project presentation: ceen-2016cpst- : date: team members...
TRANSCRIPT
![Page 1: Project Presentation: CEEn-2016CPST- : Date: Team Members ...cecapstone.groups.et.byu.net/sites/default/files/... · CAPSTONE Design, Analysis & Results Verified 500 cfs flow used](https://reader034.vdocument.in/reader034/viewer/2022050216/5f61b6a1c7c26d58760549b1/html5/thumbnails/1.jpg)
CAPSTONE
CEEn-2016CPST-
Development Accommodation Realignment Study – Riverton City
April 18, 2017 1
001
X-Stream Engineers
Brad Mason
Tavin Griffeth
Kevin Woolf
![Page 2: Project Presentation: CEEn-2016CPST- : Date: Team Members ...cecapstone.groups.et.byu.net/sites/default/files/... · CAPSTONE Design, Analysis & Results Verified 500 cfs flow used](https://reader034.vdocument.in/reader034/viewer/2022050216/5f61b6a1c7c26d58760549b1/html5/thumbnails/2.jpg)
CAPSTONE
Introduction
The City of Riverton wants to realign 3500 feet of a natural stream to support future development.
Determined the best possible path to realign the stream.
Goals1. create the necessary space for
new development2. improve the conditions of stream
flow Problems include heavy erosion,
minor flooding, and super critical flow.
April 18, 2017 2
Rose Creek Current Path
![Page 3: Project Presentation: CEEn-2016CPST- : Date: Team Members ...cecapstone.groups.et.byu.net/sites/default/files/... · CAPSTONE Design, Analysis & Results Verified 500 cfs flow used](https://reader034.vdocument.in/reader034/viewer/2022050216/5f61b6a1c7c26d58760549b1/html5/thumbnails/3.jpg)
CAPSTONE
Photos of Current Problems
April 18, 2017 3
![Page 4: Project Presentation: CEEn-2016CPST- : Date: Team Members ...cecapstone.groups.et.byu.net/sites/default/files/... · CAPSTONE Design, Analysis & Results Verified 500 cfs flow used](https://reader034.vdocument.in/reader034/viewer/2022050216/5f61b6a1c7c26d58760549b1/html5/thumbnails/4.jpg)
CAPSTONE
Watershed Analysis Photos
April 18, 2017 4
Watershed using WMS modeling
![Page 5: Project Presentation: CEEn-2016CPST- : Date: Team Members ...cecapstone.groups.et.byu.net/sites/default/files/... · CAPSTONE Design, Analysis & Results Verified 500 cfs flow used](https://reader034.vdocument.in/reader034/viewer/2022050216/5f61b6a1c7c26d58760549b1/html5/thumbnails/5.jpg)
CAPSTONE
Design, Analysis & Results
Verified 500 cfs flow used for design
The new path of the stream
1. Close to the layout of the natural stream.
2. Improved cross section.
-lower trapezoid capacity= 200 cfs.
-total capacity=500 cfs
3. Minimized relocation cost/natural base
4. Improved channel flow and slope
April 18, 2017 5
New Proposed Path
![Page 6: Project Presentation: CEEn-2016CPST- : Date: Team Members ...cecapstone.groups.et.byu.net/sites/default/files/... · CAPSTONE Design, Analysis & Results Verified 500 cfs flow used](https://reader034.vdocument.in/reader034/viewer/2022050216/5f61b6a1c7c26d58760549b1/html5/thumbnails/6.jpg)
CAPSTONE
Conclusions & Recommendations
Rose Creek restored to its original path
Design slope maintains sub critical flow to prevent erosion.
Rose Creek will be returned to natural state and prevent further maintenance.
April 18, 2017 6