    PARBATI H.E. PROJECTS

    NHPC Limited( A Govt. of India Enterprise)

    Dam of Parbati-III

    3rd Regional Customer Meet forEsteemed Beneficiaries

    Welcomes

    Delegates ofDam of Parbati-II

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    2/32

    Projects under construction by NHPCin Kullu valley

    PARBATI H. E. PROJECT STAGE-II ( 800 MW )

    PARBATI H. E. PROJECT STAGE-III ( 520 MW )

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    3/32

    PARBATI H. E. PROJECT STAGE-III ( 520 MW )

    VIEW OF DAM AREA

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    4/32

    SCHEMATIC DIAGRAM OF PROJECT

    Lot-1 (M/s Patel-L&T Consortium) Lot-2 (M/s Jagger-Gammon JV)

    De-silting ChambersIntake Tunnels

    HRT

    SFT

    Intake

    Diversion Tunnels

    TRT

    TRT Outlet

    PowerHouse

    D/s SurgeChamber

    GIS cumTransformer

    Spillway

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    5/32

    SALIENT FEATURES

    DIVERSION TUNNEL - 2 Nos. 6.75 m Dia

    - 391 m & 440 m Length

    DAM - Rock fill 43m High 218 m LongSPILLWAY - Orifice Type 2Nos. 7.2m Wide

    with 2 Radial Gates of 7.2m X14m

    DESILTING CHAMBERS - 2 Nos. 12.2m X 22.5m X 250m

    HEAD RACE TUNNEL- 7.25m Dia. 7869m Long

    SURGE SHAFT - Restricted Orifice Type 13m

    Dia 147m High

    VERTICAL PRESSURE SHAFT - 2 Nos. Steel Lined 4.5m Dia 310m

    POWERHOUSE - Underground Machine Hall of Size 123mX22mX43.6m

    TAILRACE TUNNEL - 8.1m Size, 2713m Long

    COMPLETION SCHEDULE - July.2012

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    6/32

    SALIENT FEATURES

    ANNUAL ENERGY GENERATION 1963 MU

    Unit Tariff(Current CERC notification and prevailinginterest rate)

    Rs. 2.97

    CCEA CLEARED PROJECT COST

    (AT MAY 2005 PRICE LEVEL) 2304.55 Cr.

    CUMMULATIVE EXPENDITURE

    (Up to Aug 2011- Provisional)

    1539.02

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    7/32

    M.O.U (Govt. of HP & NHPC) : 20 Nov.1998

    Techno-Economic Clearance by CEA : 12 Nov. 2003

    Environment Clearance by MOEF, : 16 Apr. 2005

    Forest Clearances by MOEF : 13 Jun 2005

    CCEA Clearance (Govt. of India) : 09 Nov.2005

    Environment Clearance by SCST&E,

    Shimla (Govt. of H.P) : 26 Dec.2005

    Consent by HP SPCB : 20 Jan. 2006

    CHRONOLOGY OF CLEARANCE

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    8/32

    MAJOR HIGHLIGHTS

    1. DT cum Spillway Tunnels including Lining

    2. DT Intake Structure including HM gates

    3. Cut-off wall

    4. Overt lining of both Branch tunnels

    5. Excavation of HRT From Face-1,2,3 & 4

    6. Concreting of Power Intake structure7. Intake Structure area concrete

    8. Spillway Control Structure Concrete

    WORKS COMPLETED (DAM)

    WORKS COMPLETED (POWER HOUSE)

    1. All Major Excavation Works.2. Barrel Concrete of Unit-1 & 2.

    3. Control Block Concrete

    4. TRT U/s Overt Concrete

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    9/32

    MAJOR HIGHLIGHTS

    1. Plunge Pool Excavation

    2. HRT Concrete Lining

    WORKS UNDER PROGRESS (DAM)

    WORKS UNDER PROGRESS (POWER HOUSE)

    1. HRT Concrete Lining

    2. Surge Shaft Concrete Lining3. Pressure Shafts Concrete Lining

    4. Transformer Cavern Concreting

    5. Power House Unit-3 & 4 Concreting

    6. Surge Chamber & Draft Tube Concreting

    7. TRT D/s Concrete Lining

    WORKS UNDER PROGRESS (E&M)

    1. Assembling of Unit-1

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    10/32

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    11/32

    Damages due to recent Cloud Burst near Adit-2

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    12/32

    Damages due to recent unexpected rainfall

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    13/32

    PARBATI H.E. PROJECT, STAGE - II

    (4x200MW)

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    14/32

    LAYOUT PLAN PARBATI H.E. PROJECTSTAGE-II (800 MW)

    Intake structure

    Diversion

    Tun

    nel

    Pa

    rbatiRiver

    Head Race Tunnel

    Adit 1

    Pancha Nallah Trench Weir

    Feeder Tunnel

    Power House

    Adit 2 Adit 3

    Adit 4Adit 5

    Jiwa NallahSainj River

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    15/32

    PARBATI H.E. PROJECT, STAGE-II (800MW)

    The Parbati Hydroelectric project Stage-II is a run off the river and inter-basin transfer scheme and is spread over four valleys namely Manikaran

    valley, Garsa Valley, Sainj Valley and Jiwa Valley in Kullu district ofHimachal Pradesh.

    Date of Signing of MOU/PIA: Project taken over from

    HPSEB on 20.11.1998

    DPR of Parbati Stage-II cleared Oct-2000

    TEC accorded Jan-2001

    Environmental Clearance June-2001

    RR Plan Approved Feb-2002

    Date of Signing of ImplementationAgreement (IA) Sept-2002 (as perCCEA)

    Schedule Commissioning as per IA Sept-2009 (as per CCEA)

    Date of start of construction date Sept-2002

    Proposed Commissioning Date Aug-2014

    Chronology of Events

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    16/32

    SALIENT FEATURES

    DAM83.7m high Concrete Gravity across river

    Parbati

    SPILLWAY 3 Nos. Orifice type, 6m x 9m Radial Gates

    DIVERSION TUNNEL 7.5 Dia., 275m long

    DESILTING CHAMBERS 3 Nos., 15m X 16m X 170m

    HEAD RACE TUNNEL6m Dia., 31.5 km long (22.5 km by DBM &

    9.05 km by TBM)

    SURGE SHAFT 17m Dia., 130m depth

    PRESSURE SHAFT2 Nos., 3.5m Dia Steel lined 2150m &

    2133m length (1546m Inclined)

    POWERHOUSE Surface, Size 123m x 47m x 44m

    UNITS 4 Nos. of 200 MW each, Pelton Turbine

    RATED HEAD 789m (Gross Head 867m)

    ANNUAL ENERGY GENR. 3108 MU

    ESTIMATED COST Rs. 3919.59 Crs.

    TARIFF Rs. 3.54 per KWH

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    17/32

    PARBATI H.E. PROJECT STAGE-II (800MW)

    UNIQUE HIGHLIGHTS

    1. Two inclined pressure shafts of 1546M length each at an

    inclination of 300 successfully bored for the first time in the

    world by using Tunnel Boring Machine and completed in record

    time of 16 months.

    2. Concreting & Grouting in the inclined pressure shafts, behind the

    steel liners had been done up to a height of 800 meter by using

    Schwing pump for the first time in World.

    3. Total length of Head Race Tunnel is 31.52 km which is the longest

    hydro tunnel in Indiabeing constructed.

    4. In the Dam area, the weak zone of the hill (Fossil Valley) grouted

    successfully up to a depth of 120 m in two stages with ultra fine

    cement of high Blaine value imported from Japan, for the first

    time in India.

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    18/32

    PARBATI H.E. PROJECT STAGE-II (800MW)

    STATUS OF WORKS

    ITEMS UNIT TOTAL COMPLETED

    Dam & Intake

    Concreting

    cum 1.96Lakhs 1.78Lakhs

    (90.8%)

    HRT Excavation km 31.525 26.61 (84%)

    HRT Lining km 31.525 15.586 (49.4%)

    Surge Shaft

    Excavation

    m 130 Completed (100%)

    Surge Shaft Lining m 130 50.9 (39.15%)

    Pressure Shaft

    Excavation

    m 2 x 1546 Completed

    (100%)

    Pressure Shaft

    Steel Lining and

    Concreting

    m 2 x 1545 Completed

    (100%)

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    19/32

    PARBATI H.E. PROJECT STAGE-II (800MW)

    STATUS OF WORKS

    ITEMS UNIT TOTAL EXECUTED

    Power House Sub-

    Structure Concreting

    cum 28416 28416 (100%)

    Power House Super-Structure Concreting

    cum 25000 3398 (13.6%)

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    20/32

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    21/32

    PARBATI H.E. PROJECT STAGE-II (800MW)

    DAM CONCRETING

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    22/32

    INTAKE STRUCTURE CONCRETING

    PARBATI H.E. PROJECT STAGE-II (800MW)

    PARBATI H E PROJECT STAGE II (800MW)

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    23/32

    CONCRETING IN DESILTING CHAMBER

    PARBATI H.E. PROJECT STAGE-II (800MW)

    PARBATI H E PROJECT STAGE II (800MW)

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    24/32

    Status of Head Race Tunnel (Excavation)

    (Drawing not to scale)

    Inlet Adit

    F-3F-2F-1F-0 F-8 F-11

    Total 31.525 Km

    6251m 13099m 2038m 7375m 2434m

    F-4 F-6 F-7 F-9 F-10

    Adit-II Adit-III

    Adit-IV Adit-V

    215m

    LEGEND

    COMPLETED 26610m

    BALANCE 4915 m

    PARBATI H.E. PROJECT STAGE-II (800MW)

    Adit-I

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    25/32

    PARBATI H.E. PROJECT STAGE-II (800MW)

    POWER HOUSE CONCRETING WORK

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    26/32

    PARBATI H.E. PROJECT STAGE-II (800MW)

    POWER HOUSE CONCRETING WORK

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    27/32

    Inclined Pressure Shaft (Right)

    Total Length- 1545 m

    Excavation Completed- 1545 m (100 %)

    Lining Completed (100%).

    INCLINED PRESSURE SHAFTS

    Inclined Pressure Shaft

    2 Nos., Steel Lined 3.5m Dia.

    Each bifurcating into two Nos. 3m Dia.Penstocks near Power House

    Inclined Pressure Shaft (Left)

    Total Length- 1545 m

    Excavation Completed- 1545 m (100 %)

    Lining Completed -1545 m (100%)

    300 300

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    28/32

    PARBATI H.E. PROJECT STAGE-II (800MW)

    Problems Encountered During Execution of Project

    A. Head Race Tunnel :

    Severe Rock Bursting due to high superincumbent cover

    (upto 1.6 km)

    Heavy sudden ingress of water of the order of 8000 lpm

    with 7000 cum discharge of silt encountered in the tunnel

    which had buried and damaged the TBM.

    TBM refurbished and the fault zone treatment being taken

    up in consultation with international experts.

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    29/32

    PARBATI H.E. PROJECT STAGE-II (800MW)

    Submergence of TBM due to sudden heavy ingress of water

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    30/32

    PARBATI H.E. PROJECT STAGE-II (800MW)

    Submergence of TBM due to sudden heavy ingress of water

  • 8/4/2019 Presentation 2011 Sept PHEP3 Modified

    31/32

    PARBATI H.E. PROJECT STAGE-II (800MW)

    Problems Encountered During Execution of Project

    B. Powerhouse :

    Occurrence of three major slides of Power House Back slope during

    Apr04, Jun06 and Feb07.

    C. Dam :

    Ban on Aggregates:

    Hon'ble High Court H.P had imposed ban on 03.08.07 onprocurement of aggregate from any mining source in Distt. Kullu

    for all mega projects, which was lifted in March 2008. The work of

    Dam and other concreting was stopped during this period of 7

    months.