ID Task Name Duration Start Finish
1 Investigation Topic 25 days Mon 02/02/15 Fri 06/03/15
2 Get a topic 1 day Tue 03/02/15 Tue 03/02/15
3 Discuss with supervisor 1 day Tue 03/02/15 Tue 03/02/15
4 Research 10 days Wed 04/02/15 Tue 17/02/15
5 Proposal Draft 5 days Tue 17/02/15 Mon 23/02/15
6 Submit Proposal Draft 1 day Mon 23/02/15 Mon 23/02/15
7 Edit Proposal 2 days Mon 23/02/15 Tue 24/02/15
8 Submit Final Proposal 1 day Mon 02/02/15 Mon 02/02/15
9 Feedback from Supervisor 5 days Mon 02/03/15 Fri 06/03/15
10 Literature Study 10 days Wed 25/02/15 Tue 10/03/15
11 Laser Additive Manufacturing 5 days Wed 25/02/15 Tue 03/03/15
12 Titanium 2 days Wed 04/03/15 Thu 05/03/15
13 Titanium Alloys 1 day Fri 06/03/15 Fri 06/03/15
14 Titanium Diboride 1 day Sat 07/02/15 Sat 07/02/15
15 Water Jet cutting 1 day Sun 08/03/15 Sun 08/03/15
16 Experimental Design 9 days Tue 10/03/15 Fri 20/03/15
17 Develop sample preparation 2 days Tue 10/03/15 Wed 11/03/15
18 Develop Testing Procedures 5 days Thu 12/03/15 Wed 18/03/15
19 Develop Experimental Matrix 2 days Thu 19/03/15 Fri 20/03/15
20 Submit Preliminary Report Draft 1 day Fri 20/03/15 Fri 20/03/15
21 Edit Preliminary Report 1 day Sat 21/03/15 Sat 21/03/15
22 Submit final preliminary report 1 day Mon 23/03/15 Mon 23/03/15
23 Experimental Procedure 47 days Tue 24/03/15 Wed 27/05/15
24 Prepare Sample 4 days Tue 24/03/15 Fri 27/03/15
25 Analyse Powder - SEM 5 days Mon 30/03/15 Fri 03/04/15
26 Water Jet cutting 5 days Mon 06/04/15 Fri 10/04/15
27 Microstructure 5 days Mon 13/04/15 Fri 17/04/15
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Project Summary
Manual Summary
Start-only
Finish-only
Progress
Manual Progress
Page 1
Project: PJM project plan
Date: Fri 27/02/15
-
7/21/2019 PJM Project Plan
2/2
ID Task Name Duration Start Finish
28 Wear And Corrosion Testing 15 days Mon 20/04/15 Fri 08/05/15
29 Hardness 5 days Mon 11/05/15 Fri 15/05/15
30 Simulation 8 days Mon 18/05/15 Wed 27/05/15
31 Presentation 1 4 days Tue 05/05/15 Fri 08/05/15
32 Prepare Slides 2 days Tue 05/05/15 Wed 06/05/15
33Prepare Speech 2 days Thu 07/05/15 Fri 08/05/15
34 Second Preliminary Report 65 days Mon 01/06/15 Fri 28/08/15
35 Results 30 days Mon 01/06/15 Fri 10/07/15
36 Discussion 15 days Sat 11/07/15 Thu 30/07/15
37 Conclusion 15 days Thu 30/07/15 Wed 19/08/15
38 Submit Draft 1 day Thu 20/08/15 Thu 20/08/15
39 Edit Draft 5 days Fri 21/08/15 Thu 27/08/15
40 Submit final 1 day Fri 28/08/15 Fri 28/08/15
41 Presentation 2 5 days Mon 31/08/15 Fri 04/09/15
42 Prepare Slides 3 days Mon 31/08/15 Wed 02/09/15
43 Prepare Speech 2 days Thu 03/09/15 Fri 04/09/15
44 Final Dissertation 22 days Sat 05/09/15 Mon 05/10/15
45 Final Dissertation 10 days Sat 05/09/15 Thu 17/09/15
46 Submit Draft 3 days Thu 17/09/15 Mon 21/09/15
47 Edit 8 days Tue 22/09/15 Thu 01/10/15
48 Submit Final 1 day Mon 05/10/15 Mon 05/10/15
49 Poster 6 days Mon 05/10/15 Mon 12/10/15
50 Prepare Poster 5 days Mon 05/10/15 Fri 09/10/15
51Submit Poster 1 day Mon 12/10/15 Mon 12/10/15
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Project Summary
Manual Summary
Start-only
Finish-only
Progress
Manual Progress
Page 2
Project: PJM project plan
Date: Fri 27/02/15