pontoon construction project overview - wsdot.com filepontoon construction project overview february...
TRANSCRIPT
Pontoon construction project overview
February 2013
• WSDOT is moving forward with pontoon construction to replace the aging and vulnerable SR 520 floating bridge on Lake Washington
• The $367.3 million Pontoon Construction Project broke ground in February 2011 at a 55-acre site in Aberdeen. • As part of this project, contractor Kiewit-General Joint Venture (K-G) has built a new casting basin facility and is constructing 33 concrete pontoons that will be used to replace the SR 520 floating bridge.
An aerial photograph of the pontoon casting basin and Grays Harbor in May 2012. Photo courtesy of Soundview Aerial Photography.
Seattle
Kenmore
Olympia
Tacoma
GraysHarbor
Lake Washington
MEDINA
MADISON PARK
West Connection Bridge
Barrier andrestriping
EastApproach
Bridge Maintenance Facility
Floating Bridge
SR 520 Floating Bridge and Landings Project elements
99
5
5
405
405
90
90
520
167
509
Puget Sound
ElliottBay
Shoreline
Seattle
MercerIsland
FederalWay
Port of Tacoma
Kent
Renton
Bellevue
Auburn
Fife
Snohomish County
King County
King County
Pierce County
BothellKenmore
Redmond
Sea-Tac
202
900
522
Lake Washington Lake
Sammamish
509
161
99
18
516
Floating bridge and landings project area
February 2013
Project elements include:Design and construction of:
• New six-lane floating bridge superstructure and roadway, including HOV lanes and a bicycle/pedestrian path. • 44 supplemental stability pontoons. • Anchors and anchor cables. • Permanent East Approach. • Final connection to Evergreen Point Road vicinity. • Transition structures between East and West Approaches and floating bridge. • New maintenance facility and dock in Medina.
Towing pontoons to Lake Washington.Assembly of the new floating bridge.Removal of existing floating bridge and landings.
SR 520 construction activities are taking place at multiple locations in Washington state.
99
5
5
5
405
405
90
520
167
167
509
18
161
99
516
Puget Sound
ElliottBay
Shoreline
Seattle
MercerIsland
FederalWay
Port of Tacoma
Kent
Renton
Bellevue
Auburn
Fife
Snohomish County
King County
King County
Pierce County
BothellKenmore
Redmond
Sea-Tac
202
900
522
Lake Washington Lake
Sammamish
B
C
D
E
SR 520 construction around the state
A. Grays Harbor (Feb. 2011 – 2014) • Pontoon construction• Pontoon moorage• Casting basin construction
B. Port of Tacoma (Nov. 2011 – early 2014)• Pontoon construction• Pre-cast concrete elements• Pontoon moorage and outfitting
C. Kenmore (Feb. 2012 – early 2014)• Anchors• Pre-cast concrete element• Deck sections
D. Lake Washington (Spring 2012 – 2016)• Bridge assembly• Bridge Maintenance Facility• East and West Approach connections• Decommission existing bridge
E. Eastside (Spring 2011 – Winter 2014)• Lid construction• Highway widening• Culvert installation
349 direct jobsJan. 2013
174 direct jobsDec. 2012
24 direct jobsDec. 2012
254 direct jobsDec. 2012
207 direct jobsDec. 2012
1,008 direct jobsWinter 2013
TOTAL
Seattle
Kenmore
Olympia
Tacoma
GraysHarbor
A
All towing will occur in designated shipping lanes.
Crews on site in Kenmore. Pontoon progress in Tacoma.
February 2013
In addition to direct employment listed above, SR 520construction creates opportunities for vendors, suppliers and other services like restaurants and retail.
Supplemental
stability pontoons(54)
Supplemental stability pontoon
Longitudinal pontoons(21)
Longitudinal pontoon
Superstructure
Cross pontoons(2)
Cross pontoon
The three types of pontoons that will support the new SR 520 floating bridge.
A representation of pontoons being assembled on Lake Washington.
February 2013
SR 520 floating bridge pontoons The new SR 520 floating bridge will be supported by three types of concrete pontoons:
Longitudinal pontoons (21) – These are the largest pontoons at approximately 360 feet long. They form the backbone of the bridge and support the roadway superstructure. • Constructed in Aberdeen facility • Weight: 11,100 tons
Cross pontoons (2) – These mark the ends of the floating bridge section and the transition to the East and West Approach structures. • Constructed in Aberdeen facility • Weight: 10,100 - 10,550 tons
Supplemental stability pontoons (54) – These smaller pontoons help stabilize and support the weight of the new floating bridge. • Constructed in Aberdeen facility (10) and Tacoma facility (44) • Weight: 2,500 - 2,820 tons
February 2013
FOR ILLUSTRATION PURPOSE ONLY - NOT TO SCALE
???
Wall forms
Keel slab
Wall formsupports Wall form
supports
Wall formsupports
Precast panelInternalwatertightcell
Rebar
Rebar
Rebar
Post-tensioning ducts
Post-tensioning duct
Exterior wall slab
Wall FormSupports
How to build a pontoon
bals leek ni etercnoc ruop dna slenap tsacerp roiretni llatsnI stcud gninoisnet-tsop llatsni dna ,raber ,smrof llaw teS • Longitudinal pontoons: 90 precast panels • Cross pontoons: 57 precast panels • Supplemental stability pontoons: 9 precast panels
Pour top slab rebar and post-tensioning ducts Remove wallforms and perform post-tensioningto add strengh
Pour concrete for exterior walls and joints between interior precast pannels
1 2 3
64
Post-tensioning duct
Wall formsupports
Pour top slab concrete5
Remove wall forms
Remove wall forms
Post-tensioninghead
Post-tensioning cable
End wall
Top slabTop slab
Computer analysis shows rebar in pontoons provides required structural capacity; expert review panel adds two new members
who will assist in the panel’s review of the design, materials, construction methods, and overall integrity of the pontoonsFloating bridge assembly continues on Lake Washington
Crews encounter spalling and end-wall cracking after a
pontoon is post-tensioned
Crews completed repairs to the first pontoon and pre-emptive
modification in remaining pontoons
WSDOT convenes an expert review panel to
address causes of spalling and end-wall cracking
Repaired pontoons are floated out of the casting basin; crews complete
pre-tow inspections
Pontoons are towed into Lake WashingtonA leak is found and then repaired between two internal cells where
ballast water was placed; Crews find additional moisture and WSDOT begins analysis of additional repair options
WSDOT reconvenes expert review panel to conduct additional analysis of pontoon design, repairs
and construction management processes
KG rejects 9 of 345 precast panels for Cycle 2 pontoons in accordance with
quality assurance process
2012 Aberdeen pontoon issues and repairs
Location of leak between cells
Expert review panel issues its report, and recommends WSDOT revise post-tensioning design
and maintain rigorous concrete thermal controlsWSDOT starts Cycle 2 construction with revised post-tensioning
design and other panel recommendations
May June July Aug Sept Oct Nov Dec
February 2013
February 2013
Pontoon joining on Lake Washington
N
Note: For illustrative purposes only. Not to scale. All joints are sealed with concrete grout.
W
W
VU
V U
Joining bolt (total of 80)
Alignment key
Recess frame
VNEVNW
VNW, VNE, VSW, VSE
VSEVSW
Alignment key
Recess frame
Post-tensioning strand (total of 28)
Joining bolt (total of 16)
Post-tensioning strandJoining bolt
Rubber gasket seal
Rubber gasket seal
Cross pontoon
Longitudinal pontoons
Supplemental pontoons
February 2013
SR 520 longitudinal pontoons design components
Lake Washington
TB C D E F G H I J K L M N O P Q R SA U V W
For illustration purposes only - not to scale
Longitudinal pontoon
Final six-lane bridge configuration on Lake Washington
Other components include:• Inserts for electrical conduit• Walkways and ladders for crew access• Maintenance access hatches
Pre-cast interior walls1
2
4
5
Post-tensioningducts
Cast in place concrete (bottom, sides and top)
Bolt beam that allowspontoons to be joinedtogether.
3aHole for bolt shaft connection between pontoons
3bPost-tensioning heads at the end wall of the pontoon
Cross pontoons
LongitudinalpontoonsSupplementalstability pontoons