Procurement Plan-Goods
Country/Organisation: NIGERIA / LAGOS METROPOLITAN DEVELOPMENT AND GOVERNANCE PROJECT
Project/Programme: LMDGP
Loan #: 4219
Description*PackageNumber
LotNumber
Estimated Amount in US $
Procurement Method
Pre-or Post Qualification
Prior or Post Review
Plan vs.
Actual
Prep & Submission
by Ex Agency
No-objectionDate
If Prequalification Plan 4 - 7 wks 1 - 1.5 wks
add 7-13 wks Actual
List of Contracts
LMDGP/ICB/G08/01 Lot 1 1,000,000.00 ICB Post Prior Plan 24-Mar-08 7-Apr-08
Actual
LMDGP/ICB/G08/02 Lot 1 1,000,000.00 ICB Post Prior Plan 28-Feb-08 13-Mar-08
Actual
LMDGP/ICB/G08/03 Lot 1 3,000,000.00 ICB Post Prior Plan 30-May-08 13-Jun-08
Actual
LMDGP/ICB/G08/04 Lot 1 600,000.00 ICB Post Prior Plan 19-Feb-08 4-Mar-08
Actual
LMDGP/NCB/G08/01 Lot 1 60,000.00 NCB Post Post Plan 12-Mar-08 NA
Actual
LMDGP/NCB/G08/02 Lot 1 150,000.00 NCB Post Post Plan 16-Apr-08 NA
Actual
LMDGP/NCB/G08/03 Lot 1 150,000.00 NCB Post Post Plan 16-Apr-08 NA
Actual
LMDGP/NCB/G08/04 Lot 1 200,000.00 NCB Post Post Plan 12-Mar-08 NA
Actual
LMDGP/NCB/G08/05 Lot 1 150,000.00 NCB Post Post Plan 8-Oct-08 NA
Actual
LMDGP/NCB/G08/06 Lot 1 300,000.00 NCB Post Post Plan 8-Oct-08 NA
Actual
LMDGP/NCB/G08/07 Lot 1 100,000.00 NCB Post Post Plan 30-Jul-08 NA
Furniture for Primary Health Centres
Supply and Installation of 14 Electric Transformers for slum communities
Heavy Duty Plants and Equipment (Excavators, Dredgers etc) for ODS and LAWMA
Procurement of Satellite Imagery for Lagos (Balance of 52% coverage)
Survey Equipment (Measuring wheel, Total Station etc) Hand GPS
Office Funiture for PCU office and CEAs
Office Equipment for PCU office and CEAs
Equipment for Primary Health Centres
BASIC DATA
Draft Bid Documents, including specs and quantities, draft SPN
Norm Duration of Proc Steps
Furniture for Rehabilitated & New Schools/ Constructed schools
Project vehicles - 1 No. 4 x 4 Vehicle Jeep,1No. OBS Vehicle,2Nos Saloon Cars and 9 Nos. Utility Pick-ups for PUs
42439.xls 1 of 44 2/11/2008 1:40 PM
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Procurement Plan-Goods
Actual
LMDGP/NCB/G08/08 Lot 1 400,000.00 NCB Post Post Plan 30-Aug-08 NA
Actual
Software (Arc GIS/ SPSS data Mining)
Refurbishment of LAWMA Plants
42439.xls 2 of 44 2/11/2008 1:40 PM
Procurement Plan-Goods
LMDGP/SH/G07/002 Lot 1 50,000.00 Shopping Post Post Plan 12-Mar-07 NA
Actual
LMDGP/SH/G07/001B Lot 1 50,000.00 Shopping Post Post Plan 12-Mar-07 NA
Actual
LMDGP/SH/G07/001C Lot 1 50,000.00 Shopping Post Post Plan 12-Mar-07 NA
Actual
LMDGP/SH/G07/03 Lot 1 50,000.00 Shopping Post Post Plan 19-Nov-07 NA
Actual 05-Nov-07
LMDGP/SH/G07/03 Lot 2 50,000.00 Shopping Post Post Plan 19-Nov-07 NA
Actual 05-Nov-07
LMDGP/SH/G07/03 Lot 3 50,000.00 Shopping Post Post Plan 19-Nov-07 NA
Actual 05-Nov-07
LMDGP/SH/G07/03 Lot 4 50,000.00 Shopping Post Post Plan 19-Nov-07 NA
Actual 05-Nov-07
LMDGP/SH/G07/03 Lot 5 50,000.00 Shopping Post Post Plan 19-Nov-07 NA
Actual 05-Nov-07
LMDGP/SH/G07/03 Lot 6 50,000.00 Shopping Post Post Plan 19-Nov-07 NA
Actual 05-Nov-07
LMDGP/SH/G07/03 Lot 7 50,000.00 Shopping Post Post Plan 19-Nov-07 NA
Actual 05-Nov-07
LMDGP/SH/G07/03 Lot 8 50,000.00 Shopping Post Post Plan 19-Nov-07 NA
Actual 05-Nov-07
LMDGP/SH/G07/03 Lot 9 50,000.00 Shopping Post Post Plan 19-Nov-07 NA
Actual 05-Nov-07
LMDGP/SH/G07/001 Lot 1 50,000.00 Shopping Post Post Plan 30-Nov-07 NA
Actual 15-Nov-07
LMDGP/SH/G08/001 Lot 1 50,000.00 Shopping Post Post Plan 14-Jan-08 NA
Actual 07-Jan-08
Office Furniture for slum communities (Social Sustainability programme)
Desks and Chairs for Social sustainability Programme
Equipment and goods (Police Stations, PHCs and community centres in Slum communities) under social Sustainability Programme
Supply and Installation of Solar Powered Street Lights in Badia
Supply of Anti- Virus for computers
Supply of Projet Site sign Boards
Supply and Installation of Solar Powered Street Lights in Amukoko
Supply and Installation of Solar Powered Street Lights in Makoko
Supply and Installation of Solar Powered Street Lights in Iwaya
Supply and Installation of Solar Powered Street Lights in Ajegunle
Supply and Installation of Solar Powered Street Lights in Bariga
*Supply and Installation of Solar Powered Street Lights in Agege
Supply and Installation of Solar Powered Street Lights in Itire
Supply and Installation of Solar Powered Street Lights in Ilaje
42439.xls 3 of 44 2/11/2008 1:40 PM
Procurement Plan-Goods
LMDGP/SH/G08/002 Lot 1 50,000.00 Shopping Post Post Plan 08-Apr-08 NA
Actual
LMDGP/DC/G08/001 Lot 1 120,000.00**Direct Contract Post Prior Plan 7-Jan-08 NA
Actual 10-Jan-08
Total Cost 7,980,000.00 Plan
0.00 Actual
NB
*Waiver for Shopping in Pilot Solar powered Light obtained from the Bank.
**Direct contracting for procurement of project vehicles for the use of Supervising consultant agreed to in principle by the Bank during the November 2007 Supervision mission.
**Procurement of Vehicles for Supervising Consultant
Procurement of 100kva Generator
EXPLANATORY NOTES
The 4x4 Jeep used by the former PD was also used as a pool car before the resumption of the new PD.The cost of maintenance is on the increase.The estimated cost for the new Jeep includes cost of comprehensive insurance
There are two officers per Project Unit (PU).Only one out of the two have been provided with project vehicles .With the procurement of these 9 Nos all PU officers would have been provided for.
The movement of the Project Office to a new and larger office space to cater for more staff and office units will expectedly call for increased electricity demand hence the plan to procure a new 100KVA Generator
42439.xls 4 of 44 2/11/2008 1:40 PM
Procurement Plan-Goods
Country/Organisation:
Project/Programme:
Loan #: 4219
Description*
List of Contracts
Furniture for Primary Health Centres
Supply and Installation of 14 Electric Transformers for slum communities
Heavy Duty Plants and Equipment (Excavators, Dredgers etc) for ODS and LAWMA
Procurement of Satellite Imagery for Lagos (Balance of 52% coverage)
Survey Equipment (Measuring wheel, Total Station etc) Hand GPS
Office Funiture for PCU office and CEAs
Office Equipment for PCU office and CEAs
Equipment for Primary Health Centres
Norm Duration of Proc Steps
Furniture for Rehabilitated & New Schools/ Constructed schools
Project vehicles - 1 No. 4 x 4 Vehicle Jeep,1No. OBS Vehicle,2Nos Saloon Cars and 9 Nos. Utility Pick-ups for PUs
If Post-Review, No-objection Dates are not neededSpec Proc Notice
Advert
On-line UNDBGatewayNat Press
Bid Invitation Date
Bid Closing-Opening
SubmissionBid Eval Rpt
No-objectionDate
Plan vs.
Actual
Contract Amount in US$’000
DateContractAward
Date ContractAdvert
1.5 - 2 wks 6 to 12 wks 1.5 - 3 wks 1 - 1.5 wks Plan 1 wk
Actual
14-Apr-08 14-Apr-08 28-May-08 11-Jun-08 25-Jun-08 Plan 1,000,000.00 2-Jul-08 9-Jul-08
Actual
20-Mar-08 20-Mar-08 17-Apr-08 1-May-08 15-May-08 Plan 1,000,000.00 22-May-08 29-May-08
Actual
20-Jun-08 20-Jun-08 18-Jul-08 1-Aug-08 15-Aug-08 Plan 3,000,000.00 22-Aug-08 29-Aug-08
Actual
11-Mar-08 11-Mar-08 8-Apr-08 22-Apr-08 6-May-08 Plan 600,000.00 13-May-08 20-May-08
Actual
13-Mar-08 26-Feb-08 25-Mar-08 NA NA Plan 60,000.00 1-Apr-08 8-Apr-08
Actual
17-Apr-08 26-Feb-08 25-Mar-08 NA NA Plan 150,000.00 1-Apr-08 8-Apr-08
Actual
17-Apr-08 26-Feb-08 25-Mar-08 NA NA Plan 150,000.00 1-Apr-08 8-Apr-08
Actual
13-Mar-08 27-Mar-08 24-Apr-08 NA NA Plan 200,000.00 1-May-08 8-May-08
Actual
30-May-08 30-May-08 27-Jun-08 NA NA Plan 150,000.00 4-Jul-08 11-Jul-08
Actual
30-May-08 30-May-08 27-Jun-08 NA NA Plan 300,000.00 4-Jul-08 11-Jul-08
Actual
31-Jul-08 31-Jul-08 28-Aug-08 NA NA Plan 100,000.00 4-Sep-08 11-Sep-08
Contract FinalizationBidding Period Bid Evaluation
42439.xls 5 of 44 2/11/2008 1:40 PM
Procurement Plan-Goods
Software (Arc GIS/ SPSS data Mining)
Refurbishment of LAWMA Plants
Actual
29-Aug-08 29-Aug-08 26-Sep-08 NA NA Plan 400,000.00 3-Oct-08 10-Oct-08
Actual
42439.xls 6 of 44 2/11/2008 1:40 PM
Procurement Plan-Goods
Office Furniture for slum communities (Social Sustainability programme)
Desks and Chairs for Social sustainability Programme
Equipment and goods (Police Stations, PHCs and community centres in Slum communities) under social Sustainability Programme
Supply and Installation of Solar Powered Street Lights in Badia
Supply of Anti- Virus for computers
Supply of Projet Site sign Boards
Supply and Installation of Solar Powered Street Lights in Amukoko
Supply and Installation of Solar Powered Street Lights in Makoko
Supply and Installation of Solar Powered Street Lights in Iwaya
Supply and Installation of Solar Powered Street Lights in Ajegunle
Supply and Installation of Solar Powered Street Lights in Bariga
*Supply and Installation of Solar Powered Street Lights in Agege
Supply and Installation of Solar Powered Street Lights in Itire
Supply and Installation of Solar Powered Street Lights in Ilaje
NA 26-Mar-07 23-Apr-07 NA NA Plan 50,000.00 30-Apr-07 7-May-07
Actual
NA 26-Mar-07 23-Apr-07 NA NA Plan 50,000.00 30-Apr-07 7-May-07
Actual
NA 26-Mar-07 23-Apr-07 NA NA Plan 50,000.00 30-Apr-07 7-May-07
Actual
NA 21-Nov-07 19-Dec-07 NA NA Plan 50,000.00 26-Dec-07 2-Jan-08
Actual
NA 21-Nov-07 19-Dec-07 NA NA Plan 50,000.00 26-Dec-07 2-Jan-08
Actual
NA 21-Nov-07 19-Dec-07 NA NA Plan 50,000.00 26-Dec-07 2-Jan-08
Actual
NA 21-Nov-07 19-Dec-07 NA NA Plan 50,000.00 26-Dec-07 2-Jan-08
Actual
NA 21-Nov-07 19-Dec-07 NA NA Plan 50,000.00 26-Dec-07 2-Jan-08
Actual
NA 21-Nov-07 19-Dec-07 NA NA Plan 50,000.00 26-Dec-07 2-Jan-08
Actual
NA 21-Nov-07 19-Dec-07 NA NA Plan 50,000.00 26-Dec-07 2-Jan-08
Actual
NA 21-Nov-07 19-Dec-07 NA NA Plan 50,000.00 26-Dec-07 2-Jan-08
Actual
NA 21-Nov-07 19-Dec-07 NA NA Plan 50,000.00 26-Dec-07 2-Jan-08
Actual
NA 3-Dec-07 31-Dec-07 NA NA Plan 50,000.00 7-Jan-08 14-Jan-08
Actual
NA 16-Jan-08 13-Feb-08 NA NA Plan 50,000.00 20-Feb-08 27-Feb-08
Actual42439.xls 7 of 44 2/11/2008 1:40 PM
Procurement Plan-Goods
Total Cost
**Procurement of Vehicles for Supervising Consultant
Procurement of 100kva Generator
EXPLANATORY NOTES
The 4x4 Jeep used by the former PD was also used as a pool car before the resumption of the new PD.The cost of maintenance is on the increase.The estimated cost for the new Jeep includes cost of comprehensive insurance
There are two officers per Project Unit (PU).Only one out of the two have been provided with project vehicles .With the procurement of these 9 Nos all PU officers would have been provided for.
The movement of the Project Office to a new and larger office space to cater for more staff and office units will expectedly call for increased electricity demand hence the plan to procure a new 100KVA Generator
NA 10-Apr-08 08-May-08 NA NA Plan 50,000.00 15-May-08 22-May-08
Actual
NA 4-Feb-08 3-Mar-08 NA NA Plan 120,000.00 10-Mar-08 17-Mar-08
Actual
Plan 7,980,000.00
Actual 0.00
**Direct contracting for procurement of project vehicles for the use of Supervising consultant agreed to in principle by the Bank during the November 2007 Supervision mission.
42439.xls 8 of 44 2/11/2008 1:40 PM
Procurement Plan-Goods
Country/Organisation:
Project/Programme:
Loan #: 4219
Description*
List of Contracts
Furniture for Primary Health Centres
Supply and Installation of 14 Electric Transformers for slum communities
Heavy Duty Plants and Equipment (Excavators, Dredgers etc) for ODS and LAWMA
Procurement of Satellite Imagery for Lagos (Balance of 52% coverage)
Survey Equipment (Measuring wheel, Total Station etc) Hand GPS
Office Funiture for PCU office and CEAs
Office Equipment for PCU office and CEAs
Equipment for Primary Health Centres
Norm Duration of Proc Steps
Furniture for Rehabilitated & New Schools/ Constructed schools
Project vehicles - 1 No. 4 x 4 Vehicle Jeep,1No. OBS Vehicle,2Nos Saloon Cars and 9 Nos. Utility Pick-ups for PUs
Contract Implementation
DateContractSignature
Openingof
Let of Credit
Arrivalof
Goods
InspectionFinal
Acceptance
1.5-3 wks
16-Jul-08 NA 30-Sep-08 5-Oct-08
5-Jun-08 NA 22-Oct-08 27-Oct-08
5-Sep-08 26-Sep-08 25-Nov-08 30-Nov-08
27-May-08 17-Jun-08 17-Jul-08 22-Jul-08
6-Apr-08 20-Apr-08 27-Apr-08 2-May-08
6-Apr-08 20-Apr-08 27-Apr-08 2-May-08
6-Apr-08 20-Apr-08 27-Apr-08 2-May-08
6-May-08 20-May-08 27-May-08 1-Jun-08
9-Jul-08 23-Jul-08 30-Jul-08 4-Aug-08
9-Jul-08 23-Jul-08 30-Jul-08 4-Aug-08
9-Sep-08 23-Sep-08 30-Sep-08 5-Oct-0842439.xls 9 of 44 2/11/2008 1:40 PM
Procurement Plan-Goods
Software (Arc GIS/ SPSS data Mining)
Refurbishment of LAWMA Plants
8-Oct-08 22-Oct-08 29-Oct-08 3-Nov-08
42439.xls 10 of 44 2/11/2008 1:40 PM
Procurement Plan-Goods
Office Furniture for slum communities (Social Sustainability programme)
Desks and Chairs for Social sustainability Programme
Equipment and goods (Police Stations, PHCs and community centres in Slum communities) under social Sustainability Programme
Supply and Installation of Solar Powered Street Lights in Badia
Supply of Anti- Virus for computers
Supply of Projet Site sign Boards
Supply and Installation of Solar Powered Street Lights in Amukoko
Supply and Installation of Solar Powered Street Lights in Makoko
Supply and Installation of Solar Powered Street Lights in Iwaya
Supply and Installation of Solar Powered Street Lights in Ajegunle
Supply and Installation of Solar Powered Street Lights in Bariga
*Supply and Installation of Solar Powered Street Lights in Agege
Supply and Installation of Solar Powered Street Lights in Itire
Supply and Installation of Solar Powered Street Lights in Ilaje
5-May-07 19-May-07 26-May-07 31-May-07
5-May-07 19-May-07 26-May-07 31-May-07
5-May-07 19-May-07 26-May-07 31-May-07
31-Dec-07 14-Jan-08 21-Jan-08 26-Jan-08
31-Dec-07 14-Jan-08 21-Jan-08 26-Jan-08
31-Dec-07 14-Jan-08 21-Jan-08 26-Jan-08
31-Dec-07 14-Jan-08 21-Jan-08 26-Jan-08
31-Dec-07 14-Jan-08 21-Jan-08 26-Jan-08
31-Dec-07 14-Jan-08 21-Jan-08 26-Jan-08
31-Dec-07 14-Jan-08 21-Jan-08 26-Jan-08
31-Dec-07 14-Jan-08 21-Jan-08 26-Jan-08
31-Dec-07 14-Jan-08 21-Jan-08 26-Jan-08
12-Jan-08 26-Jan-08 2-Feb-08 7-Feb-08
25-Feb-08 10-Mar-08 17-Mar-08 22-Mar-08
42439.xls 11 of 44 2/11/2008 1:40 PM
Procurement Plan-Goods
Total Cost
**Procurement of Vehicles for Supervising Consultant
Procurement of 100kva Generator
EXPLANATORY NOTES
The 4x4 Jeep used by the former PD was also used as a pool car before the resumption of the new PD.The cost of maintenance is on the increase.The estimated cost for the new Jeep includes cost of comprehensive insurance
There are two officers per Project Unit (PU).Only one out of the two have been provided with project vehicles .With the procurement of these 9 Nos all PU officers would have been provided for.
The movement of the Project Office to a new and larger office space to cater for more staff and office units will expectedly call for increased electricity demand hence the plan to procure a new 100KVA Generator
20-May-08 05-Jun-08 12-Jun-08 17-Jun-08
15-Mar-08 29-Mar-08 5-Apr-08 10-Apr-08
42439.xls 12 of 44 2/11/2008 1:40 PM
Procurement Plan-Works Country/Organisation: NIGERIA / LAGOS METROPOLITAN DEVELOPMENT AND GOVERNANCE PROJECTProject/Programme: LMDGP
Loan #: 4219
Description*PackageNumber
LotNumber
Lumpsum or Bill of
Quantities
Procurement Method
Estimated Amount in
US $
Pre-or Post Qualificatio
n
Prior or Post
Review
If Prequalification
add 7-13 wks
List of Contracts
Slum Upgrading Component
Water Supply to Slum Communities
LMDGP-SU-NCB-07-01 Lot 1 BOQ NCB 250,000.00 Post Post
LMDGP-SU-NCB-07-01 Lot 2 BOQ NCB 250,000.00 Post Post
LMDGP-SU-NCB-07-01 Lot 3 BOQ NCB 300,000.00 Post Post
LMDGP-SU-NCB-07-11 Lot 1 BOQ NCB 73,313.50 Post Post
LMDGP-SU-NCB-07-11 Lot 2 BOQ NCB 73,313.50 Post Post
LMDGP-SU-NCB-07-11 Lot 3 BOQ NCB 73,313.50 Post Post
LMDGP-SU-NCB-07-11 Lot 4 BOQ NCB 97,751.34 Post Post
LMDGP-SU-NCB-07-11 Lot 5 BOQ NCB 73,313.50 Post Post
LMDGP-SU-NCB-07-11 Lot 6 BOQ NCB 73,313.50 Post PostConstruction of 3 Boreholes at Oniwaya,Akerele and Owo Streets of Agege
Construction of 3 Boreholes at Smith,Kushimo/Odebode and Adetayo Streets of
Itire/Ijeshatedo Slum community
Construction of 3 Boreholes at Okeyemi,Ronke and Osindero Streets of Itire/Ijeshatedo Slum
community
Construction of 4 Boreholes atOlayinka,Shofolahan,Ijesha Rd and Adebayo
Rufai Streets of Itire/Ijeshatedo Slum
Construction of 3 Boreholes at Kasumu,Agege Motor Rd and Olusanya Streets of Agege Slum
community
Basic Data
Construction of 13 Nos. Boreholes at Ilaje, Iwaya and Makoko
Construction of 11 Nos. Boreholes at Agege and Itire
Construction of 3 Boreholes at Fadairo,Osinfowokan and Olubodun Streets of
Itire/Ijeshatedo Slum community
Norm Duration of Proc Steps
Construction of remaining Boreholes in the slum communities
Construction of 11 Nos. Boreholes at Badia and Ajegule
42439.xls 13 of 44 2/11/2008 1:40 PM
Procurement Plan-Works
LMDGP-SU-NCB-07-11 lot 7 BOQ NCB 73,313.50 Post Post
Rehabilitation of Schools and PHC
LMDGP-SU-NCB-07-04 Lot 1 BOQ NCB 800,000.00 Post Post
Water Supply to Institutions
LMDGP-SU-NCB-08-01 Lot 1 BOQ NCB 100,000.00 PostPost
LMDGP-SU-NCB-08-01 Lot 2 BOQ NCB 100,000.00 PostPost
LMDGP-SU-NCB-08-01 Lot 3 BOQ NCB 120,000.00 Post Post
Reconstruction & New Construction of Facilities
LMDGP-SU-ICB-08-01 Lot 1 BOQ ICB 7,046,688.84 Post Prior
LMDGP-SU-ICB-08-01 Lot 2 BOQ ICB 2,825,821.86 Post Prior
LMDGP-SU-ICB-08-01 Lot 3 BOQ ICB 4,546,201.75 Post Prior
LMDGP-SU-ICB-08-01 Lot 4 BOQ ICB 3,531,396.40 Post Prior
LMDGP-SU-ICB-08-01 Lot 5 BOQ ICB 3,540,940.08 Post Prior
Oniwaya,Akerele and Owo Streets of Agege Slum community
Construction of 3 Schools at Iwaya in Lagos City
Construction of Water Supply facilities for Schools and PHC at Bariga, Badia and Makoko
Construction of Water Supply facilities for Schools and PHC at Ilaje, Amukoko and Itire
Rehabilitation of Schools (7 Nos) and Clinics (3 Nos)
Construction of Boreholes at 3 locations in Slum Area, Lagos
Construction of 2 Schools at Ilaje in Lagos City
Construction of 2 Schools at Bariga in Lagos City
Construction of 2 Schools at Bariga and Gbagada in Lagos City
Construction of 1 School at Ajegunle in Lagos City
Construction of Water Supply facilities for Schools, PHC and Community Hall at Ajegunle, Iwaya & Agege
42439.xls 14 of 44 2/11/2008 1:40 PM
Procurement Plan-Works
LMDGP-SU-ICB-08-01 Lot 6 BOQ ICB 3,221,545.54 Post Prior
LMDGP-SU-ICB-08-01 lot 7 BOQ ICB 2,354,008.45 Post Prior
LMDGP-SU-ICB-08-02 Lot 1 BOQ ICB 7,000,000.00 Post Prior
LMDGP-SU-ICB-08-03 Lot 1 BOQ ICB 25,000,000.00 Post Prior
LMDGP-SU-NCB-07-08 Lot 1 BOQ NCB 800,000.00 Post Post
LMDGP-SU-NCB-07-08 Lot 1 BOQ NCB 980,000.00 Post Post
LMDGP-SU-NCB-07-10 Lot 1 BOQ NCB 221,993.00 Post Post
LMDGP-SU-NCB-07-10 Lot 2 BOQ NCB 548,125.81 Post Post
LMDGP-SU-NCB-07-10 Lot 3 BOQ NCB 596,637.03 Post Post
LMDGP-SU-NCB-07-08 Lot 1 BOQ NCB 900,000.00 Post Post
Drainage Component
Deferred Maintenance of Drainage Channels
Construction of Market at Amukoko
Construction of 1 No. Market at Ilaje and Itire, 1 No. Public Toilet at Itire
Installation of Street light in all slum communities
Construction of One Primary Health Center at Agege
Construction of 2 Nos. Fish smoking facilities at Ilaje and Makoko
Construction of Roads and Street Drains in all slum communities
Construction of Two Primary Health Centers at Amukoko and Badia
Construction of One Primary Health Center at Bariga One Community Hall at Iwaya
Construction of 2 Schools at Badia in Lagos City
Construction of 2 Schools at Amukoko and Badia in Lagos City
42439.xls 15 of 44 2/11/2008 1:40 PM
Procurement Plan-Works
LMDGP-DR-ICB-08-01 Lot 1 BOQ ICB 3,400,000.00 Post Prior
LMDGP-DR-ICB-08-01 Lot 2 BOQ ICB 3,880,000.00 Post Prior
LMDGP-DR-ICB-08-01 Lot 3 BOQ ICB 8,700,000.00 Post Prior
LMDGP-DR-ICB-08-01 Lot 4 BOQ ICB 3,470,000.00 Post Prior
Construction of Drainage Channels
LMDGP-DR-ICB-08-02 Lot 1 BOQ ICB 3,430,000.00 Post Prior
LMDGP-DR-ICB-08-02 Lot 2 BOQ ICB 3,780,000.00 Post Prior
LMDGP-DR-ICB-08-02 Lot 3 BOQ ICB 2,190,000.00 Post Prior
LMDGP-DR-ICB-08-02 Lot 4 BOQ ICB 1,800,000.00 Post Prior
Solid Waste Management Component
Evacuation of Ilegal Dump Sites
LMDGP-SWM-NCB-07-01 Lot 1 BOQ NCB 700,000.00 Post Post
LMDGP-SWM-NCB-07-01 Lot 2 BOQ NCB 700,000.00 Post Post
Construction of Ogba channel
Construction of Amukoko/ Alafia Channel
Evacuation of ilegal dump sites in Lagos City (location - Obele Oniwala)
Maintenance of Surulere Channel (System 5)
Maintenance of Iganmu Channel (System 5)
Maintenance of Ajegunle Channel (System 5)
Construction of Gbagada/ Bariga Channel
Construction of Elere Channel
Maintenance of Igbobi Channel (System 2)
Evacuation of ilegal dump sites at Bolaji Omupo, Oba-Ogunji, Opebi and Ajah
42439.xls 16 of 44 2/11/2008 1:40 PM
Procurement Plan-Works
LMDGP-SWM-NCB-07-01 Lot 3 BOQ NCB 960,000.00 Post Post
LMDGP-SWM-NCB-07-01 Lot 4 BOQ NCB 600,000.00 Post Post
Communal Waste Depots (CWD)
LMDGP-SWM-NCB-08-01 Lot 1 BOQ NCB 600,000.00 Post Post
Transfer Loading Stations (TLS)
LMDGP-SWM-ICB-08-02 Lot 1 BOQ ICB 4,700,000.00 Post Prior
LMDGP-SWM-ICB-08-02 Lot 2 BOQ ICB 4,650,000.00 Post Prior
LandFill Management
LMDGP-SWM-NCB-08-02 Lot 1 BOQ NCB 950,000.00 Post Post
Total Cost 110,080,991.10
0.00
Construction of CWD at various locations ( Ilu Eri, Agunlejika, Olatunde Onimole, Berger and Iponri)
Landfill Management at Olusosun, Abule-Egba and Solus
Lagos City (location - Obele Oniwala)
Evacuation of ilegal dump sites in Lagos City (location - Ikate Olaogun)
Evacuation of ilegal dump sites at Ilu- Eri, Festac , Mechanic Village (Ajegunle) and Agunlejika
Construction of Waste Transfer Station at Marini
Construction of Waste Transfer Station at Oba Ogunji
42439.xls 17 of 44 2/11/2008 1:40 PM
Procurement Plan-Works Country/Organisation:Project/Programme:
Loan #: 4219
Description*
List of Contracts
Slum Upgrading Component
Water Supply to Slum Communities
Construction of 3 Boreholes at Oniwaya,Akerele and Owo Streets of Agege
Construction of 3 Boreholes at Smith,Kushimo/Odebode and Adetayo Streets of
Itire/Ijeshatedo Slum community
Construction of 3 Boreholes at Okeyemi,Ronke and Osindero Streets of Itire/Ijeshatedo Slum
community
Construction of 4 Boreholes atOlayinka,Shofolahan,Ijesha Rd and Adebayo
Rufai Streets of Itire/Ijeshatedo Slum
Construction of 3 Boreholes at Kasumu,Agege Motor Rd and Olusanya Streets of Agege Slum
community
Construction of 13 Nos. Boreholes at Ilaje, Iwaya and Makoko
Construction of 11 Nos. Boreholes at Agege and Itire
Construction of 3 Boreholes at Fadairo,Osinfowokan and Olubodun Streets of
Itire/Ijeshatedo Slum community
Norm Duration of Proc Steps
Construction of remaining Boreholes in the slum communities
Construction of 11 Nos. Boreholes at Badia and Ajegule
If Post-Review, No-objection Dates are not neededSpec Proc
NoticeAdvert
Plan vs.
Actual
Prep & Submission
by Ex Agency
No-objection
Date
On-line UNDB
GatewayNat Press
Bid Invitation
Date
Bid Closing-Opening
SubmissionBid Eval Rpt
No-objectionDate
Plan 4 - 7 wks 1 - 1.5 wks 1.5 - 2 wks 1.5 - 2 wks 6 to 12 wks 1.5 - 3 wks
Actual
Plan 16-May-07 NA 21-May-07 26-May-07 25-Jun-07 NA NA
Actual 21-May-07 21-May-07 05-Jul-07
Plan 16-May-07 NA 21-May-07 26-May-07 25-Jun-07 NA NA
Actual 21-May-07 21-May-07 05-Jul-07
Plan 16-May-07 NA 21-May-07 26-May-07 25-Jun-07 NA NA
Actual 21-May-07 21-May-07 05-Jul-07
Plan 20-Nov-07 NA 25-Nov-07 30-Nov-07 30-Dec-07 NA NA
Actual 27-Dec-07
Plan 20-Nov-07 NA 25-Nov-07 30-Nov-07 30-Dec-07 NA NA
Actual 27-Dec-07
Plan 20-Nov-07 NA 25-Nov-07 30-Nov-07 30-Dec-07 NA NA
Actual 27-Dec-07
Plan 20-Nov-07 NA 25-Nov-07 30-Nov-07 30-Dec-07 NA NA
Actual 27-Dec-07
Plan 20-Nov-07 NA 25-Nov-07 30-Nov-07 30-Dec-07 NA NA
Actual 27-Dec-07
Plan 20-Nov-07 NA 25-Nov-07 30-Nov-07 30-Dec-07 NA NA
Bidding Period
Draft Bid Documents, including specs and
quantities, draft SPNBid Evaluation
42439.xls 18 of 44 2/11/2008 1:40 PM
Procurement Plan-Works
Rehabilitation of Schools and PHC
Water Supply to Institutions
Reconstruction & New Construction of Facilities
Oniwaya,Akerele and Owo Streets of Agege Slum community
Construction of 3 Schools at Iwaya in Lagos City
Construction of Water Supply facilities for Schools and PHC at Bariga, Badia and Makoko
Construction of Water Supply facilities for Schools and PHC at Ilaje, Amukoko and Itire
Rehabilitation of Schools (7 Nos) and Clinics (3 Nos)
Construction of Boreholes at 3 locations in Slum Area, Lagos
Construction of 2 Schools at Ilaje in Lagos City
Construction of 2 Schools at Bariga in Lagos City
Construction of 2 Schools at Bariga and Gbagada in Lagos City
Construction of 1 School at Ajegunle in Lagos City
Construction of Water Supply facilities for Schools, PHC and Community Hall at Ajegunle, Iwaya & Agege
Actual 27-Dec-07
Plan 20-Nov-07 NA 25-Nov-07 30-Nov-07 30-Dec-07 NA NA
Actual 27-Dec-07
Plan 23-May-07 NA 28-May-07 2-Jun-07 2-Jul-07 NA NA
Actual 28-May-07 28-May-07 10-Jul-07
Plan29-Feb-08 NA 5-Mar-08 10-Mar-08 9-Apr-08 NA NA
Actual
Plan29-Feb-08 NA 5-Mar-08 10-Mar-08 9-Apr-08 NA NA
Actual
Plan 29-Feb-08 NA 5-Mar-08 10-Mar-08 9-Apr-08 NA NA
Actual
Plan 10-Dec-07 8-Jan-08 11-Jan-08 11-Jan-08 22-Feb-08 14-Mar-08 28-Mar-08
Actual
Plan 10-Dec-07 8-Jan-08 11-Jan-08 11-Jan-08 22-Feb-08 14-Mar-08 28-Mar-08
Actual
Plan 10-Dec-07 8-Jan-08 11-Jan-08 11-Jan-08 22-Feb-08 14-Mar-08 28-Mar-08
Actual
Plan 10-Dec-07 8-Jan-08 11-Jan-08 11-Jan-08 22-Feb-08 14-Mar-08 28-Mar-08
Actual
Plan 10-Dec-07 8-Jan-08 11-Jan-08 11-Jan-08 22-Feb-08 14-Mar-08 28-Mar-08
Actual42439.xls 19 of 44 2/11/2008 1:40 PM
Procurement Plan-Works
Drainage Component
Deferred Maintenance of Drainage Channels
Construction of Market at Amukoko
Construction of 1 No. Market at Ilaje and Itire, 1 No. Public Toilet at Itire
Installation of Street light in all slum communities
Construction of One Primary Health Center at Agege
Construction of 2 Nos. Fish smoking facilities at Ilaje and Makoko
Construction of Roads and Street Drains in all slum communities
Construction of Two Primary Health Centers at Amukoko and Badia
Construction of One Primary Health Center at Bariga One Community Hall at Iwaya
Construction of 2 Schools at Badia in Lagos City
Construction of 2 Schools at Amukoko and Badia in Lagos City
Plan 10-Dec-07 8-Jan-08 11-Jan-08 11-Jan-08 22-Feb-08 14-Mar-08 28-Mar-08
Actual
Plan 10-Dec-07 8-Jan-08 11-Jan-08 11-Jan-08 22-Feb-08 14-Mar-08 28-Mar-08
Actual
Plan 10-Apr-08 20-Apr-08 30-Apr-08 30-Apr-08 29-Jun-08 13-Jul-08 27-Jul-08
Actual
Plan 10-Aug-08 20-Aug-08 29-Aug-08 29-Aug-08 28-Oct-08 11-Nov-08 25-Nov-08
Actual
Plan 7-Nov-07 NA 12-Nov-07 17-Nov-07 17-Dec-07 NA NA
Actual 18-Sep-07 18-Sep-07 25-Oct-07
Plan 7-Nov-07 NA 12-Nov-07 17-Nov-07 17-Dec-07 NA NA
Actual 18-Sep-07 18-Sep-07 25-Oct-07
Plan 14-Dec-07 NA 19-Dec-07 24-Dec-07 23-Jan-08 NA NA
Actual
Plan 14-Dec-07 NA 19-Dec-07 24-Dec-07 23-Jan-08 NA NA
Actual
Plan 14-Dec-07 NA 19-Dec-07 24-Dec-07 23-Jan-08 NA NA
Actual
Plan 7-Apr-08 NA 12-Apr-08 17-Apr-08 17-May-08 NA NA
Actual
42439.xls 20 of 44 2/11/2008 1:40 PM
Procurement Plan-Works
Construction of Drainage Channels
Solid Waste Management Component
Evacuation of Ilegal Dump Sites
Construction of Ogba channel
Construction of Amukoko/ Alafia Channel
Evacuation of ilegal dump sites in Lagos City (location - Obele Oniwala)
Maintenance of Surulere Channel (System 5)
Maintenance of Iganmu Channel (System 5)
Maintenance of Ajegunle Channel (System 5)
Construction of Gbagada/ Bariga Channel
Construction of Elere Channel
Maintenance of Igbobi Channel (System 2)
Evacuation of ilegal dump sites at Bolaji Omupo, Oba-Ogunji, Opebi and Ajah
Plan 13-Dec-07 8-Jan-08 11-Jan-08 11-Jan-08 11-Mar-08 25-Mar-08 8-Apr-08
Actual
Plan 13-Dec-07 8-Jan-08 11-Jan-08 11-Jan-08 11-Mar-08 25-Mar-08 8-Apr-08
Actual
Plan 13-Dec-07 8-Jan-08 11-Jan-08 11-Jan-08 11-Mar-08 25-Mar-08 8-Apr-08
Actual
Plan 13-Dec-07 8-Jan-08 11-Jan-08 11-Jan-08 11-Mar-08 25-Mar-08 8-Apr-08
Actual
Plan 15-Jan-08 11-Feb-08 28-Feb-08 28-Feb-08 28-Apr-08 12-May-08 26-May-08
Actual
Plan 15-Jan-08 11-Feb-08 28-Feb-08 28-Feb-08 28-Apr-08 12-May-08 26-May-08
Actual
Plan 15-Jan-08 11-Feb-08 28-Feb-08 28-Feb-08 28-Apr-08 12-May-08 26-May-08
Actual
Plan 15-Jan-08 11-Feb-08 28-Feb-08 28-Feb-08 28-Apr-08 12-May-08 26-May-08
Actual
Plan 2-Oct-07 NA 7-Oct-07 12-Oct-07 11-Nov-07 NA NA
Actual06-Aug-07 06-Aug-07 07-Sep-07
Plan 2-Oct-07 NA 7-Oct-07 12-Oct-07 11-Nov-07 NA NA
42439.xls 21 of 44 2/11/2008 1:40 PM
Procurement Plan-Works
Communal Waste Depots (CWD)
Transfer Loading Stations (TLS)
LandFill Management
Total Cost
Construction of CWD at various locations ( Ilu Eri, Agunlejika, Olatunde Onimole, Berger and Iponri)
Landfill Management at Olusosun, Abule-Egba and Solus
Lagos City (location - Obele Oniwala)
Evacuation of ilegal dump sites in Lagos City (location - Ikate Olaogun)
Evacuation of ilegal dump sites at Ilu- Eri, Festac , Mechanic Village (Ajegunle) and Agunlejika
Construction of Waste Transfer Station at Marini
Construction of Waste Transfer Station at Oba Ogunji
Actual 06-Aug-07 06-Aug-07 07-Sep-07
Plan 2-Oct-07 NA 7-Oct-07 12-Oct-07 11-Nov-07 NA NA
Actual 24-Oct-07 24-Oct-07 22-Nov-07
Plan 2-Oct-07 NA 7-Oct-07 12-Oct-07 11-Nov-07 NA NA
Actual06-Aug-07 06-Aug-07 07-Sep-07
Plan 20-Mar-08 NA 25-Mar-08 30-Mar-08 29-Apr-08 NA NA
Actual
Plan 10-Feb-08 20-Feb-08 1-Mar-08 11-Mar-08 10-May-08 24-May-08 7-Jun-08
Actual
Plan 10-Feb-08 20-Feb-08 1-Mar-08 11-Mar-08 10-May-08 24-May-08 7-Jun-08
Actual
Plan 2-Oct-07 NA 7-Oct-07 12-Oct-07 11-Nov-07 NA NA
Actual 06-Aug-07 06-Aug-07 14-Sep-07
Plan
Actual
42439.xls 22 of 44 2/11/2008 1:40 PM
Procurement Plan-Works Country/Organisation:Project/Programme:
Loan #: 4219
Description*
List of Contracts
Slum Upgrading Component
Water Supply to Slum Communities
Construction of 3 Boreholes at Oniwaya,Akerele and Owo Streets of Agege
Construction of 3 Boreholes at Smith,Kushimo/Odebode and Adetayo Streets of
Itire/Ijeshatedo Slum community
Construction of 3 Boreholes at Okeyemi,Ronke and Osindero Streets of Itire/Ijeshatedo Slum
community
Construction of 4 Boreholes atOlayinka,Shofolahan,Ijesha Rd and Adebayo
Rufai Streets of Itire/Ijeshatedo Slum
Construction of 3 Boreholes at Kasumu,Agege Motor Rd and Olusanya Streets of Agege Slum
community
Construction of 13 Nos. Boreholes at Ilaje, Iwaya and Makoko
Construction of 11 Nos. Boreholes at Agege and Itire
Construction of 3 Boreholes at Fadairo,Osinfowokan and Olubodun Streets of
Itire/Ijeshatedo Slum community
Norm Duration of Proc Steps
Construction of remaining Boreholes in the slum communities
Construction of 11 Nos. Boreholes at Badia and Ajegule
Plan vs.
Actual
Contract Amount in US$ ’000
DateContractAward
DateContractAdvert
DateContractSignature
MobilizationAdvancePayment
SubstantialCompletion
FinalAcceptance
Plan 1 wk 1.5-3 wks
Actual
Plan 250,000.00 5-Jul-07 12-Jul-07 19-Jul-07 2-Aug-07 29-Jan-08 28-Feb-08
Actual 223,148.47 24-Aug-07 27-Aug-07 05-Dec-07
Plan 250,000.00 5-Jul-07 12-Jul-07 19-Jul-07 2-Aug-07 29-Jan-08 28-Feb-08
Actual 416,226.52 24-Aug-07 27-Aug-07 05-Oct-07
Plan 300,000.00 5-Jul-07 12-Jul-07 19-Jul-07 2-Aug-07 29-Jan-08 28-Feb-08
Actual 296,679.69 24-Aug-07 27-Aug-07 10-Oct-07
Plan 73,313.50 31-Jan-08 7-Feb-08 14-Feb-08 28-Feb-08 26-Aug-08 25-Sep-08
Actual
Plan 73,313.50 31-Jan-08 7-Feb-08 14-Feb-08 28-Feb-08 26-Aug-08 25-Sep-08
Actual
Plan 73,313.50 31-Jan-08 7-Feb-08 14-Feb-08 28-Feb-08 26-Aug-08 25-Sep-08
Actual
Plan 97,751.34 31-Jan-08 7-Feb-08 14-Feb-08 28-Feb-08 26-Aug-08 25-Sep-08
Actual
Plan 73,313.50 31-Jan-08 7-Feb-08 14-Feb-08 28-Feb-08 26-Aug-08 25-Sep-08
Actual
Plan 73,313.50 31-Jan-08 7-Feb-08 14-Feb-08 28-Feb-08 26-Aug-08 25-Sep-08
Contract ImplementationContract Finalization
42439.xls 23 of 44 2/11/2008 1:40 PM
Procurement Plan-Works
Rehabilitation of Schools and PHC
Water Supply to Institutions
Reconstruction & New Construction of Facilities
Oniwaya,Akerele and Owo Streets of Agege Slum community
Construction of 3 Schools at Iwaya in Lagos City
Construction of Water Supply facilities for Schools and PHC at Bariga, Badia and Makoko
Construction of Water Supply facilities for Schools and PHC at Ilaje, Amukoko and Itire
Rehabilitation of Schools (7 Nos) and Clinics (3 Nos)
Construction of Boreholes at 3 locations in Slum Area, Lagos
Construction of 2 Schools at Ilaje in Lagos City
Construction of 2 Schools at Bariga in Lagos City
Construction of 2 Schools at Bariga and Gbagada in Lagos City
Construction of 1 School at Ajegunle in Lagos City
Construction of Water Supply facilities for Schools, PHC and Community Hall at Ajegunle, Iwaya & Agege
Actual
Plan 73,313.50 31-Jan-08 7-Feb-08 14-Feb-08 28-Feb-08 26-Aug-08 25-Sep-08
Actual
Plan 800,000.00 24-Aug-07 31-Aug-07 27-Aug-07 10-Sep-07 8-Mar-08 7-Apr-08
Actual 482,643.69 04-Dec-07
Plan 100,000.0016-Apr-08 23-Apr-08 30-Apr-08 14-May-08 10-Nov-08 10-Dec-08
Actual
Plan 100,000.0016-Apr-08 23-Apr-08 30-Apr-08 14-May-08 10-Nov-08 10-Dec-08
Actual
Plan 120,000.00 16-Apr-08 23-Apr-08 30-Apr-08 14-May-08 10-Nov-08 10-Dec-08
Actual
Plan 7,046,688.84 4-Apr-08 11-Apr-08 18-Apr-08 2-May-08 28-Dec-08 27-Jan-09
Actual
Plan 2,825,821.86 4-Apr-08 11-Apr-08 18-Apr-08 2-May-08 28-Dec-08 27-Jan-09
Actual
Plan 4,546,201.75 4-Apr-08 11-Apr-08 18-Apr-08 2-May-08 28-Dec-08 27-Jan-09
Actual
Plan 3,531,396.40 4-Apr-08 11-Apr-08 18-Apr-08 2-May-08 28-Dec-08 27-Jan-09
Actual
Plan 3,540,940.08 4-Apr-08 11-Apr-08 18-Apr-08 2-May-08 28-Dec-08 27-Jan-09
Actual42439.xls 24 of 44 2/11/2008 1:40 PM
Procurement Plan-Works
Drainage Component
Deferred Maintenance of Drainage Channels
Construction of Market at Amukoko
Construction of 1 No. Market at Ilaje and Itire, 1 No. Public Toilet at Itire
Installation of Street light in all slum communities
Construction of One Primary Health Center at Agege
Construction of 2 Nos. Fish smoking facilities at Ilaje and Makoko
Construction of Roads and Street Drains in all slum communities
Construction of Two Primary Health Centers at Amukoko and Badia
Construction of One Primary Health Center at Bariga One Community Hall at Iwaya
Construction of 2 Schools at Badia in Lagos City
Construction of 2 Schools at Amukoko and Badia in Lagos City
Plan 3,221,545.54 4-Apr-08 11-Apr-08 18-Apr-08 2-May-08 28-Dec-08 27-Jan-09
Actual
Plan 2,354,008.45 4-Apr-08 11-Apr-08 18-Apr-08 2-May-08 28-Dec-08 27-Jan-09
Actual
Plan 7,000,000.00 3-Aug-08 10-Aug-08 17-Aug-08 31-Aug-08 28-Apr-09 28-May-09
Actual
Plan 25,000,000.00 2-Dec-08 9-Dec-08 16-Dec-08 30-Dec-08 27-Aug-09 26-Sep-09
Actual
Plan 800,000.00 24-Dec-07 31-Dec-07 7-Jan-08 21-Jan-08 17-Oct-08 16-Nov-08
Actual 888,041.40 16-Nov-07 21-Dec-07
Plan 980,000.00 24-Dec-07 31-Dec-07 7-Jan-08 21-Jan-08 17-Oct-08 16-Nov-08
Actual 1,003,907.23 15-Nov-07 18-Dec-07
Plan 221,993.00 30-Jan-08 6-Feb-08 13-Feb-08 27-Feb-08 24-Oct-08 23-Nov-08
Actual
Plan 548,125.81 30-Jan-08 6-Feb-08 13-Feb-08 27-Feb-08 24-Oct-08 23-Nov-08
Actual
Plan 596,637.03 30-Jan-08 6-Feb-08 13-Feb-08 27-Feb-08 24-Oct-08 23-Nov-08
Actual
Plan 900,000.00 24-May-08 31-May-08 7-Jun-08 21-Jun-08 16-Feb-09 18-Mar-09
Actual
42439.xls 25 of 44 2/11/2008 1:40 PM
Procurement Plan-Works
Construction of Drainage Channels
Solid Waste Management Component
Evacuation of Ilegal Dump Sites
Construction of Ogba channel
Construction of Amukoko/ Alafia Channel
Evacuation of ilegal dump sites in Lagos City (location - Obele Oniwala)
Maintenance of Surulere Channel (System 5)
Maintenance of Iganmu Channel (System 5)
Maintenance of Ajegunle Channel (System 5)
Construction of Gbagada/ Bariga Channel
Construction of Elere Channel
Maintenance of Igbobi Channel (System 2)
Evacuation of ilegal dump sites at Bolaji Omupo, Oba-Ogunji, Opebi and Ajah
Plan 3,400,000.00 15-Apr-08 22-Apr-08 29-Apr-08 13-May-08 8-May-09 7-Jun-09
Actual
Plan 3,880,000.00 15-Apr-08 22-Apr-08 29-Apr-08 13-May-08 8-May-09 7-Jun-09
Actual
Plan 8,700,000.00 15-Apr-08 22-Apr-08 29-Apr-08 13-May-08 8-May-09 7-Jun-09
Actual
Plan 3,470,000.00 15-Apr-08 22-Apr-08 29-Apr-08 13-May-08 8-May-09 7-Jun-09
Actual
Plan 3,430,000.00 2-Jun-08 9-Jun-08 16-Jun-08 30-Jun-08 25-Jun-09 25-Jul-09
Actual
Plan 3,780,000.00 2-Jun-08 9-Jun-08 16-Jun-08 30-Jun-08 25-Jun-09 25-Jul-09
Actual
Plan 2,190,000.00 2-Jun-08 9-Jun-08 16-Jun-08 30-Jun-08 25-Jun-09 25-Jul-09
Actual
Plan 1,800,000.00 2-Jun-08 9-Jun-08 16-Jun-08 30-Jun-08 25-Jun-09 25-Jul-09
Actual
Plan 700,000.00 18-Nov-07 25-Nov-07 2-Dec-07 16-Dec-07 13-Jun-08 13-Jul-08
Actual 588,942.9019-Nov-07 18-Dec-07
Plan 700,000.00 18-Nov-07 25-Nov-07 2-Dec-07 16-Dec-07 13-Jun-08 13-Jul-08
42439.xls 26 of 44 2/11/2008 1:40 PM
Procurement Plan-Works
Communal Waste Depots (CWD)
Transfer Loading Stations (TLS)
LandFill Management
Total Cost
Construction of CWD at various locations ( Ilu Eri, Agunlejika, Olatunde Onimole, Berger and Iponri)
Landfill Management at Olusosun, Abule-Egba and Solus
Lagos City (location - Obele Oniwala)
Evacuation of ilegal dump sites in Lagos City (location - Ikate Olaogun)
Evacuation of ilegal dump sites at Ilu- Eri, Festac , Mechanic Village (Ajegunle) and Agunlejika
Construction of Waste Transfer Station at Marini
Construction of Waste Transfer Station at Oba Ogunji
Actual 739,955.79 16-Nov-07 21-Jan-08
Plan 960,000.00 18-Nov-07 25-Nov-07 2-Dec-07 16-Dec-07 13-Jun-08 13-Jul-08
Actual 28-Dec-07
Plan 600,000.00 18-Nov-07 25-Nov-07 2-Dec-07 16-Dec-07 13-Jun-08 13-Jul-08
Actual 660,664.1619-Nov-07 05-Dec-07
Plan 600,000.00 6-May-08 13-May-08 20-May-08 3-Jun-08 31-Oct-08 30-Nov-08
Actual
Plan 4,700,000.00 14-Jun-08 21-Jun-08 28-Jun-08 12-Jul-08 7-Jul-09 6-Aug-09
Actual
Plan 4,650,000.00 14-Jun-08 21-Jun-08 28-Jun-08 12-Jul-08 7-Jul-09 6-Aug-09
Actual
Plan 950,000.00 18-Nov-07 25-Nov-07 2-Dec-07 16-Dec-07 10-Dec-08 9-Jan-09
Actual 682,225.00 14-Nov-07 18-Dec-07
Plan 110,080,991.10
Actual 5,982,434.85
42439.xls 27 of 44 2/11/2008 1:40 PM
Procurement Plan-Works Country/Organisation:Project/Programme:
Loan #: 4219
Description*
List of Contracts
Slum Upgrading Component
Water Supply to Slum Communities
Construction of 3 Boreholes at Oniwaya,Akerele and Owo Streets of Agege
Construction of 3 Boreholes at Smith,Kushimo/Odebode and Adetayo Streets of
Itire/Ijeshatedo Slum community
Construction of 3 Boreholes at Okeyemi,Ronke and Osindero Streets of Itire/Ijeshatedo Slum
community
Construction of 4 Boreholes atOlayinka,Shofolahan,Ijesha Rd and Adebayo
Rufai Streets of Itire/Ijeshatedo Slum
Construction of 3 Boreholes at Kasumu,Agege Motor Rd and Olusanya Streets of Agege Slum
community
Construction of 13 Nos. Boreholes at Ilaje, Iwaya and Makoko
Construction of 11 Nos. Boreholes at Agege and Itire
Construction of 3 Boreholes at Fadairo,Osinfowokan and Olubodun Streets of
Itire/Ijeshatedo Slum community
Norm Duration of Proc Steps
Construction of remaining Boreholes in the slum communities
Construction of 11 Nos. Boreholes at Badia and Ajegule
#######
FinalCost
250,000.00
250,000.00
300,000.00
73,313.50
73,313.50
73,313.50
97,751.34
73,313.50
73,313.5042439.xls 28 of 44 2/11/2008 1:40 PM
Procurement Plan-Works
Rehabilitation of Schools and PHC
Water Supply to Institutions
Reconstruction & New Construction of Facilities
Oniwaya,Akerele and Owo Streets of Agege Slum community
Construction of 3 Schools at Iwaya in Lagos City
Construction of Water Supply facilities for Schools and PHC at Bariga, Badia and Makoko
Construction of Water Supply facilities for Schools and PHC at Ilaje, Amukoko and Itire
Rehabilitation of Schools (7 Nos) and Clinics (3 Nos)
Construction of Boreholes at 3 locations in Slum Area, Lagos
Construction of 2 Schools at Ilaje in Lagos City
Construction of 2 Schools at Bariga in Lagos City
Construction of 2 Schools at Bariga and Gbagada in Lagos City
Construction of 1 School at Ajegunle in Lagos City
Construction of Water Supply facilities for Schools, PHC and Community Hall at Ajegunle, Iwaya & Agege
73,313.50
800,000.00
100,000.00
100,000.00
120,000.00
7,046,688.84
2,825,821.86
4,546,201.75
3,531,396.40
3,540,940.08
42439.xls 29 of 44 2/11/2008 1:40 PM
Procurement Plan-Works
Drainage Component
Deferred Maintenance of Drainage Channels
Construction of Market at Amukoko
Construction of 1 No. Market at Ilaje and Itire, 1 No. Public Toilet at Itire
Installation of Street light in all slum communities
Construction of One Primary Health Center at Agege
Construction of 2 Nos. Fish smoking facilities at Ilaje and Makoko
Construction of Roads and Street Drains in all slum communities
Construction of Two Primary Health Centers at Amukoko and Badia
Construction of One Primary Health Center at Bariga One Community Hall at Iwaya
Construction of 2 Schools at Badia in Lagos City
Construction of 2 Schools at Amukoko and Badia in Lagos City
3,221,545.54
2,354,008.45
7,000,000.00
25,000,000.00
800,000.00
980,000.00
221,993.00
548,125.81
596,637.03
900,000.00
42439.xls 30 of 44 2/11/2008 1:40 PM
Procurement Plan-Works
Construction of Drainage Channels
Solid Waste Management Component
Evacuation of Ilegal Dump Sites
Construction of Ogba channel
Construction of Amukoko/ Alafia Channel
Evacuation of ilegal dump sites in Lagos City (location - Obele Oniwala)
Maintenance of Surulere Channel (System 5)
Maintenance of Iganmu Channel (System 5)
Maintenance of Ajegunle Channel (System 5)
Construction of Gbagada/ Bariga Channel
Construction of Elere Channel
Maintenance of Igbobi Channel (System 2)
Evacuation of ilegal dump sites at Bolaji Omupo, Oba-Ogunji, Opebi and Ajah
3,400,000.00
3,880,000.00
8,700,000.00
3,470,000.00
3,430,000.00
3,780,000.00
2,190,000.00
1,800,000.00
700,000.00
700,000.0042439.xls 31 of 44 2/11/2008 1:40 PM
Procurement Plan-Works
Communal Waste Depots (CWD)
Transfer Loading Stations (TLS)
LandFill Management
Total Cost
Construction of CWD at various locations ( Ilu Eri, Agunlejika, Olatunde Onimole, Berger and Iponri)
Landfill Management at Olusosun, Abule-Egba and Solus
Lagos City (location - Obele Oniwala)
Evacuation of ilegal dump sites in Lagos City (location - Ikate Olaogun)
Evacuation of ilegal dump sites at Ilu- Eri, Festac , Mechanic Village (Ajegunle) and Agunlejika
Construction of Waste Transfer Station at Marini
Construction of Waste Transfer Station at Oba Ogunji
960,000.00
600,000.00
600,000.00
4,700,000.00
4,650,000.00
950,000.00
110,080,991.10
0.00
42439.xls 32 of 44 2/11/2008 1:40 PM
Procurement Plan-Consultants 2
Country/Organisation: NIGERIA / LAGOS METROPOLITAN DEVELOPMENT AND GOVERNANCE PROJECTFor Contracts under projects approved before the May 2002 GuidelinesProject/Programme: LMDGP If Post-Review, No-objection Dates are not needed
Loan #: 4219Contract
Type
Description*Selection Method
Lumpsumor
Time-Based
Estimated Amount
in US$ ’000
Prior/Post Review
Plan vs.
Actual
Prep & Submissionby Ex Ag
No-objectionDate
On-line UNDBGatewayNat Press
Lead-time before
shortlist
SubmissionDate
No-objectionDate
Plan 3 - 6 wks 1 - 2 wks 1 - 1.5 wks 2 wks 1 - 2 wks
Actual
List of ContractsQCBS Lump Sum 1,300,000.00 Prior Plan 14-Sep-05 24-Sep-05 1-Oct-05 15-Oct-05 14-Nov-05 28-Nov-05
QCBS Lump Sum Prior Actual 8-Aug-05 22-Aug-05 31-Aug-05 14-Sep-05 21-Nov-05 28-Nov-05
*SS Time based 820,000.00 Prior Plan NA NA NA NA NA NA
Actual
QCBS Lump Sum 2,500,000.00 Prior Plan 31-Jul-07 10-Aug-07 17-Aug-07 31-Aug-07 20-Sep-07 4-Oct-07
Actual06-Apr-07 20-Apr-07 27-Apr-07 23-May-07 19-Sep-07 26-Sep-07
QCBS Lump sum 3,500,000.00 Prior Plan 29-May-07 8-Jun-07 15-Jun-07 29-Jun-07 19-Jul-07 2-Aug-07
Actual27-Dec-06 26-Jan-07 16-May-07 24-May-07
QCBS Lump sum 450,000.00 Prior Plan 20-Dec-06 30-Dec-06 6-Jan-07 20-Jan-07 9-Feb-07 23-Feb-07
Actual23-Jan-07 22-Feb-07 14-Mar-07 11-Apr-07
CQ Lump Sum 180,000.00 Post Plan NA NA 12-Mar-08 2-Apr-08 NA NA
Actual
QCBS Time based 500,000.00 Prior Plan 30-Jul-08 9-Aug-08 16-Aug-08 30-Aug-08 19-Sep-08 3-Oct-08
Actual
QCBS Lump sum 400,000.00 Prior Plan 30-Jul-07 9-Aug-07 16-Aug-07 30-Aug-07 8-Aug-07 13-Dec-07
20-Mar-07 16-Apr-07 04-Oct-07 **13-Dec-07
ShortList
Consultancy Services for MTEF
Hydraulic Modelling and Drainage studies on selected drainage basins and techical assistance to ODS
Transaction Advisor for Design, Build and Operate (DBO) and Landfills Investigations/ Preliminary Designs for Lagos
Environmental and Social Assessment (ESA) -Solid Waste Componenet
Urban Upgrading: Supervision of Civil Works in the Slum Areas
Urban Upgrading: Engineering Design of Roads in the Slum Areas
Preparation Request for Proposals
*Integrated Supervision of Civil Works Invetment in Drainage, Solid Waste Management and Slum Upgrading
Norm Duration of Proc Steps
Completion of Design of Integrated Civil Works investment in Drainage, Solid Waste Management and Slum Upgrading
Request for EOI(where required)
42439.xls 33 of 44 2/11/2008 1:40 PM
Procurement Plan-Consultants 2
QCBS Lump sum 300,000.00 Prior Plan 30-Jul-07 9-Aug-07 16-Aug-07 30-Aug-07 19-Sep-07 3-Oct-07
Actual20-Mar-07 16-Apr-07
QCBS Lump sum 400,000.00 Prior Plan 30-Nov-07 10-Dec-07 17-Dec-07 31-Dec-07 20-Jan-08 3-Feb-08
Actual ****21-Dec-07 1-Feb-08
CQ Lump sum 180,000.00 Post Plan NA NA NA NA NA NA
Actual22-Nov-07 27-Dec-07
IC Lump sum 30,000.00 Post Plan 30-Jun-08 10-Jul-08 NA NA 14-Jul-08 NA
Actual
CQ Lump sum 150,000.00 Post Plan NA NA NA NA NA NA
28-Mar-07 23-Apr-07
CQ Lump sum 100,000.00 Post Plan NA NA NA NA NA NA
Actual
IC Lump sum 90,000.00 Post Plan NA NA NA NA NA NA
Actual
IC Lump sum 80,000.00 Post Plan 30-Jun-08 10-Jul-08 NA NA 14-Jul-08 NA
Actual
IC Lump sum 50,000.00 Post Plan 12-Nov-07 22-Nov-07 NA NA 26-Nov-07 NA
Actual
IC Lump sum 150,000.00 Post Plan 30-Apr-07 10-May-07 NA NA 14-May-07 NA
Actual
IC Lump sum 80,000.00 Post Plan 30-Apr-07 10-May-07 NA NA 14-May-07 NA
Actual
IC Lump sum 80,000.00 Post Plan 12-Nov-07 22-Nov-07 NA NA 26-Nov-07 NA
Actual 18-Sep-07 23-Oct-07
IC Lump sum 60,000.00 Post Plan 30-Apr-07 10-May-07 NA NA 14-May-07 NA
Actual
IC Lump sum 15,000.00 Post Plan 16-Mar-08 26-Mar-08 NA NA 30-Mar-08 NA
Transformation of PSSDC-Consultancy Firm
GIS Data Collection and Analysis
Update of public Finanace legislations
Procument Consultant (Consultancy Services)
Improving Budget Execution and Treasury management (International
Public Expenditure Tracking (International)
Project Director - Project Management Services
Development of Mechanical Specifications for Drainage/ Solid
M & E-Individual Consultant
Procument Consultant ( Works & Goods )
Transformation of PSSDC-Individual Firm
Development of poverty map
Comprehensive review of IFMIS implementation to date
Information, Communication and Education Strategies and Implementation
42439.xls 34 of 44 2/11/2008 1:40 PM
Procurement Plan-Consultants 2
Actual
IC Lump sum 30,000.00 Post Plan 12-Jun-08 22-Jun-08 NA NA 26-Jun-08 NA
Actual
Total Cost 11,945,000.00 Plan
Actual
• All Terms of Reference will be prior reviewed by the technical specialists in IDA’s task Team
Row 1 is ongoing project.
* The Bank granted No Objection to sole source the Design Consultant to undertake the supervision assignment** There was an earlier NOB dated 9th Oct. 2007 which was ammended with that of 13th Dec. 2007*** The Bank granted No Objection to engagement of a short term Procurement consultant on sole source basis**** There was an earlier advert publication on 2nd Dec 2007
Computation of State GDP
Specifications for Drainage/ Solid waste Equipment
42439.xls 35 of 44 2/11/2008 1:40 PM
Procurement Plan-Consultants 2
Country/Organisation:Project/Programme:
Loan #: 4219
Description*
List of Contracts
Consultancy Services for MTEF
Hydraulic Modelling and Drainage studies on selected drainage basins and techical assistance to ODS
Transaction Advisor for Design, Build and Operate (DBO) and Landfills Investigations/ Preliminary Designs for Lagos
Environmental and Social Assessment (ESA) -Solid Waste Componenet
Urban Upgrading: Supervision of Civil Works in the Slum Areas
Urban Upgrading: Engineering Design of Roads in the Slum Areas
*Integrated Supervision of Civil Works Invetment in Drainage, Solid Waste Management and Slum Upgrading
Norm Duration of Proc Steps
Completion of Design of Integrated Civil Works investment in Drainage, Solid Waste Management and Slum Upgrading
Plan vs.
Actual
InvitationDate
Submission/Opening
Date
SubmissionEvaluationReport (T)
No-objectionEvaluationReport (T)
Opening Financial Proposals
PreparationEval Report
(T) (F)Negotiations (N)
Plan 4 to 12 wks 2 - 3 wks 0.5 - 2 wks 2 wks 1 - 2 wks 2 wks
Actual
Plan 5-Dec-05 3-Feb-06 17-Feb-06 27-Feb-06 13-Mar-06 27-Mar-06 10-Apr-06
Actual 29-Nov-05 27-Jan-06 8-Feb-06 27-Apr-06 17-May-06 20-May-06 23-May-06
Plan NA NA NA NA NA NA 6-Nov-07
Actual
7-May-07
Plan 14-Oct-07 13-Dec-07 27-Dec-07 6-Jan-08 20-Jan-08 3-Feb-08 17-Feb-08
Actual05-Oct-07 14-Nov-07 18-Dec-07
Plan 12-Aug-07 11-Oct-07 25-Oct-07 4-Nov-07 18-Nov-07 2-Dec-07 16-Dec-07
Actual26-May-07 06-Sep-07 07-Nov-07 16-Nov-07 16-Nov-07
Plan 5-Mar-07 4-May-07 18-May-07 28-May-07 11-Jun-07 25-Jun-07 9-Jul-07
Actual13-Apr-07 21-May-07 26-Jul-07 02-Aug-07 23-Aug-07 11-Sep-07 27-Sep-07
Plan 16-Apr-08 16-May-08 NA NA NA NA 6-Jun-08
Actual
Plan 13-Oct-08 12-Dec-08 26-Dec-08 5-Jan-09 19-Jan-09 2-Feb-09 16-Feb-09
Actual
Plan 23-Dec-07 21-Feb-08 6-Mar-08 16-Mar-08 30-Mar-08 13-Apr-08 27-Apr-08
23-Oct-07 26-Nov-07 02-Jan-08
ConsultantProposals
Proposal Evaluation and Negotiation for Projects after May 2002Technical (T) & Financial (F) and Negotions (N)
42439.xls 36 of 44 2/11/2008 1:40 PM
Procurement Plan-Consultants 2
Transformation of PSSDC-Consultancy Firm
GIS Data Collection and Analysis
Update of public Finanace legislations
Procument Consultant (Consultancy Services)
Improving Budget Execution and Treasury management (International
Public Expenditure Tracking (International)
Project Director - Project Management Services
Development of Mechanical Specifications for Drainage/ Solid
M & E-Individual Consultant
Procument Consultant ( Works & Goods )
Transformation of PSSDC-Individual Firm
Development of poverty map
Comprehensive review of IFMIS implementation to date
Information, Communication and Education Strategies and Implementation
Plan 13-Oct-07 12-Dec-07 26-Dec-07 5-Jan-08 19-Jan-08 26-Dec-07 9-Jan-08
Actual
Plan 13-Feb-08 13-Apr-08 27-Apr-08 7-May-08 21-May-08 4-Jun-08 18-Jun-08
Actual
Plan 23-Nov-07 27-Dec-07 NA NA NA NA 6-Feb-08
Actual
Plan 21-Jul-08 20-Aug-08 3-Sep-08 13-Sep-08 20-Aug-08 3-Sep-08 17-Sep-08
Actual
Plan 20-Apr-07 20-May-07 NA NA NA NA 5-Mar-08
Plan 4-Apr-08 4-May-08 NA NA NA NA 9-Jul-08
Actual
Plan 20-Mar-08 19-Apr-08 NA NA NA NA 18-Jun-08
Actual
Plan 4-Apr-08 4-May-08 NA NA NA NA 9-Jul-08
Actual
Plan 5-Feb-08 6-Mar-08 NA NA NA NA 2-May-08
Actual
Plan 21-May-07 20-Jun-07 4-Jul-07 14-Jul-07 20-Jun-07 4-Jul-07 18-Jul-07
Actual
Plan 21-May-07 20-Jun-07 4-Jul-07 14-Jul-07 20-Jun-07 4-Jul-07 18-Jul-07
Actual
Plan 3-Dec-07 2-Jan-08 16-Jan-08 26-Jan-08 2-Jan-08 16-Jan-08 30-Jan-08
Actual
Plan 21-May-07 20-Jun-07 4-Jul-07 14-Jul-07 20-Jun-07 4-Jul-07 18-Jul-07
Actual
Plan 6-Apr-08 6-May-08 20-May-08 30-May-08 6-May-08 20-May-08 3-Jun-0842439.xls 37 of 44 2/11/2008 1:40 PM
Procurement Plan-Consultants 2
Total Cost
• All Terms of Reference will be prior reviewed by the technical specialists in IDA’s task Team
Row 1 is ongoing project.
* The Bank granted No Objection to sole source the Design Consultant to undertake the supervision assignment** There was an earlier NOB dated 9th Oct. 2007 which was ammended with that of 13th Dec. 2007*** The Bank granted No Objection to engagement of a short term Procurement consultant on sole source basis**** There was an earlier advert publication on 2nd Dec 2007
Computation of State GDP
Specifications for Drainage/ Solid waste Equipment
Actual
Plan 3-Jul-08 2-Aug-08 16-Aug-08 26-Aug-08 2-Aug-08 16-Aug-08 30-Aug-08
Actual
Plan
Actual
42439.xls 38 of 44 2/11/2008 1:40 PM
Procurement Plan-Consultants 2
Country/Organisation:Project/Programme:
Loan #: 4219
Description*
List of Contracts
Consultancy Services for MTEF
Hydraulic Modelling and Drainage studies on selected drainage basins and techical assistance to ODS
Transaction Advisor for Design, Build and Operate (DBO) and Landfills Investigations/ Preliminary Designs for Lagos
Environmental and Social Assessment (ESA) -Solid Waste Componenet
Urban Upgrading: Supervision of Civil Works in the Slum Areas
Urban Upgrading: Engineering Design of Roads in the Slum Areas
*Integrated Supervision of Civil Works Invetment in Drainage, Solid Waste Management and Slum Upgrading
Norm Duration of Proc Steps
Completion of Design of Integrated Civil Works investment in Drainage, Solid Waste Management and Slum Upgrading
Plan vs.
ActualSubmission Date
No-objection Date
Contract Amount in US$ ’000
Contract Award Date
ContractAdvert
Contract Signature
Plan 1 - 2 wks 1 - 2 wks 1 wk 1 - 3 wks
Actual
Plan 20-Apr-06 4-May-06 1,300,000.00 11-May-06 14-May-06 1-Jun-06
Actual 16-Oct-06 23-Oct-06 809,397.56 23-Oct-06 16-Nov-06 6-Nov-06
Plan 16-Nov-07 30-Nov-07 820,000.00 7-Dec-07 10-Dec-07 28-Dec-07
Actual
6-Jul-07 10-Jul-07 1,125,033.73 18-Oct-07 08-Nov-07
Plan 27-Feb-08 12-Mar-08 2,500,000.00 19-Mar-08 22-Mar-08 9-Apr-08
Actual
Plan 26-Dec-07 9-Jan-08 3,500,000.00 16-Jan-08 19-Jan-08 6-Feb-08
Actual
Plan 19-Jul-07 2-Aug-07 450,000.00 9-Aug-07 12-Aug-07 30-Aug-07
Actual455,131.67 02-Oct-07 02-Oct-07
Plan NA NA 180,000.00 20-Jun-08 27-Jun-08 4-Jul-08
Actual
Plan 26-Feb-09 12-Mar-09 500,000.00 19-Mar-09 22-Mar-09 9-Apr-09
Actual
Plan 7-May-08 21-May-08 400,000.00 28-May-08 31-May-08 18-Jun-08
Contract FinalizationDraft Contract
42439.xls 39 of 44 2/11/2008 1:40 PM
Procurement Plan-Consultants 2
Transformation of PSSDC-Consultancy Firm
GIS Data Collection and Analysis
Update of public Finanace legislations
Procument Consultant (Consultancy Services)
Improving Budget Execution and Treasury management (International
Public Expenditure Tracking (International)
Project Director - Project Management Services
Development of Mechanical Specifications for Drainage/ Solid
M & E-Individual Consultant
Procument Consultant ( Works & Goods )
Transformation of PSSDC-Individual Firm
Development of poverty map
Comprehensive review of IFMIS implementation to date
Information, Communication and Education Strategies and Implementation
Plan 19-Jan-08 2-Feb-08 300,000.00 9-Feb-08 12-Feb-08 1-Mar-08
Actual
Plan 28-Jun-08 12-Jul-08 400,000.00 19-Jul-08 22-Jul-08 9-Aug-08
Actual
Plan NA NA 180,000.00 20-Feb-08 27-Feb-08 12-Mar-08
Actual
Plan 27-Sep-08 11-Oct-08 30,000.00 18-Oct-08 NA 8-Nov-08
Actual
Plan NA NA 150,000.00 19-Mar-08 26-Mar-08 9-Apr-08
Plan NA NA 100,000.00 23-Jul-08 30-Jul-08 13-Aug-08
Actual
Plan NA NA 90,000.00 2-Jul-08 NA 23-Jul-08
Actual
Plan NA NA 80,000.00 16-Jul-08 NA 6-Aug-08
Actual
Plan NA NA 50,000.00 9-May-08 NA 30-May-08
Actual
Plan 28-Jul-07 11-Aug-07 150,000.00 18-Aug-07 NA 8-Sep-07
Actual 129,166.66 24-Sep-07
Plan 28-Jul-07 11-Aug-07 80,000.00 18-Aug-07 NA 8-Sep-07
Actual 26-Jul-07 ***09-Aug-07 16,800.00 13-Aug-07
Plan 9-Feb-08 23-Feb-08 80,000.00 1-Mar-08 NA 22-Mar-08
Actual
Plan 28-Jul-07 11-Aug-07 60,000.00 18-Aug-07 NA 8-Sep-07
Actual 55,033.33 06-Nov-07
Plan 13-Jun-08 27-Jun-08 15,000.00 4-Jul-08 NA 25-Jul-0842439.xls 40 of 44 2/11/2008 1:40 PM
Procurement Plan-Consultants 2
Total Cost
• All Terms of Reference will be prior reviewed by the technical specialists in IDA’s task Team
Row 1 is ongoing project.
* The Bank granted No Objection to sole source the Design Consultant to undertake the supervision assignment** There was an earlier NOB dated 9th Oct. 2007 which was ammended with that of 13th Dec. 2007*** The Bank granted No Objection to engagement of a short term Procurement consultant on sole source basis**** There was an earlier advert publication on 2nd Dec 2007
Computation of State GDP
Specifications for Drainage/ Solid waste Equipment
Actual
Plan 9-Sep-08 23-Sep-08 30,000.00 30-Sep-08 NA 21-Oct-08
Actual
Plan 11,945,000.00
Actual 2,389,562.96
42439.xls 41 of 44 2/11/2008 1:40 PM
Procurement Plan-Consultants 2
Country/Organisation:Project/Programme:
Loan #: 4219
Description*
List of Contracts
Consultancy Services for MTEF
Hydraulic Modelling and Drainage studies on selected drainage basins and techical assistance to ODS
Transaction Advisor for Design, Build and Operate (DBO) and Landfills Investigations/ Preliminary Designs for Lagos
Environmental and Social Assessment (ESA) -Solid Waste Componenet
Urban Upgrading: Supervision of Civil Works in the Slum Areas
Urban Upgrading: Engineering Design of Roads in the Slum Areas
*Integrated Supervision of Civil Works Invetment in Drainage, Solid Waste Management and Slum Upgrading
Norm Duration of Proc Steps
Completion of Design of Integrated Civil Works investment in Drainage, Solid Waste Management and Slum Upgrading
Plan vs.
Actual
MobilizationAdvancePayment
DraftReport
FinalReport
FinalCost
Plan
Actual
Plan 1-Jul-06 15-Aug-06 27-Jan-07 1,300,000.00
Actual 25-Feb-2007 16-May-07 31-Jul-07
Plan 27-Jan-08 24-Aug-08 20-Jul-09 820,000.00
Actual
Plan 9-May-08 4-May-09 29-Apr-10 2,500,000.00
Actual
Plan 7-Mar-08 3-Sep-08 24-Sep-08 3,500,000.00
Actual
Plan 29-Sep-07 27-Mar-08 17-Apr-08 450,000.00
Actual
Plan 18-Jul-08 16-Oct-08 11-Sep-09 180,000.00
Actual
Plan 9-May-09 5-Nov-09 3-Jul-10 500,000.00
Actual
Plan 18-Jul-08 14-Jan-09 4-Feb-09 400,000.00
Contract Implementation
42439.xls 42 of 44 2/11/2008 1:40 PM
Procurement Plan-Consultants 2
Transformation of PSSDC-Consultancy Firm
GIS Data Collection and Analysis
Update of public Finanace legislations
Procument Consultant (Consultancy Services)
Improving Budget Execution and Treasury management (International
Public Expenditure Tracking (International)
Project Director - Project Management Services
Development of Mechanical Specifications for Drainage/ Solid
M & E-Individual Consultant
Procument Consultant ( Works & Goods )
Transformation of PSSDC-Individual Firm
Development of poverty map
Comprehensive review of IFMIS implementation to date
Information, Communication and Education Strategies and Implementation
Plan 31-Mar-08 27-Sep-08 18-Oct-08 300,000.00
Actual
Plan 8-Sep-08 7-Mar-09 28-Mar-09 400,000.00
Actual
Plan 11-Apr-08 8-Oct-08 29-Oct-08 180,000.00
Actual
Plan 8-Dec-08 6-Jun-09 27-Jun-09 30,000.00
Actual
Plan 9-May-08 5-Nov-08 26-Nov-08 150,000.00
Plan 12-Sep-08 11-Mar-09 1-Apr-09 100,000.00
Actual
Plan 22-Aug-08 18-Feb-09 11-Mar-09 90,000.00
Actual
Plan 5-Sep-08 4-Mar-09 25-Mar-09 80,000.00
Actual
Plan 29-Jun-08 26-Dec-08 16-Jan-09 50,000.00
Actual
Plan 8-Oct-07 2-Oct-08 23-Oct-08 150,000.00
Actual
Plan 8-Oct-07 2-Oct-08 23-Oct-08 80,000.00
Actual
Plan 21-Apr-08 16-Apr-09 7-May-09 80,000.00
Actual
Plan 8-Oct-07 2-Oct-08 23-Oct-08 60,000.00
Actual
Plan 24-Aug-08 20-Feb-09 13-Mar-09 15,000.0042439.xls 43 of 44 2/11/2008 1:40 PM
Procurement Plan-Consultants 2
Total Cost
• All Terms of Reference will be prior reviewed by the technical specialists in IDA’s task Team
Row 1 is ongoing project.
* The Bank granted No Objection to sole source the Design Consultant to undertake the supervision assignment** There was an earlier NOB dated 9th Oct. 2007 which was ammended with that of 13th Dec. 2007*** The Bank granted No Objection to engagement of a short term Procurement consultant on sole source basis**** There was an earlier advert publication on 2nd Dec 2007
Computation of State GDP
Specifications for Drainage/ Solid waste Equipment
Actual
Plan 20-Nov-08 19-May-09 9-Jun-09 30,000.00
Actual
Plan 11,945,000.00
Actual
42439.xls 44 of 44 2/11/2008 1:40 PM