ny rising reconstruction program project · pdf fileny rising reconstruction program project...
TRANSCRIPT
NY Rising Reconstruction Program Project UpdateRye City Council Monthly Meeting
PRESENTERS:
Bradley Cantor
Governor’s Office of Storm Recovery
(GOSR)
Regional Lead
Brian Platt
O’Brien & Gere Engineers,
Inc. (OBG)
Engineer
Peter Johantgen
Dormitory Authority of the State of New York
(DASNY)
Project Manager
Kate Seely-Kirk
Dormitory Authority of the State of New York
(DASNY)
Director Construction Administration
2
Bowman Dam Automation - Benefit-Cost-Analysis (BCA) Results Summary
Milton Road Drainage Improvements Results Summary
PRESENTATION OUTLINE
3
Objective #2: Sluice Gate Operation – Assess effectiveness of previously proposed operating algorithm when combined with work performed in Objective #1
Objective #1: Expansion of Upper Pond – Refinement to match available funding ($2 million)
PREVIOUS STUDY - ANALYSIS OF UPPER POND RESIZING
Bowman Dam
2000 4000 6000 8000
10
20
30
40
50
BowmanDamProject Plan: 1) OBG_exist-10y 11/30/2016 2) OBG-Plan-13KCUT -10y 11/30/2016 3) OBG-Plan-13KCUT -10y-PB@I-287-new 12/1/2016
Main Channel Distance (ft)
Ele
vation
(ft)
Legend
WS Max WS - OBG_exist-10y
WS Max WS - OBG-Plan-13KCUT-10y
WS Max WS - OBG-Plan-13KCUT-10y-PB@I-287-new
Ground
4
PREVIOUS STUDY – RESULTS COMPARISON – POND EXPANSION VS. SLUICE GATE OPERATION
I-95 I-287
Highland Rd.Purchase St.
10-YEAR FLOOD
EXCAVATION+
SLUICE GATE
13.5K EXCAV.
Existing WSE
Conclusion: The benefits associated with Upper Pond resizing are an order of magnitude less than the benefits from utilizing a gate operation strategy.
13.5k CY Excavation + Sluice Gate
Ap
pro
x. ~
0.7
ft.
Stream Bed
5
-0.50
0.00
0.50
1.00
1.50
2-Y
ear 1 2 3 4
5-Y
ear 1 2 3 4
10
-Yea
r 1 2 3 4
25
-Yea
r 1 2 3 4
50
-Yea
r 1 2 3 4
10
0-Y
ear 1 2 3 4
PB@Indian Village
PB@l-287
2-year 5-year 25-year10-year 50-year 100-year
PREVIOUS STUDY – RESULTS COMPARISON – PB ALGORITM BY CONTROL LOCATION
Conclusions: • The gate should
remain open for events < 5-yearreturn frequency
• Selection of algorithm control location may influence observed WSE reductions
• Majority of reduction is attributed to sluice gate control
Wat
er S
urf
ace
Elev
atio
n R
edu
ctio
n (
ft)
Locations (1 2 3 4)
SLUICE GATE AT BOWMAN DAM
6
Gate installed: 2013
EXISTING CONDITION
The dam in fixed “closed” position
Previously developed operational algorithms not implemented
Need for additional stream monitoring stations and system integration
7
BENEFIT COST ANALYSIS STUDY OBJECTIVES
Compare the following:
Costs of stream gauge construction and sluice gate operation
Benefits associated with avoided property damage if stream gauges were constructed and integrated with existing sluice gate
Comparison is made by calculating a Benefit Cost Ratio
8
BENEFIT COST RATIO
FEMA Benefit-Cost Analysis (BCA) Toolkit
The outcome is a Benefit-Cost Ratio (BCR)
BCR > 1A project is economically viable
9
CONCEPTUAL DESIGN PROCESS – STREAM GAUGES
Site visit performed to identify potential gauge locations.
Radio survey performed to assess data transmission options
• Due to terrain and vegetation, cellular technology is proposed
Modeling performed to estimate potential water surface elevation reduction
Conceptual gauge and instrumentation design performed
Conceptual capital cost estimation
Operation and maintenance cost estimation
10
COST ESTIMATION
Components: Stream gauge and gate control system design, construction, and operation
Stream monitoring system design
Means of gauge communication
Data storage and access
Existing infrastructure integration
Model & algorithm calibration
Implementation
Operation & maintenance
11
PROPOSED GAUGE LOCATION BROOKSIDE WAY (UPSTREAM)
GAUGE
12
PROPOSED GAUGE LOCATION PURCHASE ST. (DOWNSTREAM)
GAUGE
13
BENEFIT ESTIMATION
Benefit Component: Potentially avoided property damage
If flood elevations are reduced by approximately 1 foot, how would residential flood damage be reduced?
• Estimate number of residences affected by reduction
• Estimate avoided damage costs
EXIS
TIN
G
PR
OP
OSE
D
14
BENEFIT COST ANALYSIS SUMMARY
TOTAL ESTIMATED BENEFITS: $10,800,000 TOTAL ESTIMATED COST: $630,000
Benefit cost ratio (BCR) is 14
BCR is greater than 1, therefore the project is economically viable
AVOIDED PROPERTY DAMAGE: $8,800,000
SOCIAL BENEFITS: $2,000,000 ANNUAL MAINTENANCE: $25,000
INITIAL COST: $398,000
Notes:
1. Values are expressed in 2017 dollars
2. Annual maintenance portion of the total estimated cost is expressed in 2017 dollars assuming 7% annual discount rate. Annual maintenance would not be funded with NY Rising Project funding.
3. Project life assumed to be 15 years (i.e., instrumentation and controls are assumed to require updating after 15 years of use).
Notes:
1. Mental stress and anxiety includes treatment cost per person
2. Values are expressed in 2017 dollars
APPROXIMATE BENEFITS APPROXIMATE COSTS
Milton Road Drainage Improvements Study
15
16
CATCH BASIN
MANHOLE
OUTLET
MILTON HARBOR HOUSE AREA
17
DRAINAGE AREA
SYSTEM OUTFALL Flow generating rainfall
Tidal conditions in the bayAverage High Tide: 3.4 ft
(NAVD88)
MODEL INPUTS
18
EXISTING CONDITIONS: CURRENT STORMWATER SYSTEM CONFIGURATION
MODELED CONDITIONS:TIDE: 3.4 ft
WITH CHECK VALVE AT SYSTEM OUTFALLRAINFALL EVENT: 10-YEAR STORM
MODEL VIEW: PLAN VIEW MODEL VIEW: PROFILE
19
REPLACE WITH 24” PIPE
REPLACE WITH 24” PIPE
REPLACE WITH 24” PIPE
PROPOSED IMPROVEMENTS: REPLACE EXISTING PIPES
EXISTING CONDITIONSTIDE ELEVATION: 3.4 FT
WITH CHECK VALVE AT OUTFALLRAINFALL EVENT: 10-YEAR STORM
20
REPLACE WITH 24” PIPE
REPLACE WITH 24” PIPE
REPLACE WITH 24” PIPE
PROPOSED CONDITIONSTIDE ELEVATION: 3.4 FT
WITH CHECK VALVE AT OUTFALLRAINFALL EVENT: 10-YEAR STORM
PROPOSED IMPROVEMENTS: REPLACE EXISTING PIPES
21
MODELED CONDITIONS:TIDE: 3.4 ft
WITH CHECK VALVE AT SYSTEM OUTFALLRAINFALL EVENT: 10-YEAR STORM
PROFILE VIEW: EXISTING CONDITIONSPROFILE VIEW: PROPOSED IMPROVEMENTS
(INCREASE PIPE SIZES)
PROPOSED IMPROVEMENTS: REPLACE EXISTING PIPES
22
NYS DEC SEA-LEVEL RISE PROJECTION REGULATION
23
REPLACE WITH 24” PIPE
REPLACE WITH 24” PIPE
REPLACE WITH 24” PIPE
PROPOSED IMPROVEMENTS: REPLACE EXISTING PIPES
2050 CONDITIONSTIDE ELEVATION: 4.7 FT
WITH CHECK VALVE AT OUTFALLRAINFALL EVENT: 10-YEAR STORM
24
REPLACED WITH 24” PIPE
REPLACED WITH 24” PIPE
REPLACED WITH 24” PIPE
PROPOSED IMPROVEMENTS: REPLACE EXISTING PIPES
PROPOSED CONDITIONSTIDE ELEVATION: 4.7 FT
WITH CHECK VALVE AT OUTFALLRAINFALL EVENT: 25-YEAR STORM
25
CATCH BASIN
MANHOLEOUTLET
DIVERTING WATER BY CONNECTING DRAINAGE SYSTEMS
PROPOSED CONNECTION
EXISTING DRAINAGE
SYSTEM
OUTLET
MODEL CONDITIONSTIDE ELEVATION: 4.7 FT
WITH CHECK VALVE AT OUTFALLRAINFALL EVENT: 25-YEAR STORM
26
MILTON HARBOR HOUSE AREA SUMMARY
Replacing existing pipes would reduce flooding on Milton Harbor House property during a 10-year
storm event
Flooding would be reduced for both the current high tide of 3.4 feet and projected 2050 high tide of
4.7 feet
In addition to replacing existing pipes, constructing a pipe to divert water to an adjacent storm sewer
system would provide additional capacity to manage larger storms
Hewlett Street Area
27
28
HEWLETT STREET SYSTEM CONFIGURATION
RECOMMEND INSTALLING
CHECK VALVE
LOCATION OF PERIODIC
FLOODING
29
HEWLETT STREET PROPOSED IMPROVEMENTS
Prevents water and sediment from entering the pipe
Creates additional storage for storm water
Slightly reduces flooding at Hewlett Street and
Milton Road intersection
30
COST ANALYSIS SUMMARY
STORM SEWER IMPROVEMENT CONCEPTUAL CONSTRUCTION COST
Replace Existing Pipes (Milton Harbor House Area) $310,000
Replace Existing Pipes & Divert Water (Milton Harbor House Area) $647,000
Check Valve (Hewlett Street & Milton Road Intersection) $55,000
Note:Construction costs do not include engineering and construction oversight costs.
31
NY Rising Reconstruction Program Project UpdateRye City Council Monthly Meeting
QUESTIONS?