peoples energy limited
TRANSCRIPT
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | i November 2019
PEOPLES ENERGY LTD.
Shree Krishna Sadan – 6th Floor, New Baneshwor-10, Kathmandu, Nepal. Tel.: +977-1-4781891, 4786030 Email: [email protected], [email protected] Website: www.peoplesenergy.com.np
Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report
November 2019
Contact Details:
Head Office: Shree Krishna Sadan, New Baneshwor-10, Kathmandu Metropolitan City, Kathmandu, State No. 3, Nepal.
Tel.: 01-4781891, 4786030
Site Office: Bhimsenthan, Gokulganga Rural Municipality, Ramechhap, State No. 3, Nepal. Tel.: 9849150807, 9840231804
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | ii November 2019
Table of Contents PEOPLES ENERGY LIMITED ....................................................................................................................... i
LIST OF ABBREVIATIONS ........................................................................................................................ iii
CHAPTER – 1 PREAMBLE ................................................................................................................... 4
1.1 Introduction ............................................................................................................................ 4
1.2 Objective of this report ........................................................................................................... 4
1.3 Key Dates and Milestones....................................................................................................... 5
1.4 Bank Consortium .................................................................................................................... 6
1.5 The Employer .......................................................................................................................... 6
1.6 Procurement and EPC-F Contract ........................................................................................... 6
1.7 Local Contractors for Site Infrastructures............................................................................... 7
1.8 Access to the Site .................................................................................................................... 8
CHAPTER – 2 TECHNICAL FEATURES OF THE PROJECT ..................................................................... 9
2.1 Salient Features of the Project ............................................................................................... 9
CHAPTER – 3 PROGRESS DETAILS ................................................................................................... 15
3.1 Progress Summary on Construction of Site Infrastructures ................................................. 15
3.2 Administrative Works ........................................................................................................... 16
3.3 Design and Physical Model Study ......................................................................................... 17
3.4 Progress work in Detail/ Photographs .................................................................................. 19
3.4.1 Access Road .................................................................................................................. 19
3.4.2 Bailey Bridge ................................................................................................................. 23
3.4.3 Camp Facilities .............................................................................................................. 25
3.4.4 33Kv Transmission line for Construction Power ........................................................... 26
3.4.5 Design & Engineering Works ........................................................................................ 27
3.4.6 Administrative Works ................................................................................................... 29
3.5 Site Progress Photographs .......................................................................................................... 31
CHAPTER – 4 RESOURCE DETAILS ................................................................................................... 33
4.1 Manpower Details ................................................................................................................ 33
4.2 Equipment Details ................................................................................................................. 34
4.3 Difficulties & issues being faced / envisaged at site ............................................................. 34
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | iii November 2019
LIST OF ABBREVIATIONS
PEL Peoples Energy Ltd.
PHCL Peoples Hydro Co-operative Ltd.
PPA Power Purchase Agreement
NEA Nepal Electricity Authority
K2HEP Khimti-2 Hydroelectric Project
HEP Hydroelectric Project
MW Mega Watts
RCOD Required Commercial Operation Date
HCE Hydro-Consult Engineering Limited
CWTW Chongqing Water Turbine Works Co. Ltd.
IEE Initial Environmental Examination
EPC-F Engineering Procurement Construction-Financing
TOR Term of Reference
LC Letter of Credit
FC Financial Closure
DFO District Forest Office
KV Kilo Volt
PH Power House
MoU Memorandum of Understanding
BDR Basic Design Report
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 4 November 2019
CHAPTER – 1 PREAMBLE
1.1 Introduction Peoples Energy Limited is being developing Khimti-2 Hydroelectric Project (48.8 MW) located in the
border of Ramechhap and Dolakha districts of Janakpur zone. Khimti River is a tributary of Tamakoshi
a major branch of Saptakoshi river system of Nepal. The Khimti River originates at EL. 4500m and
converges with the Tamakoshi River at EL. 600m. The total drainage area of the Khimti River is
492.4km2, and the drainage area in front of the intake and powerhouse is 295.34km2 and
351.4km2respectively. The river section from the dam site to powerhouse is about 7km long. The
ridges on both banks are at EL. 2,300~3,000m; the riverbed at the dam is at EL. 1,627m; the riverbed
at the powerhouse tailrace is at EL. 1,278m. The run-of-river development scheme is selected.
The headworks site is located at Rasnalu/Gokulganga Rural Municipality of Ramechhap and Jiri
Municipality of Dolakha district whereas the powerhouse site is located at Simlep and
Hawa/Tamakoshi Rural Municipality of Dolakha District. The headwork is located about 150m
downstream the confluence of Jiri Khola and Khimti Khola with headrace alignment passing along the
right bank of Khimti Khola and powerhouse site also located on the right bank.
Geographical Coordinates of Khimti-2 Hydroelectric Project
Coordinates From To
Latitude 27°33'07"N 27°35'13"N
Longitude 86°09'26"E 86°14'18"E
1.2 Objective of this report
Objective of this report is;
To update the status of various development activities completed and being undertaken in
implementation of 48.8 MW Khimti-2 Hydroelectric Project.
To update the status of schedules and planning
To bring forward the difficulties & issues being faced / envisaged at site to the notice of
concern authorities and stakeholders
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 5 November 2019
1.3 Key Dates and Milestones
S/N Activity Date Remarks
1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed
2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed
3. Updated Survey License Issuance (48.8 MW) 2070 Chaitra 7 Closed
4. IEE ToR Approval 2071 Bhadra 28 Closed
5. Grid Connection Agreement 2071 Kartik 13 Closed
6. IEE Report Approval 2072 Kartik 22 Closed
7. Power Purchase Agreement (PPA) with NEA 2072 Ashwin 14 Closed
8. Application for Generation License 2072 Kartik 11 Closed
9. Public Notice of Generation License 2073 Kartik 9-10 Closed
10. Generation License Issuance 2073 Paush 25 Closed
11. Generation License Transfer from PHCL to PEL 2073 Falgun 5 Closed
12. Land Ownership Transfer from PHCL to PEL 2074 Jestha 11 Closed
13. IEE Report Approval transfer from PHCL to PEL 2074 Ashoj 2 Closed
14. PPA Transfer from Peoples Hydro to Peoples Energy Limited 2074 Ashad 22 Closed
15. Financial Closure 2074 Ashoj 8 Closed
16. Memorandum of Understanding (MoU) Signing with CWTW in EPC-F modality 2074 Kartik 26 Closed
17. EPC-F Contract Agreement signed Between PEL and CWTW
14 March 2018 Closed
18. Shifting of Grid Connection for Power Evacuation (loop-in, loop-out with 132 kV line near PH site)
2073 Chaitra 17 Awaiting approval
19. Forest and Government Land Approval/Cabinet approval 2073 Falgun 22 Awaiting
approval
20. Explosive License 2074 Shrawan Awaiting approval
21. Updated IEE Report 2075 Chaitra Awaiting Approval
22. Required Commercial Operation Date (RCOD) 2021 July 16 (2078 Shrawan 1) Fixed Date
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 6 November 2019
1.4 Bank Consortium Financial closure (FC) for the development of Khimti-2 HEP was concluded with the bank consortium of erstwhile ten Class 'A' Commercial Banks of Nepal and now 9 after merger between Global IME Bank and Janata Bank , with Sanima Bank as the lead bank, on September 24th, 2017.
List of Consortium Banks:
S/N Name of the Bank Role Remarks 1. Sanima Bank Lead Bank/ Participating Bank 2. Siddhartha Bank Participating Bank 3. Nabil Bank Participating Bank 4. Better to delete 5. NIC Asia Bank Participating Bank 6. NMB Bank Participating Bank 7. Bank of Kathmandu Participating Bank 8. Civil Bank Participating Bank 9. Global IME Bank Participating Bank 10. NCC Bank Participating Bank
1.5 The Employer Peoples Energy Ltd. (PEL), previously Peoples Hydro Co-operative Ltd. (PHCL), is the developer of Khimti-2 Hydroelectric Project, situated at Dolakha and Ramechhap districts. PEL obtained the survey license for the project on 2012/10/31. After, feasibility level investigation was concluded and the Power Purchase Agreement (PPA) was signed with Nepal Electricity Authority (NEA) on 2015/10/01. Generation license was obtained for the project on 2017/01/06 by PHCL, and later transferred to PEL on 2017//02/16.
1.6 Procurement and EPC-F Contract The Employer has identified Chongqing Water Turbine Works (CWTW) as the EPC Contractor appropriate party to execute and implement Khimti-2 HEP in an EPC+F modality. PEL and CWTW have signed contract agreement on 14th March 2018.
EPC Contract Contract Details
Contractor: Chongqing Water Turbine Works Ltd. (Govt. Owned)
Contract Signing Date 2074 Falgun 30
Contractor’s Parent Company CME (China Govt. Owned)
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 7 November 2019
EPC Contract Price: US$88 million
EPC Cost Includes: Civil Cost, Hydro mechanical Cost, Electromechanical Cost, Transmission Line Cost, Access road and bridges, IDC, Detail Design
Developers Part: Pre-Operation Cost, Operation Cost, Land Cost, Client’s Camp, Project Supervision Cost, Environmental Cost, Documentation Cost etc.
Payment Model:
5% of Contract Price as advance payment: Within June 2018 against APG issued from Bank of China
5% of Contract Price as advance Payment: within December 2018 against APG issued from Bank of China
Rest 90% of Contract Price to be paid within 700 days from COD.
Design Company: Power China Guiyang Engineering
TAX & TDS: Included
Escalation: will not effective
Contractors Bank at China Construction Bank of China
Insurance Sinosure
1.7 Local Contractors for Site Infrastructures PEL has engaged several local contractors for the construction of site infrastructures as pre-construction activities such as access track opening and slope protection works for Access Road, drainage and stone soling for improvement of Access Road, Project Camp, Boundary wall construction and construction of three motorable bailey bridges etc. To execute the mentioned works PEL has engaged some of the local contractors employed at site are: For Bridge Construction (three bridges over Khimti Khola)
• S.K. Construction (for Dharapani Bridge at Dam Site)- Bridge I • Likhu Nirman Sewa (for Hodampa Bridge for HRT adit site)- Bridge II • Him Sagarmatha Construction (for Palate Bridge/PH site)-Bridge III
For Road Access and Gabion Works
• Bhimeshwor Nirman Sewa • Chandrama Nirman Sewa • Dangdunge Nirman Sewa • Dharmasthali Suppliers
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 8 November 2019
• Dipshree Construction • Greenland Construction • Khani Nirman Sewa • Kritim Nirman Sewa • Likhu Nirman Sewa • Moti Construction Pvt. Ltd. • New Jagriti Nirman Sewa • Peoples Nirman Sewa • Prakriti Nirman Sewa • Rambole Construction Pvt. Ltd. • Serakali Builders Pvt. Ltd. • Seti Bhumi Nirman Sewa • Sunuwar Nirman Sewa
For Camp Construction • Edgemark Consultancy Pvt. Ltd. • Jyoti Shree Interior Pvt. Ltd.
Transmission Line-Construction Power
• New Satakri Khimti Construction Pvt. Ltd.
1.8 Access to the Site The project site is accessible from Kathmandu by the following roads:
i. Kathmandu – Dhulikhel - Dolalghat – Lamosangu - Charikot - Jiri – Headworks site (198 km length)
ii. Kathmandu – Dhulikhel – Nepalthok – Khurkot – Manthali – Khimti – Betali – Bhimsenthan – Powerhouse site (174 km length)
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 9 November 2019
CHAPTER – 2 TECHNICAL FEATURES OF THE PROJECT
2.1 Salient Features of the Project
Name of Project: Khimti -2 Hydroelectric Project Installed Capacity: 48.8 MW Type of Project: Run of River (ROR) Location: Jiri Municipality and Tamakoshi Rural Municipality of Dolkha
District (Previous Jiri, Thulopatal and Hawa VDC) of Dolkha District) Gokulganga Rural Municipality of Ramechhap District (Previous Rasnalu VDC of Ramechhap District)
Comparative Salient Features of the Project:
Project Features Features Details (As per Feasibility/IEE)
Features Details (As per final DPR)
Remarks
General
Project Boundary 27°33'07"N to 27°35'13"N 86°09'26"E to 86°14'28"E
27°33'07"N to 27°35'13"N 86°09'26"E to 86°14'28"E
Gross Head 355m 351.5m
Rated Head 345.66m 341.643m
FSL 1633.00masl 1633.00 masl
Normal TWL 1275.96 masl 1275.96 masl
Minimum TWL 1275.00 masl 1275.00 masl
Turbine Centre Line 1278.00 masl 1281.50 masl
Hydrology
Catchment area at Intake site 317.94 km2 317.94 km2
Catchment area at Powerhouse 351.4 km2 351.4 km2
Average Flow 27.36 m3/sec 27.36 m3/sec
Minimum Monthly flow 4.45m3/sec 4.45m3/sec
Design Discharge(Q40) 16.11 m3/sec 16.11 m3/sec
Design flood at intake site (Q100) 1165 m3/sec 1165 m3/sec
Design flood at intake site (Q1000) 1657 m3/sec 1657 m3/sec
Diversion Structure
Type of diversion structure Ogee weir with U/ S vertical face
Ogee weir with U/ S vertical face and undersluice gates
D/S Slope 1:1 1:0.7
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 10 November 2019
Weir crest level 1633.00masl 1633.00masl
Crest Length of Chute section 10m
Crest length of Ogee section 16m 17.5 m
Total Crest Length of Weir 26m 17.5 m
Width of Weir 18.3m 12.10 m
Riverbed Level 1628.00 masl 1627.00 masl
Undersluice
Crest length of undersluice 8.5m 10 m
Width of undersluice 11.5m 14.35 m
Dimension of undersluice (L x B) 2 Nos. 3.5m x 5.5m 2 Nos. 5m X 6m
Undersluice crest level 1628.0 m 1627 masl
Undersluice Gate Radial gate, 2nos 3.5m x 5.5m
Radial gate, 2nos. 5m x 6m
Stilling Basin
Stilling Basin for Ogee Weir (L x B) 34.5 m x 16 m
26.35m X 21.08m
Stilling basin for Undersluice (L x B) 41.2 m x 9,5 m
Floor level of stilling basin 1624.00 masl 1625.00 masl
End level of stilling basin 1627.00 masl 1625.00 masl
Intake
Intake type Side intake Side Intake
Coarse trashrack (B x H) 2 nos 2.6m x 4.0 m 8 nos. 4m X 2m
Intake gate (B x H) 2nos 2.6 m x 2.6 m 2nos 2.6 m x 2.6 m
Invert level of Intake gate 1630.00 masl 1631.00 masl
Gravel Flushing Culverts Forebay Flushing Tunnel
Size (B x H) before/after gate 0.6 m x 1.0 m /1.2 m x 1.2 m 1m X 1m, 3m X 3.5m
Length after junction 19.86 m 65.2m
Number of culverts/ tunnels 2 1
Flushing Gate One, 1.2 m x 1.2 m One, 1m X 1m
Invert level of Opening 1628.8 masl 1627.00 masl
Level at beginning of culvert/tunnel 1626.6 masl 1627.00 masl
Level at Flushing end 1626.4 masl 1626.00 masl
Settling Basin
Location Surface Underground Changed
Type Dufour Dufour
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 11 November 2019
Number of compartments 2 2
Effective length 100m 55.27m, 67.31m
Total width of basin 16m 25.24m
Width of one compartment 8m 12.62 m
Height in rectangular section 8m 16.00m
Side slope of the compartment 1:1 1:1.7
Flushing system Intermittent Intermittent
Longitudinal slope of flushing channel 1:50 1:50
Invert level at the beginning of flushing channel 1624.10 masl 1624.00 masl
Invert level at the end of flushing channel 1622.10 masl 1622.65 masl
Width of the flushing channel 0.6m 1 m
Flushing Pipe NA 1 m dia.
Invert level at the beginning of flushing pipe NA 1622.65 masl
Invert level at the end of flushing pipe NA 1621.00 masl
Flushing Culvert/Tunnel (L x H) 1 m x 1 m 2mX2m (Inverted-D)
Invert level at the beginning of flushing culvert/ tunnel 1622.10 masl 1621 masl
Invert level at the end of flushing culvert/ tunnel 1621.5 masl Not Applicable
Water Conveyance system (Headrace Tunnel)
Type of flow Pressurized Pressurized
Shape of Tunnel Horse shoe Inverted D type
Length 6.6 km 6.7 km
Diameter 3.6 m 4.0m (W)X 4.25m (H)
Gradient of HRT 1:389 1:333
Tunnel Portal Level 1617 masl 1624.30 masl
Surge shaft bottom 1600 masl 1602 masl
No. of bends in HRT 5 5
Adit Tunnels
No. of Adit Tunnels 3 6 Changed
Total Length of Adit Tunnel 1029 m 2017 m
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 12 November 2019
Diameter 4 m 4m(W) X 4.25m (H)
Shape Inverted D type Inverted D type
Adit -1 Length 412m 223.78 m
Adit -1 HRT junction chainage 2+094 0+000
Adit -1 Portal level 1590 masl 1620 masl
Adit -2 Length 440 m 315.80 m
Adit -2 HRT junction chainage 3+944 3+302
Adit -2 Portal level 1590 masl 1590 masl
Adit -3 Length 177m 342m
Adit -3 HRT junction chainage 0+027(from surge tunnel outlet) 4+440
Adit -3 Portal level 1590 masl 1612 masl
Adit -4 Length 386.50m
Adit -4 HRT junction chainage 6+650
Adit -4 Portal level 1580 masl
Adit -5 Length 207.7m
Adit -5 HRT junction chainage 6+771
Adit -5 Portal level 1440 masl
Adit -6 Length 453.33 m
Adit -6 HRT junction chainage 6+902
Adit -6 Portal level 1320 masl
Surge Tunnel
Diameter 4 m 4 m
Shape Inverted D type Inverted D type
Length 437 m 412m
Surge Tunnel –HRT junction chainage 6+614 6+627
Invert level of inlet 1600.00 masl 1602 masl
Invert level of outlet 1660.00 masl 1655.20 masl
Pressure Shaft / Tunnel
Diameter 2.3 m 2.3 m
Total Length 822 m
Length upto Manifold 425.7 m 653 m
Vertical section 323.8 m 353 m (Inclined Shaft)
Horizontal shaft section 101.9 m 300m
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 13 November 2019
Manifold length 18.3 m Not Applicable
Manifold diameter 1.9 m Not Applicable
Pressure shaft after Manifold 2 x 24.13 m 169m in total
Diameter of pressure after manifold 1.5 m 1.3 m
Lining Steel lined embedded in concrete
Shotcrete wire mesh and bolts lining
Powerhouse
Type of Power house Underground Surface Changed
Powerhouse cavern dimension (l x B x H)
46 m x 12m x 21m (from turbine CL) 45m x 16m x 32m
Transformer cavern dimension (l x B x H) 37m x 10m x 18 m Not Applicable Surface
structure
Cavern Crown level 1299.00 masl Not Applicable
Machine floor level 1286.00 masl 1293.80 masl
Turbine Axis Level 1278.00 masl 1281.50 masl
Turbine
Type of turbine Pelton Pelton
Shaft configuration Vertical Vertical
No.of turbine 2 3
Turbine Output 24.4 MW 16.267 MW
No of nozzle 5 6
Specific speed 500 rpm 500 rpm
Optimal jet diameter 180mm 128 mm
Generator
Type Synchronous Synchronous
Rated output capacity per unit 24.4 MW 16.267 MW
Power Factor 0.85 0.85
Voltage 11 KV 11kV
Frequency 50 Hz 50 Hz
No. of Units 2 3
Efficiency 98% greater than 97.5%
Transformer
No. of Transformer 7 Nos., single phase including 1 sphere 3 Nos., three-phase
Rated capacity 2 units of 3 x 10 MVA 3 units, 3 x 22 MVA
Voltage ratio 11/132 kV 11/132 kV
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 14 November 2019
Efficiency 99% 99%
Transmission line
Length 11.5 km 11.5 km
Type 132 kV,Single circuit 132 kV,Single circuit
Cable ASCR,Bear ASCR,Bear
Tailrace Outlet
Type Tunnel Box Culvert
Type of flow Free flow Free flow
Shape Inverted D type Rectangular
Diameter 4m 3.5m X 3.5m
Total length of tailrace tunnel 562 m 180m
Invert level of outlet 1274.36 masl 1274.91 masl
Energy
Wet Energy 217.5 GWh 219.5 GWh
Dry Energy 44 GWh 40.8 GWh
Total Energy 261 GWh 260.3 GWh
Firm Energy 113 GWh 107 GWh
Financial
Total Project cost NRs. 7.45 billion NRs. 7.45 billion
Revenue NRs. 1.4 billion NRs. 1.4 billion
B/C Ratio 1 .41 1 .41
IRR 16.01 % 16.01 %
Cost per MW (USD) 1550 1550
Access to the site
Kathmandu- Charikot - Jiri 198 km (188 km blacktopped)
198 km (188 km blacktopped)
Jiri to Dam site 11 km Gravel Road 11 km Gravel Road
Dam Site to Powerhouse site 16 km Gravel Road 16 km Gravel Road
Birgunj-Bardibas-Khurkot- Manthali-Kirnetar/Khimti 290 km 290 km
Khimti to Powerhouse site 27 km Gravel Road 27 km Gravel Road
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 15 November 2019
CHAPTER – 3 PROGRESS DETAILS
3.1 Progress Summary on Construction of Site Infrastructures
S/N Project Activity Total Length Status/Progress
ACCESS ROAD
1. Dharapani to Dam site (Ramechhap side) • 1.0 km
• 1.0 km of Track opening works – Completed.
• Gabion works/Slope protection – Completed.
2. Intake-Dharapani Road (Dolakha Side) • 0.5 km
• 200 m of Track Opening – completed. • Rock cutting till foundation level of right
abutment – Completed.
3. Burke – Hodampa/Phulping (Ramechhap side)
• 2.5 km
• 2.5 km track opening completed Gabion works and Maintenance of Burke-Bhage road- Ongoing.
4. Thulopatal – Hodampa/Phulping - Gaighat (Dolakha side)
• 2.0 km • 2.0 km Track opening - Completed. • Gabion works and widening the track is
remaining
5. Hanwa - Palate (Dolakha side) • 5.5 km
• 3.0 km (out of 5.5 km) of Track opening – Completed.
• Remaining works on 2.5 km – Pending due to forest clearance issue.
6.
Bhimsenthan – Palate/Powerhouse site new track (Ramechhap side)
• 0.5 km
• 0.5 km of Track opening – Completed. • Slope protection completed. • Gabion work to protect road section at
river side remaining.
7.
Bhimsenthan – Palate/Powerhouse site Old track to be upgraded (Ramechhap side)
• 3.0 km • Stone soling works & side drainage for access road improvement – Completed.
PROJECT CAMP
8. Camp Boundary Wall – Civil/Masonry works
• Wall and Permanent fencing
• Camp Boundary Wall construction completed
• Fencing work completed
9. Camp Building Construction works
• Total 12 Buildings
• All civil and electrical works completed • Partial Furnishing has been done • Full Furnishing is ongoing • Landscaping work is ongoing
10. Water Supply System • Drinking
water to Project Camp
• Construction of water supply system completed and is in operational
• Some of the balance protection work of intake and reservoir area is ongoing
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 16 November 2019
• Drinking water to Locals
• Reservoir tank- Location fixed • Pipe Laying remaining • Tap stand construction remaining.
33KV TRANSMISSION LINE FOR CONSTRUCTION POWER
11. 33 KV Transmission Line for Construction power
• 9 km 33 kV sub-transmission line
• Contract awarded to New Satakri Khimti Construction
• Pole erection from Dam site to PH site completed.
• Cable installation completed in Ramechhap side.
• Pole erection and cable installation in Dolakha side remaining.
• Transformer installation remaining. • Connection in grid with KREC-Ongoing
BAILEY BRIDGE
12. Dharapani Bridge (Bridge I) • 42.672m
• Civil works Completed. • Erection work Completed. • Approach Slab and Traffic signs installation-
remaining.
13. Hodampa Bridge (Bridge II) • 33.528m
• Civil works Completed. • Erection work Completed. • Approach Slab and Traffic signs installation-
remaining.
14. Hawa-Palate Bridge (Bridge III) • 51.816m
• Civil works Completed. • Erection work Completed. • Approach Slab and Traffic signs installation-
remaining. OTHER ACTIVITIES
15. Hydrology and Sediment Study
• Hydrology and Sediment Study
• Sediment collection & Analysis by HydroLab-Completed.
• Discharge Measurement & Hydrological Analysis by Recham Consult -Completed.
3.2 Administrative Works
16. ADMINISTRATIVE WORKS
• Various administrative issues
• Shifting grid
Connection for Power Evacuation
• Forest clearance approval – File forwardedto Ministry of Forest
• Land acquisition: about 95% completed • Survey License for Transmission Line
(Power Evacuation): Documents being compiled.
• Explosives License: initiated.
• Preliminary discussion held on loop-in, loop-out with NEA Grid Division.
• CC committee formed, a brief study has been done and submitted to NEA
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 17 November 2019
• Explosive
License • Updated IEE
Report
• First CC meeting held and initiated discussion
• Applied to DoED with all required
document • Received the recommendation from DoED
and letter to Ministry of Home. • Ministry of Home written letter to Ministry
of Defense and concerned Districts CDO to issue the carrier License.
• Approval received for Nepali explosive only.
• Appointed Nepal Environment and
Development Consultant for IEE update works
• Application submitted on March 7,2019 • Approval to update received on April 10,
2019 • Consultant team visited site and
completed the data collection • Public consultation and focus group
discussion completed • Final Updated IEE report is submitted to
DoED Final approval awaited
17. LOCAL STAKEHOLDERS ENGAGAMENT • Local issues
• Local Stakeholders Engagement through various discussion, addressing the project related environmental and social issues
• Implementing various social and local infrastructural development works
3.3 Design and Physical Model Study
18. BASIC DESIGN REPORT (BDR)
• EPC Contractors (CWTW)
• Responsibility
• EPC Contractor has Submitted the Final Basic Design Report after incorporation of Employers Comments
• Employers Responsibility
• Employer has again reviewed and provided the conditional approval; Subject to required modifications during construction.
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 18 November 2019
19. PHYSICAL HYDRAULIC MODEL STUDY
• Model of Revised Headworks
• Consulting contract award to Hydrolab • Provided required documents • Hydrolab completed river model validation
works • Similarly, completed model construction
of structures. • First model run carried out and joint
observation of the performance was completed and noticed some modification was required for certain structures
• The design modification was carried out • The modified design constructed and
model validation re-run carried out on 22nd July,2019. Observed good performance with bed load sluice; remaining change to be verified by the modification of the Model.
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 19 November 2019
3.4 Progress work in Detail
3.4.1 Access Road Headworks Area-Dharapani Road (Ramechhap) The track to headworks of Khimti-2 Hydroelectric project of 1.0 Km length is completed connecting from existing road in Dharapani, Ramechhap. Cross-drainage has been provided in three major parts of the road section along with masonry side drain in critical section of the road. Gabion works and Masonry breast wall are provided for slope protection in vulnerable portions of the road section.
Future Plans:
• Side drain in full section of the road is required in order to protect the road from the heavy downpour.
• Soling at certain portion are required in order for heavy vehicle to travel uphill slope of the road.
• Slope Protection by gabion are required in certain portions damaged recently by rainfall.
Headworks-Intake Area (Dolakha) Massive rock back cutting just Infront of headworks’ bailey bridge in order to provide required turning radius for the vehicle has been completed.
Future Plans:
• 300m length section of road to dam site is remaining.
• Locals are demanding the connection of existing road (Hawa-Phulping-Jiri Road) to bridge in headworks of Khimti-2 in dolakha side.
Dharapani Access Road
Access road to Headworks-Dolakha
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 20 November 2019
HRT adit-Burke-Hodampa Road (Ramechhap) Track opening of 2.5 Km stretch of road from Burke through bhage to hodampa is completed. Earthen side drain and cross drainage through causeway are provided in burke to bhage road section. Gabion in critical road turnings are provided.
Future Plans:
• This road section is most affected by the monsoon rain causing landslide in multiple sections completely blocking the road hence, necessary gabion works and permanent cross drainage are required.
• Side drain and proper cross drainage is required.
HRT adit- Phulping-Gaighat Road (Dolakha) Track from gaighat is connected to Bailey Bridge II (Hodampa Bridge) in phulping linking dolakha and ramechhap district. This 2.0 Km section of roads serves as a connection to project HRT adit from major road Bhirkot-Jiri of dolakha side.
Future Plans:
• Grade of the road in certain portion of road is to be maintained. • Water from monsoon has eroded away fill side of the road section which needs to be maintained
providing gabion in critical sections. • Widening of road section is required in certain places. • Cross drainage, side drain and slope protection are to be provided for the longevity of the road.
Phulping-Gaighat Access Road
Burke Hodammpa Access road to Phulping Adit
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 21 November 2019
Powerhouse- Bhimsenthan-Palate Road (Ramechhap) Out of 3.5 Km length of Bhimsenthan palate road, track opening of 3.0 Km road section was already completed by khimti-1 project. Remaining 0.5 Km of road to powerhouse site has been completed. Side drain has been provided throughout the length of the road. Hume pipe is provided for cross drainage of water. Freshly cut 0.5 Km section of road triggered a landslide which was controlled by providing gabion as retaining structure. Stone soling in all the slippery slopes of the road is provided to give traction to the vehicle.
Future Plans:
• Gabion work to protect road section at river side of freshly cut 0.5Km section is remaining.
HRT outlet, surge tunnel-Hawa-Palate Road (Dolakha) 3.0 Km out of 5.5 Km section of hawa-tuspe-palate road track has been excavated, gabion in the venerable slopes has been completed for this 3.0 km stretch. Two major landslides were triggered in
Bhimsenthan-Palate Access Road
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 22 November 2019
this road section, one of which is stabilized by nailing bamboo in the ground and addressing seepage by providing perforated hdpe pipes throughout the unstable slope. Hume pipe is placed for cross drainage in the road. Remaining 2.5 Km section of road is pending due to forest clearance issue.
Future Plans:
• Remaining 2.5 Km track is to be opened and provide necessary protection works. • Permanent side drain is required to protect the road.
Bhimsenthan-Palate Access Road
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 23 November 2019
3.4.2 Bailey Bridge Bailey Bridge I (Dharapani Bridge) • Civil work: By S. K. Construction pvt. Ltd. – Completed • Span: 42.672m • Maximum Load capacity: 30T • Bailey Bridge erection work: Completed
Bailey Bridge II (Hodampa Bridge) • Civil work: By Likhu Nirman Sewa – Completed • Maximum Load Capacity: 20T • Span: 33.528m • Bailey Bridge erection work: Completed
Bailey Bridge I: Dharapani Bridge
Bailey Bridge II: Hodampa Bridge
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 24 November 2019
Bailey Bridge III (Hawa-Palate Bridge) • Civil work: By Him Sagarmatha – Completed • Maximum Load Capacity: 30T • Span: 51.816m • Bailey Bridge erection work: Completed
Future Plans
• Dirt wall and Approach wall for all three bridges are remaining which is planned to be completed within next one month.
Bailey Bridge III: Hawa-Palate Bridge
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 25 November 2019
3.4.3 Camp Facilities
Civil Works The Khimti-2 main camp located in Lamatar, Rasnalu Ramechhap contains 12 buildings with 7 Staff Quarters, one Kitchen, two office buildings, one Guest house and a Guard house. This camp is to facilitate during the construction phase of the project as well as during operation phase of the Project.
Work progress on Camp buildings
• The Fencing work surrounding the camp area with chain link and masonry wall along with erection of gate has been completed.
• All civil works of 12 buildings including truss works and roofing has been completed. • Aluminum doors and windows of all buildings completed. • All painting works has been completed. • False Ceiling works all buildings completed. • Sanitary work -Manhole and pipe laying for all the building are completed and construction of
third Soak pit is also completed. • Electrical works of all buildings completed.
Future Plans
• Landscaping of the camp area • Completion of balance furnishing of all residential as well as office building
Khimti-2 Project Camp
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 26 November 2019
Water supply work Drinking water supply for the camp facility of the Khimti -2 project is tapped from the underground water near darkha about 1km away from the camp area.
Work Progress on Water supply to camp
• Drinking water source identified and registration process completed. • Pipe laying from intake to the camp has been completed. • All the civil works and pipe fitting works in Intake area is completed. • All the civil works of reservoir tank is completed. • Pipe laying and fitting works inside the camp area are completed.
Future Plans
• Works for supplying drinking water to some locals near the camp area in ongoing. • Construction of reservoir tank, pipe laying and tap stand for drinking water facility to locals.
3.4.4 33Kv Transmission line for Construction Power About 9km sub-transmission line from Headworks area of Khimti2 HEP , Dharapani to powerhouse site of Khimti-2 hydroelectric project is required to supply power to different sites during the construction phase.
Work Progress on 33kv construction power
• Contract awarded to New Satakri Khimti Construction. • Pole erection, cable installation along with all necessary
accessories from headworks to powerhouse site in Ramechhap side completed.
Water Supply works: Intake Area Water Supply works: Reservoir tank
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 27 November 2019
Future Plans
• Connection from Hodammpa to Phulping adit . • Connection from powerhouse site to surge shaft site. • Installation of Transformer in different site location.
3.4.5 Design & Engineering Works
Design approval and site mobilization of contractor
Basic design report (BDR) submitted by CWTW has been given conditional approval: subjected to required modification during construction on 5th Dec, 2018.
Work Progress on Physical Hydraulic Modelling
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 28 November 2019
• Agreement done with Hydro-lab for construction of Physical Hydraulic model
• River model and headworks model construction completed
• Joint observation of model run conducted • Noticed serious problems requiring major
modification on the design • Thick bedload deposit in front of intake
was observed blocking the intake • Outlet of the flushing tunnel was
submerged during high flood operation.
• The modified design constructed and model validation re-run carried out on 22nd July,2019. • In the modified design, bottom bedload sluice with radial gate flushing was added with changes
in forebay hopper. No. of intake was reduced to five from initially proposed eight.
First run of Physical hydraulic model of Khimti-2 Project
Re-run of hydraulic model after major changes in structure
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 29 November 2019
After the re-run of model, the performance of the bed load sluice was satisfactory remaining changes are to be verified by the modification of the model.
Progress on CWTW site Mobilization
• As mobilization of contractor is dependent on the advance payment, works on applying for the loan are at its final stage.
• CWTW have finalized the civil sub-contractor.
3.4.6 Administrative Works
Progress on Updated IEE Report
• Nepal Environment and Development Consultant has been appointed for the preparation of the updated IEE report.
• Consultant team visited to site and completed the data collection work • Public consultation and Focus group discussions are completed. • Review and comments on the draft UIEE report has been addressed. • Final Report submitted to DoED and awaited for final approval.
Progress on Survey License for Loop in Loop out
• Discussion was done with NEA for shifting the connection agreement • A study for the technical and economical assessment has been done and submitted to NEA. • First CC meeting was held.
Progress on Other Administrative works
• Technical Verification Process-Ongoing • Survey License for Loop in Loop out has been initiated. • Approval has been received for the Nepali Explosives.
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 30 November 2019
• For the Forest Clearance Approval, the file has been forwarded to Ministry of Forest from Forest Department.
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 31 November 2019
3.5 Site Progress Photographs
Project Camp: External Painting Work Sanitary Works: Excavation for Manhole Preparation
Sanitary Work: Pipe Laying Sanitary Works: Manhole Preparation
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 32 November 2019
Sanitary Work: Soak Pit
Painting Work: Internal painting of the Building
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 33 November 2019
CHAPTER – 4 RESOURCE DETAILS
4.1 Manpower Details
S/N Name Designation
Head Office:
1. Dev Bahadur Poudel Chhetri Director, Public Relations/Social Issues 2. Prof. Hari Prasad Pandit, Ph.D. Chief Technical Adviser 3. Ram Hari Sharma Project Manager 4. Kushal Sundar Shrestha Head, Procurement/Human Resources 5. Janardan Aryal General Manager 6. Bindu Shrestha Account Officer 7. Anjuli Khadka Civil Engineer 8. Prachan Shrestha Civil Engineer 9. Samrat Acharya Procurement/Admin Officer 10. Bikram Acharya Procurement/Logistics Officer 11. Anjali Aryal Account Assistant
Site Office:
12. Pradip Nepal Deputy Project Manager (Civil Engineer) 13. Toya Nath Ghimire Geologist 14. Amul Tandukar Civil Engineer 15. Niroj Kusi Civil Engineer 16. Sagar Poudel Civil Engineer 17. Sujan Kasichhwa Electrical Engineer 18. Hari Sharan Adhikari Social Mitigation Officer 19. Krishna Hari Neupane Accountant 20. Anish Bhandari Surveyor 21. Sangita Sunuwar Supervisor 22. Birendra Karki Sub-Overseer 23. Bishnu Gharti Vehicle Driver 24. Dhan Bahadur Magar Vehicle Driver 25. Mohan Khatri Vehicle Driver 26. Dhurba Karki Cook 27. Moti Lal Tamang JCB Operator 28. Surya Bahadur Bhujel Tractor Driver 29. Hom Dhoj Karki Security Guard
Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)
Progress Report Page | 34 November 2019
4.2 Equipment Details
S/N Vehicle/Equipment Location Number Remarks 1. JCB Backhoe Loader At Site 1 PEL Owned 2. New-Holland Tractor At Site 1 PEL Owned 3. Mahindra Bolero Pick-up At Site 1 PEL Owned 4. Bolero Pick up Jeep At Site 1 PEL Owned 5. Motorcycle (Honda Shine) At Site 1 PEL Owned 6. Hired Excavators At Site 3 Hire
4.3 Difficulties & issues being faced / envisaged at site Local disturbances for the construction reservoir tank for water supply in project camp. Delay to open the access to surge shaft due to pending of forest land approval file at Ministry
of Forest to be approved by Cabinet through Ministry of Forest. Delay to get the Explosive license and bunker construction as well as security barrack
construction. Locals various demands like infrastructure development, contracts as well as employment.