Pascua Yaqui Tribe DOE Solar Energy Feasibility and Deployment Study Pascua Yaqui Tribe/DOE Solar Feasibility & Deployment

Upload: others

Post on 05-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Pascua Yaqui Tribe - Energy.gov...Pascua Yaqui Tribe The reservation is located in Tucson, Arizona Reservation population approximately 4,000 Total tribal enrollment 18,000This study

Pascua Yaqui Tribe

DOE Solar Energy Feasibility and Deployment Study

Pascua Yaqui Tribe/DOE Solar Feasibility & Deployment

Page 2: Pascua Yaqui Tribe - Energy.gov...Pascua Yaqui Tribe The reservation is located in Tucson, Arizona Reservation population approximately 4,000 Total tribal enrollment 18,000This study

Pascua Yaqui Tribe

The reservation is located in Tucson, Arizona

Reservation population approximately 4,000

Total tribal enrollment 18,000

Pascua Yaqui Tribe/DOE Solar Feasibility & Deployment

Page 3: Pascua Yaqui Tribe - Energy.gov...Pascua Yaqui Tribe The reservation is located in Tucson, Arizona Reservation population approximately 4,000 Total tribal enrollment 18,000This study

History

Pascua Yaqui Tribe/DOE Solar Feasibility & Deployment

In 1978, the Pascua Yaqui Tribe of Arizona became federally recognized and in 1994 the designation was converted to that of a historical tribe. Today, Pascua Pueblo consists of 1,820 acres of trust land with an additional 436.18 acres of fee land surrounding the reservation.

The Tribe also owns Tortuga Ranch, fee land of 6,455.59 acres west of Tucson.

Page 4: Pascua Yaqui Tribe - Energy.gov...Pascua Yaqui Tribe The reservation is located in Tucson, Arizona Reservation population approximately 4,000 Total tribal enrollment 18,000This study

Feasibility & Deployment Study

This study was initiated in 2013

Red Mountain Energy Partners were hired to complete study

Pascua Yaqui Tribe/DOE Solar Feasibility & Deployment

Page 5: Pascua Yaqui Tribe - Energy.gov...Pascua Yaqui Tribe The reservation is located in Tucson, Arizona Reservation population approximately 4,000 Total tribal enrollment 18,000This study

Project Area

Sites evaluated for solar energy were: Tortuga Ranch Casino del Sol Tribal Administrative buildings

Pascua Yaqui Tribe/DOE Solar Feasibility & Deployment

Page 6: Pascua Yaqui Tribe - Energy.gov...Pascua Yaqui Tribe The reservation is located in Tucson, Arizona Reservation population approximately 4,000 Total tribal enrollment 18,000This study

Casino del Sol

Pascua Yaqui Tribe/DOE Solar Feasibility & Deployment

Page 7: Pascua Yaqui Tribe - Energy.gov...Pascua Yaqui Tribe The reservation is located in Tucson, Arizona Reservation population approximately 4,000 Total tribal enrollment 18,000This study

Casino Parking Lot

Pascua Yaqui Tribe/DOE Solar Feasibility & Deployment

Page 8: Pascua Yaqui Tribe - Energy.gov...Pascua Yaqui Tribe The reservation is located in Tucson, Arizona Reservation population approximately 4,000 Total tribal enrollment 18,000This study

PYT Reservation & Tortuga Ranch

Pascua Yaqui Tribe/DOE Solar Feasibility & Deployment

Page 9: Pascua Yaqui Tribe - Energy.gov...Pascua Yaqui Tribe The reservation is located in Tucson, Arizona Reservation population approximately 4,000 Total tribal enrollment 18,000This study

Pascua Yaqui Tribe/DOE Solar Feasibility & Deployment

Page 10: Pascua Yaqui Tribe - Energy.gov...Pascua Yaqui Tribe The reservation is located in Tucson, Arizona Reservation population approximately 4,000 Total tribal enrollment 18,000This study

DOE START Grant Strategic Technical Assistance Response Team Grant,

November 2012 Three day facilitated community workshop NREL

Developed an Strategic Plan to guide the development of a Tribal Energy Plan

Pascua Yaqui Tribe/DOE Solar Feasibility & Deployment

Page 11: Pascua Yaqui Tribe - Energy.gov...Pascua Yaqui Tribe The reservation is located in Tucson, Arizona Reservation population approximately 4,000 Total tribal enrollment 18,000This study

Planning Process

Looked at past accomplishments, current issues, and future goals of the tribe

Created a vision for future energy development, year 2023

Created an Energy Task force to help drive future energy projects

Pascua Yaqui Tribe/DOE Solar Feasibility & Deployment

Page 12: Pascua Yaqui Tribe - Energy.gov...Pascua Yaqui Tribe The reservation is located in Tucson, Arizona Reservation population approximately 4,000 Total tribal enrollment 18,000This study

Energy Plan

Comprehensive energy plan to include the following in regards to future development:

Energy conservation Alternative energy Energy related building codes Increase energy self-sufficiency

Pascua Yaqui Tribe/DOE Solar Feasibility & Deployment

Page 13: Pascua Yaqui Tribe - Energy.gov...Pascua Yaqui Tribe The reservation is located in Tucson, Arizona Reservation population approximately 4,000 Total tribal enrollment 18,000This study

TA Outcomes Provided a framework for addressing future energy projects

NREL staff provided specific technical data and resources

Established partners and key players in the development of future energy projects: staff (government & casino), local energy provider (TRICO),community leaders, tribal council

Community focus group developed strategies to present future energy projects to the community and to Tribal Council

Pascua Yaqui Tribe/DOE Solar Feasibility & Deployment

Page 14: Pascua Yaqui Tribe - Energy.gov...Pascua Yaqui Tribe The reservation is located in Tucson, Arizona Reservation population approximately 4,000 Total tribal enrollment 18,000This study

Community Input

Approximately 100 surveys were completed by community members demonstrating overwhelming community support for alternative energy projects

Pascua Yaqui Tribe/DOE Solar Feasibility & Deployment

Page 15: Pascua Yaqui Tribe - Energy.gov...Pascua Yaqui Tribe The reservation is located in Tucson, Arizona Reservation population approximately 4,000 Total tribal enrollment 18,000This study

Results of Study

Red Mountain’s study provides useful information on identified sites for solar development including:

Potential production Estimated cost Energy users, Tribe or other

Pascua Yaqui Tribe/DOE Solar Feasibility & Deployment

Page 16: Pascua Yaqui Tribe - Energy.gov...Pascua Yaqui Tribe The reservation is located in Tucson, Arizona Reservation population approximately 4,000 Total tribal enrollment 18,000This study

Lessons Learned

Solar is becoming more affordable

Most feasible projects would produce energy to offset current energy usage by tribal government or enterprises

Solar projects may need to be phased in

Pascua Yaqui Tribe/DOE Solar Feasibility & Deployment

Page 17: Pascua Yaqui Tribe - Energy.gov...Pascua Yaqui Tribe The reservation is located in Tucson, Arizona Reservation population approximately 4,000 Total tribal enrollment 18,000This study

Next Steps Currently working to gather more information from local

contractors and solar energy developers to present energy opportunities to tribal council and develop an RFP

Convening a sector strategy meeting in April to promote further alternative energy development in the region

Pascua Yaqui Tribe/DOE Solar Feasibility & Deployment

Page 18: Pascua Yaqui Tribe - Energy.gov...Pascua Yaqui Tribe The reservation is located in Tucson, Arizona Reservation population approximately 4,000 Total tribal enrollment 18,000This study

Acknowledgments

Thank you to DOE for providing the resources to make this study possible.

Thanks to: NREL Red Mountain Energy Partners Kabotie Consulting For support and collaboration

Pascua Yaqui Tribe/DOE Solar Feasibility & Deployment

Page 19: Pascua Yaqui Tribe - Energy.gov...Pascua Yaqui Tribe The reservation is located in Tucson, Arizona Reservation population approximately 4,000 Total tribal enrollment 18,000This study

Questions?

Maria Arvayo

Community & Economic Development Services Director

Pascua Yaqui Tribe

Tucson, AZ

[email protected]

520-879-6316

Pascua Yaqui Tribe/DOE Solar Feasibility & Deployment