PEOPLES ENERGY LIMITED KHIMTI-2 HYDROELECTRIC PROJECT (48.8 MW) PROGRESS REPORT November 2019

Upload: others

Post on 18-Mar-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

PEOPLES ENERGY LIMITED KHIMTI-2 HYDROELECTRIC PROJECT

(48.8 MW)

PROGRESS REPORT November 2019

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | i November 2019

PEOPLES ENERGY LTD.

Shree Krishna Sadan – 6th Floor, New Baneshwor-10, Kathmandu, Nepal. Tel.: +977-1-4781891, 4786030 Email: [email protected], [email protected] Website: www.peoplesenergy.com.np

Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report

November 2019

Contact Details:

Head Office: Shree Krishna Sadan, New Baneshwor-10, Kathmandu Metropolitan City, Kathmandu, State No. 3, Nepal.

Tel.: 01-4781891, 4786030

Site Office: Bhimsenthan, Gokulganga Rural Municipality, Ramechhap, State No. 3, Nepal. Tel.: 9849150807, 9840231804

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | ii November 2019

Table of Contents PEOPLES ENERGY LIMITED ....................................................................................................................... i

LIST OF ABBREVIATIONS ........................................................................................................................ iii

CHAPTER – 1 PREAMBLE ................................................................................................................... 4

1.1 Introduction ............................................................................................................................ 4

1.2 Objective of this report ........................................................................................................... 4

1.3 Key Dates and Milestones....................................................................................................... 5

1.4 Bank Consortium .................................................................................................................... 6

1.5 The Employer .......................................................................................................................... 6

1.6 Procurement and EPC-F Contract ........................................................................................... 6

1.7 Local Contractors for Site Infrastructures............................................................................... 7

1.8 Access to the Site .................................................................................................................... 8

CHAPTER – 2 TECHNICAL FEATURES OF THE PROJECT ..................................................................... 9

2.1 Salient Features of the Project ............................................................................................... 9

CHAPTER – 3 PROGRESS DETAILS ................................................................................................... 15

3.1 Progress Summary on Construction of Site Infrastructures ................................................. 15

3.2 Administrative Works ........................................................................................................... 16

3.3 Design and Physical Model Study ......................................................................................... 17

3.4 Progress work in Detail/ Photographs .................................................................................. 19

3.4.1 Access Road .................................................................................................................. 19

3.4.2 Bailey Bridge ................................................................................................................. 23

3.4.3 Camp Facilities .............................................................................................................. 25

3.4.4 33Kv Transmission line for Construction Power ........................................................... 26

3.4.5 Design & Engineering Works ........................................................................................ 27

3.4.6 Administrative Works ................................................................................................... 29

3.5 Site Progress Photographs .......................................................................................................... 31

CHAPTER – 4 RESOURCE DETAILS ................................................................................................... 33

4.1 Manpower Details ................................................................................................................ 33

4.2 Equipment Details ................................................................................................................. 34

4.3 Difficulties & issues being faced / envisaged at site ............................................................. 34

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | iii November 2019

LIST OF ABBREVIATIONS

PEL Peoples Energy Ltd.

PHCL Peoples Hydro Co-operative Ltd.

PPA Power Purchase Agreement

NEA Nepal Electricity Authority

K2HEP Khimti-2 Hydroelectric Project

HEP Hydroelectric Project

MW Mega Watts

RCOD Required Commercial Operation Date

HCE Hydro-Consult Engineering Limited

CWTW Chongqing Water Turbine Works Co. Ltd.

IEE Initial Environmental Examination

EPC-F Engineering Procurement Construction-Financing

TOR Term of Reference

LC Letter of Credit

FC Financial Closure

DFO District Forest Office

KV Kilo Volt

PH Power House

MoU Memorandum of Understanding

BDR Basic Design Report

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 4 November 2019

CHAPTER – 1 PREAMBLE

1.1 Introduction Peoples Energy Limited is being developing Khimti-2 Hydroelectric Project (48.8 MW) located in the

border of Ramechhap and Dolakha districts of Janakpur zone. Khimti River is a tributary of Tamakoshi

a major branch of Saptakoshi river system of Nepal. The Khimti River originates at EL. 4500m and

converges with the Tamakoshi River at EL. 600m. The total drainage area of the Khimti River is

492.4km2, and the drainage area in front of the intake and powerhouse is 295.34km2 and

351.4km2respectively. The river section from the dam site to powerhouse is about 7km long. The

ridges on both banks are at EL. 2,300~3,000m; the riverbed at the dam is at EL. 1,627m; the riverbed

at the powerhouse tailrace is at EL. 1,278m. The run-of-river development scheme is selected.

The headworks site is located at Rasnalu/Gokulganga Rural Municipality of Ramechhap and Jiri

Municipality of Dolakha district whereas the powerhouse site is located at Simlep and

Hawa/Tamakoshi Rural Municipality of Dolakha District. The headwork is located about 150m

downstream the confluence of Jiri Khola and Khimti Khola with headrace alignment passing along the

right bank of Khimti Khola and powerhouse site also located on the right bank.

Geographical Coordinates of Khimti-2 Hydroelectric Project

Coordinates From To

Latitude 27°33'07"N 27°35'13"N

Longitude 86°09'26"E 86°14'18"E

1.2 Objective of this report

Objective of this report is;

To update the status of various development activities completed and being undertaken in

implementation of 48.8 MW Khimti-2 Hydroelectric Project.

To update the status of schedules and planning

To bring forward the difficulties & issues being faced / envisaged at site to the notice of

concern authorities and stakeholders

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 5 November 2019

1.3 Key Dates and Milestones

S/N Activity Date Remarks

1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed

2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed

3. Updated Survey License Issuance (48.8 MW) 2070 Chaitra 7 Closed

4. IEE ToR Approval 2071 Bhadra 28 Closed

5. Grid Connection Agreement 2071 Kartik 13 Closed

6. IEE Report Approval 2072 Kartik 22 Closed

7. Power Purchase Agreement (PPA) with NEA 2072 Ashwin 14 Closed

8. Application for Generation License 2072 Kartik 11 Closed

9. Public Notice of Generation License 2073 Kartik 9-10 Closed

10. Generation License Issuance 2073 Paush 25 Closed

11. Generation License Transfer from PHCL to PEL 2073 Falgun 5 Closed

12. Land Ownership Transfer from PHCL to PEL 2074 Jestha 11 Closed

13. IEE Report Approval transfer from PHCL to PEL 2074 Ashoj 2 Closed

14. PPA Transfer from Peoples Hydro to Peoples Energy Limited 2074 Ashad 22 Closed

15. Financial Closure 2074 Ashoj 8 Closed

16. Memorandum of Understanding (MoU) Signing with CWTW in EPC-F modality 2074 Kartik 26 Closed

17. EPC-F Contract Agreement signed Between PEL and CWTW

14 March 2018 Closed

18. Shifting of Grid Connection for Power Evacuation (loop-in, loop-out with 132 kV line near PH site)

2073 Chaitra 17 Awaiting approval

19. Forest and Government Land Approval/Cabinet approval 2073 Falgun 22 Awaiting

approval

20. Explosive License 2074 Shrawan Awaiting approval

21. Updated IEE Report 2075 Chaitra Awaiting Approval

22. Required Commercial Operation Date (RCOD) 2021 July 16 (2078 Shrawan 1) Fixed Date

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 6 November 2019

1.4 Bank Consortium Financial closure (FC) for the development of Khimti-2 HEP was concluded with the bank consortium of erstwhile ten Class 'A' Commercial Banks of Nepal and now 9 after merger between Global IME Bank and Janata Bank , with Sanima Bank as the lead bank, on September 24th, 2017.

List of Consortium Banks:

S/N Name of the Bank Role Remarks 1. Sanima Bank Lead Bank/ Participating Bank 2. Siddhartha Bank Participating Bank 3. Nabil Bank Participating Bank 4. Better to delete 5. NIC Asia Bank Participating Bank 6. NMB Bank Participating Bank 7. Bank of Kathmandu Participating Bank 8. Civil Bank Participating Bank 9. Global IME Bank Participating Bank 10. NCC Bank Participating Bank

1.5 The Employer Peoples Energy Ltd. (PEL), previously Peoples Hydro Co-operative Ltd. (PHCL), is the developer of Khimti-2 Hydroelectric Project, situated at Dolakha and Ramechhap districts. PEL obtained the survey license for the project on 2012/10/31. After, feasibility level investigation was concluded and the Power Purchase Agreement (PPA) was signed with Nepal Electricity Authority (NEA) on 2015/10/01. Generation license was obtained for the project on 2017/01/06 by PHCL, and later transferred to PEL on 2017//02/16.

1.6 Procurement and EPC-F Contract The Employer has identified Chongqing Water Turbine Works (CWTW) as the EPC Contractor appropriate party to execute and implement Khimti-2 HEP in an EPC+F modality. PEL and CWTW have signed contract agreement on 14th March 2018.

EPC Contract Contract Details

Contractor: Chongqing Water Turbine Works Ltd. (Govt. Owned)

Contract Signing Date 2074 Falgun 30

Contractor’s Parent Company CME (China Govt. Owned)

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 7 November 2019

EPC Contract Price: US$88 million

EPC Cost Includes: Civil Cost, Hydro mechanical Cost, Electromechanical Cost, Transmission Line Cost, Access road and bridges, IDC, Detail Design

Developers Part: Pre-Operation Cost, Operation Cost, Land Cost, Client’s Camp, Project Supervision Cost, Environmental Cost, Documentation Cost etc.

Payment Model:

5% of Contract Price as advance payment: Within June 2018 against APG issued from Bank of China

5% of Contract Price as advance Payment: within December 2018 against APG issued from Bank of China

Rest 90% of Contract Price to be paid within 700 days from COD.

Design Company: Power China Guiyang Engineering

TAX & TDS: Included

Escalation: will not effective

Contractors Bank at China Construction Bank of China

Insurance Sinosure

1.7 Local Contractors for Site Infrastructures PEL has engaged several local contractors for the construction of site infrastructures as pre-construction activities such as access track opening and slope protection works for Access Road, drainage and stone soling for improvement of Access Road, Project Camp, Boundary wall construction and construction of three motorable bailey bridges etc. To execute the mentioned works PEL has engaged some of the local contractors employed at site are: For Bridge Construction (three bridges over Khimti Khola)

• S.K. Construction (for Dharapani Bridge at Dam Site)- Bridge I • Likhu Nirman Sewa (for Hodampa Bridge for HRT adit site)- Bridge II • Him Sagarmatha Construction (for Palate Bridge/PH site)-Bridge III

For Road Access and Gabion Works

• Bhimeshwor Nirman Sewa • Chandrama Nirman Sewa • Dangdunge Nirman Sewa • Dharmasthali Suppliers

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 8 November 2019

• Dipshree Construction • Greenland Construction • Khani Nirman Sewa • Kritim Nirman Sewa • Likhu Nirman Sewa • Moti Construction Pvt. Ltd. • New Jagriti Nirman Sewa • Peoples Nirman Sewa • Prakriti Nirman Sewa • Rambole Construction Pvt. Ltd. • Serakali Builders Pvt. Ltd. • Seti Bhumi Nirman Sewa • Sunuwar Nirman Sewa

For Camp Construction • Edgemark Consultancy Pvt. Ltd. • Jyoti Shree Interior Pvt. Ltd.

Transmission Line-Construction Power

• New Satakri Khimti Construction Pvt. Ltd.

1.8 Access to the Site The project site is accessible from Kathmandu by the following roads:

i. Kathmandu – Dhulikhel - Dolalghat – Lamosangu - Charikot - Jiri – Headworks site (198 km length)

ii. Kathmandu – Dhulikhel – Nepalthok – Khurkot – Manthali – Khimti – Betali – Bhimsenthan – Powerhouse site (174 km length)

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 9 November 2019

CHAPTER – 2 TECHNICAL FEATURES OF THE PROJECT

2.1 Salient Features of the Project

Name of Project: Khimti -2 Hydroelectric Project Installed Capacity: 48.8 MW Type of Project: Run of River (ROR) Location: Jiri Municipality and Tamakoshi Rural Municipality of Dolkha

District (Previous Jiri, Thulopatal and Hawa VDC) of Dolkha District) Gokulganga Rural Municipality of Ramechhap District (Previous Rasnalu VDC of Ramechhap District)

Comparative Salient Features of the Project:

Project Features Features Details (As per Feasibility/IEE)

Features Details (As per final DPR)

Remarks

General

Project Boundary 27°33'07"N to 27°35'13"N 86°09'26"E to 86°14'28"E

27°33'07"N to 27°35'13"N 86°09'26"E to 86°14'28"E

Gross Head 355m 351.5m

Rated Head 345.66m 341.643m

FSL 1633.00masl 1633.00 masl

Normal TWL 1275.96 masl 1275.96 masl

Minimum TWL 1275.00 masl 1275.00 masl

Turbine Centre Line 1278.00 masl 1281.50 masl

Hydrology

Catchment area at Intake site 317.94 km2 317.94 km2

Catchment area at Powerhouse 351.4 km2 351.4 km2

Average Flow 27.36 m3/sec 27.36 m3/sec

Minimum Monthly flow 4.45m3/sec 4.45m3/sec

Design Discharge(Q40) 16.11 m3/sec 16.11 m3/sec

Design flood at intake site (Q100) 1165 m3/sec 1165 m3/sec

Design flood at intake site (Q1000) 1657 m3/sec 1657 m3/sec

Diversion Structure

Type of diversion structure Ogee weir with U/ S vertical face

Ogee weir with U/ S vertical face and undersluice gates

D/S Slope 1:1 1:0.7

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 10 November 2019

Weir crest level 1633.00masl 1633.00masl

Crest Length of Chute section 10m

Crest length of Ogee section 16m 17.5 m

Total Crest Length of Weir 26m 17.5 m

Width of Weir 18.3m 12.10 m

Riverbed Level 1628.00 masl 1627.00 masl

Undersluice

Crest length of undersluice 8.5m 10 m

Width of undersluice 11.5m 14.35 m

Dimension of undersluice (L x B) 2 Nos. 3.5m x 5.5m 2 Nos. 5m X 6m

Undersluice crest level 1628.0 m 1627 masl

Undersluice Gate Radial gate, 2nos 3.5m x 5.5m

Radial gate, 2nos. 5m x 6m

Stilling Basin

Stilling Basin for Ogee Weir (L x B) 34.5 m x 16 m

26.35m X 21.08m

Stilling basin for Undersluice (L x B) 41.2 m x 9,5 m

Floor level of stilling basin 1624.00 masl 1625.00 masl

End level of stilling basin 1627.00 masl 1625.00 masl

Intake

Intake type Side intake Side Intake

Coarse trashrack (B x H) 2 nos 2.6m x 4.0 m 8 nos. 4m X 2m

Intake gate (B x H) 2nos 2.6 m x 2.6 m 2nos 2.6 m x 2.6 m

Invert level of Intake gate 1630.00 masl 1631.00 masl

Gravel Flushing Culverts Forebay Flushing Tunnel

Size (B x H) before/after gate 0.6 m x 1.0 m /1.2 m x 1.2 m 1m X 1m, 3m X 3.5m

Length after junction 19.86 m 65.2m

Number of culverts/ tunnels 2 1

Flushing Gate One, 1.2 m x 1.2 m One, 1m X 1m

Invert level of Opening 1628.8 masl 1627.00 masl

Level at beginning of culvert/tunnel 1626.6 masl 1627.00 masl

Level at Flushing end 1626.4 masl 1626.00 masl

Settling Basin

Location Surface Underground Changed

Type Dufour Dufour

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 11 November 2019

Number of compartments 2 2

Effective length 100m 55.27m, 67.31m

Total width of basin 16m 25.24m

Width of one compartment 8m 12.62 m

Height in rectangular section 8m 16.00m

Side slope of the compartment 1:1 1:1.7

Flushing system Intermittent Intermittent

Longitudinal slope of flushing channel 1:50 1:50

Invert level at the beginning of flushing channel 1624.10 masl 1624.00 masl

Invert level at the end of flushing channel 1622.10 masl 1622.65 masl

Width of the flushing channel 0.6m 1 m

Flushing Pipe NA 1 m dia.

Invert level at the beginning of flushing pipe NA 1622.65 masl

Invert level at the end of flushing pipe NA 1621.00 masl

Flushing Culvert/Tunnel (L x H) 1 m x 1 m 2mX2m (Inverted-D)

Invert level at the beginning of flushing culvert/ tunnel 1622.10 masl 1621 masl

Invert level at the end of flushing culvert/ tunnel 1621.5 masl Not Applicable

Water Conveyance system (Headrace Tunnel)

Type of flow Pressurized Pressurized

Shape of Tunnel Horse shoe Inverted D type

Length 6.6 km 6.7 km

Diameter 3.6 m 4.0m (W)X 4.25m (H)

Gradient of HRT 1:389 1:333

Tunnel Portal Level 1617 masl 1624.30 masl

Surge shaft bottom 1600 masl 1602 masl

No. of bends in HRT 5 5

Adit Tunnels

No. of Adit Tunnels 3 6 Changed

Total Length of Adit Tunnel 1029 m 2017 m

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 12 November 2019

Diameter 4 m 4m(W) X 4.25m (H)

Shape Inverted D type Inverted D type

Adit -1 Length 412m 223.78 m

Adit -1 HRT junction chainage 2+094 0+000

Adit -1 Portal level 1590 masl 1620 masl

Adit -2 Length 440 m 315.80 m

Adit -2 HRT junction chainage 3+944 3+302

Adit -2 Portal level 1590 masl 1590 masl

Adit -3 Length 177m 342m

Adit -3 HRT junction chainage 0+027(from surge tunnel outlet) 4+440

Adit -3 Portal level 1590 masl 1612 masl

Adit -4 Length 386.50m

Adit -4 HRT junction chainage 6+650

Adit -4 Portal level 1580 masl

Adit -5 Length 207.7m

Adit -5 HRT junction chainage 6+771

Adit -5 Portal level 1440 masl

Adit -6 Length 453.33 m

Adit -6 HRT junction chainage 6+902

Adit -6 Portal level 1320 masl

Surge Tunnel

Diameter 4 m 4 m

Shape Inverted D type Inverted D type

Length 437 m 412m

Surge Tunnel –HRT junction chainage 6+614 6+627

Invert level of inlet 1600.00 masl 1602 masl

Invert level of outlet 1660.00 masl 1655.20 masl

Pressure Shaft / Tunnel

Diameter 2.3 m 2.3 m

Total Length 822 m

Length upto Manifold 425.7 m 653 m

Vertical section 323.8 m 353 m (Inclined Shaft)

Horizontal shaft section 101.9 m 300m

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 13 November 2019

Manifold length 18.3 m Not Applicable

Manifold diameter 1.9 m Not Applicable

Pressure shaft after Manifold 2 x 24.13 m 169m in total

Diameter of pressure after manifold 1.5 m 1.3 m

Lining Steel lined embedded in concrete

Shotcrete wire mesh and bolts lining

Powerhouse

Type of Power house Underground Surface Changed

Powerhouse cavern dimension (l x B x H)

46 m x 12m x 21m (from turbine CL) 45m x 16m x 32m

Transformer cavern dimension (l x B x H) 37m x 10m x 18 m Not Applicable Surface

structure

Cavern Crown level 1299.00 masl Not Applicable

Machine floor level 1286.00 masl 1293.80 masl

Turbine Axis Level 1278.00 masl 1281.50 masl

Turbine

Type of turbine Pelton Pelton

Shaft configuration Vertical Vertical

No.of turbine 2 3

Turbine Output 24.4 MW 16.267 MW

No of nozzle 5 6

Specific speed 500 rpm 500 rpm

Optimal jet diameter 180mm 128 mm

Generator

Type Synchronous Synchronous

Rated output capacity per unit 24.4 MW 16.267 MW

Power Factor 0.85 0.85

Voltage 11 KV 11kV

Frequency 50 Hz 50 Hz

No. of Units 2 3

Efficiency 98% greater than 97.5%

Transformer

No. of Transformer 7 Nos., single phase including 1 sphere 3 Nos., three-phase

Rated capacity 2 units of 3 x 10 MVA 3 units, 3 x 22 MVA

Voltage ratio 11/132 kV 11/132 kV

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 14 November 2019

Efficiency 99% 99%

Transmission line

Length 11.5 km 11.5 km

Type 132 kV,Single circuit 132 kV,Single circuit

Cable ASCR,Bear ASCR,Bear

Tailrace Outlet

Type Tunnel Box Culvert

Type of flow Free flow Free flow

Shape Inverted D type Rectangular

Diameter 4m 3.5m X 3.5m

Total length of tailrace tunnel 562 m 180m

Invert level of outlet 1274.36 masl 1274.91 masl

Energy

Wet Energy 217.5 GWh 219.5 GWh

Dry Energy 44 GWh 40.8 GWh

Total Energy 261 GWh 260.3 GWh

Firm Energy 113 GWh 107 GWh

Financial

Total Project cost NRs. 7.45 billion NRs. 7.45 billion

Revenue NRs. 1.4 billion NRs. 1.4 billion

B/C Ratio 1 .41 1 .41

IRR 16.01 % 16.01 %

Cost per MW (USD) 1550 1550

Access to the site

Kathmandu- Charikot - Jiri 198 km (188 km blacktopped)

198 km (188 km blacktopped)

Jiri to Dam site 11 km Gravel Road 11 km Gravel Road

Dam Site to Powerhouse site 16 km Gravel Road 16 km Gravel Road

Birgunj-Bardibas-Khurkot- Manthali-Kirnetar/Khimti 290 km 290 km

Khimti to Powerhouse site 27 km Gravel Road 27 km Gravel Road

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 15 November 2019

CHAPTER – 3 PROGRESS DETAILS

3.1 Progress Summary on Construction of Site Infrastructures

S/N Project Activity Total Length Status/Progress

ACCESS ROAD

1. Dharapani to Dam site (Ramechhap side) • 1.0 km

• 1.0 km of Track opening works – Completed.

• Gabion works/Slope protection – Completed.

2. Intake-Dharapani Road (Dolakha Side) • 0.5 km

• 200 m of Track Opening – completed. • Rock cutting till foundation level of right

abutment – Completed.

3. Burke – Hodampa/Phulping (Ramechhap side)

• 2.5 km

• 2.5 km track opening completed Gabion works and Maintenance of Burke-Bhage road- Ongoing.

4. Thulopatal – Hodampa/Phulping - Gaighat (Dolakha side)

• 2.0 km • 2.0 km Track opening - Completed. • Gabion works and widening the track is

remaining

5. Hanwa - Palate (Dolakha side) • 5.5 km

• 3.0 km (out of 5.5 km) of Track opening – Completed.

• Remaining works on 2.5 km – Pending due to forest clearance issue.

6.

Bhimsenthan – Palate/Powerhouse site new track (Ramechhap side)

• 0.5 km

• 0.5 km of Track opening – Completed. • Slope protection completed. • Gabion work to protect road section at

river side remaining.

7.

Bhimsenthan – Palate/Powerhouse site Old track to be upgraded (Ramechhap side)

• 3.0 km • Stone soling works & side drainage for access road improvement – Completed.

PROJECT CAMP

8. Camp Boundary Wall – Civil/Masonry works

• Wall and Permanent fencing

• Camp Boundary Wall construction completed

• Fencing work completed

9. Camp Building Construction works

• Total 12 Buildings

• All civil and electrical works completed • Partial Furnishing has been done • Full Furnishing is ongoing • Landscaping work is ongoing

10. Water Supply System • Drinking

water to Project Camp

• Construction of water supply system completed and is in operational

• Some of the balance protection work of intake and reservoir area is ongoing

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 16 November 2019

• Drinking water to Locals

• Reservoir tank- Location fixed • Pipe Laying remaining • Tap stand construction remaining.

33KV TRANSMISSION LINE FOR CONSTRUCTION POWER

11. 33 KV Transmission Line for Construction power

• 9 km 33 kV sub-transmission line

• Contract awarded to New Satakri Khimti Construction

• Pole erection from Dam site to PH site completed.

• Cable installation completed in Ramechhap side.

• Pole erection and cable installation in Dolakha side remaining.

• Transformer installation remaining. • Connection in grid with KREC-Ongoing

BAILEY BRIDGE

12. Dharapani Bridge (Bridge I) • 42.672m

• Civil works Completed. • Erection work Completed. • Approach Slab and Traffic signs installation-

remaining.

13. Hodampa Bridge (Bridge II) • 33.528m

• Civil works Completed. • Erection work Completed. • Approach Slab and Traffic signs installation-

remaining.

14. Hawa-Palate Bridge (Bridge III) • 51.816m

• Civil works Completed. • Erection work Completed. • Approach Slab and Traffic signs installation-

remaining. OTHER ACTIVITIES

15. Hydrology and Sediment Study

• Hydrology and Sediment Study

• Sediment collection & Analysis by HydroLab-Completed.

• Discharge Measurement & Hydrological Analysis by Recham Consult -Completed.

3.2 Administrative Works

16. ADMINISTRATIVE WORKS

• Various administrative issues

• Shifting grid

Connection for Power Evacuation

• Forest clearance approval – File forwardedto Ministry of Forest

• Land acquisition: about 95% completed • Survey License for Transmission Line

(Power Evacuation): Documents being compiled.

• Explosives License: initiated.

• Preliminary discussion held on loop-in, loop-out with NEA Grid Division.

• CC committee formed, a brief study has been done and submitted to NEA

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 17 November 2019

• Explosive

License • Updated IEE

Report

• First CC meeting held and initiated discussion

• Applied to DoED with all required

document • Received the recommendation from DoED

and letter to Ministry of Home. • Ministry of Home written letter to Ministry

of Defense and concerned Districts CDO to issue the carrier License.

• Approval received for Nepali explosive only.

• Appointed Nepal Environment and

Development Consultant for IEE update works

• Application submitted on March 7,2019 • Approval to update received on April 10,

2019 • Consultant team visited site and

completed the data collection • Public consultation and focus group

discussion completed • Final Updated IEE report is submitted to

DoED Final approval awaited

17. LOCAL STAKEHOLDERS ENGAGAMENT • Local issues

• Local Stakeholders Engagement through various discussion, addressing the project related environmental and social issues

• Implementing various social and local infrastructural development works

3.3 Design and Physical Model Study

18. BASIC DESIGN REPORT (BDR)

• EPC Contractors (CWTW)

• Responsibility

• EPC Contractor has Submitted the Final Basic Design Report after incorporation of Employers Comments

• Employers Responsibility

• Employer has again reviewed and provided the conditional approval; Subject to required modifications during construction.

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 18 November 2019

19. PHYSICAL HYDRAULIC MODEL STUDY

• Model of Revised Headworks

• Consulting contract award to Hydrolab • Provided required documents • Hydrolab completed river model validation

works • Similarly, completed model construction

of structures. • First model run carried out and joint

observation of the performance was completed and noticed some modification was required for certain structures

• The design modification was carried out • The modified design constructed and

model validation re-run carried out on 22nd July,2019. Observed good performance with bed load sluice; remaining change to be verified by the modification of the Model.

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 19 November 2019

3.4 Progress work in Detail

3.4.1 Access Road Headworks Area-Dharapani Road (Ramechhap) The track to headworks of Khimti-2 Hydroelectric project of 1.0 Km length is completed connecting from existing road in Dharapani, Ramechhap. Cross-drainage has been provided in three major parts of the road section along with masonry side drain in critical section of the road. Gabion works and Masonry breast wall are provided for slope protection in vulnerable portions of the road section.

Future Plans:

• Side drain in full section of the road is required in order to protect the road from the heavy downpour.

• Soling at certain portion are required in order for heavy vehicle to travel uphill slope of the road.

• Slope Protection by gabion are required in certain portions damaged recently by rainfall.

Headworks-Intake Area (Dolakha) Massive rock back cutting just Infront of headworks’ bailey bridge in order to provide required turning radius for the vehicle has been completed.

Future Plans:

• 300m length section of road to dam site is remaining.

• Locals are demanding the connection of existing road (Hawa-Phulping-Jiri Road) to bridge in headworks of Khimti-2 in dolakha side.

Dharapani Access Road

Access road to Headworks-Dolakha

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 20 November 2019

HRT adit-Burke-Hodampa Road (Ramechhap) Track opening of 2.5 Km stretch of road from Burke through bhage to hodampa is completed. Earthen side drain and cross drainage through causeway are provided in burke to bhage road section. Gabion in critical road turnings are provided.

Future Plans:

• This road section is most affected by the monsoon rain causing landslide in multiple sections completely blocking the road hence, necessary gabion works and permanent cross drainage are required.

• Side drain and proper cross drainage is required.

HRT adit- Phulping-Gaighat Road (Dolakha) Track from gaighat is connected to Bailey Bridge II (Hodampa Bridge) in phulping linking dolakha and ramechhap district. This 2.0 Km section of roads serves as a connection to project HRT adit from major road Bhirkot-Jiri of dolakha side.

Future Plans:

• Grade of the road in certain portion of road is to be maintained. • Water from monsoon has eroded away fill side of the road section which needs to be maintained

providing gabion in critical sections. • Widening of road section is required in certain places. • Cross drainage, side drain and slope protection are to be provided for the longevity of the road.

Phulping-Gaighat Access Road

Burke Hodammpa Access road to Phulping Adit

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 21 November 2019

Powerhouse- Bhimsenthan-Palate Road (Ramechhap) Out of 3.5 Km length of Bhimsenthan palate road, track opening of 3.0 Km road section was already completed by khimti-1 project. Remaining 0.5 Km of road to powerhouse site has been completed. Side drain has been provided throughout the length of the road. Hume pipe is provided for cross drainage of water. Freshly cut 0.5 Km section of road triggered a landslide which was controlled by providing gabion as retaining structure. Stone soling in all the slippery slopes of the road is provided to give traction to the vehicle.

Future Plans:

• Gabion work to protect road section at river side of freshly cut 0.5Km section is remaining.

HRT outlet, surge tunnel-Hawa-Palate Road (Dolakha) 3.0 Km out of 5.5 Km section of hawa-tuspe-palate road track has been excavated, gabion in the venerable slopes has been completed for this 3.0 km stretch. Two major landslides were triggered in

Bhimsenthan-Palate Access Road

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 22 November 2019

this road section, one of which is stabilized by nailing bamboo in the ground and addressing seepage by providing perforated hdpe pipes throughout the unstable slope. Hume pipe is placed for cross drainage in the road. Remaining 2.5 Km section of road is pending due to forest clearance issue.

Future Plans:

• Remaining 2.5 Km track is to be opened and provide necessary protection works. • Permanent side drain is required to protect the road.

Bhimsenthan-Palate Access Road

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 23 November 2019

3.4.2 Bailey Bridge Bailey Bridge I (Dharapani Bridge) • Civil work: By S. K. Construction pvt. Ltd. – Completed • Span: 42.672m • Maximum Load capacity: 30T • Bailey Bridge erection work: Completed

Bailey Bridge II (Hodampa Bridge) • Civil work: By Likhu Nirman Sewa – Completed • Maximum Load Capacity: 20T • Span: 33.528m • Bailey Bridge erection work: Completed

Bailey Bridge I: Dharapani Bridge

Bailey Bridge II: Hodampa Bridge

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 24 November 2019

Bailey Bridge III (Hawa-Palate Bridge) • Civil work: By Him Sagarmatha – Completed • Maximum Load Capacity: 30T • Span: 51.816m • Bailey Bridge erection work: Completed

Future Plans

• Dirt wall and Approach wall for all three bridges are remaining which is planned to be completed within next one month.

Bailey Bridge III: Hawa-Palate Bridge

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 25 November 2019

3.4.3 Camp Facilities

Civil Works The Khimti-2 main camp located in Lamatar, Rasnalu Ramechhap contains 12 buildings with 7 Staff Quarters, one Kitchen, two office buildings, one Guest house and a Guard house. This camp is to facilitate during the construction phase of the project as well as during operation phase of the Project.

Work progress on Camp buildings

• The Fencing work surrounding the camp area with chain link and masonry wall along with erection of gate has been completed.

• All civil works of 12 buildings including truss works and roofing has been completed. • Aluminum doors and windows of all buildings completed. • All painting works has been completed. • False Ceiling works all buildings completed. • Sanitary work -Manhole and pipe laying for all the building are completed and construction of

third Soak pit is also completed. • Electrical works of all buildings completed.

Future Plans

• Landscaping of the camp area • Completion of balance furnishing of all residential as well as office building

Khimti-2 Project Camp

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 26 November 2019

Water supply work Drinking water supply for the camp facility of the Khimti -2 project is tapped from the underground water near darkha about 1km away from the camp area.

Work Progress on Water supply to camp

• Drinking water source identified and registration process completed. • Pipe laying from intake to the camp has been completed. • All the civil works and pipe fitting works in Intake area is completed. • All the civil works of reservoir tank is completed. • Pipe laying and fitting works inside the camp area are completed.

Future Plans

• Works for supplying drinking water to some locals near the camp area in ongoing. • Construction of reservoir tank, pipe laying and tap stand for drinking water facility to locals.

3.4.4 33Kv Transmission line for Construction Power About 9km sub-transmission line from Headworks area of Khimti2 HEP , Dharapani to powerhouse site of Khimti-2 hydroelectric project is required to supply power to different sites during the construction phase.

Work Progress on 33kv construction power

• Contract awarded to New Satakri Khimti Construction. • Pole erection, cable installation along with all necessary

accessories from headworks to powerhouse site in Ramechhap side completed.

Water Supply works: Intake Area Water Supply works: Reservoir tank

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 27 November 2019

Future Plans

• Connection from Hodammpa to Phulping adit . • Connection from powerhouse site to surge shaft site. • Installation of Transformer in different site location.

3.4.5 Design & Engineering Works

Design approval and site mobilization of contractor

Basic design report (BDR) submitted by CWTW has been given conditional approval: subjected to required modification during construction on 5th Dec, 2018.

Work Progress on Physical Hydraulic Modelling

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 28 November 2019

• Agreement done with Hydro-lab for construction of Physical Hydraulic model

• River model and headworks model construction completed

• Joint observation of model run conducted • Noticed serious problems requiring major

modification on the design • Thick bedload deposit in front of intake

was observed blocking the intake • Outlet of the flushing tunnel was

submerged during high flood operation.

• The modified design constructed and model validation re-run carried out on 22nd July,2019. • In the modified design, bottom bedload sluice with radial gate flushing was added with changes

in forebay hopper. No. of intake was reduced to five from initially proposed eight.

First run of Physical hydraulic model of Khimti-2 Project

Re-run of hydraulic model after major changes in structure

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 29 November 2019

After the re-run of model, the performance of the bed load sluice was satisfactory remaining changes are to be verified by the modification of the model.

Progress on CWTW site Mobilization

• As mobilization of contractor is dependent on the advance payment, works on applying for the loan are at its final stage.

• CWTW have finalized the civil sub-contractor.

3.4.6 Administrative Works

Progress on Updated IEE Report

• Nepal Environment and Development Consultant has been appointed for the preparation of the updated IEE report.

• Consultant team visited to site and completed the data collection work • Public consultation and Focus group discussions are completed. • Review and comments on the draft UIEE report has been addressed. • Final Report submitted to DoED and awaited for final approval.

Progress on Survey License for Loop in Loop out

• Discussion was done with NEA for shifting the connection agreement • A study for the technical and economical assessment has been done and submitted to NEA. • First CC meeting was held.

Progress on Other Administrative works

• Technical Verification Process-Ongoing • Survey License for Loop in Loop out has been initiated. • Approval has been received for the Nepali Explosives.

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 30 November 2019

• For the Forest Clearance Approval, the file has been forwarded to Ministry of Forest from Forest Department.

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 31 November 2019

3.5 Site Progress Photographs

Project Camp: External Painting Work Sanitary Works: Excavation for Manhole Preparation

Sanitary Work: Pipe Laying Sanitary Works: Manhole Preparation

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 32 November 2019

Sanitary Work: Soak Pit

Painting Work: Internal painting of the Building

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 33 November 2019

CHAPTER – 4 RESOURCE DETAILS

4.1 Manpower Details

S/N Name Designation

Head Office:

1. Dev Bahadur Poudel Chhetri Director, Public Relations/Social Issues 2. Prof. Hari Prasad Pandit, Ph.D. Chief Technical Adviser 3. Ram Hari Sharma Project Manager 4. Kushal Sundar Shrestha Head, Procurement/Human Resources 5. Janardan Aryal General Manager 6. Bindu Shrestha Account Officer 7. Anjuli Khadka Civil Engineer 8. Prachan Shrestha Civil Engineer 9. Samrat Acharya Procurement/Admin Officer 10. Bikram Acharya Procurement/Logistics Officer 11. Anjali Aryal Account Assistant

Site Office:

12. Pradip Nepal Deputy Project Manager (Civil Engineer) 13. Toya Nath Ghimire Geologist 14. Amul Tandukar Civil Engineer 15. Niroj Kusi Civil Engineer 16. Sagar Poudel Civil Engineer 17. Sujan Kasichhwa Electrical Engineer 18. Hari Sharan Adhikari Social Mitigation Officer 19. Krishna Hari Neupane Accountant 20. Anish Bhandari Surveyor 21. Sangita Sunuwar Supervisor 22. Birendra Karki Sub-Overseer 23. Bishnu Gharti Vehicle Driver 24. Dhan Bahadur Magar Vehicle Driver 25. Mohan Khatri Vehicle Driver 26. Dhurba Karki Cook 27. Moti Lal Tamang JCB Operator 28. Surya Bahadur Bhujel Tractor Driver 29. Hom Dhoj Karki Security Guard

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 34 November 2019

4.2 Equipment Details

S/N Vehicle/Equipment Location Number Remarks 1. JCB Backhoe Loader At Site 1 PEL Owned 2. New-Holland Tractor At Site 1 PEL Owned 3. Mahindra Bolero Pick-up At Site 1 PEL Owned 4. Bolero Pick up Jeep At Site 1 PEL Owned 5. Motorcycle (Honda Shine) At Site 1 PEL Owned 6. Hired Excavators At Site 3 Hire

4.3 Difficulties & issues being faced / envisaged at site Local disturbances for the construction reservoir tank for water supply in project camp. Delay to open the access to surge shaft due to pending of forest land approval file at Ministry

of Forest to be approved by Cabinet through Ministry of Forest. Delay to get the Explosive license and bunker construction as well as security barrack

construction. Locals various demands like infrastructure development, contracts as well as employment.