pre-feasibility report for girgita limestone mine of m/s...
TRANSCRIPT
Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.)
1) Executive Summary
Project Girgita Limestone Mine Name of Company / Mine Owner M/s KJS Cements Ltd. Location
Village Amilia, Girgita and Sonwari Taluka Maihar
District Satna State Madhya pradesh
1 Mining Lease Area & Type of land 258.988 Ha. Mine lease area includes existing
mine pits, surface dumps, haulage roads,
infrastructure and undisturbed waste/barren,
agricultural land. The proposal is for
production of limestone to a tune of 1.75
MTPA.
2 Geographical co-ordinates Corner Latitude Longitude
1 24°15’12.2” 80°47’50.2”
2 24°14’19.5” 80°46’59.6”
3 24°13’55.5” 80°47’23.2”
4 24°14’47.4” 80°48’19.2”
3 Name of Rivers/ Nallahs/ Tanks/
Spring/ Lakes etc
Tamas river - 121 m E
Seranji Nallah - 1.6 km NE
Lilji Nallah - 6.3 km N
Ghusra Nallah - 3.5 km WNW
Gadha Nallah - 6.2 km NE
Pathna Nallah - 6.6 km N
4 Name of Reserve Forest(s), Wild
life Sanctuary/ National parks etc.
Ghutehi P.F. (6.02 km W)
Kaimur R.F. (5.4 km S)
Tamas River (121m E)
5 Topography of ML area Highest elevation :339 m AMSL
Lowest elevation : 328 m AMSL
6 Name of Mineral mined Limestone
7 Rate of Production (in MTPA) Proposed : 1.75 MTPA Limestone
Crusher : 1200 TPH
Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.)
8 Life of mine 20 Years
9 Mineral Reserve in Million Tonnes Proved reserves: 14.59 Mill. Tonne
(Limestone)
10 Drilling/ Blasting Yes. Controlled blasting using Delay
detonators.
11 Ultimate depth of Mining 40 m BGL (up to 292 m AMSL)
12 Ground water level 303 to 305 m AMSL (GWT will be intersected)
13 GWT intersection Yes.
14 Drainage pattern/ water courses There is no perennial surface water body
within the mine lease area. The main drainage
of the study area is through Tamas river
flowing 0.16 km east of the mine lease. The
study area is drained by a number of First and
Second order streams ultimately joining the
Tamas river.
15 Break-up of Land Utilization
Pattern
Enclosed as Annexure 2 of Form I
16 Water requirement & Source Total water requirement for dust
suppression, plantation and drinking is
197.50m3/day. Water will be sourced from
mine pits for plantation and dust suppression
and ground water for drinking.
17 Solid waste 21,00,000 cum of soil and 14,00,000 cum of
OB/Waste is proposed to be generated upto
Conceptual stage.
18 IBM approval : Date Mining plan has been prepared and submitted
to IBM for approval.
19 Public hearing : Date To be applied
20 Cost of project Rs.25.1 crores.
21 Any Other (specify) --
Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.)
2) Introduction of the Project / Background Information
(i) Identification of Project and Project Proponent
Name of the Project: Girgita Limestone Mine
Location : Girgita, Amilia and Sonwari villages, Tehsil Maihar, District
Satna, Madhya Pradesh state.
Production : Production of 1.75 MTPA of Limestone
Crusher 1200 TPH
ML Area : 258.998 Ha existing mine pits, surface dumps, haul roads,
agricultural land and Waste / Barren Land
The area under reference is situated in Village Amilia, Girgita & Sonwari of
District Satna (M.P.). The area prior to 1975 was worked under quarry lease. The
area was then granted under mining lease to The Maihar Stone & Lime Co. Ltd.
for 20 years period w.e.f. 20.09.1975 to 19.09.1995. The mining lease was
renewed for 20 years period to the lessee company w.e.f. 20.09.1995 to
19.09.2015. The lease area was transferred to M/s. Sarveshwari Minerals Pvt.
Ltd. Vide State Govt. order No. – F3-70/2002/12/2 dated 02.12.2002. The
transfer deed was executed on 19.12.2002 and registered on 22.05.2003 for rest
of the lease period i.e. 19.09.2015. The lease area has again been transferred to
M/s. KJS Cement Ltd. Vide State Govt. order No. – F3-70/2002/12/2 dated
23.10.2010 and hence transfer deed was executed as per Rule 37 of MCR 1960.
The mine is closed after transfer of mining lease. The past production details are
given in Annexure 4.
The Girgita Limestone Mine along with Adjoining Amilia Limestone Mine are
captive to KJS Cement Plant located adjacent to this mine lease area.
Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.)
Name and Address of the Project Proponent:
Shri. Pawan Kumar Ahluwalia
Managing Director
M/s KJS Cement Ltd.
Village - Amilia, P.O.- Maihar
Dist. – Satna (M.P.)
Pin - 485771,
E mail: [email protected]
Tel: 07674 – 233947
Fax: 07672 – 257590
ii) Brief Description of the Nature of the Project.
The lease area was under quarry lease of M/s Maihar Stone & Lime Co. Ltd. and
the company was granted mining lease with effect from 20.9.1975. The company
has done extensive development and mining in the lease area. The mine lease
area is partly private land, partly own land and partly Govt. land.
Opencast fully mechanised method of mining will be adopted. The OB soil and
shale limestone will be removed, drilling, loading and transport, face clearing
and removal of shale and mine debris will be done by HEMM. Drilling and
blasting will be carried out to mine the mineral. The development and
production will be done side by side. Proposed limestone from the mine will be
1.75 MTPA.
(iii) Need for the project and its importance to the country and or region
Girgita limestone mine is captive to the KJS cement plant located adjacent to the
mine lease area. All the limestone produced will be consumed in the cement
plant for cement production. Apart from this, the production of mineral will
benefit to the State in the form of Royalty. The project will generate direct and
Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.)
indirect employment opportunities to the tune of about 150 persons from the
nearby villages.
(iv) Demand Supply Gap / Use of Mineral
The limestone from the mine lease area will be used for cement production in the
Company’s cement plant located adjacent to the mine lease area. All the mineral
produced in the mine will be consumed in the cement plant.
(v) Domestic / Export Markets
The mine is captive to Company’s cement plant located adjacent to the mine.
(vii) Employment Generation (Direct and Indirect) Due to Project.
The total manpower requirement in this project is 100 persons and the indirect
employment generation from the project will be around for 50 persons.
3) Project Description
(i) Type of Project (including interlinked and interdependent project, if
any)
The mine lease along with adjoining Amilia limestone mine is captive to the KJS
cement plant of the company. The cement plant is located adjacent to the mine.
Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.)
(ii) Location (map showing general location, specific location and project
boundary & project site specific layout) with coordinates.
The mine lease area is situated in Girgita, Sonwari and Amilia villages, in Maihar
Taluka, Satna District of Madhya Pradesh. The co-ordinates of the mine lease
area are :
Pillar No. Latitude - North Longitude - East
1. 24°15’12.2” 80°47’50.2”
2. 24°14’19.5” 80°46’59.6”
3. 24°13’55.5” 80°47’23.2”
4. 24°14’47.4” 80°48’19.2”
Khasra No. / Plot No. / Block
Range /Survey No
: List of the Khasra No. is enclosed as
Annexure – 1
Lease Area (ha) : 258.998 Ha
Type of Land : Existing mine pits, Surface dumps,
Haul roads and waste/ Barren Land,
agricultural land.
The mine lease area is partly private
land, partly own land and partly Govt.
land.
(iii) Details of alternate sites considered and the basis of selecting the
proposed site, particularly the environmental considerations should be
highlighted.
This is an existing mine. Mining is a site specific project hence no alternate site is
considered.
Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.)
(iv) Size or Magnitude of operation.
The maximum rated capacity of the project will be 1.75 MTPA of Limestone and
the mine lease area is spread over 258.998 Ha. A Crusher of 1200 TPH capacity
will be installed in the northern part of the mine lease area.
(v) Project Description with Process details (a schematic diagram/ Flow
chart showing the project layout, components of the project etc. should be
given.
Mining Process
Fully mechanised Opencast method of mining will be adopted in the lease area.
Drilling and blasting will be practiced for excavation of the mineral. The OB soil
and shale limestone will be removed, drilling, loading and transport, face
clearing and removal of shale and mine debris will be done by HEMM. Hydraulic
excavators will be used for progressing benches and for handling ore/waste
material. 35 ton / 10 ton capacity dumpers will be used for transportation of the
mineral and waste. The mineral will be sent to the 1200 TPH capacity crusher
located in the mine lease area for size reduction. After crushing, the mineral will
be sent to KJS cement plant located adjacent to the mine lease area. The existing
haul roads will be extended at a gradient of 1 in 16. The OB/waste generated will
be utilised for backfilling besides Plantation will be carried out along the mine
lease boundary, on protective bund, barrier zones, along haulage and mineral
transport roads, around infrastructure area, etc.
Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.)
(vi) Availability of water, its source, Water Requirement
Activity Water requirement,
m3/d Source
Dust suppression 158
Mine pit water Green Belt 15 Workshop 20 Domestic 4.5 Ground water
Total 197.5
Energy/ power source
The mine will be fully mechanised. All the mining machinery and transport
vehicles will be diesel operated. Electrical power will be required only for site
office and lighting purposes and will be obtained from State Electricity Board.
(viii) Quantity of wastes to be generated (liquid and solid) and scheme for
their management / disposal.
Waste generation and Disposal of waste
Overburden soil and shale on the ore body and interburden is the waste material
to be handled during mining. 21,00,000 cum of soil and 14,00,000 cum of
OB/Waste is proposed to be generated upto Conceptual stage. The solid waste
will be backfilled in the mined out area and utilised for preparation of protective
bund.
Generation of waste water
Domestic waste water generated from the site office will be discharged in septic
tank / soak pit. Effluent from workshops will be treated in oil and grease trap
and will be re-circulated. No effluent is proposed to be discharged outside the
mine lease.
Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.)
4) SITE ANALYSIS
(i) Connectivity
Road : The mine lease area is situated at 2.5 km from Maihar on Maihar
Saralanagar road.
Railway Station: Maihar (3 km)
Airport: Jabalpur (160 km)
(ii) Land Form, Land use and Land Ownership
Land Form: The mine lease area includes existing mine pits, surface dumps, haul
roads, infrastructure, agricultural land and barren /waste land. The mine lease
area is partly private land, partly own land and partly Govt. Land..
Existing and proposed Land Use of the mine lease area
Sl. No.
Particulars
Land Use (in Ha.)
Present 5th year At the end
of mine life
1. Total area excavated (broken) 27.300 46.610 140.600 2. Area fully mined out (out of 1) 3.000 20.000 140.600
3. Area fully reclaimed (Backfilled out of 2)
0.500 12.000 65.600
4. Area rehabilitated out of 3 by afforestation
- - 65.600
5. Area reclaimed by water harvesting
- - 75.000
6. Total area under dumps 10.000 10.000 - 7. Area under active dumps 4.800 - - 8. Area under Road/water body 2.100 2.100 1.750
9. Area under Green belt (i.e. plantation on area other than dump and backfilled area)
1.000 3.000 18.150
10. Area under infrastructure / Bund / Drain etc
0.300 9.280 -
11. Undisturbed area 218.298 188.008 98.498 12. Total lease area 258.998 258.998 258.998
Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.)
(iii) Topography along with maps
Topography of Mine Lease Area
The mine lease area is mostly flat terrain with a large number of agricultural
fields. The relief is gentle with a maximum elevation difference of about 11 m. An
average elevation of the area is about 332 m AMSL. The minimum elevation of
the lease area is 328 m AMSL and the highest elevation is 339 m AMSL in NE and
East respectively.
Topographical Map is enclosed as Attachment
(iv) Existing Land use pattern and distances from forests, CRZ, etc.
The existing land use of the mine lease area is given in Table above. The Mine
lease area includes existing mine pits, surface dumps, haul roads, infrastructure
and waste / barren land.
Forests: Ghutehi P.F. : 6.02 km W
Kaimur R.F. : 5.4 km S
Wildlife sanctuary : None within the study area
CRZ : Not present in the study area
(v) Existing infrastructure
Roads: Maihar Saralanagar road passes through the mine lease area
Railway: Maihar (3.5 km)
(vi) Soil classification
The soil in the area is mainly sandy and calcareous in nature. At some places,
black soil is present.
Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.)
(vii) Social infrastructure Available
Existing:
Road : The Maihar Saralanager PWD road passes through the southern part of
the mine lease area..
Railway Station: Maihar (3.5 km)
Airport: Jabalpur (160 km)
Water Supply: Requirement of domestic water is fulfilled by open wells and
tube wells in the nearby villages.
All the basic facilities are available at Maihar (2.5 km) including Primary Health
Centre and schooling & Post Office, banking and rest house, etc.
5. Planning Brief
(i) Planning Concept
The mining plan has been prepared for 1.75 MTPA limestone production and is
submitted to IBM for approval.
(ii) Population Projection
The project has employed most of the workers from nearby villages. There will
not be any increase in population due to the project. However, few people from
other area may migrate in this area for business opportunities.
(iii) Land use planning (Break up along with green belt, etc.)
The proposed land use at the end of mine life is given in table above:
Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.)
(iv) Assessment of Infrastructure Demand
The following facilities will be extended to the nearby villages by the mine
management.
Proposed facilities:
Provision of green belt along the mine lease boundary
Direct Employment to required number of persons from nearby villages.
Indirect employment opportunities to about 50 persons from the nearby
villages.
Arrangements for safe and healthy working conditions
Provision of Drinking water to nearby villages through tankers in dry period.
Medical facilities and Health check-up camps for the workers
Conducting medical camps in nearby villages at regular interval.
Conducting socio-economic welfare activities in the nearby villages
6) Proposed Infrastructure
(i) Industrial Area (Processing area)
Office and stores have already been provided in the mine lease area. Specified
first Aid box have been maintained at the site office and the rest shelter as per
mines Act-1952. Additional facilities will be made as per the requirement.
(ii) Residential area (Non Processing area)
There is no residential area in the mine lease. Only Site office and rest shelter
have been provided.
Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.)
(iii) Green Belt
It is proposed to plant trees along the mine lease boundary as well as on the
backfilled area. Plantation will also be carried out on the barrier zone, around
infrastructure facilities, along the sides of haul roads, mineral transport roads
etc. The species of Babool, Sub-babool, Karanj, Amla and Mango tress will be
planted every year. Barbed wire fencing will be done to protect the plants from
animals.
(iv) Social Infrastructure
Road facility (existing roads will be maintained regularly)
Employment opportunity
Medical camps
Social awareness camps,
Donations to schools
Secondary employment opportunities
Formation of self help groups for the women in nearby villages
(v) Connectivity
The area is well connected to Maihar by road.
(vi) Drinking Water Management (Source and supply of Water)
Ground water will be used for drinking.
(vii) Sewerage System
The domestic effluent from the site office and rest shelter will be discharged in
septic tank and soak pit system.
Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.)
(viii) Industrial Waste Management
There will not be any industrial waste generation. The only waste generated
from the mine will be overburden.
(ix) Solid Waste Management
Solid waste generated from the mine will be initially dumped in surface dumps
within the mine lease area. Backfilling will be started once the mined out area is
available. Plantation will be carried out on the backfilled area.
(x) Power requirement & Supply / Source.
The mine will be fully mechanised. All the mining and transportation equipments
will be diesel operated. Electrical power is required only for site office and
lighting and the electrical power is obtained from State Electricity Board.
7) Rehabilitation and Resettlement (R & R) Plan
The mine was in operation during past and there was no disturbance to human
settlement due to the mining activities. No Rehabilitation and resettlement of
population is proposed as there is no human settlement within ML area.. The
private land owners will be paid as per the applicable State Govt. Norms/
present market rates, whichever is greater. The land owners will also be offered
job in the mine as per their eligibility or the mine management will help him/her
to start his own business for the livelihood.
Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.)
8) Project Schedule and Cost Estimates The Mining plan is prepared for five years and the mine life is 20 years. Sr. no. Description Cost in Rs.
1 Land cost expenditure 200 millions
2 Cost of infrastructure, Equipment, vehicles,
Manpower, machineries, etc.
50 millions
3 Environmental protection (check dams etc) 0.50 millions
4 Socio-economic development 0,50 millions
TOTAL 251 millions
9. Analysis of Proposed (Final Recommendations)
The proposed production will bring economical benefits to the state by the way
of increase in Royalty for mineral and to the local people by way of additional
direct and secondary employment opportunities. The mine management will
also help the nearby villages by conducting various socio-economic welfare
activities on regular basis, especially keeping in view the tribal and economically
backward population in the area. Thus the project will bring about socio-
economic improvement of the area and will prove beneficial to the area.