production cost model data work group (pdwg) in-person meeting - pdwg... · nrel has new hourly...

29
Production Cost Model Data Work Group (PDWG) In-Person Meeting - Day 1 August 14, 2019 Jamie Austin–PDWG Chair Kevin Harris–PDWG Vice Chair Tyler Butikofer–WECC Liaison

Upload: others

Post on 25-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

Production Cost Model

Data Work Group

(PDWG) In-Person

Meeting - Day 1

August 14, 2019

Jamie Austin–PDWG Chair

Kevin Harris–PDWG Vice Chair

Tyler Butikofer–WECC Liaison

Page 2: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

▪ Day 1

• 2028 ADS PCM Phase 2 V2.0

◦ Testing of CCCTs Disaggregation

◦ Modify default Summer Time Simulation Settings

• PCM 2030 2-Yr Work Plan

• Process Diagram

• Other Topics warrant further conversation

• Dispatch Cost for wind, solar and Hydro

• What is the minimum up & down time and what should it be?

▪ Day 2

• ADS Data Development and Validation Manual (DDVM)

• Development of the 2030 ADS PCM

◦ Managing Electric Vehicle Load, Building Electrification

◦ Coincident Energy Year

◦ Modify the definition of “Regions/Areas

• Heat Rate Curves Update

◦ Managing Station Service

2

Overview

Page 3: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

▪ DS turned down approving date changes for summer de-rates, at the May, 2019 meeting. Proposed was to use “June through September” to “April through October”. It is intended to address previous concerns with the following approach:

▪ Working with PMWG and ABB, it was agreed that a more robust solution can be achieved through software modification by applying de-rates at the area level. The broader approach suggested in point 1 attempts to cover all geographic diversities and results in misconstruing representations in some areas.

3

Default simulation Summer Time

Schedule Potential Solutions

Page 4: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

▪ Build the 2030 ADS PCM dataset, starting

with the 2028 ADS PCM Phase 2 – V2.0

▪ Transmission Topology – work with SDWG to

compile a 2030 HS power flow case starting

with and export hour from the 2028 ADS

PCM Phase 2 – V2.0

▪ For resource definition, use resources

submitted to WECC L&R, in March 2020

4

PCM 2030 2-Yr Work Plan

Page 5: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

▪ Review “Draft” Work Plan

▪ Agree on Scope of Work for the 2030 Dataset? e.g.:

• Do we need to recalculate the Heat Rates?

• Should we change the Coincident Energy Shapes Year?

▪ Hold a series of informational meetings that would lead to prioritizing the updates

▪ Brainstorm assumptions, key processes and potential benefits and risk

▪ Timeline

• ADSTF is working on a process diagram, charting what would be required to build a new PCM dataset?

• Have PDWG validate and sign off on the ADSTF recommendation.

• Coordinate with WECC staff on their availability to support what needs to be done?

▪ Who is going to do what?

• What to be expected from PDWG stakeholders?

• What to be expected from WECC staff?

5

2030 ADS PCM “Draft” Work Plan

Page 6: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

▪ Dispatch Cost for wind, solar and Hydro

▪ What is the minimum up & down time and

what should it be?

6

Other Topics warrant further

conversation

Page 7: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

Production Cost Model

Data Work Group

(PDWG) In-Person

Meeting - Day 2

August 15, 2019

Jamie Austin–PDWG Chair

Kevin Harris–PDWG Vice Chair

Tyler Butikofer–WECC Liaison

Page 8: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

Demo:

Steven Wallace

Tyler Butikofer

8

ADS Data Development and

Validation Manual (DDVM)

Page 9: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

▪ Demonstration by Tyler Butikofer and Steven

Wallace

9

ADS Data Development and Validation

Manual (DDVM)

Page 10: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

Development of the 2030 ADS PCM

10

Page 11: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

Managing Electric Vehicle Load &

Building Electrification

11

Page 12: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

California 10 Million EV

Scenario Inputs

PCM Inputs for Preliminary Study

of Decarbonization

Richard Jensen

August 15, 2019

California Energy Commission

12

Page 13: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

What this is / is not…

• This is…

• The first cut at conducting

electrification scenarios

• 2030 only (for EV scenario)

and “simplistic” load build

• Built to meet 60% RPS req for

CA

• This is not…

• The final set of input assumptions and results

• An attempt to consider different or multiple EV charging profiles

• A WECC wide focused study

13

Page 14: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

• Spreadsheet tool developed by (retired) CEC staff

• Distributes user-defined number of EVs across CA

utilities based on 2015 DMV registration data

• Calculates annual energy demand by utility

• Different EV technologies considered within the tool

Load for 10mm EVs

14

Page 15: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

Load Shape used in PLEXOS

• 2018 CEDU hourly forecast – posted on CEC website

• Contains the hourly forecast for ~ 3.5mm EV’s – mid case

• Energy for 10mm EVs distributed across same shape

• Mean value of shape is .454

• EV load modeled on the demand side

0.000

0.200

0.400

0.600

0.800

1.000

14

63

92

51

38

71

84

92

31

12

77

33

23

53

69

74

15

94

62

15

08

35

54

56

00

76

46

96

93

17

39

37

85

58

31

7

Chronological Load EV Shape

0

0.2

0.4

0.6

0.8

1

1 9

17

25

33

41

49

57

65

73

81

89

97

10

5

11

3

12

1

12

9

13

7

14

5

15

3

16

1

Typical Week Load Shape

15

Page 16: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

Load Comparison

• CA 2030 Mid Case (280 TWh) load vs 10mm EV (306 TWh)

16

-

10,000

20,000

30,000

40,000

50,000

60,000

12

32

46

36

94

92

51

15

61

38

71

61

81

84

92

08

02

31

12

54

22

77

33

00

43

23

53

46

63

69

73

92

84

15

94

39

04

62

14

85

25

08

35

31

45

54

55

77

66

00

76

23

86

46

96

70

06

93

17

16

27

39

37

62

47

85

58

08

68

31

78

54

8

Me

gaw

atts

Base Case Load (MW) 10M EV Load (MW)

Page 17: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

• 60% of 26 TWh = 15.6 TWh

• Met with roughly 75% solar and 25% wind

• Capacity amount 7,900 MW total – all placed in CA

• CF may be a bit low for some technologies

• Results still under evaluation

• Offshore wind under consideration for next round of simulations

Preliminary RPS Build to meet CA requirement

17

Page 18: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

Questions or Comments?

Richard Jensen

[email protected]

916-654-4893

18

Page 19: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

▪ Coincident energy year is the base year for hourly profiles: load, wind, hydro (monthly), solar, pumping load, …

• Currently using 2009 w/exception: 2008 monthly hydro for 15 projects on the Columbia river for Jun-Aug

▪ It’s desired to preserve coincident, weather related behavior, between load and the various supply shapes

▪ NREL has new hourly wind and solar data for 2014

• Previously 2007-2013

▪ It’s difficult to get agreement as to what is the best year to use given:

• What year is best represents normal for all: areas load, hydro, wind, solar, pumping load …

◦ Geographic diversity yields normal in one area but abnormal in others

▪ Load Shapes - If we switch to a more recent base year how do we manage actual BTM PV generation, included in the hourly load shape?

19

Coincident Energy Year

Page 20: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

▪ Recommend using time-coincident wind & solar data with loads

▪ Hydro

• Should allow for dispatch to respond to variable generation (wind and solar)

• Much more work needs to be done to determine cost-effective approaches within hydro constraints and reliability

▪ Underlying correlation between wind and load is dynamic/complex, but using time-sync’d data implicitly covers this

▪ Actual (or modeled) hourly for at least one year

20

Modeling Variable Generation

Page 21: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

▪ Pros

• Much work been spent on developing and validating the Wind hourly shapes

• Much work been spent on developing and validating the Solar hourly shapes

▪ Pending Work

• Need to revisit & validate Load shapes, making sure EE, AAEE, PV, AAPV and EV are disaggregated and represented independently.

• Need to update Hydro profiles

21

Reasons to Reuse 2009 Shapes in the

2030 ADS PCM Case

Page 22: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

▪ Step 1) Developing hourly load shapes

Notes:1. Historically we have assumed EE shape is same as base load shape therefore EE

forecast is subtracted from base forecast

2. BTM PV is modeled as a supply in GridView, therefore ensure base forecast includes BTM PV impact

3. If EV charging has a unique hourly shape, therefore ensure base forecast excludes EV charging and grow shape independently

22

Creating Hourly Load Shapes (1) - Kevin

Harris

Summary of Growing Hourly Load ShapesHourly Monthly Adj Base Grow Hourly

Shape Forecast Forecast* Shape

Base Load Yes Yes Base

Energy Efficiency1 Yes If needed

BTM PV2

Yes If needed

EV Charging3 Yes Yes If needed EV

Future Items

Building Electrification Yes Yes If needed Build E

Time-of-Use Rates Yes Yes If needed TOU

Climate Change Yes Yes If needed Climate

Page 23: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

▪ Step 2) Sum hourly shape

• Base load shape

• + EV Charging

• - Irrigation load shapes (if modeled as supply)

▪ Future Items

• + Building Electrification

• + Time-of-Use

• + Climate Change

23

Creating Hourly Load Shapes (2)

Page 24: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

▪ Jointly with CEC & PDWG agreed to use hourly CEMS data from years 2010 through 2014 to calculate the I\O curve for IEPR 2016 and the 2026 ADS PCM dataset; the same data is currently used in the 2028 ADS PCM dataset.• Plant operation changes over time, especially in

California, influenced by less and less dependency on thermal generation. Is the CEC ready to recalculate the I\Curves, using more recent CEMS data?

• Potential fixes that should be considered with the update:

◦ The method we use to account for Station Service.

24

Heat Rate Curves Update – Jamie Austin

Page 25: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

▪ Currently, manual intervention is necessary to reconcile differences with “Round-Trip” import-export

• The goal is to have consistent value for Pmax in both PF and PCM:

◦ PF Pmax = gross unit rating; models SS as stand alone

◦ PCM Pmax = gross unit rating net SS; SS is netted from Pmax

• Inconsistency in modeling SS leads to different values for Pmax

◦ The goal is to have a means to manage the differences between PF Pmax and PCM Max Rating

◦ Note: Pmax minus station service is not equal to reported max rating

25

Station Service Modeling Approach

Page 26: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

▪ Suggested approach• On PF import, SS load is mapped to generator on same

bus into new table

• Table can be edited by user to make appropriate correction, and map unmapped SS load

• SS load would be excluded from area load in PCM simulation

• On export if a generator is committed, mapped SS load is turned on, if unit is off, SS load is turned off

▪ Add capability in GridView to manage SS load differences, helps the Round-Trip process to use the same Pmax

26

Modeling of Station Service Load – Kevin

Harris

Page 27: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

▪ Modify the definition of “Region/Areas” to

lineup with the Western Planning Regions

Footprint.

▪ Why this is needed?

• What is the objective of the study?

◦ Load area, region other aggregation tools in PCM?

◦ If overlapping regions, any control for calculation?

◦ How does the CAISO & CEC split CAISO and non-

CAISO areas in their respective modeling?

27

Modify the definition of “Regions and Areas”

Jamie Austin, Kevin Harris, Yi Zhang, & Angela Tanghetti

Page 28: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

▪ Current set up lines up with BAAs, with

some exceptions (PACE & PACW).

▪ BAA level aggregation not all encompassing

(e.g., covers for Reserves, Wheeling, but not

for FERC 1000, Operation Planning, etc.)

▪ How we get GV to support different

aggregations? On both Supply & Load sides

28

Potential Solutions to Reporting and

Aggregation – Jin Zhu, ABB

Page 29: Production Cost Model Data Work Group (PDWG) In-Person Meeting - PDWG... · NREL has new hourly wind and solar data for 2014 • Previously 2007-2013 It’s difficult to get agreement

Contact:

Jamie Austin

[email protected]

Kevin Harris

[email protected]

Tyler Butikofer

[email protected]

29