perpetuus tidal energy · 2015. 10. 28. · smd responded straum as no response 3.3 axial flow...

26
PERPETUUS TIDAL ENERGY CENTRE LTD PTEC Developer Consultation Date – October 2013 ITP/REF – UKP 1191

Upload: others

Post on 30-Jan-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

  • PERPETUUS TIDAL ENERGY

    CENTRE LTD PTEC Developer Consultation

    Date – October 2013

    ITP/REF – UKP 1191

  • PTEC Developer Consultation Report

    UKP1191 i October 2013

    This project has been co-funded by ERDF under the INTERREG IVB NWE programme. The report

    reflects the author’s views and the Programme Authorities are not liable for any use that may be made

    of the information contained therein.

    Perpetuus Tidal Energy Centre Ltd

    IT Power reference: UKP1191

    October 2013

    Contractor:

    IT Power

    St. Brandon’s House

    29 Great George Street

    Bristol, BS1 5QT, UK

    Tel: +44 117 214 0510

    Fax: +44 117 214 0511

    E-mail: [email protected]

    www.itpower.co.uk

    Document control

    File path & name I:\Data\0WorkITP\0Projects\1191 PTEC Phase 1 Delivery FEED &

    EIA\2 Work\Developer consultation\

    Author J. Hussey, M. Leybourne

    Project Manager J. Hussey

    Approved

    Date October 2013

    Distribution level Final

    mailto:[email protected]://www.itpower.co.uk/

  • PTEC Developer Consultation Report

    UKP1191 ii October 2013

    TABLE OF CONTENTS

    1 INTRODUCTION .............................................................................. 1

    1.1 PTEC ................................................................................. 1

    2 SCOPE AND METHODOLOGY ............................................................... 1

    2.1 Scope ................................................................................ 1

    2.2 Key Objectives ..................................................................... 1

    2.3 Methodology ........................................................................ 2

    2.4 Parameters for Discussion ........................................................ 2

    3 DEVELOPERS ................................................................................. 3

    3.1 Turbine Neutral Platforms ........................................................ 4

    3.2 Floating Devices (Axial Flow) ..................................................... 5

    3.3 Axial Flow (Bottom Mounted) .................................................... 5

    3.4 Cross Flow (Bottom Mounted) .................................................... 6

    3.5 Other ................................................................................. 7

    4 CONSULTATION RESPONSES ............................................................... 8

    4.1 Interest in PTEC and Timing ...................................................... 8

    4.2 Site Design / Layout ............................................................... 9

    4.3 Device Design / Configuration ................................................... 9

    4.4 Foundations / Moorings ........................................................... 10

    4.5 Electrical Infrastructure .......................................................... 11

    4.5.1 Ratings and Voltage ....................................................... 11

    4.5.2 Power Electronics ......................................................... 11

    4.5.3 Isolation ..................................................................... 11

    4.5.4 Communications ........................................................... 11

    4.5.5 Low voltage / Back-up Electricity Supply .............................. 12

    4.6 Installation Approach .............................................................. 12

    4.6.1 Vessels ...................................................................... 12

    4.6.2 Installation Port Requirements .......................................... 12

    4.7 Operation and Maintenance Considerations .................................... 12

    4.8 Other ................................................................................. 13

    5 FUTURE MARKET GROWTH PREDICTIONS ................................................ 13

    5.1 First Arrays .......................................................................... 13

    5.2 Larger ‘Commercial’ Projects .................................................... 14

    6 CONSIDERATIONS FOR PTEC INFRASTRUCTURE AND ROCHDALE ENVELOPE ......... 15

    6.1 Size and number of berths / cables ............................................. 16

    6.2 Voltages ............................................................................. 16

    6.3 Progress towards Design Freeze ................................................. 17

    APPENDIX A: DEVELOPER QUESTIONNAIRE ....................................................... 0

    7 INTRODUCTION .............................................................................. 1

    7.1 Scope ................................................................................ 1

    7.2 Key Objectives ..................................................................... 1

    8 QUESTIONNAIRE ............................................................................. 2

  • PTEC Developer Consultation Report

    UKP1191 1 October 2013

    1 INTRODUCTION

    This document summarises the results of the developer consultation carried out as part of

    the FEED work for the PTEC project.

    The developer consultation will be used to determine the technical requirements and level

    of interest in the site by the leading tidal technologies. Also, importantly the consultation

    will be used to determine the preliminary site layout, outline Rochdale Envelope, and input

    into the EIA, infrastructure requirements and project design statement.

    Thirty nine of the most advanced or promising tidal technology developers were contacted

    as part of this exercise, these comprise companies who are already in discussions with PTEC

    about potential deployments as well as other companies identified as potential customers.

    The full list of developers approached can be found in Section 3.

    A copy of the questionnaire used can be found attached as Appendix A. The answers to these

    questions are summarised, analysed and discussed anonymously in Section 4.

    1.1 PTEC

    The Perpetuus Tidal Energy Centre (PTEC) is a managed demonstration facility for tidal

    energy developers; suitable for the deployment of up to full scale single units and small

    arrays from prototype to pre-commercial demonstrators. The offshore facility will be a

    20MW demonstration site located approximately 2.5km to the south of St. Catherine’s Point,

    and will include grid connection via subsea cables as well as navigation aids and monitoring

    equipment.

    2 SCOPE AND METHODOLOGY

    2.1 Scope

    The purpose of the consultation was to obtain a coherent list of requirements from

    technology developers that can inform the FEED study for the design of the electrical system

    and integrate effectively with the consenting process. The outputs from this consultation

    will be captured in the preliminary site layout, outline Rochdale Envelope, and input into

    the EIA, infrastructure requirements and project design statement.

    IT Power asked 40 developers, in high level terms, about their potential timescales for

    deployment, as well as a series of technical questions relating to their technology.

    IT Power did not discuss any commercial matters relating to the developers or PTEC.

    2.2 Key Objectives

    The four main objectives for the developer consultation were as follows:

    1. Obtain information to define requirements for the FEED Study, comprising:

    Technical data relating to the device.

    Infrastructure requirements.

    Deployment plans and requirements.

    O&M plans and requirements.

    Data to define the Rochdale Envelope and project design statement.

  • PTEC Developer Consultation Report

    UKP1191 2 October 2013

    2. Understand the approximate deployment timescales expected by the developers.

    3. Understand the ideal services that they would require from PTEC.

    4. Understand the ideal port and onshore support infrastructure requirements on the

    Isle of Wight.

    2.3 Methodology

    A document detailing the developers to be contacted, information about each, and the

    approach to be used (who and how contacted) was produced for approval by PTEC.

    A questionnaire was developed, based on the information described in section 2.4. This

    questionnaire was filled in from the result of face-to-face meetings or during phone

    conversations where possible, and was sent out by email where this was not the case. The

    contents of the questionnaire were used to loosely guide conversations with the developers

    in order to capture all of the necessary information and was agreed by PTEC before it was

    issued. The questionnaire is attached as Appendix B.

    In addition, an information document providing an introduction to PTEC was produced which

    outlined the work that has been carried out to date and general information about the

    project including key headline data such as bathymetry and typical flow velocities. This was

    sent to the selected developers to help sell the concept of PTEC, show how well advanced

    the project is and to raise their awareness and interest in PTEC. This document was also

    agreed by PTEC before it was issued.

    2.4 Parameters for Discussion

    IT Power discussed the following parameters with the developers:

    Site design

    Layout of berths within PTEC

    Potential layout of devices and infrastructure within the berths

    Connection to transmission infrastructure

    Number of devices, if deployed in an array

    Timing

    Approximately when will the device(s) be deployed

    What would be the intended length of deployment

    Device design

    Device configuration (axial/transverse/other)

    Surface piercing/floating/sub surface

    Foundation/mooring type and design (GBS/piled)

    Footprint of deployment

    Blade number, dimensions and rotation speed

    Electrical output – rated capacity and voltage

    Control (specifically location of converters), communications and electrical

    isolation methodology

    Installation approach

    Duration and seasonality of offshore installation activity

  • PTEC Developer Consultation Report

    UKP1191 3 October 2013

    Installation equipment and vessels to be used

    Methodology

    Port requirements

    Hard standings and road access

    Operational and maintenance considerations

    Personnel and vessels required

    Frequency of scheduled maintenance interventions

    Frequency and type of scheduled surveys

    Unscheduled maintenance

    Back-up electricity supply requirement

    Port requirements

    Decommissioning

    Approach to decommissioning

    Other onshore support infrastructure requirements

    Ideal services that a developer would expect PTEC to provide

    Other

    Personnel involved during deployment

    Health & safety considerations

    Key results of any prior EIA studies

    Willingness for sharing of data (environmental monitoring)

    The answers to these questions and all additional comments were tabulated for ease of

    collation and comparison.

    These are summarised and discussed in Section 4; to ensure confidentiality, this is done

    without reference to the developers themselves or the source of any particular response.

    Where developers were uncertain about their approach or the detail required, IT Power has

    endeavoured to fill in the data as accurately as possible, based on our knowledge of similar

    systems. Where this has been done, it is noted in the report.

    3 DEVELOPERS

    The following 40 tidal technology developers were contacted during this work. These

    represent advanced developers whose further development timescales are likely to fit those

    of PTEC, as well as promising early stage technologies, and those who have expressed an

    interest in the site.

    For the purposes of this report, the developers have been categorised into the flowing:

    Turbine Neutral Platforms

    Floating Devices (Axial Flow)

    Axial Flow (Bottom Mounted)

    Cross Flow (Bottom Mounted)

    Other

    Comments on the applicability of these technologies and their level of interest in the site

    are summarised in Sections 3.1 to 3.5.

  • PTEC Developer Consultation Report

    UKP1191 4 October 2013

    1. Andritz Hydro Hammerfest

    2. Aquascientific

    3. Atlantis Resources Corporation

    4. BioPower Systems

    5. Blue Energy Canada

    6. Bluewater Energy Services B.V.

    7. Blue Tidal Energy

    8. Clean Current Power Systems

    9. Ecomerit Technologies - Aquantis

    10. ETI

    11. Flumill

    12. Green-Tide Turbines

    13. Hyundai Heavy Industries

    14. Kawasaki Heavy Industries

    15. Kepler Energy

    16. Marine Current Turbines (MCT)

    17. Minesto

    18. Nautricity Ltd

    19. Nova Innovation Ltd

    20. Ocean Flow Energy

    21. Ocean Renewable Power Co. LLC

    22. OpenHydro

    23. Sabella SAS

    24. Scotrenewables

    25. SeaPower Gen Ltd

    26. SMD Hydrovision

    27. SME

    28. Straum - Hydra Tidal

    29. Sub Sea Turbines

    30. Swan Turbines

    31. Tidal Energy Limited

    32. Tidal Generation Ltd (TGL)

    33. Tidal Sails AS

    34. Tidal Stream Limited

    35. Tocardo BV

    36. Toshiba

    37. Verdant Power

    38. Verderg

    39. Voith Hydro

    40. QED Naval

    3.1 Turbine Neutral Platforms

    Turbine neutral platforms provide a means to mount several turbines and associated

    electrical systems on a common platform. The platforms are designed to accept different

    types of turbines from different developers. There are a wide variety of approaches used

    for the platform, from surface piercing, floating to sub-surface bottom mounted. Therefore

    different anchoring methods are used, with most opting for either piles or gravity anchors.

    Turbine neutral platforms are well suited to the PTEC site given the water depths and berth

    sizes. These platforms could also provide the opportunity to demonstrate several different

    turbines without the need to completely change the platform itself over the lifetime of the

    project.

    The turbine neutral platforms consulted as per of this exercise were:

    Developer Response Received

    Bluewater Energy Services B.V. Responded

    SME Responded

    Tidal Stream Ltd Responded

    QED Naval Responded

  • PTEC Developer Consultation Report

    UKP1191 5 October 2013

    3.2 Floating Devices (Axial Flow)

    Floating devices are intended to exploit the faster flow speeds encountered near the

    surface; the designs can reduce the foundation infrastructure required, but require

    integrated mooring and anchoring solutions. The anchors have to be selected based on the

    seabed conditions at the site. There is often some surface piercing element to the design.

    The deeper water at PTEC, when compared to many good tidal sites, makes it ideal for

    floating technology. Their deployment at the site may however have implications for

    consenting from a navigation and visual impact point of view.

    Floating devices consulted as per of this exercise were:

    Developer Response Received

    Ecomerit Responded

    Nautricity No response

    Ocean Flow Energy Responded

    Scotrenewables Responded

    SMD Responded

    Straum As No response

    3.3 Axial Flow (Bottom Mounted)

    These devices are often referred to as horizontal axis tidal turbines (HATTs).They are similar

    to technologies used in wind energy. Generally, axial flow turbines are composed of a

    number of blades which are connected to a hub which rotates about a horizontal axis. Axial-

    flow turbines extract energy from moving water in much the same way as wind turbines

    extract energy from moving air. The turbine is aligned so that it points into the flow with

    the rotational axis parallel to the flow. The turbine rotor may be housed within ducts to

    create secondary flow effects by concentrating the flow and altering the flow velocity of

    the water passing through the turbine to focus the extractable energy.

    There are also various approaches to control - rotors with fixed pitch (stall controlled) and

    variable pitch turbine blades are both under development in the industry.

    Axial flow turbines are the most well developed type of tidal energy converter technology,

    with a number of device concepts at a pre-commercial stage.

    These developers use monopoles, tripods, quadrapods, or a similar type of jacket / frame

    to mount their turbines and are held in place using either piles or weights.

    Most current 1MW, bottom mounted turbines are looking for water depths of 40 to 50m,

    although a few are looking to deploy larger machines in even deeper water. The range of

    water depths at the site provide a number of locations for such deployments. A number of

    these developers however are concentrating on smaller machines, and the lack of areas

    shallower than 35m at the site could prove difficult for these.

  • PTEC Developer Consultation Report

    UKP1191 6 October 2013

    Axial flow, bottom mounted turbines consulted as per of this exercise were:

    Developer Response Received

    AndritzHydro Hammerfest Responded

    Atlantis Resources Corporation Responded

    Clean Current Responded

    Green-Tide No response

    Hyundai Heavy Industries No response

    Kawasaki Heavy Industries No response

    MCT (Siemens) Responded

    Nova Innovation Responded

    OpenHydro Responded

    Sabella SAS No response

    Sub Sea Turbines No response

    Swan Turbines No response

    TGL (Alstom) Responded

    Tidal Energy Limited Responded

    Tocardo Responded

    Toshiba No response

    Verdant Isles Responded

    3.4 Cross Flow (Bottom Mounted)

    These devices have a cross-flow design with the blades rotating about an axis perpendicular

    to the direction of the tidal flow mounted either vertically or horizontally. Cross-flow

    turbines have not reached the same level of development as axial flow turbines, with no

    full scale, pre-commercial devices deployed. A cross-flow turbine rotates in one direction

    making it suitable for bidirectional tidal flows. As with axial-flow turbines, some designs

    also make use of ducts to enhance flow. Devices typically have a lower hydrodynamic

    performance than axial-flow turbines, but have other benefits such as rectangular swept

    area, better suited to shallow tidal flows, and scalability (up to multi-MW devices).

    Straight bladed configurations are often referred to as Darrieus turbines in recognition of

    the original patent holder Georges Jean Marie Darrieus. A helical bladed configuration of

    the Darrieus turbine (often referred to as a Gorlov turbine after their original patent holder

    - Alexandar m. Gorlov) can improve consistency of shaft torque output as well as improving

    rotor self-starting characteristics.

  • PTEC Developer Consultation Report

    UKP1191 7 October 2013

    As with the bottom mounted axial flow devices, the developers use monopoles, tripods,

    quadrapods, or a similar type of jacket / frame to mount their turbines and are held in

    place using either piles or weights.

    A key advantage of cross flow turbines is the ability to deploy them in shallower water than

    a similarly rated axial flow machine. As such, most developers of this technology are

    targeting shallow water regions (less than 30m), the lack shallow water at PTEC could be a

    problem for many of these.

    Cross flow, bottom mounted turbines consulted as per of this exercise were:

    Developer Response Received

    Ocean Renewable Power Company Responded

    Blue Energy Canada Responded

    Blue Tidal Energy Responded

    SeaPower Gen Responded

    Kepler Energy Responded

    3.5 Other

    This category covers all other technologies that do not fit into the categories above.

    Operating principals include, oscillating or ‘traversing’ hydrofoils, venturies, Archimedes

    screws and novel applications of ‘standard’ turbine types.

    The foundation systems envisaged for these technologies are broadly similar to those

    employed by the classifications above.

    Developer consulted as per of this exercise were:

    Developer Response Received

    Minesto Responded

    Aquascientific No response

    BioPower Systems No response

    Flumill Responded

    Tidal Sails No response

    Verderg Responded

    ETI Responded

  • PTEC Developer Consultation Report

    UKP1191 8 October 2013

    4 CONSULTATION RESPONSES

    IT Power obtained responses from 27 of the 40 developers consulted; the remainder declined

    to do so or did not respond to approaches. Where known, IT Power have filled in details for

    those who did not respond.

    16 of the developers consulted have already constructed and deployed a full or near-

    full scale prototype machine.

    26 have tested a scale turbine in realistic conditions.

    14 are still at the concept or preliminary design stage.

    A summary of these developer’s responses is provided in the reminder of this section. To

    ensure confidentiality, this is done without reference to the developers themselves or the

    source of any particular response.

    4.1 Interest in PTEC and Timing

    Interest shown in PTEC by respondents was as follows:

    18 developers stated they were interested in deploying technology at PTEC.

    11 were very keen and / or are already in discussions with PTEC themselves about

    such deployments.

    7 saw the site as a possible back-up to their existing strategies if they didn’t go

    according to plan.

    7 developers were not interested in the site because they were only looking for

    commercial sites or they had no intention of building projects.

    Only 1 developer ruled out PTEC on the grounds of the electrical system. This was a

    developer that required a single cable to shore for each turbine deployed.

    Most respondents said they would be looking to deploy their first array project between

    2016 and 2018. This was the case even for those who had not yet built their first full-scale

    prototype; IT Power does not believe these timescales are realistic for these early stage

    developers.

    Table 1 below shows possible deployment scenarios for the site, based on those who have

    expressed an interest in the site and have indicated a size project they would like to deploy.

    The ‘possible projects’ column includes those who see PTEC as a back-up as well as early

    stage developers with expressed very ambitious plans. ‘Realistic Projects’ only includes

    advanced developers who have expressed a real interest or those who have the potential to

    meet their stated timescales.

    It is important to note that for the vast majority of devices, deployment is contingent on

    funding to build the turbines for the site. In several cases, funding is still required to design

    or prove their technology.

  • PTEC Developer Consultation Report

    UKP1191 9 October 2013

    Table 1: Possible Deployment Scenarios for PTEC

    Year Possible Projects (MWs) deployed Realistic Projects (MWs) deployed

    2016 10 Projects, 23.575 MW 6 Projects, 12.475 MW

    2017 4 Projects, 18.6 MW 3 Projects, 15 MW

    2018 5 Projects, 10 MW 2 Projects, 6 MW

    2019 3 Projects, 9 MW 1 Project, 4 MW

    2020 1 Project, 3 MW 1 Project, 3 MW

    Most of the developers questioned were looking for a lease term of at least 10 years, but

    ideally as long as possible.

    4.2 Site Design / Layout

    Only 4 developers were interested in deploying small / single machines at the site, although

    this is to some extent driven by how the site has been presented and the most advanced

    developers questioned.

    The developers of small devices had turbines rated between 30kW and 200kW. In some cases

    this was due to a deliberately slow scaling up process, others see a substantial market for

    small turbines, so do not intend at this stage to scale up their turbines. IT Power is aware

    of at least 12 developers looking to exploit this market. There is therefore scope to have a

    1MW berth available for a nursery site within the site.

    Sizes of berths that developers were interested in were as follows:

    5 wanted a berth of 6MW or more

    3 wanted a berth between 3.1MW and 5.9MW

    5 Wanted a berth between 1.1MW and 3MW

    5 wanted a berth up to 1MW

    8 developers required deep water (greater than 35 - 40m), whilst 11 required shallow areas

    (less than 30m) at the northern boundary of the site.

    4.3 Device Design / Configuration

    This element of design was understandably the most well considered, with developers

    having put a lot of time and effort into the design and layout of their rotors and power take

    off system.

  • PTEC Developer Consultation Report

    UKP1191 10 October 2013

    The majority of developers consulted were using axial flow turbines. These were also

    generally the most advanced:

    24 of the developers consulted were developing axial flow turbines.

    5 were developing cross flow turbines.

    6 were exploiting some other power take off configuration.

    4 were developing turbine neutral platforms.

    8 developers have or are intending to use large rotors of 16m diameter or more. All but 6

    had rotational speeds of 15rpm or less; these 6 had rotational speeds above25rpm. The

    majority (18) were 3 bladed.

    9 developers employed pitch control of the rotors.

    17 developers had a design employing more than one rotor on their structure; this includes

    the developers of turbine neutral platforms

    11 of the 39 developers approached would intend to deploy surface piercing technology at

    the site.

    4.4 Foundations / Moorings

    Only 17 of the 39 developers consulted had a definite foundation / anchor design. 9

    developers indicated that foundation choice was site specific, this was particularly the case

    with the floating systems. Most of the early stage developers had not yet fixed this element

    of their design.

    A few developers are also concentrating on the turbine element only, and will be relying on

    others to supply mounting (foundation) systems such as the developers of ‘turbine neutral

    platforms’

    The breakdown of foundation / mooring concepts for those with a definite solution was as

    follows:

    Monopile: 7 developers

    Multi-pile (pin piles) : 16 developers

    Tripod - 8 developers

    Qudrapod - 1 developer

    Other - 7 developers (includes pinned anchors for mooring lines of floating

    systems)

    Gravity base: 7 developers

    It should be noted that there is some overlap between these categories, i.e. a few

    developers make use of a tripod gravity base (tripod support structure secured with ballast

    weights).

    The footprint of deployment varied significantly between the developers, with single,

    bottom mounted turbines requiring a small seabed area per device (

  • PTEC Developer Consultation Report

    UKP1191 11 October 2013

    4.5 Electrical Infrastructure

    4.5.1 Ratings and Voltage

    Most machines were rated at 1MW or more. 11 developers were intending to develop

    machines rated at over 2MW, the majority of these will use multiple turbines on a single

    platform to achieve this. Only 3 developers are intending to build individual turbines rated

    2MW or more.

    Most developers did not have a definite export voltage in mind, this was largely because

    most had not yet reached a point where they had to specifically define this. Others were

    currently exporting at a relatively low voltage, and intended to scale this with device size.

    Most of the advanced developers (11) were currently exporting at 6.6kV. This is largely

    driven by the system voltage at EMEC, which is 6.6kV, and to some degree by the cost and

    availability of subsea connectors certified for higher voltages. Many of the advanced

    developers stated that they intended to export at 11kV, in the long run, but were not yet

    at that stage.

    13 developers said they were able to export at either 11kV or 6.6kV (possibly even 33kV),

    depending on the requirements of the PTEC infrastructure, through appropriate transformer

    choice.

    Only 3 developers were intending to export at their generator voltage (with no on-board

    transformer), and were therefore looking for voltages of less than 6.6kV.

    The majority of developers would connect to the PTEC cable infrastructure by a dry mate

    connection, 7 device developers preferred a wet mate connection.

    4.5.2 Power Electronics

    Most developers intend to incorporate converters and power electronics into the ‘nacelle’

    of their machine. 6 were planning converters onshore or in their own sub-sea hub. 13 had

    not considered this element in detail and were therefore unsure.

    4.5.3 Isolation

    Most developers (14) were planning a circuit breaker on each individual machine, although

    all developers expected their cable / connection to be isolated for connection and removal

    of machines. The remainder are unsure or did not respond. Only 3 developers are not

    intending a circuit breaker on-board their machine.

    4.5.4 Communications

    All but 2 of the developers questioned intended to use fibre optic cables for communication

    with their device. Most of those who had previously deployed a large scale machine (at

    EMEC) also intended to use Wi-Fi or a radio link as a backup.

    The 2 developers who expressed a preference not to use fibre optics preferred to use a

    copper data cable due to the expense of fibre optic converters, slip rings etc.

  • PTEC Developer Consultation Report

    UKP1191 12 October 2013

    4.5.5 Low voltage / Back-up Electricity Supply

    10 developers said they required a low voltage, auxiliary / backup electricity supply. 6

    stated that this was a ‘nice to have’ but could be obtained from their own on-board

    transformer or batteries if necessary. Few developers consulted were able to give an

    indication of what this supply should be; responses ranged from 1kV to 20kW.

    4.6 Installation Approach

    Installation strategies varied widely depending on the foundation / mooring approach of the

    developer.

    7 developers intend to install foundations, then lower, ballast or pull the nacelles /

    turbines down onto the foundation.

    9 developers intend to use floating systems that remain on the surface attached to

    pre-installed anchors and mooring lines.

    11 developers plan to install their foundation and turbine as a complete unit.

    4.6.1 Vessels

    The most common installation vessel required was a DP vessel; 19 developers required one

    for at least part of their installation. 8 developers required multicat or tug boats, although

    most of these required a DP vessel (or moored barge) for their foundation or anchor

    installation. Only 1 developer intended to use a bespoke installation vessel.

    This drove sea-state restrictions, which was generally a maximum of 1.5m Hs. Only one

    developer believed they may be able to install their technology in larger sea-states than

    this.

    4.6.2 Installation Port Requirements

    Most developers who have considered this aspect required a laydown area of at least 60m2,

    a quay with hardstandings to lift at least 200t (up to 400t) and a draft suitable for the DP

    installation vessel used (approximately 8m).

    6 developers intend to mobilise their machines directly from the fabrication yard, so did

    not see an installation port as a requirement.

    The majority of developers consulted had not considered this factor in enough detail to

    meaningfully answer.

    4.7 Operation and Maintenance Considerations

    O&M strategies also varied considerably, with developers falling into one of two camps.

    Those with an intervention period of several years (generally between 2 and 5) – 8

    developers.

    Those who intend to access their machines for maintenance planned and unplanned)

    many times during the years – 8 developers.

    The remainder had not considered this aspect in detail or did not respond.

  • PTEC Developer Consultation Report

    UKP1191 13 October 2013

    The first group, consisted largely of those advanced developers with very simple technology,

    the majority of their complex systems onshore and with more complex access requirements.

    There were also a few early stage developers in this category, with possibly unrealistic

    expectations around reliability of systems and components.

    Access to machines for maintenance was planned in a manner broadly similar to their

    installation process.

    7 developers were intending to carry out all but the most major of maintenance

    activities on-board machines whilst on site.

    22 intend to remove machines to an O&M port to carry out this work.

    4.8 Other

    Additional services, infrastructure or requirements from developers were as follows:

    Support for consenting. Reduction of regulatory burden.

    Relationships with universities (or similar) for pre and post construction monitoring.

    Agreed monitoring strategy across the site / all projects, supplied by PTEC as part

    of services.

    Metocean conditions - particularly tidal flow monitoring, but also realtime wave

    monitoring and forecasting for the floating devices.

    Metering of electrical output from devices / arrays.

    A range of suitable, general vessels and equipment available, including experienced

    crews with knowledge of the area, for all developers to hire as and when required.

    Office space.

    A site manager that can co-ordinate work and emergency plans across the site.

    Engineering design services available.

    Third party performance assessments, for standards & certification.

    Nearly all developers indicated that they were in principle happy to share monitoring data.

    5 FUTURE MARKET GROWTH PREDICTIONS

    To date, the UK Government has not set an official target for marine energy but the latest

    roadmaps and studies have indicated a potential to install anywhere from 100MW to 400MW

    of tidal energy by 2020.

    5.1 First Arrays

    The industry at present is in a strong position and is poised to begin deploying the first small

    commercial arrays. These are intended to prove that multiple devices can operate together

    in the same location and supply power to the grid at a rate close to utility scale. The

    successful demonstration of these first arrays will be critical in the progression of the

    industry and will result in larger, fully commercial arrays being deployed with a significant

    increase in the total installed capacity. Based on the current state of the industry and

    knowledge of the activities of technology and project developers, IT Power believes that it

    is likely to be at least 2 – 3 years before these first, small arrays are installed and grid

    connected in the UK.

  • PTEC Developer Consultation Report

    UKP1191 14 October 2013

    Demonstration sites like PTEC that allow such array projects to be built without each

    developer having to bear the full cost of the electrical infrastructure and development risk

    will have a key role to play in these early projects.

    During the demonstration and proving of first generation tidal devices, new second

    generation technologies are starting to be developed with the aim of reducing costs and

    increasing output. This will build on the learning achieved through the operational

    experience gained from the first generation turbines. Such advances will see larger turbines,

    multiple units being deployed on a common structure, improved deployment and recovery

    methods and lower installation costs. This will allow developers to access a large proportion

    of the UK’s tidal stream resource with technologies that are able to be installed at deep

    water, high velocity and hostile sites. Third generation machines are expected to target at

    low flow sites; very deep water or very shallow water. This will open up a huge area of

    resource, often ignored in estimates of exploitable potential. Exploitation of these sites has

    even more potential outside of the UK.

    The Crown estate has so far issued 26 leases or Agreements for Lease to tidal projects,

    totalling over 1.3GW of potential capacity. 16 of these are for small array projects of 10MW

    or less (totally around 50MW). Each of these projects represents a credible developer and

    thus a potential customer for PTEC. Many of these projects will not get constructed for

    various financial and consenting reasons, making PTEC an even stronger prospect for these

    developers.

    5.2 Larger ‘Commercial’ Projects

    Following these initial arrays, developers will seek to optimise the energy yield from each

    unit and the total combined array output. With the learning acquired from the first arrays

    and the installation of second generation arrays, the improved device technology should

    demonstrate cost reductions to increase the commercial competitiveness of tidal energy

    against other forms of renewable generators. The magnitude of public revenue support for

    tidal energy is expected to reduce over the next decades as the technologies mature and

    therefore require less financial support. DECC aims for the revenue support to reach parity

    with offshore wind by approximately 2027, although this is likely to be flexible, based upon

    the progress of the industry. It is, however, imperative that the cost of energy decreases

    rapidly in order for the tidal industry to become cost competitive with offshore wind and

    other large scale, renewable generating technologies before 2030.

  • PTEC Developer Consultation Report

    UKP1191 15 October 2013

    Figure 1: IT Power’s predictions for the deployment of tidal energy converters,

    including capital and revenue support mechanisms.

    (Adapted from the Marine Energy Action Plan Report, DECC 2009

    The roadmaps that have been generated have been useful in guiding Governmental policies

    and conveying the needs and requirements of the industry however, the predicted

    timescales and magnitudes of the deployment of marine energy have all been optimistic. IT

    Power’s timescale predictions for the deployment of tidal energy are shown in Figure 1 are

    based on the company’s experience in the industry and involvement with many tidal

    development projects. Whilst these may seem pessimistic, in terms of timescales, than

    many of the roadmap predictions made over the recent years, they represent a more

    realistic timescale over which significant engineering challenges will be overcome and the

    large scale deployment of TECs at a utility level will be made.

    6 CONSIDERATIONS FOR PTEC INFRASTRUCTURE AND ROCHDALE ENVELOPE

    The responses obtained during this consultation prove that PTEC will have to be very flexible

    in order to accommodate as many developers as possible, and the Rochdale Envelope would

    need to be very broad. The difficulty and expense of incorporating all technologies

    consulted as part of this work would not be worthwhile. The suggested ‘extremes’ that

    could be covered by the Rochdale Envelope are shown in Table 2 below. This will be further

    refined with appropriate sample technologies to represent these extremes selected in

    collaboration with PTEC and the EIA team. As part of the Rochdale envelope and EIA process,

    consideration will also need to be given to exclusion/safety zones and process for defining

    and implementing these if required.

  • PTEC Developer Consultation Report

    UKP1191 16 October 2013

    Table 2: Considerations for Rochdale Envelope

    Element ‘Worst case’ Possibility

    Number of machines (complete units,

    which could comprise multiple rotors) Up to 30

    Device configurations Axial flow, cross flow, ducted

    Rotors

    Up to 25m rotor diameter

    Up to 70 individual rotors

    Up to 60rpm

    Location Bottom mounted, mid-water column,

    floating / surface piercing

    Foundations (structure) Monopile, tripod, frame up to (30m x

    30m)

    Moorings, anchors (securing system) Monopile, pinpiles, gravity base

    Up to 90 individual piles installed

    Cables

    Up to 6 separate export cables

    Up to 30 separate ‘inter-array’

    (turbine) cables

    With regards to the infrastructure supplied by PTEC, the following should be considered:

    6.1 Size and number of berths / cables

    5 developers indicated they wanted a berth of at least 6MW. These were generally the most

    advanced developers with realistic possibility of coming to PTEC in the timescales indicated,

    although 3 of these were only considering PTEC as a backup. The ability to accommodate at

    least 2 berths of this size would seem appropriate. If the size (ratings) of each berth / cable

    could be varied, this would reduce the risk of unallocated capacity at the site.

    Given the projects highlighted in Table 1, 6 individual berths would seem appropriate.

    6.2 Voltages

    Nearly as many developers stated they would need to export power at 6.6kV as said 11kV.

    Cables at both voltages, with the flexibility to change the voltage would be beneficial. This

    could be achieved with multiple cables to shore and tap changers on the main transformer.

    A separate cable to shore for each berth, would also enable accommodation of those

    developers looking to keep their control equipment onshore or in their own hub, as well as

    those not planning an isolator in their own turbine.

    Given the number of developers who stated they would need an auxiliary power supply in

    ‘their’ cable, this element should be investigated. The cost of supplying this is likely to be

    small when compared to the cost of the cables.

  • PTEC Developer Consultation Report

    UKP1191 17 October 2013

    6.3 Progress towards Design Freeze

    Table 2 above summarises the considerations for the Rochdale Envelope coming out of this

    consultation. This will be further refined with appropriate sample technologies to represent

    these extremes, selected in collaboration with PTEC and the EIA team.

    The current FEED programme should reach a design freeze in March 2014; however, there

    is a requirement to accelerate this for the benefit of the EIA work; and therefore reach

    design freeze as soon as possible

    There may still be some flexibility after this date with regards to the size and rating of a

    particular berth, including voltage; but the number of cables (and thus berths) as well as

    the overall size of the project (20 or 30MW) will have to be fixed at this point. Other

    elements that need to be fixed at the same time will be:

    Size (extent) of site

    Cables and routes as well as installation/protection measures (on and offshore)

    Type of landfall

    Location and size of onshore substation

    Grid connection point

    The Rochdale Envelope and associated technologies /number that define it

    It should be noted that even after design freeze, these elements will not be set in stone

    and if there is a strong enough reason for them to change then this may be accommodated.

    Design freeze will be achieved following a review of the second issue of the design options

    report and a design workshop with IT Power, Royal HaskoningDHV and PTEC. It will also be

    dependent on an agreed strategy for the grid connection application process, the ground

    conditions report and the cabling options report.

  • PTEC Developer Consultation Report

    UKP1191 0 October 2013

    APPENDIX A: DEVELOPER QUESTIONNAIRE

  • PERPETUUS TIDAL ENERGY

    CENTRE LTD

    PTEC Developer Questionnaire

  • 7 INTRODUCTION

    The Perpetuus Tidal Energy Centre (PTEC) is a managed test / demonstration facility for tidal energy

    developers; suitable for the deployment of up to full scale single units and small arrays from prototype to

    pre-commercial demonstrators.

    The offshore facility will be a 20MW demonstration site located approximately 2.5km to the south of St.

    Catherine’s Point, and will include grid connection via subsea cables as well as navigation aids and

    monitoring equipment. For further details please see the ‘PTEC Project Introduction’ document.

    7.1 Scope

    The purpose of this industry consultation is to obtain a coherent list of requirements from tidal developers

    that can inform the FEED study for the design of the electrical system and integrate effectively with the

    consenting process to determine preliminary site layout, outline Rochdale Envelope, and input into the

    EIA, infrastructure requirements and project design statement.

    NOTE: The FEED consultation will not include discussions of a commercial nature; this will remain the

    responsibility of the PTEC team.

    7.2 Key Objectives

    There are four main objectives for this developer consultation:

    1. Obtain information to define the project requirements for the FEED Study, which will comprise:

    Technical data relating to the device.

    Infrastructure requirements

    Deployment and recovery plans and requirements.

    O&M plans and requirements.

    Data to define the Rochdale Envelope and project design statement.

    2. Understand the approximate deployment timescales expected by developers.

    3. Understand the ideal services that they would require from PTEC.

    4. Understand the ideal port and onshore support infrastructure requirements on the Isle of Wight.

    NOTE: The details given by all participants in this consultation will be held in the strictest confidence

    and will not be shared outside of the PTEC project team.

    IT Power and PTEC are prepared to enter into confidentiality agreements with all who wish in this regard.

  • 8 QUESTIONNAIRE

    Question Answer

    Genera

    l

    Would you be interested in

    deploying a project at PTEC?

    Please summarise your testing

    programmes and (3rd party)

    verification to date.

    Tim

    ing

    Approximately when would you

    be looking to deploy machines

    there?

    What would be the intended

    length of deployment for your

    project?

    Sit

    e d

    esi

    gn

    How may devices would you be

    looking to deploy?

    Comments on the number /

    layout of berths within PTEC?

    Potential layout of devices and

    infrastructure within a berth?

    Devic

    e d

    esi

    gn

    Device configuration (axial

    flow/transverse/other)

    Surface piercing/floating/sub

    surface

    Foundation/mooring type,

    number and design (e.g. gravity

    base/piled)

  • Footprint of deployment

    Number of blades, dimensions

    and rotation speed

    Electrical output – rated capacity

    and voltage

    Control strategy:

    Pitch/stall regulation

    (active, passive, speed

    etc)

    Type & location of

    converters

    Communications and electrical

    isolation methodology

    Connection to transmission

    infrastructure

    Inst

    allati

    on a

    ppro

    ach

    Installation methodology

    Installation equipment and

    vessels to be used

    Duration and seasonality

    (seastate restrictions) of offshore

    installation activity

    Installation port requirements

    (e.g. space, hard standings and

    road access, etc)

    Onshore support infrastructure

    requirements

    Oper

    ati

    on

    al

    and

    main

    tena

    nce

    consi

    dera

    tions

    O&M strategy

  • Seastate restrictions for offshore

    O&M

    Personnel and vessels required

    Planned frequency of scheduled

    maintenance interventions /

    surveys

    Back-up electricity supply

    requirement

    O&M port requirements

    Decom

    m

    issi

    onin

    g

    Approach to decommissioning

    Oth

    er

    Ideal services that a developer

    would expect PTEC to provide

    Other onshore support

    infrastructure requirements

    Key results of any prior EIA

    studies

    Willingness for sharing of data

    (environmental monitoring)

    Health & safety considerations