open access in gujarat
TRANSCRIPT
Open Access in Gujarat
Venu Birappa
Gujarat Energy Transmission Corporation Limited 27th May 2013
Flow of Presentation
• GETCO at a glance
• Open Access in Gujarat
• Short Term, Medium term and Long term Open Access
• Merchant plant, Captive generation, Third party sale
• Technical requirement
• Redundancy, Reactive power, Future load growth
• Open Access to Wind and solar power
• Impact of Open Access
• Major Impediments
No Network as such in planned for
Short term/ Medium term Open Access.
3
Current status
Installed Capacity including Central Sector Share (as on 30.04.2013):
Sr. No.
Sector Installed
Capacity in MW
1 State Sector 4996
2 Private Sector 7400
3 Central Sector 5571
Total 17967*
* Excluding renewable capacity – 4003 MW
Sr. No. Particulars Substations
(Nos.) Transmission Lines
(CKM) Transformation Capacity (MVA)
1 400 KV 11 3602 8355
2 220 KV 83 15774 20770
3 132 KV 50 4938 6323
4 66 KV 1206 23658 26230
Total 1350 47972 61678
Transmission Network Development (as on 31.03.2013)
Installed Capacity in MW
41%
28%31%State Sector
Private Sector
Central Sector
Open Access in Gujarat
GERC notified Open Access Regulation in 2005
State of Gujarat has implemented intra-state ABT w.e.f. 05.04.2010 which is pre-requisite for implementation of open access
Subsequently, GERC Open Access Regulation 2011 notified as per model Regulation of Forum of Regulators
State providing adequate infrastructure support to open access consumers in the state
4
Open Access Rules : GERC
Long-term customer: Full Transmission charges shall be determined as per the Terms & Conditions of
tariff notified by appropriate Commission from time to time. Rs.2970/MW/day for the year 2013-14 Period --exceeding12 year but not exceeding 25 years Exit option for customer available by paying compensation
Medium Term Customer
Full Transmission Charges Allowed on available margins Rs.2970/MW/day for the year 2013-14 Period– exceeding 3months but not exceeding 3 years Exit option available by paying compensation. Priority over Short Term Open Access
Short Term Customer Intra-state
ST-Rate = 0.25 x [TSC / AV-cap]/365 Rs.742.5 /MW/day for the year 2013-14
Period ----less than 3 months and not exceeding 6 months in a year
Transmission Charges:
Connectivity and Open Access relationship
• Connectivity should always be simultaneously applied with either Medium
Term Open Access or Long Term Open Access
– Open Access users may take undue advantage of taking connectivity and
then trading in short term
– Many Generators demand connectivity as merchant plants and then trade
power under short term open access as per the availability in market.
– Captive power plants also seek connectivity and trade the surplus power.
– Captive user and Merchant power plants find consumers within Gujarat for
trading power as third party sale
– Eventually disparity among Open Access users, mainly DISCOMs who pay
for the existing network
– Consumers grievance due to such disparity
– Power not availed by such open access consumers within contract
demand is being backed down/sold at lower price in market for which fixed
cost is payable by DISCOMs
Open Access granted in Gujarat
Sr. No
Year
Short Term Open Access Medium
Term Open Access
Long Term Open Access
Numbers of STOA
Application approved
Total STOA User
Capacity Approved
Sale (MW)*
Capacity Approved Purchase (MW)*
Nos. MW Nos. MW
1 2009-10 603 25 2404 -- - - 16 9547
2 2010-11 541 27 2738 -- - - 16 12745
3 2011-12 1070 49 3189 1355 6 279 15 13482
4 2012-13 4635 232 3255 3271 10 354 18 18033
*Average MW capacity approved during each month (approximately)
Captive Capacity catered by grid--------2957 MW
Details of Open Access Consumers in Gujarat
Details DGVCL UGVCL PGVCL MGVCL TPL AEC TOTAL
No. of OA Consumers (as on Mar-12) 12 11 19 7 -- 49
Power purchased under OA in Mus (FY 2011-12) 946 154 280 111 --- 1491
No. of OA Consumers (as on Mar-13) 68 50 68 32 14 232
Power purchased under OA in Mus (FY 2012-13-upto 31.3.13) 2948 456 661 350 12 4427
Presently, 232 OA consumers have been purchasing power under short term open access from Power Exchanges/ Short term Market in the State
State’s tied up capacity to supply their consumers on long term basis to meet the existing as well as future demand is remaining unutilized/ stranded
Cost of power purchased from DISCOM
W/o demand charge
Charges Rs/unit
Demand Charges -
Energy charges 4.30
Fuel Surcharge 1.18
Time of Usage charges (75 paisa/ unit) 0.25
Total 5.73
15% Electricity duty is applicable but same is also applicable for
purchase under open access
Power purchase by Open access user in range of Rs. 3.75-5.43/unit
as against the supply of power by DISCOM at the rate of Rs. 5.73/unit
Technical Requirement
Reactive Power compensation
Sr. No.
Voltage Class Shunt Capacitor
(in MVAR)
Reactor (in MVAR)
Bus Line
1 400KV 0 705 313
2 220KV 0 100 0
3 132KV 216 0 0
4 66/33KV 1328 0 0
5 22KV 73 0 0
6 11KV 3121 0 0
Total 4738 805 313
• 180 MVAR Shunt Capacitor will be installed upto March-2014
• 1885 MVAR of 400KV class Bus Reactors (7X125 + 12X80 + 1X50) will be installed
• 628MVAR of 400KV class Line Reactors (3X50 + 6X63) will be installed.
(Up to March-2013)
10
Redundancy of Transmission Network
Technical Requirement
• Unable to handle contingency during peak load condition
• Critical line loading during peak load condition
• Single source substations
• Non availability of parallel corridors.
Transfer of Power
(Existing)
Expected load growth Transfer of Power
(2012-13)
PGVCL
8770 MW (G)
4152 MW (D)
UGVCL
870 MW (G)
2918 MW (D)
MGVCL
2240 MW (G)
1423 MW (D)
DGVCL
6485 MW (G)
2146 MW (D)
DISCOM
(G)-Generation
(D)-Demand
TPAEC
500 MW (G)
1315 MW (D)
TPSEC
1148 MW (G)
600 MW (D) 12
Open Access to Renewable Energy
• Variability: generation changes according to the availability of wind velocity/sunlight – resulting in swings of the plant output
• Uncertainty : magnitude and time of the generation output is unpredictable & unreliable and need ramping requirements
• Low Plant Load Factor (PLF) to the tune of 20-22%
• Limited control on generation
• Not having proximity to the load centre.
• The over voltage problem may be observed during period of low wind / solar generation and off-peak load condition due to integration of large scale renewable energy projects.
• Due to the large oscillations in the wind / solar generation, the electrical grid is affected in its voltage control and transient stability.
• Adequate reserve capacity of gas / hydro generation is essential to meet the system demand, when there is a sudden and substantial drop in wind / solar generation.
Investment for integration of Wind power
14
400 KV
Halvad
400 KV
Varsana
220 KV
Nakhatrana
220 KV
Radhanpur
400 KV
Chorania
220 KV
Tankara
220 KV
Bhatia
220 KV
Kangasiyali
220 KV
Jasddan
Proposed 400/220 KV S/S
Proposed 220/132 KV OR
220/66 KV S/S
Proposed 400 KV D/C line
Proposed 220 KV D/C line
Proposed 132 KV D/C line
Geographical locations for Wind Power Projects
Euro Solar, Bhachau–5MW Back Bone Enterprise – 5 MW Konark Gujarat – 5 MW ICML – 9 MW Zeba Solar – 10 MW India Solar Ray – 10MW Ambit Advisory – 5MW Taxus infrastructure-5MW
Lanco, Bhadrada-5MW Lanco, Chandiyala – 15 MW PLG Power, Sami-20MW Astonfield Solar – 11.5 MW PLG Photovoltaic-20MW
JaiHindi – 5 MW
Solitaire, Mitha-15.20 MW Precious, Akhaj-15 MW
Solar Semi Conductor–20 MW Cargo Motors, Rapar – 25 MW S J Green Park Energy – 5MW
15
Sunkon Energy -5 MW Mono Steel – 10MW
Responsive – 25 MW Ujjwala -25 MW Chhatel (Ispat) -25 MW
Welspun Ltd – 15 MW Unity 5 MW
Azure Power, Dhama –5 MW ESP Urja Ltd – 5 MW Millenium Synergy, Dasada – 10 MW Loroux Bio Energy – 25 MW EMCO – 5 MW WAA Solar – 10 MW Visual Percept – 25MW Environmental – 10 MW
Tata Power Limited -25 MW
CBC solar -10 MW Ganges Green – 15 MW Ganeshwani – 5 MW Green Infra -10 MW Aravli Infra 5 MW GHI Energy - 10 MW MoserBear – 15MW APCA Power – 5MW Hiraco Renewable – 20MW
Kemrock – 10 MW
Adani Ltd – 40MW GMDC -5 MW
ACME– 15 MW
Azure Haryana – 10.20 MW
Aatash Power – 5MW
Dreisatz MySolar-15MW
MySolar24 – 15MW
Tathith Energies- 5 MW
Sun Borne – 15MW
Sand land-25MW
GIPCL – 5 MW
JSW Energy, Deodar-5MW Solar Semiconductor, Ajwada-20MW Solitaire (MoserBear), Mudetha-15MW Torrent Power, Savpura-25MW NTPC, Morwada-50MW Welspun Urja-40MW
Green colour – Projects commissioned
Red colour - Projects to be commissioned
Charanka Solar Park
Projects Commissioned – 221 MW
Project of Solar Generating Plants in Gujarat
Total Installed Capacity: 857MW 15
Impact of Open Access
Per unit fixed cost works out to Rs. 2.07 & DISCOMs recovers
approx. Rs. 0.50/unit as fixed charge from HT consumers
Retail energy charges includes partial recovery towards fixed charges
Open access consumers pays around 55 paisa/unit (39 paisa- cross subsidy & 16 paisa – wheeling & transmission
Power not availed by such open access consumers is being backed down/sold at lower price in market for which fixed cost is payable by DISCOMs
Reasons for Thrust in Open Access
• Open access is crucial for
– Mobilizing larger private investment in generation through
guaranteed access to credible buyers.
– Enhancing competition amongst generators and suppliers to
have option for consumers.
• Investment promotion objective is of higher priority in view of the
prevailing electricity shortages.
18
Major impediment
– Open Access users may take undue advantage of taking connectivity and
then trading in short term….Regulations of connectivity need to be
revisited
– Eventually disparity among Open Access users, mainly DISCOMs who pay
for the existing network
– Power not availed by such open access consumers within contract
demand is being backed down/sold at lower price in market for which fixed
cost is payable by DISCOMs
– Renewable Open Access due to its unpredictable nature is creating
constraint for normal Open Access consumers during peak harvesting
period
Thank you !!!