paint spray room proposal

17
Paint Spray Chamber Proposal Prepared by: Rajveer Singh (Intern) Dates: 1) 10/8-12/8- Data collection and analysis 2) 13/8-14/8 Report typing and calculations Supervisor: Yazid Adam Acknowledgements and thanks to: 1) Ravi Govindan 2) Muhammad 3) Julie Alias 4) Anas Anafi 5) Robert Loh 6) Shamsul Kamal 7) Sugumaran & the paint and masking crew For providing me with data, information, advice, ideas and suggestions while completing this proposal

Upload: rajveer-singh

Post on 13-Apr-2017

34 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Paint Spray Room Proposal

Paint Spray Chamber Proposal

Prepared by: Rajveer Singh (Intern)

Dates:

1) 10/8-12/8- Data collection and analysis

2) 13/8-14/8 Report typing and calculations

Supervisor: Yazid Adam

Acknowledgements and thanks to:

1) Ravi Govindan

2) Muhammad

3) Julie Alias

4) Anas Anafi

5) Robert Loh

6) Shamsul Kamal

7) Sugumaran

& the paint and masking crew

For providing me with data, information, advice, ideas and suggestions while completing this

proposal

Page 2: Paint Spray Room Proposal

Summary

Painting is the final part of the manufacturing process, and one of the most important. UPECA Aerotech

uses a manual painting system, in which a paint gun is filled with the paint that is to be used. This paint

is then sprayed onto the manufactured part at a relatively high pressure (6 bar). The process is

conducted in a spray chamber with a controlled environment to ensure optimal conditions for effective

painting. The spray chamber was designed such that only one type of product could be sprayed at any

one time, making sudden large batches of different products a complication.

The painting process in itself is long, and involves many steps. A detailed chart of the entire process can

be seen in appendix 1, while a summary of the steps and their functions can be seen in appendix 2.

Introduction

In recent weeks, the painting team has come to the conclusion that there are insufficient paint spray

chambers to cope with the demand of manufactured parts. As such, plans have been put in place to

build an additional spray chamber to ease the burden on the existing one.

However, since the capital and maintenance costs are high, further quantitative studies were required

to make a final decision as to whether an additional spray booth would increase overall productivity and

output, or merely operate at semi-capacity.

In order to come to a final conclusion, this study was conducted from two different angles, namely;

1) Efficiency and Usage of existing Spray Booth

2) Build up process to the part spraying (i.e. Part masking efficiency)

In addition to the above, a simplified economic analysis (with the limited data available) was also

conducted to project the expected maintenance, repairing and utility costs.

Justification of selection of factors of study

1. Efficiency of Spray Chamber

All the while, the paint team believed that the lack of a second spray booth was the reason that the rate

of production was slow. As such, the testing of the existing spray booth was done to see if it was

underused, and was delaying release of finished parts to the Final Quality Control department.

2. Part Marking Efficiency

The idea behind analyzing part masking efficiency was to see whether the rate of part masking was a

contributing factor to a reduced production rate. This was studied by considering the number of staff

attending to part masking, along with the projected rise with a larger staff number.

Page 3: Paint Spray Room Proposal

Literature Review

All aircraft parts that are manufactured in UPECA Aerotech are spray painted, in accordance to the

customer’s requirement. Some parts are sprayed with just a single layer (primer coat), while most parts

are sprayed with two layers (primer and top coats). Both coats of paint have their own functions, which

are stated below;

Primer Coat- Used to cover up any scratches or discontinuity on the surface of the part. Also used to

prevent rusting and corrosion.

Top Coat- Used to ensure the part is aesthetically pleasing.

A proposal has been put in place to build a new spray chamber, so that the existing one can be used for

spraying the primer coat, while the new one can be used to spray the top coat. This is done with the

intention of reducing waiting/idle time. The proposed new spray chamber will also serve as a backup,

should the existing one breakdown or require maintenance and repair. A study of two different factors

was conducted to see if an additional spray booth will have a positive effect on the efficiency of the

spraying process.

Table 1: Gantt chart of Analysis Dates

Day (Date)

Monday (10/8/15)

Tuesday (11/8/15)

Wednesday (12/8/15)

Efficiency of Painting Process

Efficiency of Part Masking Process

This was intentionally done so that both factors could be studied individually, and then together.

Due to the limited time that I had (as my attachment in the paint department was only for 2 weeks), this

data collection exercise could only be done over three days, as opposed to a longer period of time which

would have been more desirable.

Page 4: Paint Spray Room Proposal

Data Obtained

The study was conducted, data obtained and analyzed for the day shift of three consecutive weekdays,

in order to determine the efficiency of the existing spray booth. The results and calculations are shown

in the following pages

1) Efficiency of Existing Spray Booth

The results obtained were summarized in the table below:

Table 2: Spray Chamber Usage for 10/8/15

Material Batch Number Preparation Time (Minutes)

Painting Time (Minutes)

Number of Parts

1 15 44 198 (P)

2 12 29 198 (TC)

3 8 12 2 (P)

4 4 6 2 (TC)

5 10 12 3 (P)

6 8 16 3 (TC)

Total = 57 minutes

Total = 119

Total = 406

From the table above, total usage time of paint spray chamber is 57+119 minutes = 176 minutes

We will make an assumption that the working day is 8.5 hours = 510 minutes.

Justification: Working shift is 8.15a.m. – 5.45p.m. (9hours 30 minutes)

9:30 – 0:45(Lunch) – 0.15(Rest) = 8.5 hours

Hence, usage of paint spray chamber = (176/510) x 100%

= 34.5%

Page 5: Paint Spray Room Proposal

Note: This value is NOT equal to the efficiency of the spray chamber. Efficiency in this case is defined as

(actual usage/expected usage) x 100%. Since the expected usage is about 70%, the efficiency of the

existing spray chamber = (34.5/70) x 100% = 49.3%

Efficiency for Day 1= 49.3%

Table 3: Spray Chamber Usage for 11/8

Material Batch Number Preparation Time (Minutes)

Painting Time (Minutes)

Number of Parts

1 4 17 53 (P)

2 6 27 81 (TC)

3 6 9 11 (TC)

4 2 3 30 (TC)

5 15 20 53 (TC)

6 2 8 4 (P)

7 5 21 4 (TC)

Total = 40 minutes

Total = 105

= 236

Hence, total spray chamber usage time = 40 +105 = 145 minutes

Usage = (145/510) x 100% = 28.4%

Hence, efficiency = (28.4/70) x 100%

= 40.6%

Efficiency for day 2 = 40.6%

Page 6: Paint Spray Room Proposal

Hence, average efficiency of both days = (40.6+49.3)/2

Average efficiency = 45%

Index

Preparation Time:-

1) Time taken to push the trolleys of the parts into and out of the spray chamber to and from the

flashing and oven areas

2) Time taken to mix the and stir the paint in accordance to the required ratios

3) Time taken to wear and remove PPE.

4) Time taken to load the paint into the paint gun, and rinse it after use

Painting Time:-

The actual time that the parts are being sprayed with the paint.

P- Primer layer painting

TC- Top coat layer painting

Discussion

Day 1 efficiency = 49.3%

Day 2 efficiency = 40.6%

Average efficiency = 45%

Based on the datum recorded, the above values of efficiency were calculated. The average was also

calculated as well. It was noted that the efficiency for day 2 was almost 10% lower. Possible reasons for

this include:

1) The paint department leader was not around to push the team and lead the production.

2) Another regular member of the paint staff was also not around.

3) Support staff from other departments were brought in to make up for the reduced number of

workers. These support staff are not well trained in masking, and paint preparation and could have

slowed down the production.

As a whole, it is clear that the existing spray booth is not being utilised to the maximum capacity. An

average efficiency of 45% is indicative that there is further room for growth and improvement. This

value shows that the paint spray chamber “spends” more time idle, than being used. As such, it is not

recommended that an additional spray booth is added, until the efficiency can be boosted to the desired

value (~70%).

Steps that can be taken to increase efficiency of the existing spray booth:

1) Increase the number of staff at the masking area, so that the idle time can be slashed.

Page 7: Paint Spray Room Proposal

2) Request for a chart/timetable or some other form of indication (during the daily morning meetings)

from the plating and TSA departments of the expected quantity and timing of the parts arrival (for the

day) into the paint department, so that the paint crew is able to plan and delegate in advance. This will

lead to a smoother and faster painting preparation.

Conclusion

Building an additional spray booth is a large expense over a long period of time. In addition to that, the

construction period, which is estimated at 4 months, will cause disruption to the existing paint

operation, and potentially reduce the efficiency. Furthermore, the average efficiency of the spray booth

is a mere 45%. This figure does not warrant the expenditure that will come with an additional facility. As

such, the recommended course of action would be to focus on increasing the efficiency of the existing

spray booth, rather than building a new one. However, this idea must be revisited in future, when the

efficiency of the spray booth is in the range of 70-80%.

2) Part Masking Efficiency

Table 4: Part Masking for 11/8

Material Batch Number Duration (Minutes)

Number of Parts Marked

1 26 12

2 102 36

3 16 4

4 44 16

5 71 36

6 34 27

7 60 15

8 12 4

9 89 26

Total = 9 Batches

Total = 454 minutes

Total = 176 Parts

Page 8: Paint Spray Room Proposal

For the table above, it was thus calculated that the average time to mask 1 part as 2.6 minutes (454

minutes/176 parts). 5 staff members were present on 11/8.

Assuming that the total number of parts were the same, the following table was calculated and drawn. It

is obvious that a larger number of staff would lead to a lower total time for part masking. Ballpark

figures of 10%, 15% and 20% time reductions were used for 6 staff members, while 20%, 25% and 30%

reductions were considered for 7 staff members.

For the calculations that follow, the initial figure of 176 parts was retained as the total number of parts

masked over the course of the day. 454 minutes was also used as the total time spent on the masking

process.

Table 5: Predicted reductions in average time for 6 and 7 staff members respectively

5 Staff 6 staff 7 staff

Average number of parts marked per staff 35.2 29.33333 25.14286

Total time spent (Minutes) 454 N/A N/A

Actual time spent with percentage reduction in time (Minutes)

10% (20% for 7 staff) N/A 408.6 363.2

15% (25% for 7 staff) N/A 385.9 340.5

20% (30% for 7 staff) N/A 363.2 317.8

Average time per worker (Minutes)

10% (20% for 7 staff) N/A 68.1 51.88571

15% (25% for 7 staff) N/A 64.31667 48.64286

20% (30% for 7 staff) N/A 60.53333 45.4

Average Time per part (Minutes)

10% (20% for 7 staff) N/A 2.321591 2.063636

15% (25% for 7 staff) N/A 2.192614 1.934659

20% (30% for 7 staff) N/A 2.063636 1.805682

It is expected that the reduction in time will be 15% for 6 staff, and 25% for 7 staff.

Hence, the percentage reduction in time can be calculated as follows;

Page 9: Paint Spray Room Proposal

Table 6: Percentage reduction in average time per part for 11/8

Number of staff 5 6 7

Average Time Per Piece (Minutes)

2.6 2.2 1.9

Percentage reduction from original (%)

0 15.4 26.9

This translates to a 15.4% increase in efficiency for one additional member of staff, but a 26.9% increase

in efficiency for two additional members of staff.

Table 7: Park Masking for 12/8

Material Batch Number Duration (Minutes)

Number of Parts Marked

1 21 9

2 3 2

3 47 27

4 44 8

5 17 8

6 23 9

7 75 30

8 21 8

9 40 15

10 100 32

Total = 10 batches

Total = 391 minutes

Total = 148 parts

Page 10: Paint Spray Room Proposal

From the table, the average time to mask a single part was found to be = 2.6 minutes. 5 staff members

were present on 12/8.

The following table was then drawn, using similar calculation methods to those in table 5.

The calculated figure of 148 parts was retained as the total number of parts masked over the course of

the day. 391 minutes was also used as the total time spent on the masking process.

Table 8: Predicted reductions in average time for 6 and 7 staff members respectively

5 Staff 6 staff 7 staff

Average number of parts marked per staff 29.6 24.66667 21.14286

Total time spent (minutes) 391 N/A N/A

Actual time spent with percentage reduction in time (Minutes)

10% (20% for 7 staff) N/A 351.9 312.8

15% (25% for 7 staff) N/A 332.35 293.25

20% (30% for 7 staff) N/A 312.8 273.7

Average time per worker (Minutes)

10% (20% for 7 staff) N/A 58.65 44.68571

15% (25% for 7 staff) N/A 55.39167 41.89286

20% (30% for 7 staff) N/A 52.13333 39.1

Average Time per part (Minutes)

10% (20% for 7 staff) N/A 2.377703 2.113514

15% (25% for 7 staff) N/A 2.245608 1.981419

20% (30% for 7 staff) N/A 2.113514 1.849324

Similarly, it is expected that the reduction in time will be 15% for 6 staff, and 25% for 7 staff.

Hence, the percentage reduction in time can be calculated as follows;

Page 11: Paint Spray Room Proposal

Table 9: Percentage reduction in average time per part for 12/8

Number of staff 5 6 7

Average Time Per Piece (Minutes)

2.6 2.2 2.0

Percentage Reduction from Original (%)

0 15.4 23.1

This translates to a 15.4% increase in efficiency for one additional member of staff, but a 23.1% increase

in efficiency if two members of staff were to be added.

Discussion

The information obtained from both the days can be averaged and summarised into the table below;

Table10: Average reduction over 11/8 and 12/8

Number of staff 5 6 7

Average Time Per Piece (Minutes)

2.6 2.2 2.0

Percentage Reduction from Original (%)

0 15.4 25.0

The above table reads that one additional staff member into the paint department can increase the

efficiency by 15.4%, while two additional staff will increase it by 25.0%. This in turn will reduce the

masking and preparation time, before the parts are sprayed in the spray booth. Consequently, the idle

time of the spray booth (shown earlier to be around 4.7 hours per shift) can be cut.

Furthermore, an addition of a staff member will reduce the average time per piece by about 0.4 minutes

(24 seconds). Over 180 pieces, the daily average, that is a total of 1.8 man hours saved daily. Hence, it

can be said that the advantages of getting additional staff are:

1) Reduced man hours spent on masking. These saved hours can then be used in other activities within

the paint department, or event to support other divisions in production.

Page 12: Paint Spray Room Proposal

2) Enhanced efficiency of the spray chamber. An additional staff member will be able to reduce the idle

time of the spray chamber. It is hoped that an additional staff member will be able to reduce the idle

time of the spray chamber by 10-15% (to 3.7 hours). This in turn will increase the efficiency of the spray

booth to 56%.

Conclusion

The above calculations are an indication that the lack of a spray booth is not the reason for the delay,

but rather the slow delivery of the masking section to the spraying section. Hence, an investment on a

spray booth is not necessary, as the overall efficiency will not be boosted. However, it is recommended

that one additional member of staff be commissioned to join the masking division of the paint

department so that the average time can be reduced.

The cost of adding two members of staff will be 2x the cost of adding a single member. In order for this

investment to be warranted, the increase in efficiency for two additional members should be no less

than 30.8% (2x of 15.4%). Since the projected increase will only be 25%, it is suggested to add a single

member of staff.

One possible reason that the efficiency does not increase linearly with the staff count is saturation of

the work space. Beyond a certain number, no addition of further staff will lead to any increase in

productivity of the department. While this actual number is unknown, it is believed that seven members

of staff (5 original + 2 additions) would be approaching saturation. This would explain the gradual

decrease in efficiency rise.

Upon the addition of this new member of staff, this study should be redone in no less than 15 months (3

months to allow for training, and 12 months to allow for optimal performance). Then, a similar study will

reveal if there is a need for an additional spray booth.

3. Economic Analysis

A simple economic analysis was conducted. The first step was to review the costing of part

repair/changes for the years 2012-2014.

Table 11: Spray Booth Part Replacement Cost

Year 2012 2013 2014

Total Part Replacement Cost (RM)

2774.8 12050 14685

Increase from Previous Year (%)

N/A 334.3 21.9

Page 13: Paint Spray Room Proposal

From this table, it is shown that the amount being spent on part replacement is increasing yearly. There

was a three-fold increase from 2012-2013 and this coincides with increasing usage of the spray booth. A

greater usage will lead to greater wear and tear, and consequently higher repair fees. It is predicted that

the costing (and usage) will increase by 15% for 2015, and a further 20% for 2016.

Table12: Forecasted Increase in Repair Costs

Year 2014 2015 2016

Total Part Replacement Cost (RM)

14685 16887.8 20265.4

Increase from Previous Year (%)

21.9 15 20

The above values do not incorporate the annual servicing fee, which is a contract signed every

December. The servicing fee for 2014 and 2015 are shown below, together with the forecasted fee for

2016.

Table13: Annual Servicing Fee

Year 2014 2015 2016

Total Annual Servicing Fee (RM)

12600 12600 12600

Number of Services 6 6 6

In addition to that, a new spray booth will also require additional utilities (electricity). The total electrical

cost (with the inclusion of GST) for the factory for the months of May, June and July 2015 were

summarised in following table;

Forecasted Values

Page 14: Paint Spray Room Proposal

Table14: Electrical Bill for May-July 2015

This figure represents the electrical cost for the offices, the machining department, the Special

Processes Division and the Quality Control centers. As such, it was approximated that the paint

department (spray chamber) used about 10% of the total electrical consumption.

Justification

The spray booth has 4 main sources of power; lights, suction fan, air conditioning system and an air

pump. The fan, lights and air conditioners are switched on 24 hours a day, while the air pump is only

used when parts are being sprayed. Hence, it was jointly assumed that the spray booth would account

for 10% of the total electrical consumption.

10% of 1,412,687 KWh/KW = 141,268.7 KWh/KW.

Hence, the electrical bill for the spray booth for May-July = 10% of Rm568,563.9

= Rm56,856.4 over that period.

Assuming uniform usage over the year, the total electrical cost for the spray chamber

= Rm56,856.4 x 4

= Rm227425.6

Hence, we will make an assumption that the total electrical cost for a new spray booth for the year 2016

= Rm22745.6

Additional charges for environmental inspection will be Rm900 per year.

Month

Electrical Power (KWh/KW)

Cost (RM)

May 460,916 186,612.7

June 461,798 186,839.5

July 489,973 195,111.8

1,412,687 568,563.9

Page 15: Paint Spray Room Proposal

In total, the expected annual operational costs for 2016-2018, for a new spray booth, are shown below;

Table15: Expected Operational Costs for 2016-2018

Year 2016 2017 2018

Total Operational Costs (RM)

56,511 58,206

59,952

Hence, with an expected capital cost of Rm1.2mil, the total expenditure on an additional spray booth

from 2016-2020

= 1.2mil + 56,511 + 58,206 + 59,952 + 61751 + 63604 =Rm1.5 mil

Table17: Total Working Time and Sales

Year 2013 2014 2015 2016 2017

Total Working Time (Hours)

409278 711074 809342

971210.4

1116892

Increase from previous year (%)

N/A 174 114 120 115

Total Sales (mil RM)

68 75 85 110 150

Increase from previous year (%)

N/A 9.3 11.8 29.4 36.4

Average Sales per Unit Time (Rm/Hr)

166.1 105.5 105 113.3 134.3

From the calculations in tables 2&3, it can be found that the amount of time that can be saved per day

shift by the addition of a new spray booth averages out to 75 minutes (= 1.25 hours)

Values extrapolated from

existing data and forecasts

Page 16: Paint Spray Room Proposal

Assuming that the night shift shares the same efficiency, total daily time saved = 2.5 hours.

Over 365 days, total hours saved = 913 hours

Based on the average value of one working hour for the years 2016-2020, the total value gained over

one year for a new spray booth

= 913 hours saved x Rm135/hour

= Rm 123255

And hence, over 5 years

= Rm 123255 x 5

= Rm 616275

Return of Investment

= 616275/1.5mil

= 41.1%

Addition of new staff

Based on the values calculated in table 17, it was found out that 1 working hour averages out to Rm135

earned in sales.

Based on table 10, an additional staff will reduce the part mart masking time by 0.4 minutes each. If the

daily average number of parts is 162 (tables 7&4), the total time saved in a day

= 162 x 0.4

= 64.8 minutes.

In a year

= 23652 minutes

In 5 years

= 118260 minutes

= 1971 hours

= Rm 266085 saved

Assuming that a factory worker’s average monthly salary over 5 years is Rm2500 (the actual figure

wasn’t given to me), the R.O.I

= 266085/150000

= 177%

Assuming no other changes

elsewhere, payback period for new

spray chamber (based on method of

calculation) = 12.5 years

Page 17: Paint Spray Room Proposal

Discussion

The various tables and calculations in the previous pages display 3 important pieces of information:

1) The efficiency of the existing spray booth (45%)

2) The potential increase in masking efficiency with additional staff (15.4%)

3) The predicted expenditure to construct and maintain a new spray booth (Rm1.5mil)

Based on all this information, there are several conclusions that we can draw;

1. There is insufficient need to construct a new spray booth

The calculations show that the actual usage of the current spray booth is only 34%. This means that it is

only used one-third of the time. An additional spray booth will not increase the usage, but in fact cause

a division in usage to further reduce the efficiency.

Recommendation: Do not build a new spray booth

2. The part masking department is under-staffed

On average, a single part will take 2.6 minutes to mask. This value can be reduced by 15.4% with an

additional staff, to 2.3 minutes. A higher masking rate will directly lead to a higher painting rate, and

greater usage of the spray booth. An additional staff investment will have a R.O.I of 177%

Recommendation: Commission a new staff to join the paint masking team

3. R.O.I for new spray machine = 41% over 5 years.

Utilities, maintenance, repair and construction costs, along with a growth rate of 3% were factored into

this calculation. Since, the economics do not add up, and the need is not there, there is no need to build

a new spray machine

Recommendation: Do not build a new spray machine