program review presentation - energy.gov...ge presentation for the 2004 hydrogen, fuel cells &...
TRANSCRIPT
![Page 1: Program Review Presentation - Energy.gov...GE presentation for the 2004 Hydrogen, Fuel Cells & Infrastructure Technologies Program Annual Review held in Philadelphia, PA May 24-27,](https://reader035.vdocument.in/reader035/viewer/2022062402/5f7c5b39f182ea6b3d474348/html5/thumbnails/1.jpg)
1
2004 DOE Hydrogen, Fuel Cells &Infrastructure Technologies
Program Review Presentation
Dr P D Hopewell
GE Global ResearchMay 2004
This presentation does not contain any proprietary or confidential information
![Page 2: Program Review Presentation - Energy.gov...GE presentation for the 2004 Hydrogen, Fuel Cells & Infrastructure Technologies Program Annual Review held in Philadelphia, PA May 24-27,](https://reader035.vdocument.in/reader035/viewer/2022062402/5f7c5b39f182ea6b3d474348/html5/thumbnails/2.jpg)
2
Objectives
Under this DOE Contract, GE Global Research’s Hydrogen Production Team are
researching methods to achieve considerable reduction in alkaline electrolyzer
system costs, compared to prevailing prices of available new equipment.
We may do this by;
•technological advances
•production methods
•materials of construction
•or a combination of these.
Appropriate physics-based performance and cost models will be used to allow
detailed trade-off analyses to identify practicable performance and cost solutions.
![Page 3: Program Review Presentation - Energy.gov...GE presentation for the 2004 Hydrogen, Fuel Cells & Infrastructure Technologies Program Annual Review held in Philadelphia, PA May 24-27,](https://reader035.vdocument.in/reader035/viewer/2022062402/5f7c5b39f182ea6b3d474348/html5/thumbnails/3.jpg)
3
2004 Budgetfor highlighted electrolyer = $1.4M
2004-2005 Project Plan Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar 4.1 Quantify Market Requirements
4.2 Preliminary Design and Laboratory Development
4.3 Electrochemical Cell Engineering Analysis
4.4 Bench Scale Hardware Engineering
4.5 Bench Scale System Testing 4.6 Education and Outreach Initiative (SUNY) 4.7 Sensor Development (SUNY)
4.8 Conceptual Development for Technolo gy Validation and Demonstration
Milestones:
Deliverables:
M4.2 - Preliminary analysis complete and component targets identified. M4.8 - Conceptual site layout complete.
D4.5 - Design document summarizing the results and business path to commercializ ation. D4.6 – Curriculum and outreach program to disseminate hydrogen knowledge. Technical, market and economic databases. D4.7 – Reference design of novel, optical H2 sensor and performance report. D4.8 – Virtual tour of New Baltimore site.
![Page 4: Program Review Presentation - Energy.gov...GE presentation for the 2004 Hydrogen, Fuel Cells & Infrastructure Technologies Program Annual Review held in Philadelphia, PA May 24-27,](https://reader035.vdocument.in/reader035/viewer/2022062402/5f7c5b39f182ea6b3d474348/html5/thumbnails/4.jpg)
4
Technical Barriers and Targets (1)From DOE’s Technical Plan – Hydrogen Production,
“By 2010, verify renewable integrated hydrogen production with
water electrolysis at a hydrogen cost of $2.50/kg (electrolyzer
capital cost of $300/kWe for 250 kg/day at 5,000 psi with 73%
system efficiency). By 2010, verify large-scale central electrolysis
at $2.00/kg hydrogen at the plant gate.”
Presently available alkaline electrolyzers cost in the region of $4000/kW to $20,000/kW(or $200,000/kgh-1 to $1,000,000/kgh-1). (This may not include compression to 5000psi.)
Main barriers include
1. Low volumes of manufacture – efficient assembly
2. System integration issues
3. Operating parameters
4. Materials of construction
![Page 5: Program Review Presentation - Energy.gov...GE presentation for the 2004 Hydrogen, Fuel Cells & Infrastructure Technologies Program Annual Review held in Philadelphia, PA May 24-27,](https://reader035.vdocument.in/reader035/viewer/2022062402/5f7c5b39f182ea6b3d474348/html5/thumbnails/5.jpg)
5
Technical Barriers and Targets (2)
Capital Cost
Manufacturing Margin
Electrolyzer Design
Assembly design
Materials
Machining Assembly
Seals
Input:Processability,
mechanicalproperties, corrosionresistance, price
Output:Material use, lifetime
Diaphragm
Input:Resistivity, price,corrosion resistance,
bubblepenetration,
wettabilitymechanical
properties,processability
Output:Material use, lifetime
MOC
Input:T,P , structural
Integrity corrosionresistance,
Processability,mechanicalstrength
Output:
Material use, lifetime
Electrodes
Input:
Material
•Corrosion Resistance
• Price
Current density, porosity
thicknessOutput:
Electrode area/thickness,lifetime
BOP
- Flow Diagram- Engineering Model (Aspen, Icarus)Input:
T,P, H2 purity, flow, storageP,feed water purityOutput:
Equipment cost, power, heat,cooling water
Program purpose is to understand how the capital costs are distributed for anelectrolyzer system and to use this knowledge to drive a targeted costreduction exercise to yield a cost-effective solution.
![Page 6: Program Review Presentation - Energy.gov...GE presentation for the 2004 Hydrogen, Fuel Cells & Infrastructure Technologies Program Annual Review held in Philadelphia, PA May 24-27,](https://reader035.vdocument.in/reader035/viewer/2022062402/5f7c5b39f182ea6b3d474348/html5/thumbnails/6.jpg)
6
Technical Approach
Stack Cost Rollup 300kW / 6kgph H2
$-
$200.00
$400.00
$600.00
$800.00
$1,000.00
$1,200.00
$1,400.00
$1,600.00
$1,800.00
Stack Concept 1 Stack Concept 2
Co
st,
$/
KW
$0.00
$10.00
$20.00
$30.00
$40.00
$50.00
$60.00
$70.00
$80.00
$90.00
Co
st,
$ /
gp
h H
2
BOP
Storage
Compressor
Stack
High Pressure Stack
Novel Compression
Methods
Current Cost
Currenttechnologyentitlement
?/ kgh-1
Optimal Cost
Incremental
improvement
Game-
Changers
High Efficiency Stack
Modeling optimizessystem parameters
Leverage GE manufacturing expertise for low-cost stack construction
0.0 0.2 0.4 0.6 0.8 1.0
1.72
1.76
1.80
1.84
1.88
1.92
1.96
2.00
P (products) = 1 bar P (products) = 30 bar
Current Density [A/cm2]
Cell
Voltage [
Volts]
63
64
65
66
67
68
69
70
71
72
73 P (products) = 1 bar P (products) = 30 bar
Effic
iency
Modeling optimizes stack performance
Learn the rules, then break the rules.
![Page 7: Program Review Presentation - Energy.gov...GE presentation for the 2004 Hydrogen, Fuel Cells & Infrastructure Technologies Program Annual Review held in Philadelphia, PA May 24-27,](https://reader035.vdocument.in/reader035/viewer/2022062402/5f7c5b39f182ea6b3d474348/html5/thumbnails/7.jpg)
7
Project Safety
Risks arise from;
1. Flammability of H2
2. Strong caustic electrolyte (KOH)
3. Temperature and pressure of stack and system
4. Voltage of electrical supply to system
5. High stack current
6. Mechanical risks occurring during equipment assembly and erection
![Page 8: Program Review Presentation - Energy.gov...GE presentation for the 2004 Hydrogen, Fuel Cells & Infrastructure Technologies Program Annual Review held in Philadelphia, PA May 24-27,](https://reader035.vdocument.in/reader035/viewer/2022062402/5f7c5b39f182ea6b3d474348/html5/thumbnails/8.jpg)
8
Project Timeline (1)
Target productscale identified19 April 04
CostPareto15 June 04
ConceptShort List30 June 04
ConceptTest Vehicles26 August 04
Single ConceptDown-Select17 Sept. 04
Concept DesignComplete12 November 04
Bench-ScaleSystem7 Feb. 05
FinalReport31 Mar. 05
DOE Project Timeline
Jugular Testing
Cell-Level Testing
Stack-Level Testing
Electrode Models
Cell-Level Models
Stack-Level Models
Low-Fidelity System Performance and
Cost Models Needed Early
2Q2004 3Q2004 4Q2004 1Q2005
Cost
Models
![Page 9: Program Review Presentation - Energy.gov...GE presentation for the 2004 Hydrogen, Fuel Cells & Infrastructure Technologies Program Annual Review held in Philadelphia, PA May 24-27,](https://reader035.vdocument.in/reader035/viewer/2022062402/5f7c5b39f182ea6b3d474348/html5/thumbnails/9.jpg)
9
Project Timeline (2)
![Page 10: Program Review Presentation - Energy.gov...GE presentation for the 2004 Hydrogen, Fuel Cells & Infrastructure Technologies Program Annual Review held in Philadelphia, PA May 24-27,](https://reader035.vdocument.in/reader035/viewer/2022062402/5f7c5b39f182ea6b3d474348/html5/thumbnails/10.jpg)
10
Accomplishments and Progress (1)(project commenced April 1st 2004)
Water Vapor Content in Hydrogen evolved at different KOH
molality
0
10
20
30
40
50
60
70
80
0 50 100 150 200 250
Temperature (degC)
% m
ole
of
wa
ter
va
po
r
6m
10m
14m
18m
6m
10m
14m
18m
6m
10m
14m
18m
1 bar
10 bars
50 bars
Understanding effects of temperature onalkaline electrolysis
![Page 11: Program Review Presentation - Energy.gov...GE presentation for the 2004 Hydrogen, Fuel Cells & Infrastructure Technologies Program Annual Review held in Philadelphia, PA May 24-27,](https://reader035.vdocument.in/reader035/viewer/2022062402/5f7c5b39f182ea6b3d474348/html5/thumbnails/11.jpg)
11
Accomplishments and Progress (2)
0 100 200 300 400 500 600 70048
49
50
51
52
53
54
To
tal W
ork
[kW
h/k
g H
2]
Output Pressure [bar]
1 bar, 2-stage intercooled 30 bar, 2-stage intercooled 100 bar, 2-stage intercooled
0.0 0.2 0.4 0.6 0.8 1.0
1.72
1.76
1.80
1.84
1.88
1.92
1.96
2.00
P (products) = 1 bar P (products) = 30 bar
Current Density [A/cm2]
Cell
Voltage [
Volts]
63
64
65
66
67
68
69
70
71
72
73 P (products) = 1 bar P (products) = 30 bar
Effic
ien
cy
Understanding effects of pressure and current densityon alkaline electrolysis
![Page 12: Program Review Presentation - Energy.gov...GE presentation for the 2004 Hydrogen, Fuel Cells & Infrastructure Technologies Program Annual Review held in Philadelphia, PA May 24-27,](https://reader035.vdocument.in/reader035/viewer/2022062402/5f7c5b39f182ea6b3d474348/html5/thumbnails/12.jpg)
12
Accomplishments and Progress (3)
UnderstandingUnderstanding that material properties may limitoperating conditions – and vice-versa
![Page 13: Program Review Presentation - Energy.gov...GE presentation for the 2004 Hydrogen, Fuel Cells & Infrastructure Technologies Program Annual Review held in Philadelphia, PA May 24-27,](https://reader035.vdocument.in/reader035/viewer/2022062402/5f7c5b39f182ea6b3d474348/html5/thumbnails/13.jpg)
13
Accomplishments and Progress (4)
UnderstandingUnderstanding that models and experimental workmust be closely aligned with project expectations
SystemPerformance
Model
MicroscopicLevel
CURRENT DENSITY (mA/cm2)
CellModel
ElectrodeModel
Stack Model
Experimental Work
Balance of Plant model
Stack modeling
![Page 14: Program Review Presentation - Energy.gov...GE presentation for the 2004 Hydrogen, Fuel Cells & Infrastructure Technologies Program Annual Review held in Philadelphia, PA May 24-27,](https://reader035.vdocument.in/reader035/viewer/2022062402/5f7c5b39f182ea6b3d474348/html5/thumbnails/14.jpg)
14
Future Work (1)
![Page 15: Program Review Presentation - Energy.gov...GE presentation for the 2004 Hydrogen, Fuel Cells & Infrastructure Technologies Program Annual Review held in Philadelphia, PA May 24-27,](https://reader035.vdocument.in/reader035/viewer/2022062402/5f7c5b39f182ea6b3d474348/html5/thumbnails/15.jpg)
15
Technology Vision
Target and reduce most significant system costs.
Develop optimum concept.
Demostrate entitlement and expected performance.
• Produce Product Roadmap to continue cost reduction activity and commercialize theconcepts flowing from DOE this program
Technology & Research Areas Product families employingnew, cost-effective conceptswill become available in this
timeframe
Today 2010
Significant reduction in electrolyzer system costs
$$$
3/31/05 – End of DOE contract
$$ $
Future Work (2)
![Page 16: Program Review Presentation - Energy.gov...GE presentation for the 2004 Hydrogen, Fuel Cells & Infrastructure Technologies Program Annual Review held in Philadelphia, PA May 24-27,](https://reader035.vdocument.in/reader035/viewer/2022062402/5f7c5b39f182ea6b3d474348/html5/thumbnails/16.jpg)
16
Technology Development
Eleoctrode material
and stack geometry
Separation
H2, O2, KOH
System configuration and operation
(batch/continuous, mobile/static electrolyte)
Auxiliary
equipment
Process Technology – Temperature, Pressure,
Operating Conditions, MOC, System Integration
Reliability Durability
Cost Efficiency
Enabling Technologies: Flexibility & Leverage
FundamentalUnderstanding
and ContributionsLow Capital Cost
Electrolyzer
System
Manufacture
and assembly
Future Work (3)