Park 576 573 606 638 665 703
Roswell 93,692 90,633 92,442 99,774 103,488 107,338 Sources: 2012 Estimate obtained from State of Georgia’s Office of Planning and Budget.
Also, we would appreciate an opportunity to visit with you to discuss the City’s vision for growth. During the next two weeks, we would like to find a convenient time when you could meet with us for this discussion. We will follow up with a call to set this date. Please call me if you have questions on this matter. Sincerely, Wayne Haynie, P.E. Project Manager cc: Ms. Karen Segars, City Clerk / Administrator
whayniePencil
-
APPENDIX B – FOLLOW UP MEETINGS WITH CITIES
-
City of Alpharetta Response Information
-
Meeting Notes
Meeting Subject: Population Forecasts Meeting Date: July 13, 2015 Start Time: 2:30 PM End Time: 3:30 PM Location: City of Alpharetta, City Hall Project Name: North Fulton Wastewater Capacity Analysis Project No.: 84426 (BMcD) Attendees Organization Title Samir Abdullahi City of Alpharetta Economic Development
Manager Eric Graves City of Alpharetta Senior Engineer –
Development Services Paula Feldman Eric Nease
E-H E-H
Sr. Water Resources Sr. Water Resources
Wayne Haynie* (not present) BMcD Project Manager * Meeting organizer Notes Prepared By: Eric Nease Date Notes Issued: July 15, 2015 Meeting Notes: The following items were discussed, and commented on during our visit with Samir Abdullahi and Eric Graves at City Hall on July 13, 2015. The purpose of the meeting was to review the population forecasts the City provided to the BMcD team on June 19, 2015. In preparation for finalizing our population forecasts, we wanted to reach out to each City in North Fulton and gain context and observations from the principal planners on what development patterns are occurring and other growth factors behind the population forecasts they provided.
1. Alpharetta is an economic hub in North Fulton, with 20 million square feet of office space,
nearly equal to Buckhead’s 22 million. Plus four exits along Georgia 400, plus McFarland Parkway just outside with City Limits in Forsyth County. Hence they are using the phrase “A Technology & Employment Hub”
2. Alpharetta has commercial and retail to support their residential population plus neighboring communities such as Johns Creek, Milton & South Forsyth.
3. Therefore, Alpharetta is particular in keeping commercial development on the few remaining parcels, and allow mixed use zoning on these.
4. Current key developments are Avalon and City Center, both include mixed use. Trying to embrace an ‘after 5’ motto with restaurants and shopping to attract people after business hours.
-
ROSS+associates urban planning & plan implementation
ROSS+associates 211 Colonial Homes Drive, NW Suite 2307 Atlanta, GA 30309 web: planross.com tel: 404-626-7690
Memorandum
TO: Kathi Cook cc: Shawn Mitchell FROM: Bill Ross DATE: May 19, 2014 RE: Alpharetta Population Forecasts
The purpose of this memo is to confirm, modify or replace the population forecasts contained in the Alpharetta Comprehensive Plan 2030 for use in establishing Level of Service calculations for the City’s impact fee program update. The population forecasts will subsequently influence the housing unit and employment forecasts used in the Update.
To accomplish this, a variety of projection approaches were prepared for comparison to the Com-prehensive Plan figures. Data from both the US Bureau of the Census and the Atlanta Regional Commission were considered, as well as countywide forecasts prepared by Woods & Poole Econo-mists, Inc.
The various approaches presented in the attached analysis are:
• 2000–2012 Census population data projected to 2040 on a “straight line” basis for each city in North Fulton County.
• 2000–2012 Census population data projected to 2040 for each North Fulton city assuming that the ARC Plan 2040 North Fulton projections are incorrect by the same increment as “straight line” determined for 2016.
• 2000–2012 Census population data projected to 2040 on a “curved line” basis for each city in North Fulton County as a “growth trend” regression.
• 2000–2012 Census population data projected to 2040 assuming that the ARC Plan 2040 North Fulton projections are incorrect by the same increment as determined for 2016 using the growth trend figure.
• The percentage share of countywide population projected for each city taken against the ARC Plan 2040 forecasts and those of Woods & Poole Economists, Inc.
Conclusion
The Comprehensive Plan forecasts, adjusted to the latest Census Bureau estimates for 2010-2012 and extended to 2040, compare well within the ranges of several of the more credible alternate approaches. We conclude that the Comprehensive Plan forecasts continue to provide the basis for the City’s outlook to the future, as refined in the analysis attached to this memo and shown on Ta-ble 9.
-
Memo to: Kathi Cook, May 19, 2014 Subject: Alpharetta Population Forecasts, page 2
ROSS+associates 211 Colonial Homes Drive, NW Suite 2307 Atlanta, GA 30309 web: planross.com tel: 404-626-7690
Recommendations
Either of the modified Comprehensive Plan population forecasts shown on the following chart is recommended for use in the Impact Fee Program Update. The choice of which one to adopt boils down to this:
• If maintaining the greatest consistency with the Comprehensive Plan is paramount, the “Comprehensive Plan 2015-2030 Maintained” projections should be adopted.
• If recognizing the recent post-recession “uptick” in population increase is important, the “Comprehensive Plan Modified to 2010-2012 Actual” should be adopted.
Lastly, the span of the population forecasts should be considered. The attached analysis provides projections to 2040. However, if preferred, a 20-year time span would be appropriate, taking the forecasts out to 2035 instead.
Considering the alternative of maintaining consistency with the Comprehensive Plan, the total pop-ulation increase from 2012 to 2035 is 19,451, and there is no difference between the “red line” forecast