promises and challenges of utility scale pv grid integration … · 2009-02-04 · promises and...

50
Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i Leo F. Casey, Satcon Robert F. Johnson, SunPower Bob Reedy, FSEC 1.13.2009

Upload: vudan

Post on 03-Jul-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Promises and Challenges of

Utility Scale PV Grid Integration

- lessons from Lana’i

Leo F. Casey, Satcon

Robert F. Johnson, SunPower

Bob Reedy, FSEC

1.13.2009

Page 2: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Outline

• Leo Casey, Robert Johnson, Bob Reedy- Introduction to

Presenters and Organizations

• Robert Johnson- Lana’i PV Power Plant Project Overview

• Leo Casey- Lana’i Grid Stability Challenges

• Robert Johnson- Communications & Controls

Implementation

• Bob Reedy – Integration with SEGIS Plans

Page 3: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

The Lana’i Grid and its Stability

Challenges for Renewables

Recloser

(36)

(34)

(35)

(32)

(31)

(19)

(300)

(3)

450

kVAR

RECL 4022

RECL 4023

RECL 4021

(33)

(30)

(310)

(14)

(13)

(12)

1222 SW (NO)

(100)

RECL 1226 RECL 1227

(16) (15)

RECL 1228

RECL 1225

SW (NO) (11)

1229 SW

(102)

(103)

(101)

(77)

(7)

(71)

(9)

(5)

(4)

(6)

(61)

(8)

(1)

(999)City #1

City #2

Hotel Ckt

G~

=== V

Z

Z

G~

G~

G~

G~

G~

G~

G~

G~

Future CHP

R

WELL2

WELL1

Intertie Breaker

V1 V2 V3 Battery

1223 SW

1221 SW

1212 SW1208 SW1210 SW

MANELE

MANELSUB

4023

4022

4021

E1B

KOELE_LD

KOELETAP

HARBOR12

WELL4

MAUNB33

WELL5

WELL3

WELLB30

WELL9MAUNALEI

WELL

E6

E1

LALASUB

E13

PPTSF

KAUMALA

KOELE

HARBOR

PPTAP

LALATAP

LSRBT1LSRPV3LSRPV2LSRPV1

LANAI6LANAI5LANAI4LANAI3LANAI2

HOTEL

LANAI1

L8_D-8L7_D-7

LSRPV

LANAI A

• Two 2.2MW diesel Generating Stations

• Six 1MW diesel Locomotive ‘standby’ generators

• Nominal 4MW load

• Expensive power(fuel), great solar resource

• “diesel” grid

Page 4: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Lana’i PV Plant Impact Overview

• 1.5MW Solar Farm

• 12 SatCon, GEN I, 135kW Inverters

• 12 independent tracking solar arrays

• 10% of Lana’i annual power demand

• 30% Supply during peak solar hours (4MW)

• BUT potentially destabilizing AND limits of

Lana’I grid are extremely wide so non-UL1741

non IEEE1547 inverter required, and under

Utility Control

LSR Point

of Common

Coupling

Lanai Generators

R

Hotel

Intertie Breaker

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

DC

AC

Battery

135 kVA per

Inverter Rating

Recloser

Anticipated PV Output and effect on System Load for July

0

1,000

2,000

3,000

4,000

5,000

6,000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Hour of the Day

Kilo

wat

ts

Lanai System Load Net System Load w/PV PV Output

Anticipated PV Output and effect on System Load for January

0

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

4,500

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Hour of the Day

Kilo

watts

Lanai System Load Net System Load w/PV PV Output

Page 5: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Players / Rules of Engagement

MECO – Maui Electric Company

– Utility Company: Buying power from Solar Farm

Lanai Sustainability Research, LLC.

– Owner of Solar Farm: Selling Power

&

SunPower, PV System Designer, Integrator

Satcon, Grid Connected Inverter manufacturer (Bob Reedy –

FSEC, SEGIS partner)

Serra, SCADA Interface, SunPower Sub-Contractor

Lanai PV Interconnect Requirements Study, June 25, 2008, KEMA Inc.MECO-LSR Power Purchase Contract, “Power Purchase Contract for As-

Available Energy, August 8th, 2008”

1) Remote control of Real Power, also termed curtailment

2) Remote control of Power Factor, within a fairly narrow range

3) Grid disturbance ride-thru capability

4) Ramp rate limits and control (dP/dt)

Page 6: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Over 500 systems on 4 continents

Over 400 MW installed

Largest solar projects in North America

Worldwide footprint World record solar cell efficiency = MORE POWER

Established and Proven. Technology

Leaders.

Publicly traded (NASDAQ) and partnerships

with top-tier financiers

4,000 Employees: All we do is solar Over 85 patents and over 20 years of R&D

Over a quarter century of experience

Energy efficiency expertise

Page 7: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

SunPower Provides Solar

Wherever You Need It

ResidentialCommercial Power Plants

Largest Residential Install

Base in North America

Largest Commercial

Install Base in North

America

Largest Solar PV Power

Plants in North America

Number 1 Number 1Number 1

Page 8: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Satcon - Grid Connected Electronics

Grid Energy +Grid Support + Utility Scale

• Founded 1985

• Public 1992 (SATC)

• 275 employees

• 115 patents

Page 9: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

The New Value Equation

2010 +2000 2005

Utility ReadyLarge Scale Grid

Integrated AdoptionCommercial

ReadyEarly Majority

Ov

era

ll P

V O

utp

ut

Visionary

ReadyEarly Adopters

Today

Page 10: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Florida Solar Energy Center

Research, Applications,

Education, Training,

Testing

Solar Energy Division

Building Efficiency

Division

Advanced Fuels for

Energy Division

Creating Energy Independence Since 1975

A Research Institute of the University of Central Florida

Page 11: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Lana’i PV Power Plant – Project Overview

Manele

Hotel

PV Plant

Miko Power

Plant

Lana’i City

& Koehle

Lodge

1.2MW AC

Page 12: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Lana’i PV Power Plant – Project Overview

PV Array

Inverters

1-4

PV Array

Inverters

5-8

PV Array

Inverters 9-

12

Inverters 9-

12

Inverters 5-

9

Inverters 1-

415kV Switchgear

Overhead

Lines to

Miko Basin

Power Plant

Overhead

Lines to

Manele Bay

Hotel

Page 13: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Lana’i PV Power Plant – Single Line

• Single Line

Provisions

for energy

storage

system

Page 14: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

MECO Control Requirements

• The PPA signed between LSR and MECO stipulates several site control features:

– Curtailment Control

• Utility provides set point in fairly continuous increments between 0-1200kW

• Plant response should be rapid without violating ramp-rates limits

• Utility receives status indicating achievement of set point

– Power Factor Control

• Utility provides set point between 0.95 lagging to 0.98 leading

• Utility receives status indicating achievement of set point

• The PV Plant produces and consumes reactive power at utility command

– Ramp-Rate Limiting

• Plant output fluctuations need to be limited to 6kW/s during beginning/end of

day and startup and shutdown periods

• Plant output fluctuations needed to be limited to 40-60 kW/s at other times

Page 15: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Design – PV Site Controller - Architecture

Grid Operators on Maui control power

output and power factor set points from

their Areva HMI

Data is transmitted Ethernet over a

microwave uplink

Redundant control is available at Lanai

Control Center if communication fails

with Maui. Set points are passed

through to data gateway at PV siteData is transmitted via DNP3 protocol

over fiber to the onsite data gateway

Data Gateway (Orion 5r) acts as both

master and slave device. It translates

set points from DNP3 to modbus and

receives set points from PV Site

Controller

Data is transmitted via modbus over

RS232 and RS485 to PV Site Controller

PV Site controller maps set

points, status points and

process values between Utility

SCADA and site devicesCommunication to inverters and

other devices is via modbus TCP

over fiber and copper

Page 16: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Status Data, Process Values & Control Algorithm

• In addition to setting power output and

power factor, the grid operator requires data

on status and real-time process values to

evaluate plant operation

• Status Data

– Inverter on/off

– Last commanded global curtailment and

power factor set points

– Last commanded individual inverter

curtailment and power factor set points

– Intertie breaker status open/closed

• Process Variables

– Real-time power output and power factor at

point of interconnection

– Individual inverter real and reactive power

output

– Available generation capacity based on real-

time calculation using irradiance, wind speed

and temperature data

Change In Curtailment

Set Point From Orion 5r?

Write Inverter

Curtailment Set

Points to All

Inverter

Write All Inverter

Power Factor Set

Points to Inverter

Read Curtailment

Process Value

From Meters

Read Power

Factor Process

Value From

Meters

Read MET Data

From SunPower

DAS

Change In Power Factor

Set Point From Orion 5r?

Yes

Yes

No

No

Begin

Write Inverter

Curtailment Set

Points From

Inverters to PLC

Status Register

Write Inverter

Power Factor Set

Points From

Inverters to PLC

Status Register

Page 17: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

SUNPOWER DAS

(CR1000 w/NL115 )

Modicon

PV Site Controller

Orion 5r RTU(MECO Comm Link )

Inverter Inverter

Inverter Inverter

Switch

VerisMeter

Inverter Inverter

Inverter Inverter

Switch

VerisMeter

Inverter Inverter

Inverter Inverter

Switch

VerisMeter

Primary Switch

Modbus TCP

Over Fiber Modbus TCP

Over Fiber

Modbus TCP

Over Fiber

Modbus RTU

Over RS -232

Modbus TCP

Over Cat 5

Modbus TCP

Over Cat 5

Modbus TCP Over Cat 5 to Switch

Cellular Router

(Digi ConnectPort )

Modbus TCP Over Cat 5 to Switch

Modbus TCP Over Cat 5 to Switch

ATT 3G Connection via

Static IP

Modbus RTU

Over RS-485

Modbus RTU

Over RS -485

Orion as Master

Modbus TCP

Over Cat 5

Modbus TCP

Over Cat 5

Digi Serial to TCP/IP

Gateway

Bitronics

M871 Meter

DNP

Orion as

Slave

Modbus RTU

Over RS - 485

Control System – Communication Network

Page 18: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Interfacing with the Utility SCADA

MECO’s HMI interface with intertie breaker and

recloser**Screen shots provided by Dwight Weiding of MECO

Page 19: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Interfacing with the Utility SCADA

MECO’s HMI interface with Lanai PV

Plant* *Screen shots provided by Dwight Weiding of MECO

Page 20: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Interfacing with the Utility SCADA

MECO’s HMI interface with Lanai PV

Plant

MECO’s HMI interface with Lanai

Grid**Screen shots provided by Dwight Weiding of MECO

Page 21: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

PV Site Controller – Control Details & Challenges

– Curtailment is measured at point of interconnection, but control is achieved at the inverters

• Must account for variable transformer losses & maintenance scenarios where inverters are offline

• Suggests a closed loop control approach, but fairly complicated to implement, primarily due to latency

issues

• Open loop control requires several scale factors dependent on plant configuration

– Power Factor also measured at point of interconnection

• Must account for discrepancy in measured PF versus commanded PF

• Difficulty developing HMI for this feature. Actual implementation uses discrete set points, e.g. 0.95, 0.96,

0.97 lagging and 0.98, 0.99 leading, etc.

– One big challenge is communication latency

• This latency can occur at the inverter, which requires time to process command and then act

• Another source of latency is created by the communication network itself and the protocol employed

– Managing the broad range of device types, protocols, communication mediums and

scaling factors makes for a complex system.

Page 22: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Performance Data – Set Points with Ramp Rates

Page 23: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Performance Data – Power Factor Control

Page 24: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Future Developments

• These control features are new to PV plants and there is muchdevelopment work to be done, and many opportunities:

• Optimization of control techniques

• Normalization of Utility HMIs

• Integration with storage

• Ancillary services like voltage support

• Open loop versus closed loop control

• Remote Restart & Reclosing

• Parallels to Smart Grid

Page 25: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Power Limit (Curtailment) & Power Factor Control

• Power Limit involves disabling MPPT routine (“quasi” slew rate

possible within Inverter)

• The full range for the power factor command is from 0.71 leading to

0.71 lagging, plus status flag

• Power factor control is realized by keeping real current and reactive

current at a fixed ratio determined by the commanded power factor

Power Factor Control

Communication of power factor

set point

Modbus TCP

Power factor range 0.98 Leading to 0.95

Lagging

Power factor increment size 0.005

Power Factor response time <5s

Power Limit Control

Communication of power-limit set point Modbus TCP

Power-limit range 0-135 kW

Power-limit increment size 32.96 W

(135/4096)

Ramp-rate limit 6 kW/s

Response time <5s

Page 26: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Curtailment Power Factor Control Testing -

Results

•Implemented

•Tested in Certification Lab

•Verified at PV-Lana’i

Page 27: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Ride-Through

• Traditional Inverters (IEEE1547 & UL1741) operate in narrow range

of voltage and frequency and are required by statute to disconnect

immediately in the presence of fairly minor deviations.

• The intent here is to operate over a much wider range, and to

tolerate fairly rapid dynamics.

• Inverter must operate safely, for extended periods, over the wide

voltage and frequency extremes being considered.

• The nominal voltage “V” referenced in the requirements is 12.47 kV

at the point of grid interconnect, and 60Hz is the nominal frequency

‘f’ referenced in the table below.

• Implemented, tested (Cert Lab), tested in Microgrid, simulations,

observations

Page 28: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Required Ride-Through Capabilities

Grid

Frequenc

y

Inverter Response

65 Hz < f Inverters must disconnect after

160 milliseconds

62 Hz f

65 Hz

Inverters may disconnect after 2

seconds

61 Hz f

< 62 Hz

Inverters may disconnect after 6

seconds

57 Hz f

< 61 Hz

Inverters will stay online

55 Hz f

< 57 Hz

Inverters will stay online through

this extended ride-through

range55 Hz > f Inverters may initiate

disconnection from the grid

within 160 milliseconds

Grid Voltage Inverter Response

1.20 pu < V Inverters shall stay online for more

than 160 milliseconds

1.10 pu V

1.20 pu

Inverters shall stay online for at

more than 3 seconds

0.90 pu V

< 1.10 pu

Inverters shall remain online

0.70 pu V

< 0.90 pu

Inverters shall stay online for more

than 2 seconds

0.05 pu V

< 0.70 pu

Inverters shall stay online for more

than 600 milliseconds

0.05 pu > V Inverters may initiate disconnection

from the grid

•Verified quasi statically

•Verified dynamically in MicroGrid

Page 29: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Transient Ride-Through Performance - Simulation

• The PV inverter equipment was supplied as UL1741 compliant, but the required ride-through

capability for this project is a dramatic departure from UL standard practice,

• Grid Voltage Monitor. Anti-islanding protection has been disabled, and the ac line voltage

monitoring function has been re-designed to accommodate the specified voltage and frequency

deviations without initiating an inverter shut-down.

• Inverter Control and Self-Protection. The transient response of the inverter controls has been

evaluated to make sure that transient grid voltage deviations will not cause inverter over-current to

occur.

• A detected over-current would result in an immediate trip for inverter self-protection. This

investigation was based on a computer simulation of the power circuit, including a detailed model

of the inverter control system. the phase-locked loop (PLL) algorithm was replaced with an

alternative algorithm that is considered more suitable for dynamic tracking during voltage

disturbances.

• For this project, computer simulation was used to model equipment performance for a number of

fault conditions at the PV station MV bus. These cases are illustrated in the following charts

• The results indicate that the inverter current will not reach the over-current trip threshold for the two

unbalanced faults shown in Figs. 2 and 3. In the third case (balanced three-phase to ground fault),

shown in Fig. 4, the inverter current peak immediately following the onset of the fault is close to the

trip level and indicates that there is a slight possibility of an over-current trip under extreme

conditions. We have moved the trip points up accordingly. Automatic restart is another possibility.

Page 30: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Ride-Through Simulation Results - Model

Page 31: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Simulation Results (1)

Simulated A-phase to ground fault at the Lanai PV station MV bus.

Page 32: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Simulation Results (2)

Simulated A-phase to B-phase to ground fault at the Lanai PV station MV bus.

Page 33: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Simulation Results (3)

Simulated 3-phase to ground fault at the Lanai PV station MV bus

Page 34: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

34

FSEC Team SEGISGoal: “Walk Like a Duck”

=PV in Aggregate, Behaving Like

Conventional Utility Generation--

& Then Some

Page 35: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

35

FSEC Team SEGIS: Innovations

Utility Control of Islanding

Maintain DG when needed most

Utility Control of Inverter VAR Generation

Use of DG asset in a new way

Shared Inverter Designs for Complex Sites

Cul-de-Sac Plant, Linear PV Farm, Weird Roofs

Page 36: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

36

FSEC Team SEGIS:Critical Features

Enhanced island protection

Utility control of online/offline status

PV generation ride-through of grid disturbances

Fast & Dispatchable VAR Support

Peak-shifting & anytime-emergency peak

generation with energy storage & BEMS

Page 37: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

37

FSEC Team SEGIS:Enhanced Features

Stabilization of Mini/Micro Grids (Island Mode)

Harmonic Cancellation

Deliberate Phase Unbalance

Prognostics and Diagnostics

Real-time phase balance of feeder circuits

Enhanced transient response (H Constant)

Oscillation Damping

Spinning & Ready Reserve

Page 38: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

38

The Really BIG ISLAND:

Eastern Interconnect-- “the World’s Biggest Machine”

925,000,000 hp - 2,000,000 sq mi -- 3600rpm

Page 39: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

39

Frequency ExcursionsSouthern Control Area Frequency

8-14-03

59.000

59.200

59.400

59.600

59.800

60.000

60.200

60.400

60.600

60.800

61.000

3:10:00 PM 3:11:00 PM 3:12:00 PM 3:13:00 PM 3:14:00 PM 3:15:00 PM 3:16:00 PM 3:17:00 PM 3:18:00 PM 3:19:00 PM 3:20:00 PM

Fre

qu

en

cy

, H

z.

60.236 Hz. at 3:10:54 PM CDT

Set Point Frequency

Eastern Interconnection Frequency

t0

25 sec of interest

Page 40: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

40

Something Really Scary !

Apparent & Approximate

Envelope of the Undamped

Oscillation, before System

Reconfiguration (Islands) Led to

a Damped Oscillation

Effective Breakup of the EI into Islands

(largely due to operation of Zone 3

distance relays)

Eastern Interconnection Frequency

8-14-03

t0

Note:

Frequency of the Oscillation is

about 1/3 Hz. This is the

“Frequency of the Frequency”

Undamped Period Damped Period

Page 41: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

41

Southern Control Area

Generator UF coordination curve

54

54.5

55

55.5

56

56.5

57

57.5

58

58.5

59

59.5

60

1 10 100 1000 10000

Time (Cycles)

Fre

qu

en

cy (

Hz)

Trip Point per

IEEE 1547

Trip Point of

Turbines

Page 42: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

42

“Anti-Anti” IslandingBack to Basics:

Control Areas Use PermissivePLCC to Maintain GenerationDuring Disturbances

No Freq Push issues withhigh penetration

Certainty with down lines

Provides Control AreaShutdown Capability duringOver Generation events

William of Ockham

b. 1285 Surrey, England

Page 43: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

43

Old View – Island BAD

Page 44: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

44

New View – Island GOOD

Page 45: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

MicroGrids – “ACCESS” & SDS Enable UPS-PQ

3 3

UTILITY GRID

FACILITY LOADS

1000 kW MAX

CRITICAL LOADS

21 kV, 60 Hz

21 kV, 60 Hz

3

480 V, 60 Hz

480

21000

3

3

3

1000 kW

max

500 kW

max

500 kW

max

EXISTING FUEL CELL

EXISTING PV ARRAY

NEW ENERGY STORAGE

FACILITY LOADS

1000 KW MAX

CRITICAL LOADS

UTILITY

GRID

STATIC

DISCONNECT

SWITCH

(SDS)

ISLAND GRID

ENERGY STORAGE UNIT

CONTROLS VOLTAGE AND

FREQUENCY IN ISLAND MODE

•Renewables plus back-up generation plus storage plus SDS

•UPS quality power

Page 46: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Simulated 3-Phase Fault on Utility Grid

2.2 MVA, 0.8 P.F. Constant Load on MicroGrid

ENERGY STORAGE CONVERTER OUTPUT CURRENT

FUEL CELL CONVERTER OUTPUT CURRENT

ISLAND GRID VOLTAGE

ISLANDVOLTAGE

MAINTAINED

GRID CURRENTS THROUGH INTER-TIE

UTILITY GRID (480 V) VOLTAGES (L-N)

FAULT

SDS CLOSED

SDS OPENED

DISCHARGINGCHARGING

CHARGING

FUEL CELL

OUTPUT

MAINTAINED

Page 47: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

3 3

UTILITY GRID

FACILITY LOADS1000 kW MAX

CRITICAL LOADS

480 , 60 Hz

480 , 60 Hz

3

480 V, 60 Hz

480

21000

3

3

RENEWABLE

DIESEL GENSETS (TQGs)

NEW ENERGY STORAGE

MICROGRID

LOADS

UTILITY

GRID IF

PRESENT

STATIC

DISCONNECT

SWITCH

(SDS)

TACTICAL MICROGRID

ENERGY STORAGE UNIT

CONTROLS VOLTAGE AND

FREQUENCY IN MICROGRID

G D

Utility Grid Connection optional – Tactical

Micro Grid

Page 48: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Simulated Operation in Island Mode -Load

Suddenly Increased (1.1 to 2.2 MVA, 0.8 P.F.)

ENERGY STORAGE CONVERTER OUTPUT CURRENT

FUEL CELL CONVERTER OUTPUT CURRENT

ISLAND GRID VOLTAGE

ISLAND

VOLTAGEMAINTAINED

GRID CURRENTS THROUGH INTER-TIE

UTILITY GRID (480 V) VOLTAGES (L-N)

FUEL CELL

OUTPUT

MAINTAINED

LOAD SUDDENLY INCREASED

CHARGING

DISCHARGING

Page 49: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Lanai

True “Island” Grid

Palawai Basin - 10 Acre Site

Advanced Inverter Features implemented

under Utility Contrtol

Page 50: Promises and Challenges of Utility Scale PV Grid Integration … · 2009-02-04 · Promises and Challenges of Utility Scale PV Grid Integration - lessons from Lana’i ... Buying

Thank you.

Leo Casey

(617) 897-2435

[email protected]

Contact: Contact:

Robert Johnson

(510) 260-8373

[email protected]

Contact:

Bob Reedy

(321) 638-1470

[email protected]