s. smith lcls facility advisory [email protected] april 16, 2007 1 bpms and toroids...

17
S. Smith LCLS Facility Advisory Committee [email protected] April 16, 2007 1 BPMs and Toroids Facility Advisory Committee April 16, 2007 System overview Status Schedule

Post on 19-Dec-2015

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: S. Smith LCLS Facility Advisory Committeessmith@slac.stanford.edu April 16, 2007 1 BPMs and Toroids Facility Advisory Committee April 16, 2007 System overview

S. Smith

LCLS Facility Advisory Committee [email protected]

April 16, 2007 1

BPMs and ToroidsFacility Advisory Committee

April 16, 2007

System overviewStatusSchedule

Page 2: S. Smith LCLS Facility Advisory Committeessmith@slac.stanford.edu April 16, 2007 1 BPMs and Toroids Facility Advisory Committee April 16, 2007 System overview

S. Smith

LCLS Facility Advisory Committee [email protected]

April 16, 2007 2

Charge Monitoring

Should be commissioning 6 toroids, 2 Faraday cups

Injector charge monitor electronics installed

Only 3 of 6 toroids installed

IMS, IMBC1in commissioning

IM01 installed but

Output shorted by vacuum bolt

Replace when we can break vacuum

IM02, IM03, IMBC1out not installed

Two Faraday cups installed

FCG1 functional

FC01disabled on insertion

Page 3: S. Smith LCLS Facility Advisory Committeessmith@slac.stanford.edu April 16, 2007 1 BPMs and Toroids Facility Advisory Committee April 16, 2007 System overview

S. Smith

LCLS Facility Advisory Committee [email protected]

April 16, 2007 3

Charge Monitors

4 Chan Fast Digitizer

Toroids 5-8

Toroids 1-4

Toroid/CalCables

ChannelAccess

trig AnalogChargeValues

ChannelAccess

IOC

AD

CE

VR

MPS

MPSSignals

Acromag IP33016 channel, 16-bit8uS conv. time

RawData

LMR-400 x 8LNA +

-

BaselineInt#1

S1

S3

S4

Beam PulseInt#2

S/H

S5

to Fast Acquisition Boardfor waveform capture

S2

EVR t1 t2 t5 t6t4t3

Int#1

Int#2

Sig

na

l a

mp

litu

de

DarkCurren

t

Beam

Pulse

Page 4: S. Smith LCLS Facility Advisory Committeessmith@slac.stanford.edu April 16, 2007 1 BPMs and Toroids Facility Advisory Committee April 16, 2007 System overview

S. Smith

LCLS Facility Advisory Committee [email protected]

April 16, 2007 4

Toroid Dark Current Monitor

Page 5: S. Smith LCLS Facility Advisory Committeessmith@slac.stanford.edu April 16, 2007 1 BPMs and Toroids Facility Advisory Committee April 16, 2007 System overview

S. Smith

LCLS Facility Advisory Committee [email protected]

April 16, 2007 5

Toroid Interior

Page 6: S. Smith LCLS Facility Advisory Committeessmith@slac.stanford.edu April 16, 2007 1 BPMs and Toroids Facility Advisory Committee April 16, 2007 System overview

S. Smith

LCLS Facility Advisory Committee [email protected]

April 16, 2007 6

ResultsTwo toroids measure charge

Readings appear to jitter +-5%

more than we think the beam current jitters

Amp input bandwidth too high

Decrease bandwidth into first amp

Present bandwidth not useful

May be causing several percent jitter

Expect this will be resolved quickly

Early indication is that an impromptu RC filter reduces jitter

Will engineer proper mod to input network

Page 7: S. Smith LCLS Facility Advisory Committeessmith@slac.stanford.edu April 16, 2007 1 BPMs and Toroids Facility Advisory Committee April 16, 2007 System overview

S. Smith

LCLS Facility Advisory Committee [email protected]

April 16, 2007 7

Next PhaseComplete Injector installation/commissioning

7 more toroids :

BC2

LTU

Undulator

Dump

BC2 / BTH west installation design in progress

Page 8: S. Smith LCLS Facility Advisory Committeessmith@slac.stanford.edu April 16, 2007 1 BPMs and Toroids Facility Advisory Committee April 16, 2007 System overview

S. Smith

LCLS Facility Advisory Committee [email protected]

April 16, 2007 8

Beam Position MonitorsSystem overview

Status

Schedule

Page 9: S. Smith LCLS Facility Advisory Committeessmith@slac.stanford.edu April 16, 2007 1 BPMs and Toroids Facility Advisory Committee April 16, 2007 System overview

S. Smith

LCLS Facility Advisory Committee [email protected]

April 16, 2007 9

StatusBuilt 23 BPM processors

Installed 21 BPM processors

Problems remaining

Parts for remaining two

Commissioning software

No global setup tool

Page 10: S. Smith LCLS Facility Advisory Committeessmith@slac.stanford.edu April 16, 2007 1 BPMs and Toroids Facility Advisory Committee April 16, 2007 System overview

S. Smith

LCLS Facility Advisory Committee [email protected]

April 16, 2007 10

Page 11: S. Smith LCLS Facility Advisory Committeessmith@slac.stanford.edu April 16, 2007 1 BPMs and Toroids Facility Advisory Committee April 16, 2007 System overview

S. Smith

LCLS Facility Advisory Committee [email protected]

April 16, 2007 11

BPM Diagnostic PanelView/ adjust BPM parameters

View digitizer waveformSet attenuators

Set timing

Watch beam position pulse to pulse

Page 12: S. Smith LCLS Facility Advisory Committeessmith@slac.stanford.edu April 16, 2007 1 BPMs and Toroids Facility Advisory Committee April 16, 2007 System overview

S. Smith

LCLS Facility Advisory Committee [email protected]

April 16, 2007 12

Orbit Plot

Page 13: S. Smith LCLS Facility Advisory Committeessmith@slac.stanford.edu April 16, 2007 1 BPMs and Toroids Facility Advisory Committee April 16, 2007 System overview

S. Smith

LCLS Facility Advisory Committee [email protected]

April 16, 2007 13

Gun Jitter

Beam jitter plus BPM resolution ~10 microns

Page 14: S. Smith LCLS Facility Advisory Committeessmith@slac.stanford.edu April 16, 2007 1 BPMs and Toroids Facility Advisory Committee April 16, 2007 System overview

S. Smith

LCLS Facility Advisory Committee [email protected]

April 16, 2007 14

Status (cont.)

Performance at least adequate for commissioning

Preformance not yet well studied

Just getting access to tools

Correlation plots, beam synch acquisition

Page 15: S. Smith LCLS Facility Advisory Committeessmith@slac.stanford.edu April 16, 2007 1 BPMs and Toroids Facility Advisory Committee April 16, 2007 System overview

S. Smith

LCLS Facility Advisory Committee [email protected]

April 16, 2007 15

Next

Characterize BPM performance

Establish resolution, offset, stability in operation

Plan for BC2, linac BPM installation

8 BPMs per sector

New environmetally-controlled racks

Revise BPM processor board

Fab, test, install linac BPM system this year

Page 16: S. Smith LCLS Facility Advisory Committeessmith@slac.stanford.edu April 16, 2007 1 BPMs and Toroids Facility Advisory Committee April 16, 2007 System overview

S. Smith

LCLS Facility Advisory Committee [email protected]

April 16, 2007 16

Full document:

PRD 1.1-314

Page 17: S. Smith LCLS Facility Advisory Committeessmith@slac.stanford.edu April 16, 2007 1 BPMs and Toroids Facility Advisory Committee April 16, 2007 System overview

S. Smith

LCLS Facility Advisory Committee [email protected]

April 16, 2007 17

Beam Position Monitor System

Input

Low Noise Amplifier

AmpBandpass Amp

To ADC

Bandpass

NF=2.8dBGain=20dBIP3=40dBm

Fc=140MHzBW=14MHz(was 20 MHz)

Fc=140MHzBW=6 MHz

NF=3.3dBGain=15dBIP3=40dBm

NF=3.3dBGain=15dBIP3=40dBm

Switchable Attenuators

0dBto

15dB

0dBto

15dB

6 dB

Pad

Analog Frontend Version Three