pre- feasibility reportenvironmentclearance.nic.in/writereaddata/online/tor/0_0_10_jan_2… ·...
TRANSCRIPT
PRE- FEASIBILITY
REPORT
1
1.0 EXECUTIVE SUMMARY
1.1 Executive Summary
The proposed mining project falls under Category “A” Project or activity
1(a) as per EIA Notifications 2006 and amended thereof due to the
presence of Mukundra Hills Tiger Reserve within 5km.
1.2 Salient features of the project
Project Name Lambakhoh Sand Stone Mining project (M. L.
No. 40/09)
Name of applicant M/s New Mateshwari Stone Suppliers
Location of mine Village - Lambakhoh, Tehsil - Bundi, District - Bundi,
State - Rajasthan
Location
Latitude : 25° 3'5.50"N to 25° 3'6.47"N
Longitude : 75°29'3.05"E to 75°28'54.05"E
Topo sheet number 45 O/8
Area 1.3187 ha
Minerals of mine Sandstone
Total Mineable reserves 41224 Tonnes
Life of mine 5 years
Proposed production of mine
14705.5 TPA
Total Cost of Project 35 Lakh
Method of mining Opencast Mechanized
No of working days 300 days
Water demand Total water requirement is about 3 KLD = 1 KLD (Drinking & Domestic Uses) + 1 KLD
(Plantation) KLD + 1 KLD (Dust Suppression).
Sources of water Drinking water will be brought from the
nearby Tube-wells and water for dust suppression and plantation will be collected from nearby villages. At the monsoon time,
rain water accumulated on the pit will be used for same purposed.
Man power 20
Nearest railway station Dakaniya Talaav Railway Station (about 31 km in E direction)
Nearest State highway/national highway
N.H. 76 about 2 km away in S direction
Nearest airport Kota - Airport (about 30 km in NE direction)
Seismic zone Zone II
2
2.0 INTRODUCTION OF THE PROJECT/BACKGROUND INFORMATION
2.1 Identification of Project and Project Proponent
Lambakhoh Sand Stone Mining project (M. L. No. 40/09) is situated at
Village - Lambakhoh, Tehsil- Bundi, District- Bundi, and State- Rajasthan
over an area of 1.3187ha. The mining lease for an area 1.3187 hect. was
granted in favour of M/s New Mateshwari Stone Suppliers C/o Shri Ramesh
Chandra Dhakar R/o- Lambakhoh Vaya- Dabi, Dist.- Bundi (Raj) vide order
no. 1183 on dated 19/07/2010 and lease deed was registered on dated
19/10/2010 for 20 years. Mining Plan has been approved by department of
mines Kota vide order No. SME/Kota/CC-I/MP13/1847 dated 13-08-2013.
2.2 Brief Information about the Project
The project has been proposed for mining of Mineral Sandstone by adopting
opencast mechanized mining method.
2.3 Need for the Project and Its Importance to the Country or Region
Today in India Sandstone is used widely in domestic construction sector,
monuments construction markets, hospitality industry, export market and
handicraft and antiques. The material is starting to be more well-known and
popular because of technological advancements, sophisticated quarrying
techniques, and decreased cost of mining and growth in usage as material in
the decoration sector. Sandstone as material is showing beauty and long-
lasting value and therefore people have started to use it more and more in
memorials and in other funerary items. Today Sandstone is popular material
in laying floors and cladding walls in airports, hotels and other public and
commercial centers.
2.4 Demands-Supply Gap
The demand for Sandstone is ever growing with the growth of the
infrastructure sector in our country. The mineral is used in the
construction activities like buildings, structures. The requirement for the
3
mineral is always high in the nearby cities and towns. Therefore there is
always a good demand of the mineral in the domestic market.
2.5 Imports vs. Indigenous Production
Development needs will be met only through indigenous produced
Sandstone material against the high cost of imported material.
2.6 Export Possibility
There is no proposal to export the Sandstone. However, Sandstone produced
from the mine will fulfill the needs of the region and surplus if any, will be
considered for export.
2.7 Domestic/ Export Markets
Domestic Market
The mineral is used in Tiles flooring, column making, graveyard, pre
fabrication unit, statue making and in small usages like monument of table
top, name plate, vases, candle holder etc.
Export Market
The proposed mining activity is for indigenous consumption only for real
state, decorative accessories etc.
2.8 Employment Generation
The proposed mining activity will provide employment to about 20 workers.
The workers will be hired mostly from the nearby villages.
3.0 PROJECT DESCRIPTION
3.1 Type of Project Including Interlinked and Interdependent
Projects, If Any.
The mine is over an area of 1.3187Hectares. The proposed production is
14705.5 TPA. This is an independent mining project and there are no
interlinked projects involved.
4
The project falls under Category “A” Project or activity 1(a) as per EIA
Notifications 6996, 2009, 2011 and 2013
Location: The mining lease area is located at khasra 486, 487, 488, 489
Village - Lambakhoh, Tehsil -Bundi, District - Bundi, and State- Rajasthan
The mining lease area falls in toposheet number 45O/8.
Latitude : 25° 3'5.50"N to 25° 3'6.47"N
Longitude : 75°29'3.05"E to 75°28'54.05"E
5
Fig 1: Location Map of proposed Project site
Project Area
Project Area
6
3.3 Details of Alternate Sites
Mining is site specific so no alternative site is proposed.
3.4.1 Size or magnitude of operation
The mining lease has been granted over an area of 1.3187hect. During five
year total production of sandstone shall be approximately 42150.5 Tonnes.
The average number of working days in the year would be 300.
3.5 Geology
3.5.1 Regional geology
Geologically the district consists of diverse rock types belonging to oldest
arche and me tamarphics of bhilwara super- group and middle to upper
proterozoic sedimentaries of vindhyam supergroup. NE-SW part of the
district is exposed by the rock types belonging to bhilwara super group and
in remaining part, rock types of vindhyam super group exist. Modified and
generalised lithographic sequence after G.S.I. (2000) is given below-
Lithostratigraphic sequence of Bundi District :
Supergroup Group Formation/Lithology
Recent to subrecent – Soil/ Alluvium
Bhander Dholpuer (Upper
Bhander) shale. Balwan(Upper Bhander)
limestone Maihar(Upper Bhander ) Sandstone
VINDHYAM
SUPERGROUP
Sirbu shale with siltsone. Sandstone, grit and
stromatolitic limestone
Lower Bhander (Bundi hill)
Sandstone with lower shale, middle sandstone, Upper shale,
Upper sandstone Samaria shale
Lower Bhander (Lakheri) Limestone Ganurgarh shale
Rewa Govindgarh (Upper Rewa) Sandstone
Jhiri shale
Indergarh (Lower Rewa)
Sandstone Panna shale
Kaimur Akoda Mahadev (kaimur)
7
sandstone
Badanpur conglomerate
Granite and Dolerite
Bhilwara super group
Bhadesar shale, slate
Hindoli group phylite/Quartzite/Dolomitic limestone
The rocks of Hindoli group of Bhilwara Supergroup has occuried NE-NW
part of the district and extends from village Hindoli and khinya in the west
to the village Dabi in east. Insrusives like granite & dolerites are exposed
near village Basni, Deva ka khera & Odhnda of Hindoli tehsill of Bundi
district. General trend of rocks is N 400 E with 600 NW dip.
Lakheri Limestone of Bhander group occurs in between greenish grey
sacaria shale above and reddish brown Ganurgarh shale below and marked
by intraformational conglomertate & breccia at the base and extends
intermittently for about 80 kms. In 1-2 kms. Wide belt upto Indergarh.
Samaria shale is overlain by Bundi hill sandstone. Bundi hill sandstone
onatitute the Bundi hill and mostly in the southern part of district. The
Sirbu shale is conformably underlain by the Bundi hill sandstone and
overlain by Maiher sandstone ocurring in eastern, southern and western
part of the district. The limestone of Sirbu shale is generally confined in
lower & middle part of the birbru shale.
3.5.2 Local Geology:
The local geological succession for the area may be summarized as below:-
Recent Group Formation Lithology
Vindhyan Supergroup
Bhander Group
Lower Bhander Sand stone
formation
Upper sandstone
upper shale
Middle sandstone
Lower shale
Lower sandstone
3.6 Reserve Estimation
The following Parameters have been considered while estimating the
geological reserves (in situ):
1. Average 3m cover has been considered as soil and 3m cover has been
considered as Toll. Recovery of Toll 1% to 10% (Cobbles/small pieces of sand
stone) now we are considering as 5% recovery of fractured sand stone for the
next five year planning
8
2. Average 2m cover has been considered as salable sandstone in proved
category. Recovery of saleable Sandstone 30% to 70%,
Project Description with Process Details
3.6.1 Method of Mining
The Sand Stone mine shall be developed by Mechanized opencast Mining.
The mineral is lying on the sub surface therefore open cast mining has been
the obvious choice.
For splitable sandstone Benches.
Overburden shall be removed on contractual basis. Machineries for the
overburden removal shall be on contract basis as when required. Required
more machine shall be taken on rent basis to achieve the production.
The following mining parameters are proposed
Type of working : Opencast, Mechanized Mining
Bench height : 1-6m
Bench width : 1-6m
Small blasting with low charge of holes just to loosen the rocks is proposed
in upper layers to remove the hard overburden. The Blasting shall be done
by the authorized contractors on contractual Basis. These contractors have
their own safety explosive container as well as Explosive License.
Type of Explosive
Special Gellatin, Ordinary Plain Detonator, Safety Fuse
1 • Site prepration (demarcation by pillars)
2 • Excavation of mineral
3 • Loading of Mineral
4 • Transportation
Length of Shot Holes : 1.6 m
Diameter of Shot Holes : 32 mm
Spacing : 1 m
Burden : 0.8 m
Stemming : 30%
9
The details of machinery, to be used
S. no.
Type Nos. Bucket Capacity in Cu. M.
Make Motive Power
H.P.
1. Dumper 6 10 tonner Tata Diesel 119HP
2. Diesel Pump 1 Local Diesel --
3. Compressor 2 75 CFM Local Diesel --
4. Jack
Hammer 4 32mm Local --- --
5. Excavator 2 1 m3 Local Diesel --
Production details
The Proposed Production of Sandstone in next five year:
Year Total salable sand stone MT
First Year 3633
Second Year 6102
Fifth years 6606
Fourth Year 11104
Fifth Year 14705.5
Total 42150.5
3.7 Raw Material Required Along With Estimated Quantity, Likely
Source, Marketing
Area of Final Product/s, Mode of Transport of Raw Material and
Finished Product
No raw material will be required for production of sandstone. The
sandstone blocks and Laffers / Khanda are transported to Kota and other
places from mine in trucks dispatched to the Gang saw Unit & cutter for
processing.
The overburden is transported from mine in tippers and dumpers.
3.8 Resource Optimization/ Recycling and Reuse
Not envisaged.
3.9 Availability of Water Its Source, Energy/ Power Requirement and
Source
3.8.1 Water Requirement
Water for domestic, dust suppression and plantation is required to be 3
KLD.
3.8.2 Power
The operation will be done only from sun rise to sun set hence there is no
10
power requirement for the project at site. The electricity line passes out
side near the M.L area. The electricity facility is not available at mining
lease area. Only diesel equipment will be used.
3.10 Quantity of wastes to be generated (Liquid and Solid) and Scheme
for their
Management/Disposal
3.10.1 Solid Waste Generation& its Disposal
The waste as overburden in the area is top soil and Hard Sandstone. The
soil cover in the area varies from 3 m and fractured sandstone layer varies
in thickness upto 10 meters. The rock fragments of small size are also
resulted after mining.
Proposed Waste to be generation
S. No Year I II III IV V Total
1 Mineral Waste (MT)
3762 5492 18723 24013.5 31075 83065.5
2 Over burden (MT)
2492 ---- 41601.5 67945.5 89940 201979
3 Total Waste (1+2)
MT
6254 5492 60324.5 91959 121015 285044.5
4 In m3 2316 2034 22342 34059 44820 105572
5 Swell Volume (m3)
2780 2441 26811 40871 53784 126686
3.10.2 Liquid Effluent
Not applicable.
4.0 SITE ANALYSIS
4.1 Connectivity
The applied lease area is approachable thorough NH 76 which 2 km in
the S direction from the lease area. Nearest Railway Station is Dakaniya
Talaav Railway Station (about 31 Km in NE direction) & Kota - Airport
(about 30 Km in NE direction)
11
4.2 Landform, Land use and Land ownership
4.2.1Landform
There is no forestland in and around this M.L. The lease area is a having
Pvt. Waste Land
4.2.2 Land use
The lease area is a Pvt. Waste Land. There is no village or human
settlement in the lease area. In the total lease area is a virgin land.
4.2.3 Land Ownership
The proposed lease area is Pvt. Waste Land.
4.3Topography
The area falls in G.T. sheet No. 45 O/8. opographically the area comprises
flat land
4.4 Existing land Use Pattern
The lease area is having fractured cover of 12m. 100% of the total area is
covered by fractured.
The lease area is having Pvt. Waste Land. There is no village or human
settlement in the lease area. In the total lease area is a virgin land.
4.5 Existing Infrastructure
No existing infrastructure within lease area.
4.6 Soil Classification
No Top soil Proposed.
4.7 Climate data from Secondary Sources:
The climate of the area is dry with extreme temperature variation i. e. in
summer as high as 440 C, whereas in winter it lowers to 60C or even less.
Most of the rain falls during the period of July to September. Maximum and
minimum rain fall varies (500mm- 200mm).
4.8 Social Infrastructure available:
Police station The nearest is at Dabi.
Post Office The nearest Post & Telegraph Office is at Dabi.
Medical Facilities Nearest Dispensary is at village Dabi.
12
Education Facility up to primary school facility is available at Lambakhoh
Village and Senior Secondary school facility at Dabi.
Availability of water The Ground water table is 40m (in rainy season) to 45m
(in Dry Season). The drinking water can be brought from the wells at a
distance of 500m.
Electricity - The Electric Line passes out side to the M.L. area. The electric
facility is not available at mining site Area.
5.0 PLANNING BRIEF
5.1 Planning Concept
The proposed project is for the mining of sand stone. Mining is proposed to
be done through mechanized method. Rajasthan Minor Mineral Rules &
MCDR will be followed in the mining. Mining will be done in benches and
will not intersect the ground water table.
5.2 Land use Planning
Details of land use are given below:
*All the areas are given in Hectares
Forest Land
Grazing Land
Govt. waste
Land
Pvt. Waste
Land
Total
1 Pits & Quarries ---- ---- ---- 0.5277 0.5277
2 Top soil Dump ---- ---- ---- ---- ----
3 Dumps ---- ---- ---- ---- ----
4 Stack Yard ---- ---- ---- ---- ----
5 Sub Grade stack Yard ---- ---- ---- ---- ----
6 Infrastructure ( Work
shop, administrative Building)
---- ---- ---- ---- ----
7 Roads ---- ---- ---- 0.0313 0.0313
8 Railway ---- ---- ---- ---- ----
9 Green Belt ---- ---- ---- ---- ----
10 Tailing Pond ---- ---- ---- ---- ----
11 Effluent Treatment
Plant
---- ---- ---- ---- ----
12 Mineral Separation Plant
---- ---- ---- ---- ----
13 Township ---- ---- ---- ---- ----
14 Non Utilized ---- ---- ---- 0.7597 0.7597
Total ---- ---- 1.3187 1.3187
13
Proposed Land use pattern during next five years
*All the areas are given
in Hectares
Forest Land
Pvt. Ag.
Land
Govt. waste Land
Pvt. Waste Land
Total
1 Pits & Quarries ---- ---- ---- 0.8621 0.8621
2 Top soil Dump ---- ---- ---- ---- ----
3 Dumps ---- ---- ---- 0.3585 0.3585
4 Mineral Stack Yard ---- ---- ---- 0.0009 0.0009
5 Sub Grade stack
Yard ---- ---- ---- 0.0041 0.0041
6 Infrastructure (Work shop,
administrative Building)
---- ---- ---- 0.0039 0.0039
7 Roads ---- ---- ---- ---- ----
8 Railway ---- ---- ---- ---- ----
9 Green Belt ---- ---- ---- 0.0067 0.0067
10 Tailing Pond ---- ---- ---- ---- ----
11 Effluent Treatment Plant
---- ---- ---- ---- ----
12 Mineral Separation Plant
---- ---- ---- ---- ----
13 Township ---- ---- ---- ---- ----
14 Non Utilized ---- ---- ---- 0.0825 0.0825
Total ---- ----- 1.3187 1.3187
5.3 Assessment of Infrastructure demand (Physical & Social)
On the basis of the preliminary site visit, the infrastructure demand in the
village was assessed on the basis of need and priority.
The health infrastructure of the study area requires improvement. The lack
of medical facilities needs improvement. Medical facilities will be provided by
mine owner during mining.
5.4 Amenities/Facilities
Workshop
For maintenance of machinery it is proposed to establish a workshop nearby
to mine site for Welding, puncture etc.
Power supply
Village is electrified. The electric power facility is not available up to the
mine site presently.
First Aid
A first aid facility is proposed at Mines office.
14
Rest Shelter
Temporary rest shelter has been provided near mining lease site.
Latrines and Urinals
At the mining lease site urinal and latrine are proposed.
5.4.1Budget for facilities provided to Labours
Sl. No.
Scheme Capital Cost
(in Rs)
Annual Recurring
Cost (in Rs)
1 Drinking water facility 10,000
2 Shelter 20,000
3 Health facility 10,000
5 sanitation facility 20,000
Total 40,000 20,000
6.1Industrial Area (Processing Area)
No infrastructure is proposed.
6.2 Residential Area (Non Processing Area)
As local workers from nearby areas will be engaged for the mining
activity, no residential area/ housing are proposed.
6.3 Green Belt
A total 33% of the total lease area will be used for plantation.
Programme for Plantation
The plantation shall be done at the following places:-
At the boundary of the Lease.
Both site of the transportation road
6.4 Social Infrastructure
The Applicant shall spend 2% of profit for the development of the area
i.e. treatment of poor, schools, temples and other social work.
6.4.1. Budget for Environmental Social Responsibility (ESR)
SI. No. Activity ESR in Rs.
1 Provide drinking water facility in surrounding
villages and schools by hand pump/dug well/water tank or funds for Ambulance
30,000/-
15
3 Clothes distribution to poor villagers 20,000/-
TOTAL 50,000/-
6.5 Sewerage System
Domestic waste water will be treated into septic tank followed by soak pit
6.6 Industrial Waste Management
Not applicable
6.8 Environmental Management Plan
The environmental management plan consists of the set of mitigation,
management, monitoring and institutional measures to be taken during
the implementation and operation of the project, to eliminate adverse
environmental impacts or reduce them to acceptable levels. The present
environmental management plan addresses the components of
environment, which are likely to be affected by the different operations
in the mine area.
Budget Allotted for the EMP
Sr.
No.
Measures Recurring
cost (in Rs.)
1 Pollution Control i) Dust Suppression
ii) Garland drain & ground dump
20,000/-
20,000/-
2 Pollution Monitoring
i) Air pollution ii) Water pollution
10, 000/- 10,000/-
3 Green Belt 10, 000/-
4 Reclamation of mined out area 10, 000/-
Total 80,000/-
7.0 REHABILITATION AND RESETTLEMENT (R&R) PLAN
As no personnel are expected to be migrated due to mining in the lease
area and the adjoining region is also having a good mineral potential, the
rehabilitation of the employees is not going to be a problem. The workers
and other staff can get job in the neighboring areas after the end of life of
mine. The applicant shall also try for employment of the workers.
16
8.0 PROJECT SCHEDULE & COST ESTIMATES
8.1 Likely Date of Start of Construction and Likely Date of Completion
No construction activities are proposed. The mining activity will
commence only after receiving environmental clearance and other
statutory clearance.
8.2 Estimated Project Cost along with analysis in Terms of Economic
Viability of the
Project
Estimated project cost is Rs. 30 lakh.The lessee has all the mining
equipments used for the scientific mining. The mine is Eco-Friendly.
Economically the ore is mineable as compared to overburden thickness.
The entire mineable reserve as estimated is categorized as 121.
9.0 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)
The proposed mine will bring economical benefits to the state by the way
of Royalty for mineral and to the local people by way of direct and
secondary employment opportunities. sandstone is used for a variety of
structural and decorative purposes. The material is in high demand at
the local market for real estate industry.
The project will bring about socio-economic improvement of the area and
will prove beneficial to the area.
****************
17