pelamis joint system test

Upload: metin-mehel

Post on 01-Jun-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/9/2019 Pelamis Joint System Test

    1/49

     

    PELAMIS WEC – FULL-SCALE

    JOINT SYSTEM TEST 

    V/06/00191/00/00/REPDTI URN 03/1435

    ContractorOcean Power Delivery Ltd. 

    Prepared by Dr. Richard Yemm 

    The work described in this report was carried

    out under contract as part of the DTI New

    and Renewable Energy Programme, which is

    managed by Future Energy Solutions. Theviews and judgements expressed in this

    report are those of the contractor and do not

    necessarily reflect those of the DTI or Future

    Energy Solutions.

    First Published 2003© Crown Copyright 2003 

  • 8/9/2019 Pelamis Joint System Test

    2/49

     I  

    EXECUTIVE SUMMARY

    INTRODUCTION & BACKGROUND

    The Pelamis Wave energy Converter (WEC) is an innovative concept for extracting

    energy from ocean waves and converting it into a useful product such as electricity,direct hydraulic pressure or potable water. The system is a semi-submerged,

    articulated structure composed of cylindrical sections linked by hinged joints. The

    wave-induced motion of these joints is resisted by hydraulic rams that pump high-

     pressure oil through hydraulic motors via smoothing accumulators. The hydraulic

    motors drive electrical generators to produce electricity. The complete machine isflexibly moored so as to swing head-on to the incoming waves and derives its

    'reference' from spanning successive wave crests.

    OPD has systematically tackled design of the first full-scale machine through a

    rigorous RD&D programme including concept development, extensive numerical and

    experimental work, demonstration of the whole machine concept at 7th scale (through project Reference V/06/00188), preparation of several full machine designs, and a

    thorough analysis of the initial and future economics of the system. The programme

    reported here has extended this to integrated testing of all key components at full-

    scale using a fully functional joint test rig in the laboratory.

    The programme reported here met its key objectives, and is seen as a major step inreducing the technical risk of the programme. It paves the way for the first full-scale

     prototype machine, and onward optimisation of the performance and reliability of the

    entire system.

    PROJECT OBJECTIVES

    The project had the following key objectives:

    1. Build and test a full-scale Pelamis WEC two-axis joint system

    2. Confirm functionality of active and passive ('failsafe') joint control modes3. Confirm functionality of power conversion and electrical systems

    4. Determine pressure drops through all hydraulic flow paths to ensure inlet

    cavitation and local overpressure are avoided

    5. Confirm the thermal stability of the system for of normal and failed operating

    conditions6. Determine full-cycle conversion efficiency of the complete system at a range

    of mean power levels

    7. Conduct a three-month cycle test to increase confidence in reliability beforethe first offshore test

    8. Confirm suitability of the chosen hydraulic fluid9. Preliminary assessment of static and dynamic seal performance and likely

    service life.

    10. Preliminary assessment of the suitability of the proposed prototype structure

    11. Assess space and accessibility of components and demonstrate procedures for

    installation and removal of system components

    12. Assess health and safety issues for work on the full-scale system

  • 8/9/2019 Pelamis Joint System Test

    3/49

     II  

    13. Allow the OPD team to work closely with prospective full-scale contractorsand to gain experience of assembling, testing, operating and maintaining the

    full joint system

    SUMMARY OF THE WORK PROGRAMME

    A full-scale two-axis joint system was built, commissioned and tested. A general

    view of the rig is shown below.

    The rig comprises

    1. A fully functional joint module unit (housing all the systems for two joint

    axes)2. Two pairs of external actuation rams with 500kW hydraulic actuation power

     packs3. Two end frames to couple the actuation rams to the internal systems

    4. A purpose built test facility with a full set of electrical, control and monitoring

    equipment.

    The rig was built and commissioned over an intensive 8 month period, using most ofthe OPD’s engineering resources.

    Work was split into the following six main work packages:

    Work Package (a) – Final design of all rig components. Adapting the joint moduledesign to include attachment points for the external actuation

    system, and specification/design of all elements of ancillary

    equipment.

    Work Package (b) – Rig build, including set up of the test facility and infrastructure.

    Also included a critical assessment of packaging, space,accessibility and health and safety issues before and after build.

    Heave actuation

    ram (1 of 2)

    Joint module

    structure

    Sway actuation

    ram (1 of 2)

    Floor stand

    End frame

    Main bearing

  • 8/9/2019 Pelamis Joint System Test

    4/49

     III  

    Work Package (c) – Commissioning of the complete facility and test rig

    Work Package (d) – Functionality test programme to confirm that all systems were

    working to specification, including an initial inspection

     programme to confirm any component failures.

    Work Package (e) – An extended cycle test programme to improve confidence in

    the reliability and longevity of the system.

    Work Package (f) – A detailed inspection programme following the cycle test toassess likely long term wear-rates and reliability.

    This work programme was completed, the key results are reported below.

    KEY CONCLUSIONS

    The following overall project conclusions have been drawn:

    1. A full-scale, two-axis joint module system has been successfully built,

    commissioned and tested in the laboratory. The unit is representative of thefull-scale prototype specification and design, and where possible uses

    components identical to those specified for the full-scale prototype machine.2. Actuating the system posed a number of technical challenges. The system

    chosen was a pair of large closed circuit hydraulic systems. These generally

     performed satisfactorily though at high operating pressures problems were

    encountered with limited drive rigidity due to compressibility of the oil and

    ‘stretchiness’ of the hoses. However, it is not felt that this significantly

    compromised the tests.

    3. All rig systems were proven to function satisfactorily, and in line with

     predictions.4. Active and passive control modes were demonstrated, though active

    algorithms had to be modified at elevated pressures to address the issuesrelating to drive rigidity.

    5. Pressure drops and flow losses through the system were proven to be similar

    or less than predicted. It is estimated that generally flow losses will be less

    that 1-2%.

    6. It has been confirmed that cavitation at the inlets to the ram chambers will not be a problem. Pressure drops on inlet were estimated to be less than 1 bar at

     peak flow-rates – significantly less than anticipated. The positive result of this

    is that a lower reservoir pre-charge is required, this will prolong the life ofstatic and dynamic seals.

    7. Oil cooling provided was found to be adequate. However, estimation of thethermal stability of the module as a whole was not practical. Despite this it is

    not felt that there will be a problem in this regard.

    8. The measured conversion efficiency was 75-85% across the range of power

    levels. This is in line with predictions. It is essential for the economics of the

    system that the captured primary energy is converted efficiently. The

    achieved conversion efficiency is seen as adequate for initial commercial

  • 8/9/2019 Pelamis Joint System Test

    5/49

     IV  

    machines though there are several avenues to improve performance – thesewill be actively pursued in the onward programme.

    9. The rig was cycle tested for a period of one and a half months. This was lessthat the three months originally envisaged. It was felt that the best use of the

    rig was testing and commissioning actual components and sub-systems for the

    full-scale machine. However, it is felt that sufficient testing was carried out tomeet the objectives of the programme.

    10. There is nothing to indicate that the biodegradable oil chosen is not suitable as

    a working fluid. However, only extended testing in the full-scale prototype

    and subsequent machines will determine any long term issues.

    11. Static and dynamic seal performance was generally shown to be satisfactory.The only issues arising were the front rod seals on the rams, and a damaged

    static seal on one of the system valves. I was concluded that neither of thesewas serious, and that both were probably caused by external factors.

    However, long-term performance will only become apparent through extended

    testing in the real environment.

    12. It was concluded that the structural configuration chosen for the joint moduleis satisfactory, there are no signs of cracking or yielding of the rig structure. It

    was not possible to directly confirm suitability of structural components due to

    the more severe load regime of the test rig.

    13. Experience gained with the test rig regarding packaging, installation ofcomponents, accessibility and general health and safety issues has been

    invaluable for the detailed design of the full-scale prototype. The layout andinstallation procedures have been fully revised for the prototype machine.

    14. The rig has provided invaluable experience working with full-scale

    components and systems, and with assessing and working with the intended

    suppliers for the full-scale machine.

    15. Overall, the project is seen as a major success – it has certainly achieved its

     primary objective of significantly reducing the technical risk of the onward

     programme.

  • 8/9/2019 Pelamis Joint System Test

    6/49

    V  

    TABLE OF CONTENTS

    EXECUTIVE SUMMARY I

    TABLE OF CONTENTS V

    1. INTRODUCTION…………………………………………………….. 1

    1.1 Background 1

    1.2 Scope of Work 2

    1.3 This report 3

    2. TEST RIG SPECIFICATION & DESIGN…………………………. 42.1 Joint system concept 4

    2.2 General specification 6

    2.3 Structure 8

    2.4 Actuation system 102.5 Power conversion system 11

    2.6 Test facility 15

    3. TEST & INSPECTION PROGRAMME…………………………….. 163.1 Commissioning Tests 16

    3.2 Functionality Tests 183.2.1 Primary power take-off 18

    3.2.2 Power conversion system 22

    3.3 Cycle Testing 25

    3.3.1 Details of test programme 25

    3.3.2 Anticipated future testing 26

    3.3.2 Other cycle testing 26

    3.4 Inspection Activities 28

    3.4.1 Structure 283.4.2 Hydraulic rams 28

    3.4.3 Accumulators & reservoirs 323.4.4 System valves 33

    3.4.5 Hoses & fittings 33

    3.4.6 Motors & generators 35

    3.4.7 Oil quality 35

    4. ONWARD DEVELOPMENT CONSIDERATIONS……………....... 37 4.1 General & structure 37

    4.2 Power take-off system 374.3 Electrical & control systems 40

    4.4 Conclusions 40

    5. OVERALL PROJECT CONCLUSIONS………………………..….. 41

    6. REFERENCES………………………………………………………… 43

  • 8/9/2019 Pelamis Joint System Test

    7/49

     Page 1 

    1. INTRODUCTION 

    1.1 BACKGROUND

    Ocean Power Delivery Ltd (OPD) has been actively developing the Pelamis WEC

    concept since January 1998.

    The Pelamis WEC is a semi-submerged, articulated structure composed of cylindrical

    sections linked by hinged joints (Figure 1.1). The wave-induced motion of these joints

    is resisted by hydraulic rams which pump high pressure fluid through hydraulic

    motors via smoothing accumulators. The hydraulic motors drive electrical generatorsto produce electricity. The complete device is flexibly moored so as to swing head-on

    to the incoming waves and derives its 'reference' from spanning successive wavecrests.

    Figure 1.1 – Artists impression of a Pelamis WEC wave-farm

    A novel joint configuration is used to induce a tuneable cross-coupled resonant

    response that greatly increases power capture in small seas. Control of the restraint

    applied to the joints allows the resonant response to be 'turned-up' in small seas wherecapture efficiency must be maximised or 'turned-down' to limit loads and motions in

    survival conditions. Electrical power from the joints is fed down a single umbilical

    cable to a junction on the seabed. Several machines can be connected together and

    linked to shore through a single seabed cable.

    The core theme of the Pelamis concept is survivability. The fundamental survivability

    mechanisms employed are the use of length as the source of reaction (to allow the

    system to de-reference in long storm waves) in conjunction with a finite diameter toinduce full submergence and emergence in large, steep waves, thereby limiting loads

  • 8/9/2019 Pelamis Joint System Test

    8/49

     Page 2 

    and motions. The system is slack moored and does not use mooring reaction in orderto absorb power. The moorings have a motion envelope large enough to

    accommodate extreme wave motions in addition to the low frequency wave-groupinduced response.

    As part of the overall RD&D programme, OPD has previously been supported by theDTI Sustainable Energy Programme under grants V/06/00181 (to conclude primary

    R&D considerations) and V/06/00188 (to demonstrate the Pelamis WEC concept at

    intermediate scale). The former project looked at various aspects of the design and

    consolidated previous work on small-scale wave-tank models. The latter developed a

    1/7th

     scale, full-systems model which included fully functional hydraulics and controlsystems. This successfully demonstrated the whole machine concept in real-sea

    conditions.

    From the outset OPD has been committed to a responsible, staged development

     programme to systematically tackle all major elements of technical risk before

    committing to a full-scale prototype. A complex electro-hydraulic system such as thePelamis WEC joint unit would not, for example, be cleared for service in the

    aerospace or offshore industries without extensive dry-land tests. OPD feels that

    wave energy systems should be treated in the same way.

    Consequently, the purpose of this project has been to design, build and test a full-scale

    model of the Pelamis joint system, with the aim of improving understanding of thesystem’s function, performance and control, and to further reduce the technical risk of

    the Pelamis WEC full-scale prototype programme.

    1.2 SCOPE OF WORK

    The project’s main tasks were as follows:

    1. Build and test a full-scale Pelamis WEC joint system2. Confirm functionality of active and passive ('failsafe') joint control modes

    3. Confirm functionality of power conversion and electrical systems4. Determine pressure drops through all hydraulic flow paths to ensure inlet

    cavitation and local overpressure are avoided

    5. Confirm the thermal stability of the system for of normal and failed operating

    conditions

    6. Determine full-cycle conversion efficiency of the complete system at a rangeof mean power levels

    7. Conduct a three-month cycle test to increase confidence in reliability before

    the first offshore test8. Confirm suitability of the chosen hydraulic fluid

    9. Preliminary assessment of static and dynamic seal performance and likelyservice life.

    10. Preliminary assessment of the suitability of the proposed prototype structure

    11. Assess space and accessibility of components and demonstrate procedures for

    installation and removal of system components

    12. Assess health and safety issues for work on the full-scale system

  • 8/9/2019 Pelamis Joint System Test

    9/49

     Page 3 

    13. Allow the OPD team to work closely with prospective full-scale contractorsand to gain experience of assembling, testing, operating and maintaining the

    full joint system

    At the outset of the project, it was planned to base the rig on a simplified version of

    the full-scale joint that would mainly allow testing of the system components.However, in parallel with advancements to the power take-off design, it was realised

    that testing the complete, dual-axis system would be of greater benefit, giving greater

    confidence in the structure, mounting hardware, access, operability, maintainability,

    thermal stability and safety of the joint system. Although it was recognised that a

    dual-axis rig would be more expensive, the extra cost was considered well-justified onthe grounds of increased test realism and scope. The project therefore proceeded on

    this basis.

    1.3 THIS REPORT 

    This report summarises all aspects of work carried out under the project. The main body is set out as follows:

    Section 2: A general description of the full-scale joint rig and test facility

    specification, configuration, and design.

    Section 3: A description and discussion of the test and inspection programmeincluding commissioning, functionality, and cycle testing.

    Section 4: A discussion of onward development consideration.

    Section 5: Project conclusions

  • 8/9/2019 Pelamis Joint System Test

    10/49

     Page 4 

    2. TEST RIG SPECIFICATION & DESIGN

    2.1 JOINT SYSTEM CONCEPT

    The Pelamis WEC power take-off system design underwent a major revision at the

    end of 2001. Each joint between adjacent units was formerly of a conventionaluniversal joint configuration with a 'spider' linking the main tube elements (Figure

    2.1). Opposing hydraulic rams mounted in the ends of each tube acted on the spider

    to restrain the joint about its two axes. Bellows seals were used to prevent water

    ingress as the ram exits, while the main bearings were water lubricated.

    Figure 2.1 – Old Pelamis joint configuration

    The revised configuration houses all of the systems for both joint axes within an

    elongated universal joint spider, as shown in Figure 2.2. Consequently, all of the

    complex power conversion components are contained in a single, compact space.

    This has the advantages of:

    • Allowing the system to be fully assembled and tested before movement to the

    intended launch site.

    • Minimising final assembly and commissioning operations at the launch site.

    • Separating the main structural and power take-off elements. The ‘high-tech’

     joint module can be manufactured centrally, while the ‘low-tech’ main tubes

    could be fabricated close to launch sites. This is beneficial from thecommercial perspectives of IPR protection and export sales. In this context,

    the 'joint-module' is analogous to the nacelle of a wind-turbine.

    The new configuration also has a number of significant technical advantages over the

     previous layout, some of which are summarised below.

    • All of the power take-off and conversion systems are now in one place

    allowing the heave and sway hydraulic systems to be linked. This reduces the

    total accumulator volume required to generate smooth power across the full

    range of wave conditions.

    • Two generators are retained to allow one to be run at part load. Thisdramatically improves efficiency at power levels less that 50% of rated, gives

  • 8/9/2019 Pelamis Joint System Test

    11/49

     Page 5 

    a level of redundancy in the event of partial failure, and increases the servicelife of the bearings and hydraulic motors.

    • The hydraulic circuits are designed to split into two independent systems in

    the event of failure. One heave and one sway ram are on each half of the split

    system, allowing joint restraint to be maintained even in the event of complete

    failure of the other half of the system. A good analogy for this is dual circuit braking on cars.

    Figure 2.2 – Joint-module configuration (ram seals not shown)

    • All bearings are now internal to either the joint-module or the main tube ends,

    thus allowing bearing pins to be removed for inspection without surface divers

    or water ingress.• The main bearings are now dry, sealed with ‘O’rings.

    • The structural duty of the joint-module is low as all major bending loads between the main tubes to pass through the hydraulic rams.

    A result of this change in configuration was that, to be a representative test, the full-scale joint test rig must be a full 2 degree-of-freedom unit, rather than the single axis

    unit originally proposed (Figure 2.3).

    Figure 2.3 - Single axis test rig as originally proposed

  • 8/9/2019 Pelamis Joint System Test

    12/49

     Page 6  

    2.2 GENERAL SPECIFICATION

    The dual-axis test rig configuration is shown in Figure 2.4. Two sets of actuationrams are mounted outside the module to simulate wave action and drive the internal

    systems. The main tube elements are replaced with rigid, triangulated open truss

    structures on each end of the rig to couple the drive and power take-off rams.

    Figure 2.4 – Test rig configuration as built

    For meaningful tests the system must be able to run both joint axes up to full rated

    moment, angle and power. In addition it was important to ensure that the inlet valves

    to the rams would not cavitate at extreme angular velocities. The system was

    therefore designed to run in two modes, one for all normal testing where angular

    velocity was restricted to ~7.5 degrees/second, and a ‘high-speed’ mode with one

    chamber of each actuation ram isolated giving peak angular velocities of >15

    degrees/second, (which is consistent with the highest values observed in model

    testing).

    While the rated, steady output power of each axis is ~125kW, the instantaneous peakinput power can be up to 1MW per axis in extreme seas. This overdrive ratio of >8:1

    was not possible using available hydraulic systems so a compromise was made. A

     pair of the largest displacement Denison Goldcup units were chosen to give a peak

    instantaneous power of >500kW per axis. At higher instantaneous powers the only

    important difference is the increased pressure drop in the flow path. As long as it isnot extreme this is not a problem on the high pressure side of the system, on the low

     pressure side cavitation at inlet is a potential problem as mentioned above. If the inlet

    cavitiates there will be no resistance to the return stroke, and oil foaming may causefurther problems due to oil compressibility in this state. The high speed mode

    allowed it to be confirmed that this would not be a problem.

    The test rig was therefore specified as follows:

    • Peak actuation power 500kW per axis

    • Mean actuation power 350kW per axis

    • Rated steady output power 125kW per axis• Angle limits +/- ~15 degrees

  • 8/9/2019 Pelamis Joint System Test

    13/49

     Page 7  

    • Angular velocity limits (normal) +/- ~7.5 degrees/second

    • Angular velocity limits (anti-cavitation tests) +/- ~15 degrees/second

    Further details of the rig are described in the following sections.

  • 8/9/2019 Pelamis Joint System Test

    14/49

     Page 8 

    2.3 STRUCTURE

    The rig structure (Figure 2.5) is based on the full-scale prototype structural design,with the principle differences being to accommodate the external actuation rams. The

    loading in the rig is actually much more severe than for the module in service due to

    the large moments generated between the actuation and power-take off rams, butcareful design and the use of extra stiffening plates solved this problem. The rig

    structure was been the subject of a full finite-element analysis using a similar

    methodology to that used for the full-scale prototype design. An example plot is also

    shown in Figure 2.5, with the deflection exaggerated 100 times.

    Figure 2.5 – Cutaway view of the joint test rig structure & finite element analysis

    results

    The structure comprises the main module shell and the two end frames to provide the

    reaction between the externally mounted actuation rams and the internal power take-

    off rams. The main shell is an assembly of prefabricated parts to form a rigid shell. It

    is intended that the ram and main bearing attachment points are castings in the full-scale prototype to remove welds from highly stressed areas. However, for the test rig

    heavy fabrications were used as castings were not practical for the test rig as only fourwere required. Various frames, end plates, internal stiffening rings and four rolled

    closing plates complete the structure. All internal system components are mounted on

    elements of the main structure such as the ring frames or end walls to minimise part

    count and fabrication costs.

    The structure was built by Ross Deeptech Initiatives Ltd in Stonehaven. Several

     pictures of the structure during fabrication are shown in Figure 2.6 on the following

     page. The finished structure was assembled at Ross Deeptech before shipment toOPD’s test facility for population with components and subsequent commissioning

    and testing.

  • 8/9/2019 Pelamis Joint System Test

    15/49

     Page 9 

    Figure 2.6 – Test rig structure: Ram attachment inserts during fabrication (top left),fabrication of the main shell in process (top right), welding out the completed shell

    (middle left), machining the bores on the end rigs (middle right), final finishing work

    on the completed module (bottom left), the complete, painted, assembled structureinstalled at the OPD test facility (bottom right).

  • 8/9/2019 Pelamis Joint System Test

    16/49

     Page 10 

    2.4 ACTUATION SYSTEM

    Each axis of the rig is driven by an individual closed circuit hydraulic system with a peak rating of ~500kW. A large Denison Goldcup 500cc/rev over-centre pump is

    directly coupled to each set of opposing hydraulic actuation rams. The manifolding

    system allows the power unit to deliver in excess of ~350kW of r.m.s. power intoeach axis with a peak of ~500kW. Valving allows two of the actuation ram chambers

    to be isolated to allow the system to be actuated at over twice the angular velocity at a

    reduced moment. This is to confirm that the inlets to the power take-off rams will

    not cavitate in extreme conditions.

    Each unit is mounted on an independent skid measuring approximately 4.5x2x2.5m.

    These units were designed, fabricated and assembled by Hytec Hydraulics Ltd on aturn-key basis. Various views of the actuation packs during build and installed at the

    OPD test facility are shown below in Figure 2.7 below.

    Insert pics of power packs

    Figure 2.7 - 500kW closed circuit hydraulic actuation packs: Trial fitting of drive

    motor and cooler at Hytec (top left), Denison Goldcup 500cc/rev actuation pump (topright), views of the two completed packs installed at the OPD test facility (bottom).

  • 8/9/2019 Pelamis Joint System Test

    17/49

     Page 11 

    2.5 POWER CONVERSION SYSTEM

    The general layout within the joint module is shown schematically in Figure 2.8. Ageneral schematic of the power take-off and conversion system is shown in Figure

    2.9. Certain details have been omitted for commercial reasons.

    Figure 2.8 – Joint module layout

    Figure 2.9 – Power conversion system schematic

    The PTO system is a development of the previous configurations described in the

    final reports for projects V/06/00181 [1] and V/06/00188 [2] (see Introduction). Themain changes are integration of the heave and sway systems into a single unit as

    L.P.

    H.P.

    A

    B

    AH.P.

    B

    AXIS 2AXIS 1

    M

    L.P.

    M

    MANIFOLD

    MANIFOLD

    MANIFOLD

    MANIFOLD

    FILTER

    125kW GENERATOR

    HEAT X

    HEAT X

    FILTER125kW GENERATOR

    PTO RAM

    PTO RAM

    PTO RAM

    PTO RAM

  • 8/9/2019 Pelamis Joint System Test

    18/49

     Page 12 

    described earlier. Where possible the major components were dual-sourced to allowOPD to assess what the best supplier options are for the full prototype machine.

    The heave and sway rams are specially made units designed for the required load and

    motion envelope. The rams (one-off each heave and sway) were sourced from two

    different suppliers. The inlet and outlet control manifolds are bolted directly to theram bodies to minimise compressibility effects. A semi-transparent view of the full

    manifold is shown below in Figure 2.10, and a picture of an actual unit mounted to a

    ram body in Figure 2.11. Before the main order was placed, a single chamber

     prototype was built to confirm satisfactory operation over the required pressure and

    flow envelope.

    Figure 2.10 – Ram manifold schematic

    Figure 2.11 - ram manifold installed on the ram body

    Central to the performance and reliability of the power conversion system are the high

    and low-pressure accumulators. The low-pressure circuit is maintained at a raised pre-charge pressure bar by a pair of 1000 litre low pressure bladder accumulators

  • 8/9/2019 Pelamis Joint System Test

    19/49

     Page 13 

    shown prior to installation in Figure 2.12. These use a low permeability nitrile bladder to separate the oil and gas volumes to prevent the nitrogen from being

    absorbed into the oil. The pre-charge ensures that the inlet valves do not cavitate atextreme joint velocities and that there will be a minimum of dirt and water ingress

    into the hydraulic circuit. After much iteration is was decided that the Pelamis system

    should use large piston accumulators as the high-pressure reservoirs instead of bladderaccumulators as shown in Figure 2.13. This minimises the required pipe-work and

    reduces the probability of serious problems associated with rapid gas release into the

    system (for example catastrophic failure of a bladder).

    Figure 2.12 – Hydraulic reservoirs

    Figure 2.13 – High pressure piston accumulators

    Power conversion is performed by a pair of hydraulic-motor/induction-generator

    units. OPD has chosen simple induction generator units for the prototype machine to

    minimise the complexity of the control and switch gear required. Each unit can be

    run independently from the common accumulator bank to minimise exposure to

    failure of a single unit, and to allow conversion efficiency to be maximised andrunning hours minimised at part load. OPD dual sourced the motors and generators.

  • 8/9/2019 Pelamis Joint System Test

    20/49

     Page 14 

    All of the main components are plumbed together using flexible hose and SAE

    standard flange fittings. Hard pipe work was considered, but ultimately rejected dueto cost, the difficulty of meeting the required positional tolerances, and the conclusion

    it would be unreliable due to thermal expansion and flexing of the joint module

    structure. Also, connecting and disconnecting individual components is much easierusing flexible piping. A central 'hydraulic-hub' manifold is used to make all the key

    connections (Figure 2.14). This is located at one end of the joint module.

    Figure 2.14 – Main connections manifold

    All system components were installed by OPD personnel. One of the key objectivesof this programme was to give OPD experience of working with the full-scale

    technology, it is felt by OPD that it is important for the designers of the system toexperience issues relating to assembly so that that this can inform the design of future

    systems. The experience gained from packaging and assembly of the full-scale joint

    rig has led to a number of major improvements and simplifications for the full-scale

     prototype joint modules.

    The system was originally commissioned and tested using the 7th  scale control and

    data acquisition system. However, a second revision of the control hardware has been

     built and retro fitted into the test rig since completion of the cycle tests. This hasallowed the actual control hardware to be fitted to the full-scale prototype to be tested

    on a realistic platform.

  • 8/9/2019 Pelamis Joint System Test

    21/49

     Page 15 

    2.6 TEST FACILITY

    Given the nature of the testing and the need for test supervision during the initialstages, OPD felt that the most effective route was to commission its own facility for

    the purpose, close to its offices. OPD leased and upgraded a 450m2  industrial unit

    from Forth Ports plc for the test rig. Upgrade work included thorough cleaning and painting, installation of an office, installation of a hydraulics assembly area, a

    mechanical workshop area, and the required 5tonne overhead gantry crane and 2MVA

    electrical supply. Also provided was a control area with provision for the joint

    computers and hardware, including independent condition monitoring and emergency

    shut-down system, as well as a dedicated independent 64 channel data acquisitionsuite.

    The costs of this were significant within the overall project, but were justified on the

    grounds that the location’s convenience meant that travel costs were minimised, and

    in any case, it proved impossible to source an alternative facility that did not require

    electrical upgrade.

    Various views of the facility during preparation are shown below in Figure 2.16.

    Figure 2.16 – The OPD test facility: During preparation (top left), installation of the

    overhead gantry crane (top right), during installation of the full-scale joint rig (bottom

    left), and fully commissioned (bottom right).

  • 8/9/2019 Pelamis Joint System Test

    22/49

     Page 16  

    3. TEST & INSPECTION PROGRAMME 

    Testing of the full-scale joint rig fell under three main headings:

    • Commissioning Tests – to confirm satisfactory operation of all test facility and

    rig systems• Functionality Tests – to characterise all joint power take-off systems, and

    confirm performance was as anticipated

    • Cycle Testing – to improve confidence in the initial reliability of the system

     prior to the first offshore tests, and highlight any early wear issues

    The scope and results from each of these are set out below.

    3.1 COMMISSIONING TESTS

    During December 2002 the test facility and test rig were successfully commissioned.

    Test included confirmation of satisfactory operation of:

    • The grid connection and test facility electrical systems

    • The actuation power-packs

    • The joint module instrumentation, control and electrical systems

    • The overall test facility data acquisition suite

    The 2MVA 6.6kV/415V grid connection was witness tested by Scottish Power to

    confirm satisfactory operation of the fault trip and earthing systems. This is a near

    identical process to that that will be required at the test centre prior to installation ofthe full-scale prototype, and gave valuable experience.

    Each of the actuation packs and the joint module are served by independent electrical

     panels. Each of these was commissioned on-site as a suitable connection was not

    available at the manufacturer's facility. The actuation packs were run-up to break in

    the pumps and were subsequently commissioned using a flow restrictor valve rather

    than on the rig itself. This was seen as a prudent measure as the actuation system is

    extremely powerful. Once the actuation pump controllers had been commissioned

    work concentrated on setting the closed loop control around each joint axis in turn. A

    closed loop system is required to properly simulate the action of waves on the real

    system. The control loops were closed and the system parameters optimised to givethe best response. There were a number of problems with commissioning the

    actuation power packs themselves, these were mostly concerning the boost system for

    the Denison pumps. The rapidly reversing load and rapid pressure changes in the

    system initially gave problems until a small accumulator was included in the boost

    circuit.

    The joint module systems include full electrical panels, including back-up battery

    supply. Soft-starters are included for the induction generators to reduce the inrush-

    current, a power factor correction unit is also included. The complete electricalsystem was commissioned at the manufacturer prior to shipment, however, the system

    was re-commissioned on-site to confirm wiring and local voltage drops. The pair of

  • 8/9/2019 Pelamis Joint System Test

    23/49

     Page 17  

    generators and hydraulic motors were run up, enabled and tripped to confirmsatisfactory operation.

    The joint instrumentation and control systems are essentially identical to the 7 th scale

    system. However, a number of extra channels have been introduced to allow full

     performance appraisal and better diagnostics. The full system was tested, andcalibrated where appropriate. Commissioning then moved to confirming correct

    operation of the joint control systems. This process was directly analogous to that

    carried out using the 7th  scale joint test rig. Many of the tests and analysis tools are

    common to both systems, proving the value of the earlier work.

    A National Instruments Labview based system is used to collect data from both the

    test rig itself and the actuation power packs. A total of 64 channels are available.During the majority of testing a total of approximately 40 channels were used.

  • 8/9/2019 Pelamis Joint System Test

    24/49

     Page 18 

    3.2 FUNCTIONALITY TESTS

    The most important tests carried out were the functionality trials. These were to:

    • Confirm satisfactory operation of the actuation system across the design

    load/motion envelope• Confirm satisfactory operation of the active joint control algorithms across the

    design joint restraint envelope

    • Characterise flow induced pressure drops through the complete system

    • Confirm that there was no cavitation at the inlets to the ram chambers

    • Confirm satisfactory operation of the hydraulic motors, induction generators

    and controls

    • Confirm that the full-cycle conversion efficiency is as anticipated

    The primary hydraulic system comprises the rams, manifolds, flow control valves,

    reservoirs, accumulators and pressure relief valves. Testing of the primary hydraulicsystem was the most important set as they proved the more innovative parts of the

    system. While the system is an assembly of proven components, the joint module

    assembly is a new application of this technology – it was a key objective of this

     programme to confirm the satisfactory operation of the system as a whole.

    The power generation system is conventional by comparison. Early tests were carried

    out at reduced pressure while problems with the actuation system were resolved, and

    to reduce the stored energy in the system while confidence built. After various

     problems during commissioning were solved, the actuation system the worked

    satisfactorily during all subsequent testing. It should be noted that most of the

     problems experienced during commissioning and operation have been due to theactuation system. It can be concluded that simulating the North Atlantic is not an

    easy task!

    3.2.1 Primary power-take-off

    A large number of active and passive tests were run to confirm functionality of the

     primary power take-off system. The results can not be fully presented here for

    commercial reasons. However, the key results are discussed in some detail below.

    The active primary power take-off system functionality tests were carried out using a

    control program previously proven on the 7th  scale system. Indeed, most of thealgorithms proved to be directly portable between the two systems once corrections

    had been made for geometry, pressure and the time-constants of active components.

    This proves the value of the 7th

      scale test rig and machine programmes. Example

    results are shown in Figures 3.1 & 3.2.

    Active algorithms were applied to cover the intended range of joint restraint. Initially,tests were conducted at reduced pressure to lesson the amount of stored energy in the

    system. These tests proved that the main algorithms were sound. However, tests athigher pressures caused problems due to compressibility of oil and the stiffness of the

    hoses in the actuation system. Tests at these levels had to be conducted with modified

    algorithms to prevent rapid depressurisation of the actuation system leading toundesirable pressure spikes in the inlet manifold of the primary power take-off

  • 8/9/2019 Pelamis Joint System Test

    25/49

     Page 19 

    system. This was not an issue on the 7th

     scale joint test rig as the drive system wasmore rigid. It will not be a significant issue with the full-scale prototype machine at

    the structure is of adequate rigidity. However, initial sea trials will quantify the effect.

    Figure 3.1 – Results from an example test showing high-pressure accumulator,

    reservoir, and ram chamber pressures (top), and applied moment records (bottom).

    The control algorithms used for these tests were identical to those implemented on the

    7th scale machine – proving the value of the intermediate scale programme.

    Figure 3.2 – Test results for typical stiffness (left), damping (middle) and complex(right) joint impedances. The damping and complex results show more disturbances

    and oscillation than the stiffness results due to the compliance of the rig actuationsystem (note however that the traces are repeatable). However, quantised moment

    levels are still clearly visible.

    The results from the joint test rig were correlated the Pel power take-off system

    numerical model. The methodology used was identical to that used for the 7th  scale

    system under V/06/00188, proving the value of the earlier work. Catalogue values forall system impedances, response times, volumes, compressibility etc were first entered

    y = 12.051x

    -1.6

    -1.2

    -0.8

    -0.4

    0

    0.4

    0.8

    1.2

    1.6

    -0.1 -0.05 0 0.05 0.1

    y = 21.444x-1.6

    -1.2

    -0.8

    -0.4

    0

    0.4

    0.8

    1.2

    1.6

    -0.08 -0.04 0 0.04 0.08

    y = 15.373x-1.6

    -1.2

    -0.8

    -0.4

    0

    0.4

    0.8

    1.2

    1.6

    -0.08 -0.04 0 0.04 0.08

    Upper Chamber Pressures

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    10 12 14 16 18 20 22 24 26 28 30

    Time (s)

       P  r  e  s  s  u  r  e   (   b  a  r   )

    4.1

    4.2

    3.1

    3.2

    State

    HP acc

    LP res

    Total Applied Momemt

    -1.5

    -1

    -0.5

    0

    0.5

    1

    1.5

    10 12 14 16 18 20 22 24 26 28 30

    T ime (s )

       M  o  m  e  n   t   (   M   N  m   )

    Drive

  • 8/9/2019 Pelamis Joint System Test

    26/49

     Page 20 

    into the model. Agreement was found to be poor for most cases. Measured valuesderived from results from the rig were subsequently used – agreement was much

    improved. The power take-off model in the Pel machine simulations is now a veryaccurate representation of the system for all operating cases studied, an example of

    the level of agreement achieved is shown below in Figure 3.3. The good level of

    agreement means that the power take-off model can now be used to predict theresponse and performance of the full machine with a good degree of confidence.

    Figure 3.3 – Example chamber pressure records from the test rig, plotted withcorresponding simulation results. The results show good agreement between the test

    rig and the simulation down to the level of individual pressure transient features.

    Previous analyses, and experience with the 7th scale machine have shown that ultimate

     joint restraint levels achievable are inherently limited by the frequency response of the

    control valves. OPD have been in close discussion with the valve manufacturers to

    characterise and improve the performance of the valves to be used on the full-scale prototype machine. This led to an iterative test procedure using the full-scale joint rig

    at the end of the programme. Various valves were modified and tested by OPD and

    the manufacturer. They were installed in the rig and tested under real operatingconditions. A good solution was found that gives acceptable frequency response

    characteristics without major modification to the valves. The manufacturer has since produced a batch of modified valves for installation in the full-scale prototype. It was

     precisely this kind of issue that the full-scale joint was conceived of to address. A

    large amount of time and money has been saved by identifying and addressing this

    issue before the full-scale prototype is built and deployed.

    A further key objective of the test programme was to determine the fluid resistancesin the system to quantify losses and to confirm that there would be no cavitation on

  • 8/9/2019 Pelamis Joint System Test

    27/49

     Page 21 

    inlet and no extreme over pressure on outlet across all operating conditions. Thegraphs in Figure 3.4 (below) show passive fluid resistances. The left hand graph

    shows the inlet characteristics.

    Figure 3.4 – Ram inlet (left) and outlet (right) fluid resistances

    On induction (negative half of the x-axis) the control valves are designed to ensure

    that the resistance is low, so that cavitation is avoided at high flow rates. The pressuredrop lies below 1 bar even at flows of >350litres/minute. It should be noted that the

    small pressure differences measured on induction are obscured by the datum accuracy

    of the 400bar transducers used in the ram chambers. However, the chamber pressures

    can be seen to be flat on induction at a pressure less than 1 bar different from the

    reservoir pressure. The induction pressure drop is considerably lower than has been

    assumed in the past, this is a very positive result as it will allow the system pre-charge

     pressure to be reduced, reducing the cost of the reservoir and increasing the life of all

    dynamic and static seals.

    Resistance to flow through the outlet control valves (positive half of the x-axis) ishigher due to the different flow-path, this is not a problem as cavitation is not possible

    in this case. The graph on the right of Figure 3.4 is the resistance of the high pressure

    valve as oil is pumped from the ram. A minimum of around 3.5bar is dropped due to

    the cracking pressure of the valve, the pressure drop rises to approximately 8 bar at

    300litres/minute. Again this is less than was previously anticipated due to thespecification of a larger valve.

    The pressure measurements on which the pressure drops shown above are based weretaken inside the ram chambers and at the high or low pressure reservoirs. They

    therefore include the drops over the hoses and manifold. The results imply that around1-2% of absorbed power would be lost due to pressure drops through the flow path

    depending on the operating conditions. This agrees well with previous estimates of

    flow losses made in V/06/00181. The majority of the losses are due to the cracking

     pressure of the high pressure non-return valve, the design and choice of this valve is

    currently being reviewed.

    HP (outlet) valve pressure drop vs flow for

    chamber 1.1

    0

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    0 100 200 300

    (lt/min)

            (        b      a      r        )

    LP (inlet) valve Pressure drop vs flow for

    chamber 1.1

    -2

    0

    2

    4

    6

    8

    10

    -400 -200 0 200 400

    (lt/min)

            (        b      a      r        )

  • 8/9/2019 Pelamis Joint System Test

    28/49

     Page 22 

    Further tests showed that variation of fluid resistance with oil temperature was notsignificant (see Figure 3.5).

    Figure 3.5 – Effect of oil temperature on fluid resistances (13.5oC (left), 34.3

    oC

    (right)) showing the expected small reduction in pressure drops with risingtemperature as fluid viscosity falls.

    To put losses in context, 1-2% losses due to flow restrictions would equate to £1,000-

    £2,000 per annum at Renewables Obligation prices. This clearly shows why allaspects of system efficiency must be optimised. Considerable effort will be focussed

    on optimising the flow paths for future machines.

    3.2.2 Power conversion system

    A broad range of tests have been conducted on the power generation system and

    controls. The functionality of the electrical control panels has been fully tested with

    interlocked start sequences implemented on the FPGA controller. The most important

    interlock is ensuring that the hydraulic flow cannot be enabled before the generator is

    up to speed with the power factor correction enabled. This has been fullydemonstrated along with the other more minor interlocks.

    Active over-speed shutdown has been tested using a signal generator to simulate the

    speed encoder. The system also incorporates a mechanical over-speed shutdown in

    the form of a ‘flow-fuse’ on the inlet that shuts at 1.5-2 times the full load flow-rate.

    This system is seen as a last ditch saver to prevent the hydraulic motor or generator

     being damaged in the event of the electrical load being removed while the hydraulicsare still active (the hydraulic motors are rate for up to three times rated speed). The

    flow-fuse has been tested with the hydraulic motor disconnected.

    Motor-generator performance has been as expected. Figure 3.6 shows example test

    records from the full-scale joint rig. The results show a test where both generators arerunning with an average system pressure of ~300bar. The test includes a simulated

    emergency shutdown at 50 seconds. Fluctuations in pressure and power are due to the

    fact that the input to the rig is a large sine wave. Further refinements to the control

    algorithm prior to deployment in the full-scale prototype will significantly improve

    the output smoothness.

    HP (outlet) valve pressure drop vs flow for

    chamber 1.1

    0

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    0 100 200 300

    (lt/min)

           (       b     a     r       )

    HP (outlet) valve pressure drop vs flow for

    chamber 1.1

    0

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    0 100 200 300

    (lt/min)

           (       b     a     r       )

  • 8/9/2019 Pelamis Joint System Test

    29/49

     Page 23 

    Figure 3.6 – Example power conversion system results for a short sweep of pressure

    and swash angle. The top graph shows the motor-generator rpm, the generator is aninduction machine and as such increases in speed with torque (and therefore power),

    this can clearly be seen on the trace. The spike at 50seconds corresponds to thegenerators being tripped. The next plot shows oil pressure in the HP accumulator and

    LP reservoir. The lumpiness is due to the unsteady nature of the input power. The

    following graph shows the demand and achieved swash angles for the two motors.

    The next plot shows individual hydraulic and electrical power, and total power

    electrical output power for the same test. The final graph shows overall conversion

    efficiency for the two motor-generator sets, calculated as the ratio of electrical powerout to hydraulic power in (pressure x flow-rate).

    Motor swash angles (%)

    0

    20

    40

    60

    80

    100

    0 10 20 30 40 50 60

    Low er Upper low er demand upper demand

    Generator speeds (rpm)

    1400

    1450

    1500

    1550

    1600

    0 10 20 30 40 50 60

    Low er Upper  

    Oil Pressures (bar)

    0

    50

    100

    150

    200

    250

    300

    350

    400

    0 10 20 30 40 50 60

    accumulator reservoir 

    Module 1 Powers (kW)

    0

    50

    100

    150

    200

    0 10 20 30 40 50 60

    Pow m1 upp

    Pow m1 low

    Pow m1 Total

    hyd powe upp

    hyd powe low

    Conversion efficiency

    0

    0.1

    0.2

    0.3

    0.4

    0.5

    0.6

    0.7

    0.8

    0.9

    1

    0 10 20 30 40 50 60

    Time

    upper 

    lower

  • 8/9/2019 Pelamis Joint System Test

    30/49

     Page 24 

    Efficiencies have been calculated using input power from high pressure accumulator pressure and flow-rate, and output power from the electrical panel. Measured

    efficiencies are typically ~75% at 150bar operating pressure and full-flow (~35-40kW per generator) which is in line with motor and generator data. The combined

    efficiency rises to 85% - 90% at 300 bar (~100kW per generator). Again this is in

    line with motor and generator manufacturer’s data. The results are conservative dueto losses through the long pipe work of the test rig, the motor/generator sets and heat

    exchangers were mounted outside the joint module for all testing to allow safe access

    to the equipment while the rig is running. This adds a total of ~60metres of extra

    hose, and several couplings in the circuit, giving an extra ~2-3bar of pressure drop at

    full flow. The actual module will have much shorter pipe work and overall efficiencycan be expected to rise by 1-2% from the figures presented. The power conversion

     packs and heat exchangers on the full-scale prototype have been redesigned and re-sited to minimise hose length and connections.

    The measured efficiencies of all of the components show that the overall conversion

    efficiency of the system will be better than 80% for most operating conditions. Thisis a very encouraging result as it confirms that the performance of the OPD power

    take-off and conversion system is good enough (even in its current form) for direct

    application in future commercial machines. However, improvements to the various

    flow paths are expected to lead to modest improvements of the order of 1% at high power levels, at no extra cost, with no new technology required. Larger gains are

     possible through the development of specialist hydraulic motors optimised for theapplication. OPD are in discussions with manufacturers regarding this.

  • 8/9/2019 Pelamis Joint System Test

    31/49

     Page 25 

    3.3 CYCLE TESTING

    Cycle testing was carried out over a period of three months from February – April2003. Within this, a total of approximately one-and a half months running time was

    accumulated. While this is less than anticipated (due to heavy commitments on the

    full-scale prototype design/build programme) sufficient testing has now beenconducted to meet the original project objectives – specifically, to confirm the

    satisfactory extended operation of the system and that there are no 'show-stopping'

    issues regarding reliability or component wear.

    Rather than continuing the cycle tests into May & June 2003 the rig has beenextensively utilised to test additional components for the full-scale prototype and to

    commission the actual power conversion systems to be used in the full-scale prototype. These tests are briefly discussed within this report for completeness.

    3.3.1 Details of test programme

    All cycle testing was to a common format, the testing was monitored throughout with

    continuous data logging of 38 data channels (see below) from the rig and actuation

    system, and a check of all system parameters every half-hour to confirm satisfactory

    operation. The test format was as follows:

    • Start up test rig

    • Bring system up to operating pressure

    • Start up both generators

    • Ramp up to test power levels

    •Run at steady state conditions, logging test data and monitoring every halfhour

    • Change steady state conditions as required

    • Shut down at end of test period (typically 10-12 hours continuous)

    • Perform post shutdown checks and inspection

    • View sampled test data to confirm satisfactory operation of all components

    The system proved highly reliable in operation with no un-commanded shutdowns

    due to the joint systems. On three occasions one of the generators tripped off during

    testing, due to the power limit settings on the generator soft starter. These settingswere adjusted and the problem did not recur. The soft-starter was included to limit

    the in-rush current at start-up. This was due to concerns about voltage drops in thesystem causing undesirable interactions between modules. Subsequent testing has

    shown that the voltage drops will be manageable and the soft starters have now been

    removed altogether. 

    Several problems were experienced with the actuation-system during early cycle

    testing, these were traced to faulty transducers or connections on the actuation packs.In all cases the rig safety shut-down systems and procedures worked correctly.

  • 8/9/2019 Pelamis Joint System Test

    32/49

     Page 26  

    The following data was collected for all cycle tests:

    Description Type Number of

    channels

    Heave axis angle Unipolar, differential 1

    Sway axis angle Unipolar, differential 1

    Heave drive signal Bipolar, differential 1

    Sway drive signal Bipolar, differential 1

    Heave actuation pressure Unipolar, differential 2

    Sway actuation pressure Unipolar, differential 2

    Main manifold HP & LP pressure Unipolar, single-ended 4

    Ram manifold (x4) HP & LP Unipolar, single-ended 8

    Ram chamber pressures Unipolar, single-ended 16

    Heave controller demand Digital 1

    Sway controller demand Digital 1

    TOTAL: 38

    Data was collected using a National Instruments sampling system and Labview

    software – this is the same system as will be used for full-scale prototype structural

    monitoring. Configuring and using the system and managing the considerable

    volumes of data provided useful experience for the forthcoming full-scale prototype programme.

    The data was collected to allow diagnostic analysis to be performed in the event of

     problems with system components. However, as there we no significant problems

    with the test rig systems, little actual in-depth analysis of the sampled data was carried

    out. Analysis was limited to on-line checks while the rig was running to confirm that

    the system was running to specifications.

    3.3.2 Anticipated future testing

    Subsequent to the main cycle tests, the rig has been used to test the full-scale

     prototype power conversion packs. All three units are being thoroughly tested prior toinstallation in the joint modules. The final versions of the control system hardware

    and software are also being tested. At the time of writing, the rig is operational with a

    single joint control system installed, the other two systems are set up on the bench

    with dummy inputs to allow the whole system to be tested.

    Further cycle tests will be run once commissioning test on full-scale prototype

    systems have been completed. It is anticipated that a further months test will be runahead of deployment of the prototype.

    Thereafter, the rig will become a test-bed for new valves, components and controlalgorithms, and used to simulate any failures experienced on the full-scale prototype

    in operation. The joint rig represents a considerable investment for the company and

    we are keen to utilise it fully in the future.

    3.3.3 Other cycle testing

    It was originally intended that the flexible cable unions between segments of the

    Pelamis would be tested on the FSJ rig. However, it was realised early on that theenvisaged rig cycle tests would give a maximum of the order of 1 or 2 x 105  cycles

  • 8/9/2019 Pelamis Joint System Test

    33/49

     Page 27  

    through moderate angles. It therefore was deemed preferable to build an separate,dedicated rig for this purpose. This rig incorporated both power and signal cabling

    including the correct geometry, conduits and glanding. It used a simple gearedinduction motor to drive the flexible union system through its maximum operating

    angles (rather than average) at ~3Hz, allowing tests to be conducted at approximately

    100 times the real time flexure duty. The rig was run for 1.2 x 106

     cycles, giving a predicted flexural test greater than 15 years in normal service. The individual cables

    were then examined for signs of damage – none was evident indicating that the

    system is performing adequately.

    While it was possible to address flexural life and wear with the rig, the tests did notassess the long term sealing and corrosion performance of the system. The flexible

    union system incorporates two independent seal paths giving a high degree ofintegrity in the event of a single failure (as is standard practice for marine and

    offshore systems). Also, in the event of failure of the external barriers the individual

    wire cores are sheathed, giving the system an effective third barrier. Long-term

     performance of the complete system will be monitored on the full-scale prototype andfuture machines during offshore trials. However, the multiple independent seal paths

    are expected to give the system a high degree of integrity, and will afford a good

    degree of failure tolerance. OPD therefore have a high degree of confidence in the

     performance and robustness of the flexible joint union system. The sealing andcorrosion performance of the system will be monitored in service on the full-scale

     prototype.

  • 8/9/2019 Pelamis Joint System Test

    34/49

     Page 28 

    3.4 INSPECTION ACTIVITIES 

    The rig has been thoroughly inspected during and after the cycle test programme.These inspection activities were predominantly aimed at confirming the satisfactory

    (or otherwise) operation of all system components, and identifying any components

    that were exhibiting early signs of loss of performance or wear. The tests andinspections proved highly useful. One of the aims of the FSJ programme was to

    assess alternative suppliers for the main components, the results have proved

    invaluable for specifying components for the full-scale prototype machine. 

    Inspection activities and results are summarised below.

    3.4.1 Structure

    During the test programme, the rig was visually inspected while stationary and also

    during operation. No cracking or distortion has been found to date. The rotational

    locking plates for the ram pins were found to loosen during extended cycle testing,their design has been changed for the full-scale prototype to ensure this does not

    recur.

    3.4.2 Hydraulic rams

    The rams have been thoroughly visually inspected throughout the test programme.Inspection activities have concentrated on the following:

    • Wear of external rods

    Rod exit seal leakage• Backlash in rod-end bearings & pins

    • Signs of movement in unions between ram barrels and blocks, including tierods and anchors

    External rods

    The external ram rods have been monitored for signs of early degradation, wear orundue burnishing. None of the rams shows serious wear, though the rams from one

    supplier (Supplier A) appear to be in generally better condition than the other

    (Supplier B). The visible wear on the front rods of the Supplier B rams may be due to

    higher level of dust/dirt contamination prior to installation of an effective dust shield(no dust ingress will be experienced on the full-scale prototype). However, the upper

    Supplier A heave and sway actuation rams were most exposed and shows little sign of

    wear other than normal polishing and a few shallow scores. The Supplier B sway ram

    rod looks the worst – wear here seems unlikely to be attributable to dirt and appears to be more like a degree of binding in the front rod bearing. From the tests and

    inspections conducted it appears that the design, build and performance of the unitsfrom Supplier A is superior, these have been specified for the full-scale prototype.  

    Close-up pictures of each power take-off ram rod are shown on the following two

     pages in Figure 3.7(a)-(d). 

  • 8/9/2019 Pelamis Joint System Test

    35/49

     Page 29 

    Figure 3.7(a) - Lower heave power take-off ram external rod condition showing normal degree of polishing

    Figure 3.7(b) – Upper heave power take-off ram external rod condition showing normal degree of polishing on underside (right) but some

    shallow scoring on upper face (left), possibly due to dirt contamination during early runs

  • 8/9/2019 Pelamis Joint System Test

    36/49

     Page 30 

    Figure 3.7(c) – Lower sway power take-off ram external rod condition showing normal degree of polishing

    Figure 3.7(d) – Upper sway power take-off ram showing more significant surface wear on rod (NB – the wear is not serious but is

    significantly more than on other rams and is of a different type inconsistent with scoring due to dirt ingress)

  • 8/9/2019 Pelamis Joint System Test

    37/49

     Page 31 

    Piston rod front seals

    The performance of the internal piston seals is not as critical as that of the front pistonrod seal, where the piston rod exits the ram body. All such seals will leak slowly as

    they leave a thin oil film on the rod as part of their normal operation. However, this

    should be a maximum of an (estimated) 1-2 drops/day. While it does not pose a problems in terms of oil release into the environment as the rods are inside the robust

    outer bellows seal, excessive leakage here is still highly undesirable as it will result in

    oil being lost from the system, and will cause a build up in the seal.

    All front seals are performing satisfactorily, apart from on the upper heave ram whichis showing significant leakage in operation (4-5 drops/minute) (Figure 3.8). This may

    again be due to contamination during early tests but again it is observed that the upperheave actuation ram was in the worst location for contamination, and is showing no

    signs of leakage. The poor performance of the upper heave ram front seal was

    another key reason why the other manufacturer’s units were specified for the full-

    scale prototype machine.

    Figure 3.8 – Modest oil leakage from the front seal of the upper heave power take-off

    ram

    Rod-end bearings

    The rod end bearings used on the full-scale joint rig were the recommended wideseries steel-on-steel spherical bearing units, typically used on hydraulic rams. In

    service it was found necessary to lubricate these units at regular (~daily) intervals. Atfirst OPD concluded that this would require a centralised greasing system, however,

    individual automatic greasing systems were found to be a cheaper, more reliable

    alternative.

    The frequency of greasing required led to a further detailed study into rod-end bearing

    requirements and options. The result of this was specification of larger PTFE-on-steelspherical units for the full-scale prototype, which have a higher dynamic load rating

  • 8/9/2019 Pelamis Joint System Test

    38/49

     Page 32 

    and maintenance free characteristics. It was not possible to retrofit these units ontothe test rig due to the jaw spacing of the front and rear mounts. However, the

    manufacturer has been consulted in detail about their use and in-service lifeexpectancy.

    Therefore, the lubrication requirements of the rod end bearings on the test rig cannot be taken as representative of the full-scale prototype in service, as larger PTFE-on-

    steel units have been specified. In-service performance will be determined by regular

    inspection of the front and rear units on the full-scale prototype machine.

    Ram bodies

    Careful inspection of the ram bodies was carried out at regular intervals. Allinspection was visual, mainly concentrating on whether the paint line between the

    various components had become cracked, crazed or damaged. No signs of movement

    were found (see Figure 3.9). The rams specified for the full-scale prototype are more

    conservative in terms of structural design, and this gives further confidence.

    Figure 3.9 – Two views of the ram barrel end/mid block unions showing no signs of

    movement

    3.4.3 Accumulators & reservoirs

    The accumulators and reservoirs have been examined for external signs of damage,

    and none has been found. The main criterion is confirmation of gas retention, assignificant loss of gas would seriously affect performance. While short term

    monitoring is impossible due to fluctuations in temperature, long-term monitoring has

    found no perceptible loss of gas from either the accumulators or reservoirs – either tothe outside atmosphere or into the oil.

    The only other significant potential weak point in the system is the gas connection

     between the piston accumulators and their gas back-up bottle as shown in Figure 3.10.

    If there is significant motion of either unit in the module this link may be

    compromised. While the gas link has been designed to give sufficient compliance to

    cope with small motions, gross movements are likely to result in a failure. There has

     been no sign of movement during the tests but the accumulator mounting system forthe full-scale prototype has been upgraded.

  • 8/9/2019 Pelamis Joint System Test

    39/49

     Page 33 

    Figure 3.10 – Accumulator to gas bottle connection

    The reservoir is a self contained unit, so has no problems with gas piping. However,there were concerns over the vulnerability of the gas filling valve. A more robust unit

    is fitted to the reservoirs for the full-scale prototype.

    OPD therefore currently has no concerns over the performance of the accumulator andreservoir units. Though no motion of the units has been evident, OPD have upgraded

    the mounting system for the full-scale prototype. The gas filling valves on the

    reservoirs have been upgraded to a more robust design for the full-scale prototype

    units.

    3.4.4 System valves

    The Pelamis power take-off system uses a number of valves to control oil flow

    through the primary circuits. A number of other valves are used in the rest of the

    system, including some large pressure relief valves to limit system pressure in large

    seas. Through their life, the valves will see a very large number of cycles (>107),

    manufacturers have conducted tests up to 106  cycles which gives a high degree of

    confidence for the short-medium term. However, OPD will be monitoring the

    condition of the various system valves in service to ascertain whether there is likely to be a serious longer-term problem.

    Several valves have been removed for inspection following the main block of cycle

    tests. This has included at least one of each type of valve. In general, the valves have

     been found to be in near as-new condition with little or no sign of operation. One

    valve has been found with a damaged 'O' ring seal, but this damage looks consistent

    with pinching of the seal during installation rather than pressure related extrusion.This has been discussed with the manifold supplier. Two views of system valves are

    shown in Figure 3.11.

    3.4.5 Hoses & fittings

    The Pelamis power take-off system uses a significant number of flexible hoses to link

    the main components in the hydraulic circuit. As discussed earlier, flexible hoses are

    used throughout as they are felt to be more reliable with regard to thermal expansion

    and flexing of the joint module structure and are easier to route and install. However,

    the use of flexible hoses increases the risk of failures due to pipe chafing. Inspection

    of the flexible pipe-work in the full-scale joint rig showed that one pipe had chafed inthe supporting steelwork during the cycle tests. The hose was re-routed and clamped

  • 8/9/2019 Pelamis Joint System Test

    40/49

     Page 34 

    to prevent further damage. Damage of this type is possibly the highest risk facing thefull-scale prototype hydraulic system, and consequently very careful thought has been

    applied to the routing and mounting of all flexible hoses in the full-scale prototype joint modules. Also, the system has been fully reconfigured to minimise the number

    and length of flexible pipe work used to further reduce risks.

    Figure 3.11 – One of the system check valves showing no signs of wear (left) and the

    damaged seal on one of the solenoid pilot valves (right). This looks like damage oninsertion rather than extrusion damage to the seal.

    In general the full-scale joint rig used SAE flange fitting for all hose terminations.

    However, due to compatibility issues some large BSP cone fittings and a couple of

    BSP face fittings using bonded seals were used. Both types are shown in Figure 3.12.

    We have had no problems with the SAE flange system at either high or low pressure,

    and the 'O'ring element provides effective sealing and the flange bolts have shown no

    sign of loosening or moving. However, it has been found that both of the BSP types

    are unreliable in these large sizes, perhaps due the difficulty of torquing the two

    halves of the joint against each other. Therefore, all BSP fittings requiring in-situassembly have replaced with SAE flanges.

    Figure 3.12 – Fittings used were almost exclusively SAE flange type couplings

    (shown left on main manifold block), however, a few large BSP fittings using bonded

    seals were also used (right). The latter proved less reliable and were prone to slowleakage.

  • 8/9/2019 Pelamis Joint System Test

    41/49

     Page 35 

    Pipe work has been further minimised by careful grouping of components, with due

    consideration to hose routing and clamping to prevent chafing. All large fittings arenow SAE flanges.

    3.4.6 Motors & generators

    The motors and generators have not been dismantled for inspection. This was deemed

    unnecessary as they are 100% standard off-the-shelf components. There was no

    change in the sound of the units during the test period (a very good indication of

    health), and oil samples taken downstream of the motors indicated no significantcontamination (see following section). This has shown that there are no short-term

     problems with the hydraulic circuit. However, the longevity of the motors, as withother components, remains a subject for the in-service full-scale prototype trials.

    OPD is however confident that the hydraulic motors and induction generators are

     performing satisfactorily.

    3.4.7 Oil quality 

    The oil used for all tests was BP Biohyd SE-S 32, a biodegradable synthetic ester

     based fluid. One of the aims of the full-scale joint programme was to assess thesuitability of Biohyd as the working fluid. Nothing from any of the testing has

    indicated anything to the contrary.

    One of the most powerful tools for determining the 'health' or otherwise of a hydraulic

    system is to examine the level of contamination in the working fluid (surprisingly

    similar in nature and scope to a blood test in medicine!). It is a generally accepted

    view in the industry that an estimated 80% of all failures in hydraulic systems are due

    to oil contamination. Various technologies are available for assessing the condition of

    the system oil – of most relevance to the early testing of a system such as the full-

    scale joint rig is examining the level of solid particulate contamination of the oil.

    There are various industry standards used for specifying the permissible level of oilcontamination, and for assessing sample oil against this. One of the most universal is

    the NAS Class system, and OPD have adopted this for use with the full-scale joint rig

    and full-scale prototype. OPD has purchased a MP Filtri LPA2 laser particle analyser

    for monitoring the oil quality in the test rig as shown in Figure 3.13. The laser

     particle analyser takes three independent oil samples from the system, counts thenumber of particles of different sizes in each sample, and averages the results to arrive

    at an overall NAS Class rating for the cleanliness of the oil. This is the simplest,

    cheapest, most reliable way of determining whether there are problems in the circuit,and is the industry standard method.

    During and after cycle testing, oil was sampled from key locations. Although there

    have been a few 'rogue' readings (possibly attributable to bubbles in the oil sample) in

    almost all cases the oil has achieved a cleanliness of better than NAS Class 8

    (adequate), normally all samples were better than NAS class 6 or 7 which is as good

    as required in aerospace applications. OPD will be using the laser particle analyser

    as the primary method for assessing the condition of the FSP hydraulic systemsduring maintenance in-service.

  • 8/9/2019 Pelamis Joint System Test

    42/49

     Page 36  

    Figure 3.14 shows scans of the analyser printouts from three consecutive readings,

    from oil samples taken from the lower heave ram. The results show a NAS rating of 6or 7 which is excellent for this type of system.

    Figure 3.13 – Portable MP Filtri Laser Particle Analyser

    Figure 3.14 - Example of three consecutive oil quality tests from the full-scale joint

    rig while running, each test is the average of three automated samples. The rating of NAS 6 or 7 shows that the oil is running clean enough for an aerospace application.

  • 8/9/2019 Pelamis Joint System Test

    43/49

     Page 37  

    4. ONWARD DEVELOPMENT CONSIDERATIONS 

    Overall conclusions and development considerations are discussed below withreference to the main sub-systems.

    4.1 General & structure

    The general configuration, structure, and equipment mounting points proved

    satisfactory. Stress ranges in critical components around the load points are high.

    Through discussions with WS Atkins (full-scale prototype design verifiers) is has

     been decided to manufacture the main load bearing components from discrete castingsrather than the heavy fabrications used for the test rig. This is to remove welds from

    high stress areas to improve fatigue performance.

    Actuating the system posed a number of technical challenges. The system chosen was

    a pair of large closed circuit hydraulic systems. These generally performed

    satisfactorily though at high operating pressures problems were encountered with therigidity of the drive system, due to compressibility of the oil and ‘stretchiness’ of the

    hoses. This meant that the control algorithms implemented had to be modified to

     prevent rapid decompressions as these induce unacceptable angular accelerations

    resulting in large pressure transients in the low pressure circuit. However, it is not feltthat this significantly compromised the tests.

    Thermal stability of the oil was difficult to assess. The rig was fitted with external

     plate heat exchangers, cooled by force circulation of water. There proved to be no

     problem cooling the oil with the units chosen, it is felt that the amount of cooling

    capacity provided is conservative. The direct oil water heat exchangers for the full-

    scale prototype have a similar rating to those used for the test rig. Thermal stability of

    the entire module was impossible to assess as the heat transfer path is not

    representative. OPD has carried out preliminary modelling of the likely internal air

    temperature at peak output. Temperature rise is expected to be manageable and will be monitored in service on the prototype machine.

    As a direct result of experience with the rig, individual component siting and

    mounting has been re-examined for the full-scale prototype to minimise the number

    and length of hydraulic and electrical interconnections.

    4.2 Power take-off system

    The power take-off rams in the test rig performed satisfactorily. However, it was

    evident that rams from one supplier were superior to those from the alternativesupplier. The former were specified for the full-scale prototype. In addition, a fuller

    fatigue analysis has been carried out on the ram design leading to adoption of anumber of detail design changes. While being of identical configuration, the rams to

     be installed in the prototype are of a generally stronger construction. Due to robust

    construction and some non-standard bore sizes etc the rams ended up being

    considerably more expensive than originally budgeted. While it is anticipated that

    there will be significant economies of scale associated with volume production, there

    is a need to re-engineer the units to drive down the cost. This will be addressed as part of the onward development programme.

  • 8/9/2019 Pelamis Joint System Test

    44/49

     Page 38 

    The accumulators performed satisfactorily throughout the testing. There was nothing

    to split the products from the two suppliers. The accumulators were therefore selectedfor the full-scale prototype only the basis of cost and delivery. Cost reduction will be

    a priority in the onward programme.

    The reservoirs also performed faultlessly during commissioning and trials. Similar

    units have been specified for the full-scale prototype. However, costs for the

    reservoirs are again high. Also, the reservoirs are bulky and take up lots of space in

    the module. In the future it is anticipated that the reservoirs can be integrated into the

     joint module structure to save cost and space– once again this will be an objective ofthe onward programme.

    System valves generally performed adequately. In the future work will focus on

    working with the manufacturers to improve performance in terms of reducing flow

    losses and decreasing response time. The first steps in this process are underway as

    discussed in Section 3.4.4.

    Static and dynamic seal performance was generally shown to be satisfactory. The

    only issues arising were the front rod seals on the rams, and a damaged static seal on

    one of the system valves. Performance of the front rod seals was generally goodthough all such seals will leak slowly. For most of the rams this leakage was barely

     perceptible. However, one of the ram seals developed a significant leak during thecycle tests (~4-5 drops/minute). It is not clear whether this is premature wear of the

    seal or damage due to contamination from the test facility roof falling onto the ram

    rod. Performance of the front seals on the full-scale prototype will be monitored

    closely as a result. Following close examination, it was concluded that the damaged

    ‘O’ring on one of the system valves was caused during installation of the valve, rather

    than through extrusion of the seal under pressure. The matter was raised with the

    manifold manufacturer.

    The dominant source of inefficiency in the system is the hydraulic motor/generator

    sets. It is estimated that the combination results in 10-15% loss depending on the power level. The use of dual motor-generator sets running off the same circuit goes

    some way to mitigating this as it allows a single generator to be run at higher capacity

    at times of part load. However, it is estimated that motor-generator inefficiency will

    result in a revenue loss of approximately £15,000-£20,000 per annum per 750kW

    machine assuming UK Renewables Obligation prices. There is clearly a strong case toimprove the performance of the power conversion system, and significantly higher

    component costs may be tolerable if they lead to proportionately larger increases in

    energy capture. Fortunately, there remains considerable scope for improvement ofthis system. These are off the shelf items as it is seen as essential that the prototype

    and early commercial machines use 100% available technology.

    The hydraulic motors are drawn from the mobile hydraulics industry where power to

    weight and size ratio is of prime importance and efficiency a secondary consideration.

    OPD are already in consultation with a number of motor manufacturers to develop

    improved machines optimised for efficiency, particularly at part load. Optimisation of

    generator efficiency has less potential for improvement. The generators used in thefull-scale joint rig and prototype are conventional induction units, wound for

  • 8/9/2019 Pelamis Joint System Test

    45/49

     Page 39 

    maximum efficiency as generators. Their nominal efficiency is ~95% at full load.Small improvements to this can be expected through further optimisation but gains are

    expected to be small. Larger gains are possible by moving to synchronous generators.This would confer other advantages in terms of power quality and reactive power

    control and it is anticipated that a move will be made to this technology in the near

    future. It is anticipated that this will be first tested on the full-scale joint rig.

    It was recognised in the design of the full-scale joint rig that there are a large number

    of interconnections to be made between the various system components. Each

    interconnection is a source of cost and unreliability. This was to some degree

    desirable as the system was by definition a prototype. Assessment of the optimumlayout for components for ease of