project wareham news - swanage railway · 2016-01-18 · project wareham news no. 13 jan 2016...
TRANSCRIPT
PWN – No 13. Jan 2016 Page 1
Project Wareham
NEWS No. 13 Jan 2016
Welcome to Project
Wareham Newsletter No. 13
Photo: Andrew PM Wright
Welcome
As many readers will be aware the Company
Chairman Trevor Parsons issued an internal
statement to the Swanage Railway on 22nd
December stating that the Trial Service to
Wareham could not commence in 2016. To
say that this is a huge disappointment to
many of us is an understatement. However
we must remain focused on what we have yet
to accomplish: and that is what we intend to
do!
In this edition you will find an update on the
rolling stock issues, and a report on our
recent meeting with Tim Shoveller, the
Managing Director of South West Trains.
Progress too on signage, the Road Rail
Interchange and of course Norden gates
Level Crossing.
Very much part of the overall plan is another
surge of administration. The Safety
Management System (SMS) which underpins
almost every aspect of the Railway has been
reviewed to ensure that it is fit for mainline
running; to say underpins is probably not
quite true as it actually
overarches most of our processes. This
document will be the crucial element of our
application to the Office of Rail and Road for
our Non-Mainline Safety Certificate.
Beneath the SMS are the Departmental
Standards, and a great deal of work is now
being undertaken to ensure they are also fit
for purpose. Grateful thanks here to Martin
Trott, David Rawsthorn, Nick Lloyd and James
Cox.
Frank Roberts
Senior Project Manager
Project Wareham
Our Diesel Multiple Units (DMU)
As you will be aware, the Swanage Railway’s
Class 121 ‘Bubble Car’ and our newly
acquired three car Class 117 DMU have been
located at Arlington Fleet Services, in the old
London & South Western Railway works at
Eastleigh.
PWN – No 13. Jan 2016 Page 2
Project Wareham
NEWS No. 13 Jan 2016
The most challenging element of the
overhaul has been the wheelsets where strict
standards for mainline operation exist and
where specialist work is required by a very
limited supply of competent contractors.
Following the arrival of the DMUs at Eastleigh
in September 2014, considerable time was
spent approaching wheelset contractors who,
due to already busy order books, were unable
to take on the Class 117/121 overhaul work.
Early this year we were fortunate to make
arrangements with Chiltern Railways (who
also operate Class 121s) to participate in a
contract with ZF Services UK Ltd for the
overhaul of their
wheelsets. Our components were
subsequently despatched to ZF’s sub-
contractors, Knorr
Bremse at Springburn in Glasgow last
summer where they have been subject to
detailed inspection. Unfortunately, as a result
of this our axles have been declared scrap
and will need to be replaced. ZF have notified
us that the lead time for the delivery of the
new axles is 16 weeks and 28 weeks for the
associated axle bearings.
This is, primarily, due to the relatively small
order for non-standard equipment and the
specific need to order imperial sized bearings
– which have to be manufactured in the USA.
By the time the components are assembled,
fitted to the DMUs in Eastleigh, tested and
then moved to Swanage it is almost certain
that summer and perhaps autumn will have
passed us by, following which there may well
be some snagging issues and also a period of
crew training.
We are not alone with rolling stock issues.
Tim Shoveller at a recent bi-annual Liaison
Meeting confirmed that the work on the Class
458 units, which operate on the
Reading/Windsor lines, and which are being
converted from four to five car units is only
now coming to an end; well over two years
late! FER
Bi-annual Liaison Meeting with South
West Trains.
On 8th January the Swanage Railway met with
Tim Shoveller, the Managing Director of
South West Trains. Tim continues to be very
interested in our progress to-date, despite so
much going on
within the South Western Franchise at the
moment.
PWN – No 13. Jan 2016 Page 3
Project Wareham
NEWS No. 13 Jan 2016
You may know that the formal bidding
process for the franchise commences in April,
with submissions due in July, and then the
company appointed will take over the
operation next spring. As our local Train
Operating Company (TOC) we have sought,
and secured, a good working relationship.
Tim and others within have been keen to
offer support and it is essential that this
continues even if Stagecoach is not the
company operating the franchise when we
run our first service to Wareham.
The twentieth anniversary of the first
privatised train service, run by Stagecoach
South Western Trains Ltd on 4th February
1996, occurs next month and a number of
events are planned by SWT to mark that date.
Another matter that SWT and Network Rail
are now considering is major engineering
works across Waterloo, much of which is
driven by the extension of the main Suburban
platforms (1-4) to accommodate 10 car trains.
Standby at Christmas time; and before! FER
Norden Gates Level Crossing
I have been surprised at the number of
people who have stated that the Level
Crossing (LX) was commissioned back in
November; what did take place two moons
ago was the Schweizer barrier and control
equipment was signed for by Signal &
Telegraph Manager Tony North.
Now, a lot can happen in a couple of weeks
and one unlikely occurrence was the arrival of
Storm Frank. My planning is usually very
good, but not
even I had put that in the programme. The
strong winds did inflict damage across the
country, and for us ripped off most of the
skirting on one of the two longer barriers
(this is the ‘fencing which opens out
underneath the barrier as it lowers. We are
now in consultation with Schweizer who will
arrange for repair under warranty.
A number of people asked why two of the
Road Traffic Lights ( more commonly known
as ‘Wig Wags’) were turned away from the
road for a couple of weeks. Basically they
were installed with extender arms so that they
would protrude over the pavement. However
there is only dropped kerb here, and it has
been agreed that there is a risk that tankers
could encroach onto the pavement here, and
collide (and damage) the Wig Wags; they
have therefore been fixed directly to the
poles without the extenders!
PWN – No 13. Jan 2016 Page 4
Project Wareham
NEWS No. 13 Jan 2016
This panoramic and rather wet view of Norden
Gates, shows the Country Side ‘Wig-Wags’ now
Items definitely in the plan are the various
tests being carried out by many people and
led by Tester in Charge Dave Fry who is
setting a very good tone as the works
proceeds. There have
been one or two matters to address, but
there have been no show stoppers to date.
The new
road signs associated with the LX will be
installed during the week commencing
Monday 18th January, and the fencing will be
completed too.
Today the Independent Competent Person
John Tilly and I have met to discuss the final
weeks of work. An essential element of this
will be the final testing which will commence
on 8th February and then the training of the
first members of staff that will take place at
the start of March as arranged by Mike
Whitwam. I am therefore confident that the
LX can be commissioned on Friday 18th
March!
Frank Roberts
Project Manager
Norden Gates Level Crossing
without the extender arms!
Photo: Peter Milford
Project Closeout
Whatever the term that you might be used to,
there are many matters that must be
addressed during the final stages of any
project with the aim of securing a
professional handover. One aspect is a
Health and Safety File which must be
provided as directed by the Construction
(Design Management) Regulations 2015.
PWN – No 13. Jan 2016 Page 5
Project Wareham
NEWS No. 13 Jan 2016
Over the next few months the various project
managers will be ensuring that all planning
documentation, drawings, financial matters
and equipment is handed over to the
appropriate Swanage Railway manager. FER.
Thank You Too!
A member of the Swanage Railway Trust
recently contacted me to complement the
team on how easy the Project Wareham News
is to read.
Part of the reason for this is the minimal use
of railway jargon, which many non-technical
folk may find difficult to understand. Thank
you for the compliment! FER
The Token Block Signalling
Project
Corfe Castle’s new Signal Box having been
commissioned in May 2011, the next big
project to be tackled by S&T Dept. was the
Norden to Worgret Jct Electric Token-Block
Signalling System. It was the first major
element of ‘Project
Wareham’ to be delivered, eliminating the
two Train-Staff Sections previously in force:
between Norden and the then SR/NR
Boundary at Motala (SR’s Section) and
between Worgret Jct and Motala (NR’s
Section).
This is the 4th Token Section to be introduced
on the SR but it is subtly different from the
others. Swanage-Harmans Cross and
Harmans Cross-Corfe Castle are conventional
Key Token Sections with Token Instruments at
each of the controlling signal boxes. The
Corfe Castle-Norden Section is wholly
controlled from Corfe Castle Signal Box and
has a ‘No-Signalman’ Token Instrument at
Norden, tokens from which are released by
Corfe Castle Signalman. For the new Norden-
Worgret Jct Section, signal boxes do not exist
at Norden or Worgret Jct. Thus the Token
Instrument at Norden is remotely released by
Corfe Castle Signalman (as is the Token
Instrument for the Section to Corfe Castle).
Clearly we did not want to site the far Token
Instrument where the Token Section ends at
the Junction points, so there are in fact two
Token Instruments for the far end of the
Token Section, located one on each platform
at Wareham Station.
The System was constructed over 2012 and
2013 with the co-operation of NR and their
PWN – No 13. Jan 2016 Page 6
Project Wareham
NEWS No. 13 Jan 2016
contractor for the Poole-Wool Re-Signalling
Project, Signalling Solutions Ltd. The System
requires no less than 10km of multicore cable
to connect the
three Token Instruments – the cabling is
partly owned by SR and partly by NR. There
are electrical signalling interfaces between
the two companies at Wareham and on the
Branch Line near Bridge 4 over the River
Frome. These interfaces enable the SR to
provide information about token-releases at
Wareham to the Poole to Wool Panel at NR’s
Signalling Control Centre at Basingstoke,
which on 19 May 2014 took over control of
the re-signalled main line. NR passes
information to SR about the occupancy of the
track circuits on the Branch Line for display in
Corfe Castle Signal Box.
On 8 September 2014, NR passed the
ownership of the Branch Line southwards
from Worgret Farm Bridge 2 to Dorset
County Council who then leased it to the SR.
That spelt the end of Motala as the SR/NR
Infrastructure Boundary, so the trap points,
ground frame and cabin were ceremonially
removed soon afterwards. Interestingly that
means that NR own one signal, one AWS
magnet, two-and-a half track circuits and one
treadle on SR infrastructure.
After a somewhat frantic signing of four SR-
NR Interface Agreements at the end of
January 2015, our Independent Competent
Person (ICP), Dick Spencer, was able to issue
his ‘Pre-Commissioning Statement of Safety
Verification’. This enabled our Tester-in-
Charge, Dave Helliwell, with the co-operation
of NR’s Test and Commissioning Engineer,
Pat Butler, to formally
test the whole system and sign it into use at
14:08 on 5 February 2015. Just 2 hours later
the ‘Rail Minister’, Claire Perry, MP, travelled
by Special Train from Poole to Corfe Castle
and back – the first train to use the new
Token System.
So, where are we now? Whilst the System has
been used successfully to signal onto and off
the Branch two Charter Trains and several
Ballast Trains during 2015 we are still waiting
for the ‘Final Statement of Safety Verification’
to be signed off and this depends primarily
upon the production, updating or completion
of:
PWN – No 13. Jan 2016 Page 7
Project Wareham
NEWS No. 13 Jan 2016
Risk Assessments for the various crossings
in the Section and the acceptance of any
recommendations for action by SR.
The Hazard Directory for the Branch Line.
Remedial measures on a number of snags
raised against NR regarding their
equipment on the Branch Line.
NR’s Final Records for the design of their
signalling equipment that interfaces with
the SR.
A Final Inspection and Walk-Through by
our ICP.
It is hoped to clear this final hurdle by the
end of March 2016.
Not surprisingly there have been some
challenges in this Project, which has put the
SR in the ‘Big League’ of Heritage Railways
possessing a fully signalled link onto the
National Network:
Personally handling the Project as both
Project Manager and Project Engineer.
Working with no less than four ‘opposite
number’ Project Managers on the NR side
over the period of the Project since
September 2011.
Accommodating the rigorous demands of
certain NR Signalling Specifications,
Standards and Protocols.
Having to design a unique system that
utilizes three standard Electric Token
Instruments that were in our possession,
but adapted to a remote-release role. As
part of the system we managed to
procure a set of Token-Transfer
Equipment to facilitate re-balancing the
tokens at Wareham from one platform to
the other.
Accommodating the snakes and lizards
that inhabit the Sites of Special Scientific
Interest that abut and span the Branch
Line. Actually this was not the problem it
could have been since a ‘Letter of
Consent’ was readily obtained from
Natural England and our cable-laying
contractor was able to complete the
trench-digging work within the permitted
time slot while our ‘little friends’ were
active.
Finally I would instance two personal
highlights:
The fact that our Rail Minister was the
‘Distinguished Passenger’ on the first
passenger train to use the newly
commissioned Token System.
PWN – No 13. Jan 2016 Page 8
Project Wareham
NEWS No. 13 Jan 2016
The receipt of a Christmas card from my
good friend Andy Emmerson, now the
Deputy Editor of the journal “Institution of
Railway Signal Engineers News”, in which
he wrote “Congratulations on your
remarkable – and highly successful –
project management works. I think this is
utterly brilliant!”
Mike Walshaw
LX Project Scheduler
On 17th December an Officer’s Special conveyed
guests from Dorset County Council and members
of staff to the River Frome. It is seen here passing
Embankment 4, onto which has been deposited
2,235 cubic meters of spoil, and several trainloads
of spent ballast! Photo Andrew
PM Wright
Reflections on the PWay
programme of work for
Project Wareham
Our PWay staff have done a lot of work since
I came into the Project as PW Advisor last
March. They have replaced hundreds of
sleepers, ditto tonnes of ballast, and nearly ¾
mile of rails.
That is before we count the tree and shrub
clearance, cess creation, fencing, level
crossing renewal, etc... Their task has been
to upgrade the section of track inherited from
Network Rail. But is it that simple? What level
of upgrade is required, or desirable?
Firstly I ask you to consider whether the name
“Permanent Way” is actually a misnomer?
Unless we are talking about concrete slab
track, what we unthinkingly speak of as
Permanent Way is very far from that. The
track structure, of rails, on sleepers, resting
within a bed of crushed stone has been found
to be both resilient, and adaptable, and when
it is distorted by traffic, or
ground movement, it is usually straight-
forward to put it back where we want it.
There is another problem associated with the
permanence of the track, and that is the
difficulty of defining exactly when it is life-
expired, or indeed, when it becomes unsafe.
Yes, there are numerical limits for many
obvious factors like rail depth, but we rarely
PWN – No 13. Jan 2016 Page 9
Project Wareham
NEWS No. 13 Jan 2016
reach these limits (certainly not the limits of
all components simultaneously), and when we
do get borderline the rate of wear is usually
so slow that there is no clear “OK yesterday,
unacceptable today” moment. I believe this
situation actually contributes to the idea of
“Permanent” when the opposite is true. With
every component of the track slowly
deteriorating over many years you may begin
to understand that assessing the point where
“something must be done” is extremely
difficult.
Indeed it is something of a black art to decide
when the increasing need for maintenance
activity switches to a consideration of a
renewal intervention. And then which bits?
Or the whole track structure?
It is also worth noting that top quality track
needs very little maintenance whereas poor
track deteriorates faster and faster as it gets
worse. The only problem is that getting track
into the quality end of the spectrum either
requires a lot of man-hours, or a very
expensive machine and a lot of design work.
Against this background Barry Light and I
could have produced a huge list of work to
be done between Motala and bridge 2. The
wish-list we
actually produced was pretty big and had a
cost of over £440k. What proportion of the
DMU costs does that represent?! Refining
and replanning has achieved a significant cost
reduction with limited impact on scope, but
there have been several quite important
items of pointwork that have had to be cut
right out of the scheme, being currently un-
affordable. The expanding cost of the DMU
refurbishment, and some cost over-runs in
other areas of the Project, have recently put
even further pressure on the PWay
Department to cut costs by any means
possible.
A final 900t ballast train has been cancelled to
save money following an unexpected offer of
700t for just the cost of its transport – but as I
write that offer may have evaporated into
thin air! To
compound our difficulty a quotation for the
final (and only) tamping of the line has come
in much
more expensive than expected. Without
more stone, and the tamper, we cannot get
onto the virtuous circle of better quality
leading to less maintenance.
We WILL sort it out, probably with a bit more
manual work and extended timescale as a
PWN – No 13. Jan 2016 Page 10
Project Wareham
NEWS No. 13 Jan 2016
result. Meanwhile my explanations of the
impermanence of track will hopefully improve
understanding that there is an element of
mortgaging-the-future when the track does
not get the right attention. If a DMU cannot
run there is no service; if the track is in poor
condition there are increased long term costs
that could also, eventually, prevent a service
from being operated. I am glad
to say that I am assured that the funds I have
requested are still available to enable a
quality result to be achieved.
Jim Wheeler
Honorary Permanent Way Advisor
Document Storage
All projects generate a huge amount of
paperwork and Project Wareham is no
exception, and it is extremely important to
ensure all essential documents are safely
stored electronically for future reference.
Currently all documents relating to PW are
stored in appropriate sub folders contained in
an
overarching principal PW folder on the server.
Documents stored include amongst other
things,
minutes from PW meetings, project design
drawings and legal documentation from
Dorset County Council including copies of the
Licence to Alter and Grant Agreement in
relation to the works at Norden.
A comprehensive document storage index
has been compiled to ensure documents can
be located quickly and easily.
Once the project is handed over at the end of
March 2016, relevant folders will be sent to
the appropriate departments in the railway,
together with a copy of the document
storage index.
Nichola Watts
Project Administrator
Meet Will Fooks and Ken Orchard
From time to time we have introduced
various characters who have worked in
support of Project Wareham. Following a
round of interviews, three trackmen were
engaged in 2014, to support the additional
works and their posts have been funded by
the Coastal Communities Fund.
PWN – No 13. Jan 2016 Page 11
Project Wareham
NEWS No. 13 Jan 2016
Ken and Will, and also Jamie Rudge who was
featured in an earlier edition of the PW News,
have given a massive boost to the Railway’s
Permanent Way Department since their
arrival. The work rate and the list of
achievements has been phenomenal, as can
be seen by those who
have had a chance to travel up the line to the
River Frome.
Will Fooks originated from Bushey which is a
hamlet on the other side of the Purbeck Hills
in the Rempstone Estate. He had spent a
number of years working for different firms in
the local area, and even lived in Swanage for
18 months, but apparently the rush hour was
too much for him!
He relishes the outdoor work, day or night as
was seen when he joined the rest of us and
got stuck into the overnight replacement of
the level crossing surface at Norden. Since
his arrival he had completed a number of
courses including chainsaw operation and
first aid. I asked what he enjoyed most and
he replied everything, but
especially the people in the team, the banter
and as mentioned the outdoor activity.
Will and partner Haley have a two year old
son, and another baby is on the way in
March; we wish them well with the birth.
I first met Ken when he offered me a brew,
and he always seems to get stuck into the
normal track works, then take command of
the kettle too! He has always lived in
Wareham and has spent time as a manager in
a local packaging firm. He also has
experience working trackside for Balfour
Beatty being based at their Eastleigh Depot
for 8 years. Seeking some variety away
from the railway he supported a Purbeck care
home providing building maintenance.
Ken explained that he wanted to return to the
railway and has had a thoroughly good time
since joining the Permanent Way team. He
has noticed a real difference between the
Branch and the mainline, returning to
bullhead rail (and taking some out during the
907yd relay in flat bottomed rail!), steam
engines and lots of stories of how the railway
was in the past. He sort of gave his age away
when he said he could remember the kids
going by train to Swanage Grammar School!
Ken is married to Cheryl.
PWN – No 13. Jan 2016 Page 12
Project Wareham
NEWS No. 13 Jan 2016
Wherever the PWay gang are spotted, there is
usually a good deal of good work going on,
and I take this opportunity of thanking all of
the team, including those who come and
assisted for a day or two at a time. Well done
for all of your efforts, your help and your
support.
Photo Caption: Will Fooks and Ken Orchard ready
for action with the PWay Van. Photo:
FER