  • Options Facility Advisory Committee Agenda

    • Board Directive :: Group Norms

    • Architectural Response and Options • Likes

    • Concerns

    • Questions

    • Transition | Growth | Future

    • Cost Analysis

    • Feedback

    • Next Steps

  • Options Facility Advisory Committee Directive | Outcomes

    • Board Directive

    • Clarify key components and guiding principles of the options programs;

    • Examine how to support their relocation and growth; and

    • Explore the facilities needed and available to support this expansion.

    • Outcomes of Committee Work

    • The 2017 Options Facility Advisory Committee work will provide a framework for board decisions regarding educational learning environments.

    • The school board will make the final decision regarding option programs and location. The work of the committee will provide information so the board can make an informed decision.

  • Options Facility Advisory Committee Factors

    • BISD places high value on quality options programs and recognizes their unique needs within the district;

    • Desire to expand opportunities for students;

    • Alignment of facilities to enrollment;

    • Final Phase of the BISD Facility Master Plan concludes with the need to replace Ordway and Commodore;

    • Financially the district recognizes it is not financially sustainable or prudent to support seven schools.

  • Options Facility Advisory Committee Norms

    To facilitate respectful and productive discussion between all members of the committee:

    • Remain focused on committee directive

    • Seek to understand the perspective of others

    • Recognize diverse perspectives

    • Be mindful of time constraints

  • Options Facility Advisory Committee Meeting Plans and Decision Timeline

    September 11 • Overview and response to proposals

    September 25 • Review September 11 work and feedback

    • October 18 – Introduction Advisory Committee work (to be determined)

    October 26 | School Board Meeting • Continuation of Advisory Committee work

  • Architectural Response & Options Eagle Harbor High School

    Mosaic Home Education Partnership

    Ordway | El Velero

    Odyssey 1-8

    © MAHLUM

  • Proposed Campus Organization

    © MAHLUM

  • Eagle Harbor High School ::

    What We Heard

    © MAHLUM

  • © MAHLUM

    N

    EHHS :: Conceptual Plan

  • Eagle Harbor High School ::

    Likes

    © MAHLUM

  • © MAHLUM

    Glass and flexible walls

    Dedicated EHHS space that will maintain the identity, culture

    and community!

    Proximity to BHS for walking

    Commons is a great/positive concept for EHHS

    Not-for-profit BARN could provide elective space w/in 10

    minutes of campus

    EHHS Report Back

  • Eagle Harbor High School ::

    Questions and Concerns

    © MAHLUM

  • © MAHLUM

    Does this new space support program growth? How?

    Can EHHS be sequestered where it is (Commodore) to save

    money?

    Will we have autonomous admin, admin / counselor office

    manager, shared specialists?

    Will a co-located K-12 commodore options community be

    addressed in long term campus plan?

    Do the utilization diagrams accurately reflect the peak periods?

    EHHS Report Back :: Programmatic

  • © MAHLUM

    What is the maximum capacity of the proposed space?

    Do the two east-most classrooms meet the ed specs?

    What is the square footage / student being provided?

    Please provide clarification around the district specifications –

    there is confusion around the 900 sf stat

    EHHS Report Back :: Facility

  • Proposed Program

    Dedicated @83.3*% STA SF

    Core Instruction 3 2550

    Lab 1(in 300 bldg)

    Resource 1 450

    NET ASSIGNABLE AREA5 3000

    Shared

    Admin/Counseling Office 1 180

    Workroom 1 180

    Small Group 1 180

    Teaching Stations 5

    Student Capacity FTE 150

    Support

    Independent Study/Gathering

    Gym

    School Administration

    Staff Offices/Lounge

    © MAHLUM

    EHHS :: What is the Maximum Capacity?

  • Proposed Program

    Dedicated @83.3*% STA SF

    Core Instruction 3 2550

    Lab 1(in 300 bldg)

    Resource 1 450

    NET ASSIGNABLE AREA5 3000

    Shared

    Admin/Counseling Office 1 180

    Workroom 1 180

    Small Group 1 180

    Teaching Stations 5

    Student Capacity FTE 150

    Student FTE 75

    Headcount* 110

    Support

    Independent Study/Gathering

    Gym

    School Administration

    Staff Offices/Lounge *Partially Enrolled

    © MAHLUM

    EHHS :: What is the Maximum Capacity?

  • N © MAHLUM

    EHHS :: What is the Maximum Capacity?

  • © MAHLUM N

    TEACHING SPACE

    TEACHING SPACE

    TEACHING

    SPACE

    TEACHING

    SPACE

    300 BLDG

    SCIENCE LAB

    32+

    32

    16+

    24-30

    32+

    EHHS :: What is the Maximum Capacity?

    CURRENT FTE 75

    MAX FTE 142

  • © MAHLUM N

    TEACHING SPACE

    TEACHING SPACE

    TEACHING

    SPACE

    300 BLDG

    SCIENCE LAB

    60+

    16+

    60+

    32+

    EHHS :: What is the Maximum Capacity?

    CURRENT FTE 75

    MAX FTE 142

  • © MAHLUM

    Do the utilization images accurately reflect the peak periods?

    EHHS Report Back :: Facility

  • EHHS 1st Period :: Does Utilization Reflect Peak?

    © MAHLUM N

    ALGEBRA II

    ADVISORY

    17+16

    20

    300 BLDG

    SCIENCE LAB

    32+

  • N

    WORLD HISTORY

    WORLD LIT

    AP HUGS

    STUDY

    SKILLS

    7

    15

    28

    29

    300 BLDG

    SCIENCE LAB

    32+

    EHHS 2nd Period :: Does Utilization Reflect Peak?

    © MAHLUM

  • N

    APES

    GEOMETRY

    INTEGRATED

    MATH

    4

    18

    23

    24

    ALGEBRA 1

    300 BLDG

    SCIENCE LAB

    EHHS 3rd Period :: Does Utilization Reflect Peak?

    © MAHLUM

  • N

    WORLD LIT

    ENGLISH

    BASIC

    ENGLISH

    +/-15

    12

    29

    28

    WORLD HISTORY

    300 BLDG

    SCIENCE LAB

    EHHS 4th Period :: Does Utilization Reflect Peak?

    © MAHLUM

  • N

    ACHIEVE

    ADVISORY

    STUDY

    SKILLS

    11

    28

    13

    29

    AMERICAN LIT

    300 BLDG

    SCIENCE LAB

    EHHS 5th Period :: Does Utilization Reflect Peak?

    © MAHLUM

    12 GYM

  • N

    ADVISORY

    STUDY

    SKILLS

    8

    17 30

    US HISTORY

    300 BLDG

    SCIENCE LAB

    EHHS 6th Period :: Does Utilization Reflect Peak?

    © MAHLUM

  • © MAHLUM

    Is it possible to fit 30 students in the proposed classrooms?

    EHHS Report Back :: Facility

  • N

    16+

    24

    32+

    300 BLDG

    SCIENCE LAB

    EHHS :: Do 30 Students Fit?

    © MAHLUM

    TEACHING SPACE

    TEACHING SPACE

    TEACHING

    SPACE

    TEACHING

    SPACE

    32

    32+

  • © MAHLUM

    N 24

    EHHS :: Do 30 Students Fit?

  • © MAHLUM

    N

    EHHS :: Do 30 Students Fit?

    30

  • © MAHLUM

    EHHS :: Do 30 Students Fit?

    N

  • © MAHLUM

    EHHS :: Do 30 Students Fit?

    N

  • © MAHLUM

    EHHS :: Do 30 Students Fit?

    30 32 N

  • N

    TEACHING SPACE

    TEACHING SPACE

    TEACHING

    SPACE

    TEACHING

    SPACE

    32+

    32

    16+

    24-60

    300 BLDG

    SCIENCE LAB

    32+

    © MAHLUM

    EHHS :: Do 30 Students Fit?

  • N

    TEACHING

    SPACE

    16+

    300 BLDG

    SCIENCE LAB

    32+

    © MAHLUM

    EHHS :: Do 30 Students Fit?

    TEACHING SPACE

    32-64 TEACHING

    SPACE

    24

  • N © MAHLUM

    EHHS :: Do 30 Students Fit?

    Option 01

  • N

    EHHS :: Do 30 Students Fit?

    Option 02

    © MAHLUM

    ATHLETIC

    STORAGE

    IN GYM

    (WIRE CAGE)

  • EHHS :: Do 30 Students Fit?

    Option 02

    © MAHLUM N

  • EHHS :: Do 30 Students Fit?

    Option 02

    N © MAHLUM

    TEACHING SPACE

    TEACHING SPACE

    TEACHING

    SPACE

    TEACHING

    SPACE

    32+

    15-32

    32+

    24

  • © MAHLUM

    EHHS :: Do 30 Students Fit?

    Option 02

  • © MAHLUM

    What is the capacity of the commons?

    What is the capacity of the commons if the adjacent walls are

    operable?

    If the two east-most classrooms were to grow, it shouldn’t be at the

    expense of the commons.

    EHHS Report Back :: Facility

  • 32+

    CLASSROOM

    N © MAHLUM

    EHHS :: Commons Capacity?

  • 57

    DINING

    N © MAHLUM

    EHHS :: Commons Capacity?

  • 95

    DINING

    N © MAHLUM

    EHHS :: Commons Capacity?

  • 122

    ASSEMBLY

    N © MAHLUM

    EHHS :: Commons Capacity?

  • ASSEMBLY

    204

    N © MAHLUM

    EHHS :: Commons Capacity?

  • N

    EHHS :: Commons Capacity?

    Option 01

    © MAHLUM

  • © MAHLUM

    EHHS :: Commons Capacity?

    Option 01

  • N

    EHHS :: Commons Capacity?

    Option 02

    © MAHLUM

  • © MAHLUM

    EHHS :: Commons Capacity?

    Option 02

  • 25

    CLASSROOM

    N

    EHHS :: Commons Capacity?

    Option 02

    © MAHLUM

  • 50

    DINING

    N

    EHHS :: Commons Capacity?

    Option 02

    © MAHLUM

  • N

    EHHS :: Commons Capacity?

    Option 02

    © MAHLUM

    95

    DINING

  • 107

    ASSEMBLY

    N

    EHHS :: Commons Capacity?

    Option 02

    © MAHLUM

  • N

    EHHS :: Commons Capacity?

    Option 02

    © MAHLUM

    204

    ASSEMBLY

  • © MAHLUM

    Would there be a kitchenette? We need a sink, fridge, and

    microwave.

    EHHS Report Back :: Facility

  • N

    EHHS :: Kitchenette Options

    © MAHLUM

  • © MAHLUM

    How is the noise issue with the gym addressed?

    Acoustics in general?

    Will there be carpet?

    EHHS Report Back :: Facilities

  • N

    EHHS :: Gym Wall

    © MAHLUM

    N

  • Mosaic Home Education Partnership ::

    What We Heard

    © MAHLUM

  • © MAHLUM

    N

    MHEP :: Concept

  • Mosaic Home Education Partnership ::

    Likes

    © MAHLUM

  • © MAHLUM

    Ample parking

    “Thanks for designing this; we can work with this!”

    Inexpensive use of space: a great fit for Mosaic

    Space for storage

    The kitchen is great

    Has good event meeting space for whole family programs

    MHEP Report Back

  • Mosaic Home Education Partnership ::

    Questions and Concerns

    © MAHLUM

  • © MAHLUM

    Where are kids eating lunch?

    Where are kids’ lockers?

    Can we revisit the #s of Mosaic students and utilization

    percentage?

    MHEP Report Back :: Program

  • © MAHLUM

    Mosaic HEP Program

    Proposed @ 33.3%*

    Dedicated (Tuesday/Thursday) STA SF

    Core Instruction 2 1800

    Family Resource Center (included above)

    NET ASSIGNABLE AREA 1,800

    *assumes 2 Days/Week 83.3% utilized

    Teaching Stations 2

    Student Capacity FTE 50

    Student FTE 42

    Headcount** 52

    Support

    Special Education/Learning Resources

    Shared Specialists

    Assembly/Food Service

    Gymnasium

    Library

    School Administration **Partially Enrolled

  • © MAHLUM

    Proposed @ 33.3%*

    Dedicated (Tuesday/Thursday) STA SF

    Core Instruction 2 1800

    Family Resource Center (included above)

    NET ASSIGNABLE AREA 1,800

    *assumes 2 Days/Week 83.3% utilized

    Teaching Stations 2

    Student Capacity FTE 50

    Student FTE 42

    Headcount** 52

    Support

    Special Education/Learning Resources

    Shared Specialists

    Assembly/Food Service

    Gymnasium

    Library

    School Administration **Partially Enrolled

    Mosaic HEP Program

  • © MAHLUM

    Could this allow Mosaic to grow into 3 STA with family area?

    Mosaic HEP Report Back :: Facility

  • © MAHLUM

    N

    MHEP :: 3 Teaching Stations?

    Tuesday & Thursday

    3

    2

    1

  • © MAHLUM

    Where do Mosaic students go for specialists?

    Mosaic HEP Report Back :: Facility

  • SPECIALISTS + ADMIN

    Mosaic HEP :: Mosaic Access to Specialists?

    © MAHLUM

    N

    MOSAIC

    GYM

    MUSI

    C

    (02)

    ART

    STE

    M SPEC.

    MUSIC

    (01)

    RES.

    RES.

  • © MAHLUM

    No separate entrance so we don’t disrupt other programs when

    families arrive.

    MHEP Report Back :: Facility

  • Mosaic HEP :: Entry?

    © MAHLUM

    PARKING LOT

    CAMPUS

  • © MAHLUM

    Is there an opportunity to include teacher space for collaborative

    sessions?

    How does this accommodate monthly advisor meetings?

    MHEP Report Back :: Facility

  • MHEP :: Collaborative Sessions & Advisor Meetings?

    Monday, Wednesday & Friday

    © MAHLUM

    TS

    OPEN

    RESOURC

    E

  • Mosaic Home Education Partnership ::

    GROWTH Questions and Concerns

    © MAHLUM

  • © MAHLUM

    No kids lockers or cubbies for coats/lunches/backpacks

    No meeting space for parents or staff.

    Where do kids eat lunch?

    No family space

    So isolated for students

    MHEP Growth Report Back :: Program

  • © MAHLUM

    No visibility between rooms

    No connection for large group instruction

    MHEP Growth Report Back :: Facility

  • MHEP GROWTH:: Visibility and Assembly?

    © MAHLUM

  • © MAHLUM

    How would Mosaic grow in two portables?

    Where would the resource center be housed?

    MHEP Growth Report Back :: Facility

  • MHEP GROWTH:: Space for Growth?

    © MAHLUM

    N

    MOSAIC

  • © MAHLUM

    No bathrooms; what is the safe path for kids to go to the bathroom?

    MHEP Growth Report Back :: Facility

  • SPECIALISTS + ADMIN

    Mosaic HEP :: Safe Path to Bathrooms?

    © MAHLUM

    N

    MOSAIC

  • Ordway | El Velero ::

    What We Heard

    © MAHLUM

  • © MAHLUM

    Ordway | El Velero :: Concept

    N

  • Ordway | El Velero :: Concept

    © MAHLUM

    N

  • Ordway | El Velero :: Campus Plan

    © MAHLUM

  • Ordway | El Velero ::

    Likes

    © MAHLUM

  • © MAHLUM

    Main campus receives upgrades.

    Odyssey 5-8 paired with future El Velero 5-8 creates more

    peers for students, which is a need mentioned by parents.

    Ordway | El Velero Report Back

  • Ordway | El Velero ::

    Questions and Concerns

    © MAHLUM

  • © MAHLUM

    How will neighborhood Ordway families and teachers be included

    in this process? We want to keep the neighborhood component

    Do we have enough administrative space for 500+ students?

    More clarity needed on expansion for El Velero. K-8 needs 9

    classrooms

    Have we looked at MS spaces for 5-8 El Velero and 5-8

    Odyssey?

    What was the community response to expanding Odyssey or

    adding a parallel program?

    Ordway | El Velero Report Back :: Program

  • © MAHLUM

    Why did El Velero move back in 2013 without this process?

    It feels like a lot of accommodation is being made for Odyssey

    and there is little or no attention/changes paid to El Velero

    Could we locate capital projects and district programs and

    Mosaic in the El Velero portables?

    Very limited common space (cafeteria) for 500+

    Ordway | El Velero Report Back :: Program

  • Options Facility Advisory Committee Growth | Future

    Considerations for managing Ordway campus growth: • Thoughtful expansion of Options programs • 5th and 6th El Velero – Sakai • 7th and 8th El Velero – Woodward Middle • Possible relocation of Mosaic to another facility • Construction of new Ordway campus

  • © MAHLUM

    More clarity needed on expansion for El Velero. 5 class rooms

    needed for K-4 full class. K-6 is 7 classrooms.

    Ordway | El Velero Report Back :: Facility

  • Ordway | El Velero :: EV Expansion Accommodated?

    © MAHLUM

    N

    1

    2017/18

    ORDWAY 11

    EL VELERO

    4

    2022/23

    ORDWAY 10

    EL VELERO (K-6)

    7

    2 3

    4

    5

    6 7 8

    9 10

    11

    12

    13

    14

    16

    15

    17

  • Ordway | El Velero :: EV Expansion Accommodated?

    © MAHLUM

    N

    1

    2017/18

    ORDWAY 11

    EL VELERO

    4

    2022/23

    ORDWAY 10

    EL VELERO (K-6)

    7

    2 3

    4

    5

    6 7 8 9

    10

    11

    12

    13 14 16

    15

    17

  • © MAHLUM

    Is this an equitable allocation of space? The concern is that the

    sf/student is higher for Odyssey.

    Ordway | El Velero Report Back :: Campus

  • 2,150 SF/

    50 STUDENTS =

    43 SF/ST

    21,170 SF/

    375 STUDENTS = 56

    SF/ST

    7,880 SF/

    129 STUDENTS = 61 SF/ST © MAHLUM

    N

    Ordway|El Velero :: Is SF Equitable? (550 students*) *school capacity to be determined by program

    enrollment

    **assumes 25 students/teaching space

    for Odyssey 1-6, Mosaic, Ordway and El Velero;

    assumes 27 students/teaching space

    for Odyssey 7-8

    ***assumes all non-K portables =980 sf

  • 2,150 SF/

    50 STUDENTS =

    43 SF/ST

    21,170 SF/

    375 STUDENTS = 56

    SF/ST

    8,500 SF/

    150 STUDENTS = 56 SF/ST © MAHLUM

    N

    *school capacity to be determined by program

    enrollment

    **assumes 25 students/teaching space

    for Odyssey 1-6, Mosaic, Ordway and El Velero;

    assumes 27 students/teaching space

    for Odyssey 7-8

    ***assumes all non-K portables =980 sf

    Ordway|El Velero :: Is SF Equitable? *

  • 2,150 SF/

    54 STUDENTS =

    40 SF/ST

    21,170 SF/

    375 STUDENTS = 56

    SF/ST

    8,500 SF/

    150 STUDENTS = 56 SF/ST © MAHLUM

    N

    *school capacity to be determined by program

    enrollment

    **assumes 25 students/teaching space

    for Odyssey 1-6, Mosaic, Ordway and El Velero;

    assumes 27 students/teaching space

    for Odyssey 7-8

    ***assumes all non-K portables =980 sf

    1,650 SF/

    50 STUDENTS =

    33 SF/ST

    Ordway|El Velero :: Is SF Equitable? *

    flexibility

  • © MAHLUM

    Do we have enough specialist space for 500+ students?

    Very limited common space (gym/playground) for 500+

    Ordway | El Velero Report Back :: Facility

  • MUSIC

    Ordway | El Velero :: Specialist Space for 500?

    © MAHLUM

    N

    GYM

    LIBRAR

    Y

    ART

    STEM

    Existing 5

    Classrooms 3

    Library 1

    Gym 1

  • Ordway | El Velero :: Specialist Space for 500?

    © MAHLUM

    N

    GYM

    LIBRAR

    Y

    ART

    STEM

    MUSIC

    +SPECIALIST

    Proposed

    6+

    Classrooms 4

    Library 1

    Gym 1+

  • © MAHLUM

    Could we locate 7-8 Odyssey and El Velero together in the north

    portables?

    Ordway | El Velero Report Back :: Campus

  • MOSAIC

    ORDWAY ES + EL

    VELERO

    ODYSSEY 1-6 SPECIALISTS + ADMIN

    O|EV :: Co-Located Program Opportunities?

    © MAHLUM

    N

    ODYSSEY 7-8

  • MOSAIC

    ORDWAY ES + EL

    VELERO K-4

    ODYSSEY 1-6 SPECIALISTS + ADMIN

    © MAHLUM

    N

    ODYSSEY 7-8

    O|EV :: Co-Located Program Opportunities?

  • ORDWAY ES + EL

    VELERO

    SPECIALISTS + ADMIN

    © MAHLUM

    N

    O|EV :: Co-Located Program Opportunities?

    KINDERGARTEN

    MOSAIC

    ODYSSEY 1-6

    ODYSSEY 7-8

  • Options Facility Advisory Committee Growth | Future

    Considerations for managing Ordway campus growth: • Thoughtful expansion of Options programs • 5th and 6th El Velero – Sakai • 7th and 8th El Velero – Woodward Middle • Possible relocation of Mosaic to another facility • Construction of new Ordway campus

  • © MAHLUM

    No gathering space for El Velero or parent volunteer work

    Ordway | El Velero Report Back :: Facility

  • O|EV :: Gathering & Volunteer Space?

    © MAHLUM

    N

  • O|EV :: Gathering & Volunteer Space?

    © MAHLUM

    N

    ASSEMBL

    Y

    ASSEMBL

    Y

  • Odyssey 1-8 ::

    What We Heard

    © MAHLUM

  • Odyssey 1-8 :: Concept

    © MAHLUM

    N

  • Odyssey 1-8 ::

    Likes

    © MAHLUM

  • © MAHLUM

    Nice flexible teaching spaces.

    Program building space keeps identity and Odyssey grade

    integration.

    Feels like a community.

    Shared areas with small group spots.

    Opportunity for team teaching 1-2 / 3-4 / 5-6

    Odyssey 1-8 Report Back

  • Odyssey 1-8 ::

    Questions and Concerns

    © MAHLUM

  • © MAHLUM

    Should the program add Kindergarten or allow for short-term 1/6

    expansion?

    Where will the students eat lunch?

    Is there a space for teachers/shared teachers?

    Would 1-4 specialists also serve grades 5-8?

    How and when can incremental expansion happen in 1/6? Currently

    7-8 starts on the secondary timeframe? Would they switch to start

    earlier and, if so, how would they access the upper-level math @

    BHS

    Odyssey 1-8 Report Back :: Program

  • © MAHLUM

    Where do robotics and a space for robotics 7-8 go?

    How are the classroom libraries accommodated?

    Where will the students eat lunch?

    Odyssey 1-8 Report Back :: Program

  • © MAHLUM

    Could walls between small classrooms also be flexible for

    more versatility?

    If 5/6 space needs are more similar to the 7/8 than the 1-4,

    how could this concept reinforce this?

    Can 2 different syllabi be taught to one class of 5th and 6th

    math simultaneously in these concepts (to accommodate

    Barry’s current scenario)?

    Odyssey 1-8 Report Back :: Facility

  • © MAHLUM

    N

    TEACHING

    SPACE

    STEM

    ART

    Odyssey :: Flexibility?

  • © MAHLUM

    N

    TEACHING SPACE

    TEACHING

    SPACE

    Odyssey :: Flexibility?

    STEM

    ART

  • LAB

    Odyssey :: Flexibility?

    © MAHLUM

    N

    TEACHIN

    G SPACE

    TEACHING

    SPACE

  • © MAHLUM

    N

    5/6

    5/6

    SHARED

    LEARNING

    1/4 1/4

    1/4

    STEM

    ART

    Odyssey :: Flexibility?

    7/8

    7/8

  • © MAHLUM

    How do students get into Art and STEM?

    Odyssey 1-8 Report Back :: Facility

  • © MAHLUM

    N

    STEM

    ART

    Odyssey :: Access to Specialists?

  • SPECIALISTS + ADMIN

    Odyssey :: Access to Specialists?

    © MAHLUM

    N

    GYM MUSI

    C ART

    STE

    M ADDED

    SPEC.

  • © MAHLUM

    Where is storage for rotating curriculum provided?

    Odyssey 1-8 Report Back :: Facility

  • Odyssey :: Curriculum Storage?

    © MAHLUM

    N

  • © MAHLUM

    Could teacher offices and small group instruction space be the

    same?

    Do small group spaces need to be as contained as they are being

    shown, or would those spaces work better as offices?

    Odyssey 1-8 Report Back :: Facility

  • © MAHLUM

    N

    Odyssey :: Offices and/or Small Group?

  • Odyssey 1-8::

    GROWTH Likes

    © MAHLUM

  • © MAHLUM

    Isolation vs. autonomy (7/8)

    Great space (7/8)

    Odyssey 1-8 Growth Report Back

  • Odyssey 1-8::

    GROWTH Questions and Concerns

    © MAHLUM

  • © MAHLUM

    How does the current proposal allow for incremental growth

    (beyond 12 kids) of 1/6 until 7/8 moves out and the space is

    available?

    At what point does 7/8 get pushed to the other building?

    If it is inevitable that 7-8 is going to move into this space, why

    not do it now?

    Odyssey 1-8 Growth Report Back :: Program

  • Odyssey 1-6 Program Proposed @83.3%

    Dedicated

    STA SF

    1-2 Core Instruction 1 900

    3-4 Core Instruction 1 900

    5-6 Core Instruction 1 900

    NET ASSIGNABLE AREA 2,700

    Room 1 818

    Shared

    Small Group 2 280 Flexible Learning 1 900

    Library|Parent Operations 1 550

    2 2,466otal Assignable Area 14,689

    Teaching Stations 3

    Number of Students 75

    Support

    Special Education/Learning Resources

    Shared Specialists

    Assembly/Food Service

    Gymnasium

    Library

    School Administration © MAHLUM

  • Odyssey 1-6 :: Growth Proposed @83.3%

    Dedicated

    STA SF

    1-2 Core Instruction 2 1800

    3-4 Core Instruction 2 1800

    5-6 Core Instruction 2 1800

    NET ASSIGNABLE AREA 5,400

    Room 1 818

    Shared

    Small Group 2 280 Flexible Learning 1 900

    Library|Parent Operations 1 550

    2 2,466otal Assignable Area 14,689

    Teaching Stations 6

    Number of Students 150

    Support

    Special Education/Learning Resources

    Shared Specialists

    Assembly/Food Service

    Gymnasium

    Library

    School Administration © MAHLUM

  • © MAHLUM

    N

    STEM

    ART

    Odyssey :: Incremental Growth?

    1

    2

    3

    4

    5

    * Incremental growth

    analysis assumes

    student increase is

    designed to roll up one

    class cohort at a time,

    adding +/- 25 students

    each year

    129 STUDENTS/

    7,900 SF =

    61 SF/STUDENT

    STUDENTS

    7-8 = 54

    1-6 = 75

    Using Odyssey pedagogy and team

    teaching, additional teaching staff can

    increase the max capacity of students

    such that temporary growth within the

    program can happen fluidly.

  • © MAHLUM

    N

    STEM

    ART

    Odyssey :: Incremental Growth*?

    1

    2

    3

    4

    5 6 1-2

    * Incremental growth

    analysis assumes

    student increase is

    designed to roll up one

    class cohort at a time,

    adding +/- 25 students

    each year

    154 STUDENTS/

    8,500 SF =

    56 SF/STUDENT

    STUDENTS

    7-8 = 54

    1-6 = 100

  • © MAHLUM

    N

    STEM

    ART

    Odyssey :: Incremental Growth?

    1

    2

    3

    4

    5 6

    7

    1-2

    3-4 * Incremental growth

    analysis assumes

    student increase is

    designed to roll up one

    class cohort at a time,

    adding +/- 25 students

    each year

    179 STUDENTS/

    8,500 SF =

    47 SF/STUDENT

    STUDENTS

    7-8 = 54

    1-6 = 125

  • © MAHLUM

    N

    STEM

    ART

    Odyssey :: Incremental Growth?

    1

    2

    3

    4

    5 6

    7

    1-2

    3-4

    8 5-6

    * Incremental growth

    analysis assumes

    student increase is

    designed to roll up one

    class cohort at a time,

    adding +/- 25 students

    each year

    204 STUDENTS/

    8,500 SF =

    42 SF/STUDENT

    STUDENTS

    7-8 = 54

    1-6 = 150

  • © MAHLUM

    N

    STEM

    ART

    Odyssey :: Incremental Growth?

    1

    2

    3

    4

    5 6

    7

    1-2

    3-4

    8 5-6

    * Incremental growth

    analysis assumes

    student increase is

    designed to roll up one

    class cohort at a time,

    adding +/- 25 students

    each year

    204 STUDENTS/

    8,500 SF =

    42 SF/STUDENT

    STUDENTS

    7-8 = 54

    1-6 = 150

    7-8

  • © MAHLUM

    N

    STEM

    ART

    Odyssey :: Incremental Growth?

    1

    2

    3

    4

    5 6

    7

    K

    1-2

    8 3-4

    * Incremental growth

    analysis assumes

    student increase is

    designed to roll up one

    class cohort at a time,

    adding +/- 25 students

    each year

    200 STUDENTS/

    8,500 SF =

    43 SF/STUDENT

    STUDENTS

    7-8 = 0

    K-6 = 200

    5-6

  • © MAHLUM

    Slightly isolating but could be OK as the “big kids on campus”.

    How are flexible space and small groupings provided in this

    concept?

    Odyssey 7-8 Growth Report Back :: Facility

  • Odyssey 7/8 :: Flexibility?

    © MAHLUM

    N

    TEACHING

    SPACE

    SMALL GROUP

    TEACHING

    SPACE

  • Odyssey 7/8 :: Flexibility?

    © MAHLUM

    N

    TEACHING

    SPACE

    SMALL GROUP

    TEACHING

    SPACE

  • Odyssey 7/8 :: Flexibility?

    © MAHLUM

    N

    LAB CLASSROOM

  • Odyssey 7/8 :: Flexibility?

    © MAHLUM

    N

    LAB CLASSROOM

    SMALL

    GROU

    P

  • Options Facility Advisory Committee Transition

    • Efficiency and alignment • District-wide school enrollment capacity

    • Square footage alignment

    • General fund expenditures

    • Future bond request • 2006, 2009, 2016

  • Options Facility Advisory Committee Growth

    • Desire for increased capacity in Option

    programs

    • Innovations: Designing and Implementing • The district is committed to the practice of school

    choice and to the development, implementation, and evaluation of effective schooling options that support student learning.

  • Next Steps Report Development

    Cost Estimate

    Board Meeting 10.18.17 + 10.26.17