petronet corporate presentation june 2011
TRANSCRIPT
-
7/31/2019 Petronet Corporate Presentation June 2011
1/34
PETRONET LNG LIMITED
PETRONET LNG LIMITED
2011
A CORPORATE PROFILE
-
7/31/2019 Petronet Corporate Presentation June 2011
2/34
OVERVIEWOVERVIEW
Global & Indias Primary Energy ConsumptionScenario
Indias Gas Scenario, Infrastructure
Pricing of Gas
About Petronets
Dahej & Kochi Terminals
New Initiatives
Performance
-
7/31/2019 Petronet Corporate Presentation June 2011
3/34
PRIMARY ENERGY PER CAPITA CONSUMPTIONPRIMARY ENERGY PER CAPITA CONSUMPTION
Source : BP Statistical Review June 2011
-
7/31/2019 Petronet Corporate Presentation June 2011
4/34
PRIMARY ENERGY CONSUMPTION (MTOE)PRIMARY ENERGY CONSUMPTION (MTOE) -- WORLDWORLD
Fuel 2005 % 2010 %
Oil 3837 36 4028 34
Gas 2475 24 2858 24
Coal 2930 28 3556 30
36%
28%
6%6%
Oil
Gas
coal
Nuclear
Hydro
Renewables
Year 2005
Source : BP Statistical Review-June 2011
Nuclear 627 6 626 5
Hydro 669 6 776 6
Renewables - - 159 1
Total 10537 100 12002 100
34%
24%
30%
5%6%
1%
Oil
Gas
coal
Nuclear
Hydro
Renewables
Year 2010
-
7/31/2019 Petronet Corporate Presentation June 2011
5/34
PRIMARY ENERGY CONSUMPTION (MTOE)PRIMARY ENERGY CONSUMPTION (MTOE) -- INDIAINDIA
Fuel 2005 % 2010 %
Oil 116 30 156 29
Gas 33 8 56 11
Coal 213 56 278 53
Year 2005
30%
8%56%
1%5%
Oil
Gas
coal
Nuclear
Hydro
Renewables
Nuclear 4 1 5 1
Hydro 22 5 25 5
Renewables - - 5 1
Total 387 100 524 100
Year 2010
Source : BP Statistical Review-June 2011
29%
11%53%
1% 5%1%
Oil
Gas
coal
Nuclear
Hydro
Renewables
-
7/31/2019 Petronet Corporate Presentation June 2011
6/34
INDIAINDIA A MAJOR GAS/LNG CONSUMERA MAJOR GAS/LNG CONSUMER
13th largest gas consumer 70 BCM (~190 MMSCMD)
6th largest LNG importer 16 BCM (~44 MMSCMD)
Economy increasing at CAGR of 7-8% p.a. with similarincrease in Energy Consumption
increase from 11% to 20% by 2025
Despite increase in domestic gas production-dependency on imported gas to increase substantially
Pipeline network- developing into a national grid- needsto grow faster, connecting new markets
-
7/31/2019 Petronet Corporate Presentation June 2011
7/34
CURRENT GAS DEMAND &CURRENT GAS DEMAND &DOMESTIC SUPPLY SCENARIODOMESTIC SUPPLY SCENARIO
550+ (19.5+)
253.4 (9.0)
306.4 (10.8)341.1 (12.1)
381.0 (13.5)
250.0
300.0
350.0
400.0
Demand Supply
( Bcf/Day)
( MMSCMD)
240 (8.5)
Demand Mercados Analysis
Supply Directorate General of Hydrocarbons (DGH)
178.9 (6.3)
146 (5.2) 155 (5.5)191.6 (6.8)198.4 (7.0)
202.9 (7.2)
0.0
50.0
100.0
150.0
200.0
2010-11 2011-12 2012-13 2013-14 2014-15 2019-20
(7.6)
-
7/31/2019 Petronet Corporate Presentation June 2011
8/34
-
50.00
100.00
150.00
200.00
250.00
GasDemand (MMSCMD)
SECTOR WISE PROJECTED GAS DEMANDSECTOR WISE PROJECTED GAS DEMAND
2009-10 2010-11 2011-12 2012-13 2013-14 2014-15
P owe r Fe rtilize r City Gas P etc he m-Re fine ry Sponge Ir on
2010-11 2011-12 2012-13 2013-14 2014-15
Power 87.71 149.11 185.52 212.73 243.34
Fertilizer 49.39 57.48 68.08 68.08 68.08
City Gas 13.70 17.53 22.44 28.72 36.76
Petchem-Refinery 24.44 25.42 26.43 27.49 28.59
Sponge Iron 3.71 3.82 3.93 4.05 4.17
Total 178.94 253.36 306.41 341.08 380.95
Source: Mercados Analysis, 2010
-
7/31/2019 Petronet Corporate Presentation June 2011
9/34
146185
46
185
35
185
77
185
4591
126
203
40
311
388
27659
171
25
19
230
Gas demand and supply, 2015
Mmscmd, at customer gate prices
LARGE DEMAND BUT SENSITIVE TO PRICELARGE DEMAND BUT SENSITIVE TO PRICE
SOURCE: Indianpetro; DGH; Company annual reports; Expert interviews; McKinsey analysis
High Potentialdemand,2015
Price of $8-10 mmbtu
Medium Price of $11-12/ mmbtu
Price of $13-14/ mmbtu
Price of $16-17/ mmbtu
Low2010 yearendconsumption
1 Based on estimated LNG supply of 8 mtpa in 2015 including RasGas (7.5 mtpa) and 1.5 mtpa from Gorgon LNG in 2015
21 3 4
Imports
Domestic supplies
Sectors withdemand
Industries CNG
transport
Refineries Industries Power
cogen
Peakingpowerplants
Baseloadpower
New fertilizer
plants
Prices at Crude of $ 100/Bbl
-
7/31/2019 Petronet Corporate Presentation June 2011
10/34
INDIAs GAS INFRASTRUCTUREINDIAs GAS INFRASTRUCTURE
-
7/31/2019 Petronet Corporate Presentation June 2011
11/34
LNG IN INDIALNG IN INDIA
Hydrocarbon Vision 2025 envisaged a GDP growth of 5-6% forthe E&P sector along with demand supply scenario of oil & gas in
the Country
Current GDP growth of 79% translate into overall energy
demand growth at CAGR of 7.50%
Given Indias growing energy requirements & unlikelihood ofmatching increase in the domestic supplies, despite some
significant oil & gas finds recently, the import dependence is
only going to accentuate sharply in the coming years
LNG Regas Capacities
Presently, Indias LNG import capacity is around 13.5 MMTPA through
its two terminals & meeting approx. 20% of total gas supply of the
country
-
7/31/2019 Petronet Corporate Presentation June 2011
12/34
PETRONET LNG LIMITEDPETRONET LNG LIMITED
Incorporated on April 2, 1998
Authorized Capital USD 260 mln, Paid up capital USD 160 mln
Commencement of Commercial Operations - April, 2004
Equity
, , 10% held by GDFI (part of GDF SUEZ) 5.20% ADB
-
7/31/2019 Petronet Corporate Presentation June 2011
13/34
VisionVision
To be a key energy provider to thenation by leveraging unique position inthe LNG value-chain with internationalpresence
Revenue grew 24%EBITDA growth 17%
TOWARDS THE VISIONTOWARDS THE VISION
Create and manage worldCreate and manage world--classclassLNG infrastructureLNG infrastructure
Pursue synergistic businessPursue synergistic businessopportunitiesopportunities
Continue excellence in LNGContinue excellence in LNG
Business StrategyBusiness Strategy
2849
businessbusiness
- Focus on higher capacityutilization and betteroperational efficiencies
- Diversify LNG sources
Diversify businessDiversify business
- Gas-based power generation
- Venture into city-gas
distribution/ direct marketingto far-flung consumers
- Solid cargo port at Dahej
Maintain highest standards ofMaintain highest standards ofbusiness ethicsbusiness ethics
11981425
1772
2305
146 196 208 201273
FY-07 FY-08 FY-09 FY-10 FY-11
RevenueEBIDTA
(all values in USD Million)
-
7/31/2019 Petronet Corporate Presentation June 2011
14/34
DAHEJ LNG TERMINALDAHEJ LNG TERMINAL
Located at West Coast, State of Gujarat in the Gulf ofCambay
Commencement of Operations in 2004
Capacity (Mmtpa) : 5.0 10.0
Truck Loading facility can handle 2500 loadings/ yr.
LNG Cargoes unloaded :761(September 21,2011)
Further capacity expansion to 15 Mmtpa
Second Jetty : Under Construction
Regas & Storage Capacity : DFR Under Progress
Pre Project Activities started
-
7/31/2019 Petronet Corporate Presentation June 2011
15/34
DAHEJ LNG STORAGE TANKSDAHEJ LNG STORAGE TANKS
-
7/31/2019 Petronet Corporate Presentation June 2011
16/34
DAHEJ REGAS FACILITIES WITH AIRDAHEJ REGAS FACILITIES WITH AIR--HEATERHEATER
-
7/31/2019 Petronet Corporate Presentation June 2011
17/34
LNG TRUCK LODING FACILITIESLNG TRUCK LODING FACILITIES DAHEJDAHEJ
VAPORISATIONVAPORISATIONFACILITIESFACILITIESWEIGH BRIDGEWEIGH BRIDGE
-
7/31/2019 Petronet Corporate Presentation June 2011
18/34
KOCHI LNG TERMINALKOCHI LNG TERMINAL
LNG Terminal located in Special Economic Zone with Co-developer status
Capacity 2.5 5.0 MMTPA
Tied up 1.44 MMTPA LNG from Exxon Mobils Gorgon Project
,
Regasification Facilities being constructed by CTCI, Taiwan
Marine Facilities being constructed by Afcons Infrastructure Ltd
Progress on schedule, overall completion more than
87%, scheduled commissioning by end 3rd Qtr. , 2012
-
7/31/2019 Petronet Corporate Presentation June 2011
19/34
KOCHIKOCHI STORAGE TANKSTORAGE TANK
-
7/31/2019 Petronet Corporate Presentation June 2011
20/34
KOCHIKOCHI -- MARINE FACILITIESMARINE FACILITIES
-
7/31/2019 Petronet Corporate Presentation June 2011
21/34
NEW THIRD TERMINAL AT EAST COASTNEW THIRD TERMINAL AT EAST COAST
Proposed Capacity: 5 MMTPA
Possible Locations: Andhra orOrissa Coast
Regasification Scheme:Indirect Fluid using ambient
a r ea er
PFR Completed
Site Selection Process underprogress
Process for selection of
Consultant for DFR started
-
7/31/2019 Petronet Corporate Presentation June 2011
22/34
INTEGRATED POWER PLANT AT DAHEJINTEGRATED POWER PLANT AT DAHEJ
Proposed power plant of 3 x 356 MW-ISO (total 1068 MW CCGT)with improved performance, the expected output is 1200 MW
Fuel requirement of 1.0~1.1 Mmtpa LNG
Implementation schedule
-
33 months for construction and commissioning
DFR for a 1200 MW Power Plant - completed
Land Acquisition & Environment Clearance under progress.
Power project planned to harness cold energy from LNGTerminal
-
7/31/2019 Petronet Corporate Presentation June 2011
23/34
DIRECT MARKETINGDIRECT MARKETING
Petronet exploring opportunities to supply LNG to Coastalarea consumers through small LNG Vessels in India andneighbouring countries
Direct Marketing by focusing on the following areas:
Signed HOAs with bulk end consumers in Power, Refineries
LNG/LCNG supplies through Trucks, to LNG hubs, SatelliteStations at customers premises in regions not serviced bypipelines
-
7/31/2019 Petronet Corporate Presentation June 2011
24/34
BUSINESS MODELBUSINESS MODEL
Robust Model
LNG supply contract with RasGas, Qatar & Exxon Mobil, Australia
Gas Sales Agreement with GAIL, IOCL & BPCL back to back with SPA
Time Charter Agreement with established consortium
Entire Fuel cost pass through including exchange rate
Location
Proximity to LNG suppliers
Most competitive LNG transportation cost
Proximity to Customers HBJ pipeline, DUPL and GSPC network in
Gujarat
-
7/31/2019 Petronet Corporate Presentation June 2011
25/34
FINANCINGFINANCING
Very strong parentage and a robust business model
Financing cost is amongst the lowest in the industry
With the use of effective hedging techniques, the
debt service even in such turbulent times
-
7/31/2019 Petronet Corporate Presentation June 2011
26/34
PERFORMANCE GRAPHPERFORMANCE GRAPH
287
322 321
384
412
350
400
450
Sales Trillion BTU
486
583
638
500
600
700
Net Worth (Million USD)
125
247
115
0
50
100
150
200
250
191
233
277
352
0
100
200
300
400
-
7/31/2019 Petronet Corporate Presentation June 2011
27/34
PERFORMANCE GRAPHPERFORMANCE GRAPH
Million USD
PAT Million USD
103
113
135
120
140
160
2305
2849
2000
2500
3000
Turnover USD Million
-6
42
68
88
56
-20
0
20
40
60
80
423
834
1198
1425
991
0
500
1000
1500
-
7/31/2019 Petronet Corporate Presentation June 2011
28/34
PERFORMANCE BASED ON EMPLOYEE PARAMETERSPERFORMANCE BASED ON EMPLOYEE PARAMETERS
2010-11 2009-10 2008-09
No. of Employees 276 273 256
Turnover/ employees (USD Million) 10.31 8.47 7.24
Profit Before Tax / Employee (USD Million) 0.70 0.47 0.66
Employee Remuneration cost as % of Profit) 3.3% 3.41% 2.53%
Total no. of employees : 276
Training & Development : 6 Mandays / Employee
Average Age: 34 years (58% employee in 31-40 years of age)
63% of employees are Graduates or Post Graduates
Average years of association of employees with Company 5 years
Attrition rate 2010-11 : 4%
-
7/31/2019 Petronet Corporate Presentation June 2011
29/34
FINANCIAL PARAMETERSFINANCIAL PARAMETERS
0.06
0.09
0.140.15
0.12
0.18EPS (USD)
Year EPS (USD) P/E D/E Ratio
FY-06 0.06 23.99 1.17
FY-07 0.09 11.15 1.08FY-08 0.14 11.62 0.97
FY-09 0.15 5.75 1.15
FY-10 0.12 15.19 1.12
FY-11 0.18 14.86 1.20
FY-06 FY-07 FY-08 FY-09 FY-10 FY-11
-
7/31/2019 Petronet Corporate Presentation June 2011
30/34
SHAREHOLDERS WEALTH CREATIONSHAREHOLDERS WEALTH CREATION
As on Mar, 31 2004 2005 2006 2007 2008 2009 2010 2011 Current
USD per share 0.58 1.00 1.34 1.01 1.60 0.87 1.78 2.67 3.87
Mkt. Price INR 27 46 62 47 73 40 82 123 178
USD per share
0.581.00
1.34
1.01
1.60
0.87
1.78
2.67
3.87
2004 2005 2006 2007 2008 2009 2010 2011 Sep/11
-
7/31/2019 Petronet Corporate Presentation June 2011
31/34
FINANCING STRUCTUREFINANCING STRUCTURE
Particulars DahejTerminal
KochiTerminal
2ndBerth at
Dahej
Total
Shareholders FundEquity Capital/Internalaccruals/Premium
250 270 60 580
((US$ MILLION)US$ MILLION)
Debt 550 630 140 1320
Total Means of Finance 800 900 200 1900
-
7/31/2019 Petronet Corporate Presentation June 2011
32/34
CSRCSR --THE JOURNEY HAS JUST BEGUNTHE JOURNEY HAS JUST BEGUNTOWARDS AN INCLUSIVE SOCIETYTOWARDS AN INCLUSIVE SOCIETY
Participative community development programmes with GIDC Luvara & Lakhigam villages
CODEGAZ, the CSR arm of our strategic partner GDF Suez supports our cause.
Health & Sanitation
Potable drinking water/water harvesting/laying of water pipelines/ Storm water drainage.
Preventive and Social medicine aids (includes primary health centre).
Education and Employment generation programs
Construction of School Scholarshi & Vocational Trainin .
Sponsorship of differently abled children of Tamanna School & inauguration of Petronet LNG
Centre for Vocational Rehabilitation.
Indirect employment for local villagers in the area of Housekeeping & Horticulture.
Community Development
Renovation of personal facility & fencing at Panchayat office of Luvara Village, Gujarat.
Govt. Development Schemes (Kanya Kelvani, Beti Bachao) & Devp. Distt Civic Centre.
-
7/31/2019 Petronet Corporate Presentation June 2011
33/34
NOTESNOTES
-
7/31/2019 Petronet Corporate Presentation June 2011
34/34
Dahej PlantPetronet LNG Limited
GIDC Industrial
Estate,Plot No. 7/A, Dahej,
Taluka Vagra,Distt. Bharuch
Gujarat - 392130
Corporate OfficePetronet LNG Limited,
1st Floor, World Trade Centre,Babar Road, Barakhamba
Lane,
New Delhi 110001www.petronetlng.com
For any other info. :[email protected]
Ph: 91-11-23411411
Kochi SitePetronet LNG Limited
Survey No. 347,Puthuvypu P.O. ,
Kochi, Kerala - 682508