Transformation · Innovation · Partnership
PEREKAYASAAN
DEWAN BANDARAYA KUCHING UTARA:
PERMIT PENGUBAHSUAIAN & PENYAMBUNGAN
KECILAN BANGUNAN
DEWAN BANDARAYA KUCHING UTARA
Transformation · Innovation · Partnership
Project Title: To review the process time on the approval Permit For Minor Erection, Minor Alteration & Addition of Building Works (By-Laws 14)
Business Case Opportunity Statement
Approval process takes 14 working days which is considered quite long. There is an increasing demand to improve customer satisfaction by reducing the approval time.
Goal statement Project scope
• Goal: To reduce prossesing time from
14 working days to 7 working days.
• Improve customer satisfaction index.
• Financial Gain: -
• Metric : -
Process: Permit For Minor Erection, Minor Alteration & Addition of Building Works (By-Laws 14). Start: Receive, register & compilation and process complete application.
End: Issue Permit to Applicant.
Scope: Minor erections, minor alterations and additions to buildings
which is not require submission of normal building plan.
Project Plan New Team Line-up
Phase Start End Champion: BLG DBKU
Define - - Project Owner: Mohamad Faisal Bin Haji Adenan
Measure - - Members: Ilias B. Hasan
Analyze - - Norezan Binti Ha’s
Improve - -
Control - -
To improve the process efficiency and fast services delivery to customers.
DEWAN BANDARAYA KUCHING UTARA
DEWAN BANDARAYA KUCHING UTARA
Transformation · Innovation · Partnership
PEMETAAN PROSES ‘AS IS’ PERMIT PENGUBAHSUAIAN &
PENYAMBUNGAN KECILAN BANGUNAN
DEWAN BANDARAYA KUCHING UTARA
Transformation · Innovation · Partnership
SWIMLANE APPLICATION PERNIT FOR THE APPROVAL PERMIT FOR MINOR ERECTION,
MINOR ALTERATION & ADDITION OF BUILDING WORKS (BY-LAWS 14) (AS-IS)
DEWAN BANDARAYA KUCHING UTARA
APPLICANT
PT(BUILDING CONTROL)
TECHNICIAN
UH (BUILDING CONTROL)
DH(ENV)
DH(BLG)
1. Submitting Application
Forms & Supporting
Documents
(10 min)
2. Received, Register And
Process Complete
Application
(20 min)
3. Checking Technical
Requirement And
Supporting Document
And Site Verification
(60 min)
4. Prepare Memo
To DH(ENV)
(15 min)
5. Sign Memo And
Verify Comment By
Technician
(15 min)
10. Approve The Application
(20 min)
12. Collect Non-Compliance
Letter/Permit (Make Payment)
(10 min)
NO
YES
Comply
9. Vetting And Sign
Non-Compliance/
Recommendation Of
Approval
(20 min)
6. Forward Memo
And Supporting
Document To
DH(ENV)
(15 min)
7. Recommendation Memo
(60 min)
8. Compile And Prepare
Non-Compliance/Approval Letter
(20 min)
11. Issue Non-
Compliance/Permit
(15 min)
NO
YES
Approve?
240 min
10 min
960 min
60 min
480 min
1440 min
60 min
960 min
240 min
480 min
960 min
Transformation · Innovation · Partnership
Value Analysis Permit Pengubahsuaian & Penyambungan Kecilan Bangunan (AS IS)
No. Aktiviti
Value Analysis
(Tandakan / )
Masa
Proses
Masa
Menunggu
Masa
Diambil
VA BVA NVA minit minit minit
1 Submitting application forms & supporting documents / 10 240 250
2 Received, register and process complete application / 20 10 30
3 Checking technical requirement and supporting document and site verification
/ 60 960 1020
4 Prepare memo to DH(ENV) / 15 60 75
5 Sign memo and verify comment by technician / 15 480 495
6 Forward memo and supporting document to DH(ENV) / 15 960 975
7 Recommendation memo / 60 1440 1500
8 Compile and prepare non-compliance/approval letter / 20 60 80
9 Vetting and sign non-compliance/recommendation of approval
/ 20 240 260
10 Approve the application / 20 480 500
11 Issue non-compliance/permit / 15 0 15
12 Collect non-compliance letter/permit (make payment) / 10 960 970
Total 280 5890 6170
Transformation · Innovation · Partnership
PEMETAAN PROSES CADANGAN PENAMBAHBAIKAN
DEWAN BANDARAYA KUCHING UTARA
Transformation · Innovation · Partnership
SWIMLANE APPLICATION PERNIT FOR THE APPROVAL PERMIT FOR MINOR ERECTION,
MINOR ALTERATION & ADDITION OF BUILDING WORKS (BY-LAWS 14) (AS-IS) - Penambaikan
DEWAN BANDARAYA KUCHING UTARA
APPLICANT
PT(BUILDING CONTROL)
TECHNICIAN
UH (BUILDING CONTROL)
DH(ENV)
DH(BLG)
1. Submitting Application
Forms & Supporting
Documents
(10 min)
2. Received, Register And
Process Complete
Application
(20 min)
3. Checking Technical
Requirement And
Supporting Document
And Site Verification
(60 min)
4. Prepare Memo
To DH(ENV)
(15 min)
5. Sign Memo And
Verify Comment By
Technician
(15 min)
10. Approve The Application
(20 min)
12. Collect Non-Compliance
Letter/Permit (Make Payment)
(10 min)
NO
YES
Comply
9. Vetting And Sign
Non-Compliance/
Recommendation Of
Approval
(20 min)
6. Forward Memo
And Supporting
Document To
DH(ENV)
(15 min)
7. Recommendation Memo
(60 min)
8. Compile And Prepare
Non-Compliance/Approval Letter
(20 min)
11. Issue Non-
Compliance/Permit
(15 min)
NO
YES
Approve?
240 min
10 min
960 min
60 min
480 min
1440 min
60 min
960 min
240 min
480 min
960 min
Transformation · Innovation · Partnership
PEMETAAN PROSES ‘TO BE’ PERMIT PENGUBAHSUAIAN &
PENYAMBUNGAN KECILAN BANGUNAN
DEWAN BANDARAYA KUCHING UTARA
Transformation · Innovation · Partnership
DEWAN BANDARAYA KUCHING UTARA
APPLICANT
PT(BUILDING CONTROL)
TECHNICIAN
UH (BUILDING CONTROL)
DH(ENV)
DH(BLG)
1. Submitting Application
Forms & Supporting
Documents
(10 min)
2. Received, Register And
Process Complete
Application
(20 min)
3. Checking Technical
Requirement And
Supporting Document
And Site Verification
(60 min)
4. Verify Comment
By Technician
(15 min)
9. Collect Non-Compliance
Letter/Permit (Make Payment)
(10 min)
NO
YES
6. Vetting And Sign
Non-Compliance/
Recommendation Of
Approval
(20 min)
5. Compile And Prepare
Non-Compliance/Approval Letter
(20 min)
8. Issue Non-Compliance/Permit
(15 min)
YES/NO
7. Approve
The
Application
(20 min)
240 min
960 min
480 min
240 min
480 min
240 min
960 min
KIV
240 min 240 min
SWIMLANE APPLICATION PERNIT FOR THE APPROVAL PERMIT FOR MINOR ERECTION,
MINOR ALTERATION & ADDITION OF BUILDING WORKS (BY-LAWS 14) (TO BE)
Transformation · Innovation · Partnership
Value Analysis Permit Pengubahsuaian & Penyambungan Kecilan Bangunan (TO BE)
/
No.
Aktiviti
Value Analysis
(Tandakan / )
Masa
Proses
Masa
Menunggu
Masa
Diambil
VA BVA NVA minit minit minit
1 Submitting application forms & supporting documents / 10 240 250
2 Received, register and process complete application / 20 0 20
3 Checking technical requirement and supporting document and site verification
/ 60 960 1020
4 Verify comment by technician / 15 480 495
5 Compile and prepare non-compliance/approval letter / 20 0 20
6 Vetting and sign non-compliance/recommendation of approval
/ 20 480 500
7 Approve the application / 20 240 260
8 Issue non-compliance/permit / 15 0 15
9 Collect non-compliance letter/permit (make payment) / 10 960 970
Total 190 3360 3550
Transformation · Innovation · Partnership
DEWAN BANDARAYA KUCHING UTARA
APPLICANT
PT(BUILDING CONTROL)
TECHNICIAN
UH (BUILDING CONTROL)
DH(ENV)
DH(BLG)
1. Submitting Application
Forms & Supporting
Documents
(10 min)
2. Received, Register And
Process Complete
Application
(20 min)
3. Checking Technical
Requirement And
Supporting Document
And Site Verification
(60 min)
4. Verify Comment
By Technician
(15 min)
8. Collect Non-Compliance
Letter/Permit (Make Payment)
(10 min)
NO
YES
5. Vetting And Sign
Non-Compliance/
Recommendation Of
Approval
(20 min)
7. Issue Non-Compliance/Permit
(15 min)
YES/NO
6. Approve
The
Application
(20 min)
240 min
960 min
480 min
480 min
240 min
960 min
240 min
SWIMLANE APPLICATION PERNIT FOR THE APPROVAL PERMIT FOR MINOR ERECTION,
MINOR ALTERATION & ADDITION OF BUILDING WORKS (BY-LAWS 14) (TO BE BARU)
Transformation · Innovation · Partnership
Value Analysis Permit Pengubahsuaian & Penyambungan Kecilan Bangunan (TO BE BARU)
/
No.
Aktiviti
Value Analysis
(Tandakan / )
Masa
Proses
Masa
Menunggu
Masa
Diambil
VA BVA NVA minit minit minit
1 Submitting application forms & supporting documents / 10 240 250
2 Received, register and process complete application / 20 0 20
3 Checking technical requirement and supporting document and site verification
/ 60 960 1020
4 Verify comment by technician / 15 480 495
5 Vetting and sign non-compliance/recommendation of approval
/ 20 480 500
6 Approve the application / 20 240 260
7 Issue non-compliance/permit / 15 0 15
8 Collect non-compliance letter/permit (make payment) / 10 960 970
Total 170 3360 3530
Transformation · Innovation · Partnership
No. Perkara Sebelum Selepas
1. PE (Process Efficiency) ____% _____%
3 Masa keseluruhan proses ____ BULAN ____ BULAN
Perbandingan Sebelum dan Selepas
13 DEWAN BANDARAYA KUCHING UTARA
Transformation · Innovation · Partnership
RINGKASAN PENEMUAN DAN CADANGAN PENAMBAHBAIKAN
Kelulusan Permohonan Permit Pengubahsuaian & Penyambungan
Kecilan Bangunan
Item/Perkara Sebelum Projek Selepas
Projek Catatan/Isu
1. Asas Undang - Undang BUILDING BY-LAWS 14 Sama
2. Piagam Pelanggan TIADA TIADA
3. Caj/Bayaran
1. Fi Permit - RM50.00
1. Fi - SAMA
4. Nama Borang TIADA TIADA
5. Tempoh Sahlaku TIADA TIADA
6. Pembaharuan TIADA TIADA
Pengabungan Proses Kerja:
Checking technical
requirement and supporting
document and site verification
Sign memo and verify
comment by technician
Proses Kerja Yang Tidak
Diperlukan:
Prepare memo to DH(ENV)
Forward memo and
supporting document to
DH(ENV)
Recommendation memo
7. Agensi Yang Dirujuk TIADA TIADA
Transformation · Innovation · Partnership
RINGKASAN PENEMUAN DAN CADANGAN PENAMBAHBAIKAN
Kelulusan Permohonan Permit Pengubahsuaian & Penyambungan
Kecilan Bangunan
Item/Perkara Sebelum Projek Selepas Projek Catatan/Isu
8. Keperluan Dokumen
Sokongan
COVERING LETTER SURAT TANAH PELAN LAKARAN GAMBAR DOKUMEN-DOKUMEN TAMBAHAN
COVERING LETTER SURAT TANAH PELAN LAKARAN GAMBAR DOKUMEN-DOKUMEN TAMBAHAN
DEWAN BANDARAYA KUCHING UTARA