optimizing chilled water plants - tech seminar

Upload: nay-myo-oo

Post on 10-Mar-2016

34 views

Category:

Documents


2 download

DESCRIPTION

chiller plant

TRANSCRIPT

  • March 2, 2012

    Kent W. Peterson, PE, FASHRAE

    P2S Engineering, Inc. Long Beach, CA

    [email protected]

    Chilled Water Plant Design and Control

    CH-1 CH-2

    95F 85F90F

    0.52 KW/ton 0.59 KW/ton

    0.555 KW/ton

    40F56F 48F

    0.2

    0.4

    0.6

    0.8

    1.0

    25 50 75 100

    65 ECWT 75 ECWT 85 ECWT

    Percent Loaded

    KW

    /ton

  • 2

    Handouts

    A copy of the todays slides in PDF format will be available from Trent Hunt

  • 3

    Agenda

    CHW Distribution Systems CHW Distribution System Balancing CW Distribution Systems Break Selecting CHW Distribution Systems Selecting CHW T Selecting CW T Selecting Chillers Optimizing Control Sequences Questions

  • 4

    Optimizing Energy Usage

    Chillers Type, efficiency, size, VFD

    Cooling Towers Fan type, efficiency, approach, range, speed control,

    flow turndown Chilled Water Pumps

    Arrangement, flow rate (delta-T), pressure drop, VFD Condenser Water Pumps

    Flow rate (delta-T), pressure drop, VFD Air Handling Units

    Coil sizing, air-side pressure drop, water-side pressure drop

  • Pop Quiz 1 What happens to component

    energy usage if we lower CWS setpoint? Chiller Towers Pumps

  • Pop Quiz 2

    What happens to component energy usage if we lower CW flow? Chiller Towers Pumps

  • Pop Quiz 3 What happens to component

    energy usage if we lower CW flow AND the CWS setpoint? Chiller Towers Pumps

  • 8

    Optimizing CHW Plant Design

    Ideal: Design a plant with lowest life cycle costs (first cost plus lifelong operating costs) accounting for all the complexities and interaction among plant components

    Practical: Design plant subsystems to be near-life cycle cost optimum using techniques that are simple and practical enough to be used without a significant increase in design time

  • 9

    Chilled Water Distribution Systems

  • 10

    Chilled Water System Classes

    Constant Flow No control valves 3-way control valves

    Variable Flow Primary-Only Primary/Secondary (/

    Tertiary) Primary/Distributed

    Secondary Primary/Variable Speed

    Coil Secondary These are the major categories of distribution systems. The list is by no means complete. There are many permutations and combinations.

  • 11

    Constant Flow Single Chiller, Single Coil, No Control Valve

  • 12

    Constant Flow 3-Way Valves

    100% to Coil 50% to Coil 0% to CoilPipe/Valves 2 2 2Coil and/or Bypass 8 2 6Globe Control Valve 10 7.5 12Total 20 11.5 20

    GPM @ 20 P* 100 132 100

    Pressure Drop @ 100 GPM

    *actual P available may change

    Item

    3-Way Mixing Valve

    Bypass Balance Valve

    DP 20 ft

  • 13

    Constant Flow Single Chiller, Multiple Coils

  • 14

    Constant Flow Multiple Parallel Chillers, Multiple Coils

    CH2 240 gpm

    CH1 240 gpm How many chillers do we need to run?

    Ballroom A 240 gpm 100% Loaded

    Ballroom B 240 gpm Unoccupied

  • 15

    Variable Flow

    Vary Flow Through Coil Circuit Two-way valves Variable speed coil pump

    Configurations Primary-secondary Primary-secondary variations Primary-secondary-tertiary Primary-only

  • 16

    Variable Flow Chilled Water Systems

    Old Paradigm Controls respond to changes in CHW

    temperature Variable flow causes low temperature

    trips, locks out chiller, requires manual reset (may even freeze)

    Hence: Maintain constant flow through chillers

  • 17

    Variable Flow Primary/Secondary, Multiple Chillers and Coils

    If there is no resistance in the common leg, then no flow is induced in the other circuit.

    Hydraulic Independence

  • 18

    Variable Flow Series Flow, Multiple Chillers

  • 19

    Variable Flow Primary/Distributed Secondary

  • 20

    Variable Flow Primary/Secondary/Tertiary

  • 21

    Variable Flow Chilled Water Systems

    New Paradigm Modern controls are robust and very

    responsive to both flow and temperature variations

    Variable flow OK within range and rate-of-change specd by chiller manufacturer

  • 22

    Variable Flow Primary-only, Multiple Chillers

  • 23

    Variable Flow Primary, Bypass Valve

    Location Near chillers

    Best for energy Controls less expensive Control more difficult to

    tune fast response Remote

    Smaller pressure fluctuations (easier to control)

    Keeps loop cold for fast response

    Sizing Sizing critical when at

    chillers/pumps Different size if pump has

    VFD or not

    Flow measurement Flow meter

    Most accurate Needed for Btu calc for

    staging DP across chiller

    Less expensive Accuracy reduced as tubes

    foul One required for each chiller

  • 24

    Primary CHW Pump Options

    Dedicated Pumping Advantages: Less control complexity Custom pump heads w/ unmatched chillers Usually less expensive if each pump is adjacent to chiller served Pump failure during operation does not cause multiple chiller trips

    Headered Pumping Advantages: Better redundancy Valves can soft load chillers with primary-only systems Easier to incorporate stand-by pump

  • 25

    Balancing Variable Flow Systems

  • 26

    Balancing Issues

    Ensure adequate flow available at all coils to meet loads Less than design flow may be adequate most of the

    time Ensure differential pressure across control valves

    is not so high as to cause erratic control Two-positioning Unstable control at low loads

    Cost considerations First costs (installed costs and start-up costs) Pump energy costs (peak demand and annual) Rebalancing costs (if any) as coils are added to system

  • 27

    Balancing Options

    1. No balancing Relying on 2-way control valves to automatically provide

    balancing 2. Manual balance

    Using ball or butterfly valves and coil pressure drop Using calibrated balancing valves (CBVs)

    3. Automatic flow limiting valves (AFLVs) 4. Reverse-return 5. Oversized main piping 6. Undersized branch piping 7. Undersized control valves 8. Pressure independent control valves

  • 28

    Option 5: Oversized Main Piping

    Advantages No balancing labor Coils may be added/

    subtracted without rebalance

    Reduced over-pressurization of control valves close to pumps

    Lowest pump head/energy due to oversized piping, no balance valves

    Increased flexibility to add loads due to oversized piping

    Disadvantages Added cost of larger

    piping

  • 29

    Option 6: Undersized Branch Piping

    Advantages No balancing labor Reduced cost of smaller

    piping Coils may be added/

    subtracted without rebalance

    Reduced over-pressurization of control valves close to pumps where piping has been undersized

    Disadvantages Limited effectiveness and

    applicability due to limited available pipe sizes

    High design and analysis cost to determine correct pipe sizing

    Reduced flexibility to add coils where piping has been undersized

    Coils may be starved if variable speed drives are used without DP reset

    Slightly higher pump energy depending on flow variations and pump controls

  • 30

    Option 7: Undersized Control Valves

    Advantages No balancing labor Reduced cost of smaller

    control valves Coils may be added/

    subtracted without rebalance

    Reduced over-pressurization of control valves close to pumps where control valves have been undersized

    Improved valve authority which could improve controllability where control valves have been undersized

    Disadvantages Limited effectiveness and

    applicability due to limited available control valve sizes (Cv)

    High design and analysis cost to determine correct control valve sizing

    Coils may be starved if variable speed drives are without DP reset

    Slightly higher pump energy depending on flow variations and pump controls

  • 31

    Option 8: Pressure Independent Control Valves

    Advantages No balancing labor Coils may be added/

    subtracted without rebalance

    No over-pressurization of control valves close to pumps

    Easy valve selection flow only not Cv

    Perfect valve authority will improve controllability

    Less actuator travel and start/stop may improve actuator longevity

    Disadvantages Added cost of strainer

    and pressure independent control valve

    Cost of labor to clean strainer at start-up

    Higher pump head and energy due to strainer and pressure independent control valve

    Valves have custom flow rates and must be installed in correct location

    Valves can clog or springs can fail over time

  • 32

    PICVs May Improve T?

    NBCIP Test Lab (as reported by manufacturer)

  • 33

    Ranks

    Balancing Method Controllability (all conditions) Pump Energy

    Costs First Costs

    1 No balancing 7 3 3 2 Manual balance using calibrated

    balancing valves 4 6 6 3 Automatic flow limiting valves 7 7 7 4 Reverse-return 2 2 5 5 Oversized main piping 3 1 4 6 Undersized branch piping 6 4 2 7 Undersized control valves 5 4 1 8 Pressure independent control

    valve 1 8 8

    7

  • 34

    Conclusions & Recommendations for Variable Flow Hydronic Systems

    Automatic flow-limiting valves and calibrated balancing valves are not recommended on any variable flow system Few advantages and high first costs and energy costs

    Reverse-return and oversized mains may have reasonable pump energy savings payback on 24/7 chilled water systems

    Undersizing piping and valves near pumps improves balance and costs are reduced, but significant added engineering time required

    Pressure independent valves should be considered on very large systems for coils near pumps Cost is high but going down now with competition When costs are competitive, this may be best choice for all jobs

    For other than very large distribution systems, option 1 (no balancing) appears to be a reasonable option to consider Low first costs with minimal or insignificant operational problems

  • 35

    Problems Caused by Degrading T

    For a given load Q, when T goes down, GPM goes up

    Q= 500 X GPM X T

    Result: Increases pump energy Can require more chillers to run at low load, or coils will be

    starved of flow Can result in reduced plant effective capacity: chiller capacity

    without the capability of delivering it

  • T Degradation in Large Chiller Plant (January through March)

    0 100 200 300 400 500 600 700 800

    Approximate hrs/yr

    Eva

    pora

    tor

    Del

    ta T

    (F)

    35F-40F40F-45F45F-50F50F-55F55F-60F

    2.0F-2.5F

    4.5F-5.0F

    7.0F-7.5F

    9.5F-10.0F

    Coincident Wet Bulb Ranges

    Design =10oF

  • 37

    T Conclusions

    Design, construction, and operation errors that cause low T can and should be avoided

    But other causes for low T can never be eliminated

    Conclusion: At least some T degradation is inevitable

    Therefore: Design the CHW Plant to allow for efficient chiller staging despite degrading T

  • 38

    Some Solutions

    Design CHW distribution system so chillers can have increased flow so they can be more fully loaded at low T Primary-only pumping Unequal chiller and primary pump sizes, headered

    pumps so large pump can serve small chiller Low design delta-T in primary loop

    Insures low T in secondary Higher primary loop first costs & energy costs

    Primary/secondary pumping with check valve in common leg

  • 39

    Check Valve in the Common Leg

    CHECK VALVE IN COMMON

    LEG

  • 40

    Supposed Disadvantages Check Valve in Common Leg

    Circuits are not hydraulically independent So what?

    Flow rate may exceed maximum allowed by chiller manufacturer Seldom a real problem - pump capabilities usually fall off fast

    enough due to high chiller P Maximum flow rates are usually arbitrary occasional

    excursions should not be a problem Resolved by using high design Ts (or adding auto-flow limiting

    valves at chillers as last resort) Pumps in series may force control valves open

    Not true with variable speed driven secondary pumps. Primary pumps may ride out their curves and overload

    Seldom a real problem - pump capabilities usually fall off fast enough due to high chiller P, and motor may be selected to avoid this problem.

  • 41

    Real Disadvantages Check Valve in Common Leg

    Possible dead-heading secondary pumps if primary pumps are off and chillers isolation valves are closed Logically interlock secondary pumps to

    primary pumps Ghost flow through inactive

    chillers with dedicated pumps Use isolation valves rather than dedicated

    pumps

  • 42

    Check Valve in the Common Leg

    Recommendation For fixed speed chillers with T problems, a check

    valve in the common leg can help. Make sure pump design/controls address secondary pump dead-heading and ghost-flow issues. Select a check valve with low pressure drop (i.e. swing check, not spring)

    For variable speed chillers, do not put check valve in common leg. It has little value (unless T degradation is severe) since chiller plant will not be inefficient by staging chillers on before they are fully loaded

  • 43

    Condenser Water Distribution Systems

  • 44

    Condenser Water Systems

    Old paradigm: constant flow & speed

    New paradigm: variable flow & speed Control logic to maximize efficiency?

  • 45

    Variable Speed CW Pumps

    VSCW CSCW

  • 46

    Condenser Water Pump Options

    Dedicated Pumping Advantages: Less control complexity Custom pump heads w/ unmatched chillers Usually less expensive if each pump is adjacent to chiller served and head pressure control not required

    Headered Pumping Advantages: Better redundancy Valves can double as head pressure control Easier to incorporate stand-by pump Can operate fewer CW pumps than chillers for fixed speed pumps

  • 47

    Tower Isolation Options

    1. Select tower weir dams & nozzles to allow one pump to serve all towers

    Always most efficient Almost always least expensive Usually possible with 2 or 3 cells

    2. Install isolation valves on supply lines only Need to oversize equalizers

    3. Install isolation valves on both supply & return Usually most expensive but fail safe

  • Non-integrated water-side economizer (WSE) Try to avoid this!

    Heat Exchanger in parallel with chillers

    44F 60F

    44F

    41F

    Twb 36F

    Twb 41F

    46F

    49F

    44F

    44F

    >46F

    You have to shut off the economizer to satisfy the load!

  • Heat Exchanger in series with chillers on CHW side

    Integrated water-side economizer

    You can use either a control valve or pump

    44F 60F

    Twb 41F

    46F

    49F

    44F

    44F

  • 50

    Example WSE savings building description

    200,000 ft2 office building with ~ 110 tons of data center load

    Location Pleasanton CA (ASHRAE Climate 3B)

    (2) 315 ton chillers (630 tons total) Building has air-side economizer Data center has CRAH units Water-side economizer on central plant

    with HX (integrated, see previous slide)

  • 51

    Example WSE Savings

    ~30% ~24%

    ~48%

    ~2%

  • Break

  • Design Procedure

  • 54

    Design Procedure

    Select Chilled Water Distribution System Select Temperatures, Flow Rate and

    Primary Pipe Sizes Select Cooling Tower Design Criteria Select Chillers Finalize Piping System Design, Select

    Pumps Develop Optimum Control System and

    Control Sequences

  • 55

    Recommended Chilled Water Distribution Arrangement

    Number of coils/loads served

    Size of coils/ loads served

    Distribution losses (excluding chiller)

    Control Valves Flow

    Recommended Distribution Type

    One Any Any None Constant or Staged Primary-only

    More than 1 Large Campus Any 2-way Variable Primary/ distributed secondary

    More than 1 Large coils (> 100 gpm) Any None Variable Primary/coil secondary

    Few (2 to 5) serving similar loads or system

    has only one chiller

    Small (< 100 gpm) Low (< 40 feet) 3-way

    Constant or Staged Primary-only

    Few (2 to 5) serving similar loads

    Small (< 100 gpm) High(> 40 feet)

    Many (more than 5) or few serving dissimilar

    loads

    Small (< 100 gpm) Any

    2-way Variable Primary-only

    Or Primary-Secondary

  • 56

    Primary/Secondary

    Secondary Pump w/ VFD

    at Chiller Plant

    2-Way Control Valves at AHUs

    Secondary Pump w/ VFD

    at Chiller Plant

    2-Way Control Valves at AHUs

  • 57

    Primary/Distributed Secondary

    Central Plant

    Distributed Secondary

    Pump w/ VFD - Typical at each

    Building

    No Secondary Pumps at

    Plant

  • 58

    Advantages of Distributed P/S versus Conventional P/S or P/S/T

    Reduced pump HP - each pump sized for head from building to plant

    Self-balancing No over-pressurized valves at buildings

    near plant Reduced pump energy, particularly when

    one or more buildings are off line No expensive, complex bridge

    connections used in P/S/T systems Similar or lower first costs

  • 59

    Primary/Coil Secondary

    Large AHU-1

    Distributed Secondary

    Pump w/ VFD - Typical at each

    AHU

    No Secondary Pumps at Plant

    Large AHU-2

    No Control Valves at AHUs

  • Hybrid Systems

  • 61

    Advantages of VFD Coil Pumps versus Conventional P/S system

    Reduced pump HP Each pump sized for head from coil to plant Eliminated 10 feet or so for control valves

    Self-balancing No need for or advantages to balancing valves, reverse

    return Lower pump energy

    No minimum DP setpoint Pump efficiency constant

    Better control Smoother flow control - no valve hysteresis No valve over-pressurization problems

    Usually lower first costs due to eliminated control valves, reduced pump and VFD HP

  • 62

    Disadvantages of VFD Coil Pumps Versus Conventional P/S system

    Cannot tap into distribution system without pump May be problem with small coils (low flow, high

    head pump) Possible reduced redundancy/reliability

    unless duplex coil pumps are added Possible low load temperature

    fluctuations Minimum speed on pump motor May need to cycle pump at very low loads

  • 63

    Primary-only System

    BYPASS VALVE

    Headered Pumps & Auto Isolation Valves Preferred to Dedicated Pumps: Allows slow staging Allows 1 pump/2 chiller operation Allows 2 pump/1 chiller operation if there is low T

    Flow Meter or DP Sensor Across Chiller

  • 64

    Advantages of Primary-only Versus Primary/Secondary System

    Lower first costs Less plant space required Reduced pump HP

    Reduced pressure drop due to fewer pump connections, less piping

    Higher efficiency pumps (unless more expensive reduced speed pumps used on primary side)

    Lower pump energy Reduced connected HP Cube Law savings due to VFD and variable flow

    through both primary and secondary circuit

  • 65

    Pump Energy Primary vs. Primary/Secondary (3-chiller plant)

    %

    0.00

    5.00

    10.00

    15.00

    20.00

    25.00

    30.00

    35.00

    40.00

    10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

    % GPM

    Pum

    p kW

    Primary-only

    Primary-secondary

  • 66

    Disadvantages of Primary-only Versus Primary/Secondary System

    Failure of bypass control Not as fail-safe - what if valve or controls fail? Must avoid abrupt flow shut-off (e.g. valves interlocked

    with AHUs all timed to stop at same time) Must be well tuned to avoid chiller short-cycling

    Flow fluctuation when staging chillers on Flow drops through operating chillers Possible chiller trips, even evaporator freeze-up Must first reduce demand on operating chillers and/or

    slowly increase flow through starting chiller; causes temporary high CHWS temperatures

    (Problems above are seldom an issue with very large plants, e.g. more than 3 chillers)

  • 67

    Primary-only System Staging

    1000 GPM

    0 GPM

    0 GPM

  • 68

    Primary-only System Staging

    500 GPM

    500 GPM

    0 GPM

  • 69

    Variable Flow Primary/Secondary with CHW Storage

    Advantages Peak shaving Simplifies chiller staging Provides back-up for chiller

    failure Secondary water source for

    fire department Secondary water source for

    cooling towers Disadvantages

    Installed cost Space

  • 70

    Primary-only vs. Primary/Secondary

    Use primary-only systems for: Plants with many chillers (more than three) and with

    fairly high base loads where the need for bypass is minimal or nil and flow fluctuations during staging are small due to the large number of chillers; and

    Plants where design engineers and future on-site operators understand the complexity of the controls and the need to maintain them.

    Otherwise use primary-secondary Also for plants with CHW storage

  • Pipe Sizing

  • 72

    Pipe Sizing

    Need to balance Cost of pipe and its installation Cost of pump energy Longevity of piping (erosion) Noise Sometimes space limitations

  • 73

    Accurately sizing pump head

    Guessing at pump heads Wastes money in oversized pumps, motors and (sometimes)

    VFDs and (sometimes) need for impeller trimming Wastes energy (minor impact w/VFD or if impeller is trimmed)

    Calculating pump heads Takes about 20 minutes of engineering time

    Guessing cannot possibly be cost effective!

  • Optimum T

  • 75

    Flow Rate and T

    TGPM 500 =QLoad from Load Calcs (Btu/hr)

    Conversion constant =8.33 lb/gal * 60

    minutes/hr

    Flow rate (GPM)

    Temperature Rise or Fall (F)

  • 76

    CHW T Tradeoffs

    T

    Low

    High

    Typical Range

    8F

    25F

    First Cost Impact

    smaller condenser

    smaller pipe smaller pump

    smaller pump motor

    Energy Cost Impact

    lower fan energy

    lower pump energy

  • 77

    Coil Performance with T

    Chilled Water T 11 13 15 18 20Coil water pressure drop, feet H2O

    28 20 15 10 8.1

    Coil airside pressure drop, inches H2O

    0.46 0.48 0.49 0.52 0.54

    43F chilled water supply temperature, 78F/62F entering air and 53F leaving air temperature.

  • 78

    0

    200

    400

    600

    800

    1000

    1200

    11 13 15 18 20CHW Delta-T

    kWh/

    ton/

    year

    CHP Energy kWh/yearChiller Energy kWh/yearFan Energy kWh/year

    System Performance With T Varying Airside Pressure

    CHWST = 44F

  • 79

    System Performance and T Constant Airside Pressure

    0

    200

    400

    600

    800

    1000

    1200

    1400

    41/16 42/14 43/12 44/10CHWST/Delta-T

    kWh/ton/year

    CHP Energy kWh/yearChiller Energy kWh/yearFan Energy kWh/year

  • 80

    Choosing the Right CHW T

    Both energy and first costs are almost always minimized by picking a very high T (>18F to 25F)

    Savings even greater with systems that have Large distribution piping network Water-side economizers CHW thermal energy storage

  • 81

    Condenser Water (Tower) Range at Constant CWST

    T

    Low

    High

    Typical Range

    8F

    18F

    First Cost Impact

    smaller condenser

    smaller pipe smaller pump

    smaller pump motor smaller cooling tower

    smaller cooling tower motor Energy Cost

    impact

    lower chiller energy

    lower pump energy lower cooling tower energy

  • 82

    Condenser Water Range at Constant Tower Fan Energy

    0

    100

    200

    300

    400

    500

    600

    73/16 73.5/14 74.5/12 75.5/10

    CWST/Delta-T

    kWh/ton/year

    Tower Fan CW pumpChiller

  • 83

    COOLING TOWER SELECTION

    5

    7

    9

    11

    13

    151719

    1110

    98

    76

    54

    32

    10%10%20%30%40%50%60%70%80%90%100%110%120%130%140%150%160%170%180%190%200%210%

    % D

    esig

    n C

    apac

    ity

    Approach (F)

    Range (F)

    DOE 2 Curve: Percent rated capacity at 70.0F wet bulb

    200%-210%190%-200%180%-190%170%-180%160%-170%150%-160%140%-150%130%-140%120%-130%110%-120%100%-110%90%-100%80%-90%70%-80%60%-70%50%-60%40%-50%30%-40%20%-30%10%-20%0%-10%

    Design capacity

    2 X design capacity

    1/2 of design capacity

  • 84

    Cooling Tower Selection

    Fan Control Efficiency Approach

  • 85

    Tower Fan Control

    Free Cooling ~ 15% of Capacity

    Single Speed Fan

    Two-Speed or Variable-Speed Fan

    % Capacity

    % Power

    One Cell Tower

  • 86

    Tower Fan Control Two Cell Tower

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 50% 55% 60% 65% 70% 75% 80% 85% 90% 95% 100%

    % Capacity

    % P

    ower

    Two 1-Speed Fans

    Two 2-Speed Fans

    One 1-Speed Fan andOne 2-Speed Fan

    Free Cooling Below 15% Capacity

    Two Variable Speed

    Two Cell Tower

  • 87

    Tower Fan Control

    One-speed control is almost never the optimum strategy regardless of size, weather, or application

    VFD fan speed control is best choice now Costs now comparable to two speed motors & starters Soft start reduces belt wear Lower noise Control savings for DDC systems (network card options) More precise control

    Multiple cell towers should have speed modulation on at least 2/3 of cells (required by ASHRAE 90.1). For redundancy, use VFDs on all cells

  • 88

    Tower Efficiency LCC

    90 GPM/HP 70 GPM/HP 50 GPM/HP

    1000 ton Oakland Office

  • 89

    Tower Efficiency Guidelines

    Use Propeller Fans Avoid centrifugal except where high static needed or

    where low-profile is needed and no prop-fan options available

    Consider low-noise propeller blade option and high efficiency tower where low sound power is required

    Efficiency Minimum 80 gpm/hp for commercial occupancies Minimum 100 gpm/hp for 24/7 plants (data centers)

    Approach Maximum 10F for large central plants 3F for 24/7 plants (data centers)

  • Break

  • 91

    CHILLER SELECTION

    Part-Load Ratio

  • 92

    Chiller Procurement Approaches

    Most Common Approach Pick number of chillers, usually arbitrarily or as

    limited by program or space constraints Take plant load and divide by number of chillers

    to get chiller size (all equal) Pick favorite vendor Have vendor suggest one or two chiller options Pick option based on minimal or no analysis Bid the chillers along with the rest of the job and

    let market forces determine which chillers you actually end up installing

  • 93

    Chiller Procurement Approaches

    Better Approach Estimate plant annual load profile Understand chiller efficiency curves Request chiller options from multiple

    manufacturers based on a performance desired. Multiple options encouraged.

    Estimate energy usage of options with a detailed computer model of the building/plant

  • 94

    Sample Load Profile

    0

    100

    200

    300

    400

    500

    600

    700

    800

    10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

    Percent Load

    Hour

    s pe

    r yea

    r

  • 95

    Chiller Procurement Approaches

    Another Option Pick a short list of vendors based on past

    experience, local representation, etc. Request chiller bids based on a performance

    specification. Multiple options encouraged. Adjust bids for other first cost impacts Estimate energy usage of options with a detailed

    computer model of the building/plant Select chillers based on lowest life cycle cost Bid the chillers at end of design development

    phase

  • 96

    Chiller Bid Specification Dont Specify:

    Number of chillers Chiller size Chiller efficiency Chiller unloading

    mechanism As much as possible

    keep the spec flexible!

    Do Specify: Total design load Anticipated load profile Minimum number of

    chillers and redundancy requirements

    Design CHW/CW entering and leaving temperatures and/or flows (or tables of conditions)

    Available energy sources Physical, electrical or other

    limitations Acoustical constraints Acceptable refrigerants

  • 97

    Zero Tolerance Data

    Do NOT allow tolerance to be taken in accordance with ARI 550/590

    Why insist on zero tolerance? Levels playing field tolerances applied

    inconsistently among manufacturers Modeled energy costs will be more accurate High tolerance at low loads makes chillers

    appear to be more efficient than they will be, affecting comparison with unequally sized, VFD-driven, or multiple chiller options

  • 98

    Zero Tolerance Data

    0%

    5%

    10%

    15%

    20%

    25%

    30%

    35%

    40%

    45%

    0% 20% 40% 60% 80% 100% 120%

    % of Full Load

    % T

    oler

    ance

    10F Delta-T15F Delta-T20F Delta-T

    ARI 550/590 Tolerance Curve

  • 99

    Factory Tests

    Certified Factory Tests Need to verify performance to ensure accurate

    claims by chiller vendors in performance bids Field tests are difficult or impossible and less

    accurate Last chance to reject equipment

  • 100

    Chiller Bid Evaluation

    Adjust for First Cost Impacts Estimate Maintenance Costs Calculate Energy Costs

    Energy model of building(s) and plant Calculate Life Cycle Costs Temper Analysis with Consideration for Soft Factors

    Final Selection

  • 101

    Advantages & Disadvantages OF RECOMMENDED CHILLER SELECTION APPROACH

    Disadvantages Extra work for both engineer and vendor Difficult to include maintenance impact Assumes energy rate schedules will remain as they

    are now with simplistic adjustments for escalation Advantages

    Allows manufacturers to each find their own sweet spots, both for cost and efficiency

    Usually higher energy efficiency More rational than typical selection approaches

  • 102

    OPTIMIZING CONTROLS

  • 103

    Optimizing Control Sequences

    Cookbook Solution Staging Chillers Controlling Pumps Chilled Water Reset Condenser Water Reset

    Relational Control Approach

  • 104

    Staging Chillers

    Fixed Speed Chillers Operate no more chillers than required to meet the

    load Stage on when operating chillers maxed out as

    indicated by measured load (GPM, T), CHWST, flow, or other load indicator

    For primary-secondary systems w/o check valve in the decoupler, start chiller to ensure primary-flow > secondary-flow

    Stage off when measured load/flow indicates load is less than operating capacity less one chiller be conservative to prevent short cycling

  • 105

    Staging Chillers, continued

    Variable Speed Chillers Operate as many chillers as possible provided

    load on each exceeds 30% to 40% load Energy impact small regardless of staging logic You MUST use condenser water reset to get the

    savings

  • 106

    Part Load Chiller Performance w/ Zero ARI Tolerance

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

    % Load (with Condenser Relief)

    %kW

    Fixed SpeedVariable Speed

  • 107

    Controlling CHW Pumps

    Primary-only and Secondary CHW Pumps Control speed by differential pressure measured

    as far out in system as possible and/or reset setpoint by valve demand

    Stage pumps by differential pressure PID loop speed signal: Start lag pump at 90% speed Stop lag pump at 40% speed For large HP pumps, determine flow and speed

    setpoints with detailed energy analysis

  • 108

    VFD Pump Power vs. Setpoint

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    0 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

    Percent GPM

    Perc

    ent P

    ump

    kW

    DP setpoint = Design HeadDP setpoint = Head*.75DP setpoint =Head/2DP setpoint =Head/3DP setpoint = 0 (reset)

  • 109

    Chilled Water Setpoint Reset

    Reset Impacts Resetting CHWST upwards reduces chiller energy but will

    increase pump energy in VFD variable flow systems Dehumidification

    Reset with open or indirect control loops (e.g. OAT) can starve coils and reduce dehumidification

    Reset by control valve position will never hurt dehumidification humidity of supply determined almost entirely by supply air temperature setpoint, not CHWST

    Recommendations Reset from control valve position using Trim & Respond logic For variable flow systems with VFDs

    Reset of CHWST and VFD differential pressure setpoint should be sequenced not independent like VAV systems since control valves are pressure-dependent

    Sequence reset of CHWST and DP next slide

  • 110

    CHWST/DP Setpoint Reset for VSD CHW System

    Back off on CHWST first Then back off on DP setpoint

    Tmin+ 15F

    Tmin

    DPmax

    5 psi

    CHW setpoint

    CHW setpoint

    DP setpoint

    DP setpoint

    CHW Plant Reset 0 100% 50%

  • 111

    CHW vs. DP Setpoint Reset

    Plant with 150 ft CHW pump head

  • 112

    Condenser Water Setpoint Reset

    Optimum Strategy Cannot Easily Be Generalized Depends on efficiency/sizing of tower and type of chiller Relational control by monitoring plant efficiency

    Recommendations CWS reset by plant load from [as low as manufacturer

    recommends] at 30% plant load up to [design CWST] at 80% load

    Reset based on wetbulb temperature not effective given inaccuracy of sensors

  • 113

    Optimum Sequences

    All plants are different Tower efficiency, approach Chiller efficiency, unloading control Pump efficiency, head, unloading control Number of chillers, pumps, towers

    A generalized sequence can be developed but it will not be optimum

    Solution?

  • 114

    Summary

    In this course, you have learned techniques to design and control chiller plants for near-minimum life cycle costs, including: Selecting optimum chilled water distribution system Selecting optimum CHW supply & return temperatures Selecting optimum CW and tower range and approach

    temperatures, tower efficiency, and fan speed controls Selecting optimum chillers using a performance bid and

    LCC analysis Optimizing control sequences and setpoints

  • 115

    Questions