Page 1: Public Service Company of Colorado Transmission Projects ...€¦ · 2 Nov 2010 In Service No CPCN Required 2. Midway-Waterton 345kV Transmission Project 3,4,5 Jun 2011 In Service

Public Service Company of ColoradoTransmission Projects Status

Public Service Company of ColoradoTransmission Projects Status

111

CCPGMay 5, 2016

Page 2: Public Service Company of Colorado Transmission Projects ...€¦ · 2 Nov 2010 In Service No CPCN Required 2. Midway-Waterton 345kV Transmission Project 3,4,5 Jun 2011 In Service

Transmission Ownership Colorado – 2016

Page 3: Public Service Company of Colorado Transmission Projects ...€¦ · 2 Nov 2010 In Service No CPCN Required 2. Midway-Waterton 345kV Transmission Project 3,4,5 Jun 2011 In Service

Transmission Planning Drivers► Load Service / Reliability

► Near-Term (1-5 years)► TPL Studies (5 year capital budget)

► Longer-Term (5-10 years)► WestConnect, CCPG, Public Policy

► Resource Accommodation► PSCo Resource Plans► Generator Interconnection Requests

► Public Policy► Senate Bill 07-100 (SB-100)► Clean Air Clean Jobs Act (CACJA)

► Other► Tariff Studies► Transmission Service

3

► Load Service / Reliability► Near-Term (1-5 years)

► TPL Studies (5 year capital budget)► Longer-Term (5-10 years)

► WestConnect, CCPG, Public Policy► Resource Accommodation

► PSCo Resource Plans► Generator Interconnection Requests

► Public Policy► Senate Bill 07-100 (SB-100)► Clean Air Clean Jobs Act (CACJA)

► Other► Tariff Studies► Transmission Service

Page 4: Public Service Company of Colorado Transmission Projects ...€¦ · 2 Nov 2010 In Service No CPCN Required 2. Midway-Waterton 345kV Transmission Project 3,4,5 Jun 2011 In Service

Generation

Name Interconnection Owner Net MW Type ISD

Arapahoe 3 (retired) Arapahoe PSCo -44 Coal 2014

Limon 3 Missile Site 345 kV NextEra 200 Wind 2014

Zuni 2 (retired) Zuni PSCo -65 Coal 2015

Golden West Jackson Fuller 230 kV Golden West 250 Wind 2015

4

Golden West Jackson Fuller 230 kV Golden West 250 Wind 2015

Hooper 1 San Luis Valley 230 kV Solar Star 52 Solar (PV) 2015

Comanche Solar Comanche 230 kV Comanche Solar 120 Solar (PV) 2016

Cherokee 3 (retired) Cherokee 115kV PSCo -152 Coal 2016

Cherokee 5,6, 7 Cherokee 115kV PSCo 570 Gas (CC) 2016

Rush Creek Missile Site 345 kV PSCo 600 Wind 2018

Page 5: Public Service Company of Colorado Transmission Projects ...€¦ · 2 Nov 2010 In Service No CPCN Required 2. Midway-Waterton 345kV Transmission Project 3,4,5 Jun 2011 In Service

Rush Creek Generation Project

►CPUC Rule 3660►600 MW of New Wind Generation►90 Miles of 345 kV Transmission►PSCo-Owned►Interconnect at Missile Site►In-Service Date: 2018►Need Pawnee – Daniels Project►Filing with the Commission on May 13, 2016

5

55

►CPUC Rule 3660►600 MW of New Wind Generation►90 Miles of 345 kV Transmission►PSCo-Owned►Interconnect at Missile Site►In-Service Date: 2018►Need Pawnee – Daniels Project►Filing with the Commission on May 13, 2016

Page 6: Public Service Company of Colorado Transmission Projects ...€¦ · 2 Nov 2010 In Service No CPCN Required 2. Midway-Waterton 345kV Transmission Project 3,4,5 Jun 2011 In Service

Rush Creek Map

6

Page 7: Public Service Company of Colorado Transmission Projects ...€¦ · 2 Nov 2010 In Service No CPCN Required 2. Midway-Waterton 345kV Transmission Project 3,4,5 Jun 2011 In Service

New Substations2016Happy Canyon (IREA Wholesale Load)Cloverly (Pleasant Valley - Retail Load)

2019Husky (New Ault)Graham Creek (New Eaton)

2022Beebe Draw (LaSalle Replacement)Box Elder Replacement

TBDReliability:

Bluestone Valley

DistributionAvery (2017)Thornton (2017)Moon Gulch (2018)Barker (2021)Conceptual: New Castle (TBD) Wilson (TBD) National Western (TBD) Sterling Ranch (TBD) Surrey Ridge (TBD)

7

2016Happy Canyon (IREA Wholesale Load)Cloverly (Pleasant Valley - Retail Load)

2019Husky (New Ault)Graham Creek (New Eaton)

2022Beebe Draw (LaSalle Replacement)Box Elder Replacement

TBDReliability:

Bluestone Valley

DistributionAvery (2017)Thornton (2017)Moon Gulch (2018)Barker (2021)Conceptual: New Castle (TBD) Wilson (TBD) National Western (TBD) Sterling Ranch (TBD) Surrey Ridge (TBD)

Page 8: Public Service Company of Colorado Transmission Projects ...€¦ · 2 Nov 2010 In Service No CPCN Required 2. Midway-Waterton 345kV Transmission Project 3,4,5 Jun 2011 In Service

New Transmission

Planned► 2016

► Rifle – Parachute 230 kV #2► 2018

► Rush Creek – Missile Site 345 kV► 2019

► Ault – Cloverly 230/115 kV► Pawnee – Daniels Park 345 kV

► 2021► Avon – Gilman 115 kV

► 2022► Weld – Rosedale 230 kV► Milton – Rosedale 230 kV

Conceptual► San Luis Valley► Glenwood – Rifle Upgrade► Parachute – Cameo 230 kV► Lamar – Front Range► Weld County Expansion (Greeley – East)► Hayden – Foidel – Gore Pass 230 kV

Loop

Planned► 2016

► Rifle – Parachute 230 kV #2► 2018

► Rush Creek – Missile Site 345 kV► 2019

► Ault – Cloverly 230/115 kV► Pawnee – Daniels Park 345 kV

► 2021► Avon – Gilman 115 kV

► 2022► Weld – Rosedale 230 kV► Milton – Rosedale 230 kV

Conceptual► San Luis Valley► Glenwood – Rifle Upgrade► Parachute – Cameo 230 kV► Lamar – Front Range► Weld County Expansion (Greeley – East)► Hayden – Foidel – Gore Pass 230 kV

Loop

Page 9: Public Service Company of Colorado Transmission Projects ...€¦ · 2 Nov 2010 In Service No CPCN Required 2. Midway-Waterton 345kV Transmission Project 3,4,5 Jun 2011 In Service

Denver/Boulder

# Project Comments ISD* Drivers1 Moon Gulch

SubstationProposed new Distribution Substation in eitherthe City of Arvada or Jefferson County to servedistribution loads

2017 Distribution

2 Pawnee – DanielsPark 345 kVTransmission Line

Add an additional 345 kV line between thePawnee and Daniels Park substations.

2019 Reliability

3 Cherokee-Arvada-Ridge230kVConversion

Convert the existing 115kV line between theCherokee and Ridge substations to a 230kVline.

2016 ReliabilityandDistribution

4 ThorntonSubstation

New substation in Thornton to serve distributionloads. Replaces the Brantner Substationproject.

2017 Distribution44Thornton

Moon Gulch

9*All project in-service dates subject to change

DENVERDENVER

22

33

ThorntonSubstation

New substation in Thornton to serve distributionloads. Replaces the Brantner Substationproject.

5 Barker Substation New Substation in Denver Area to servedistribution load growth in Historic Ballpark Area

2021 Distribution11

44Moon Gulch

55

Page 10: Public Service Company of Colorado Transmission Projects ...€¦ · 2 Nov 2010 In Service No CPCN Required 2. Midway-Waterton 345kV Transmission Project 3,4,5 Jun 2011 In Service

55

# Project Comments ISD* Drivers

1 Southwest WeldTransmission Project(SWEP)

Participate with Tri-State Project to improve reliability, increaseload-serving and resource injection capability

2017 ReliabilityLoad GrowthResource

2 Milton–Rosedale 230 kV New line from Rosedale Substation to Milton SubstationCombined with Weld – Rosedale 230kV line creates 230kVbackbone south of Greeley.

2022 ReliabilityLoad Growth

3 Rosedale – Weld 230 kVBeebe Draw Substation(La Salle Upgrade)

New line from Rosedale Substation to Ault Substation.Build a new 230 kV substation (Beebe Draw) to replace theexisting 44kV La Salle Substation.Combined with Milton – Rosedale 230kV to create 230kVbackbone south of Greeley.

2022 ReliabilityLoad Growth

4 Weld County Expansion High voltage transmission from Ault to Greeley TBD ReliabilityResource

5 Avery Substation New distribution substation to serve loads in the area 2017 Distribution

Foothills/Greeley Area

44

2266

77

8899

10*All project in-service dates subject to change

6 Wilson Substation New 115kV substation to serve distribution loads. This projectwill tap PRPA’s 115kV Horseshoe – West transmission line

TBD Distribution

7 Ault – Cloverly230/115kVSubs:Husky, Graham Ck.

New line from Ault Substation to Cloverly Substation.Create new substations near PSCo Ault and Eaton to move 44kV loads to higher voltage.

2019 ReliabilityLoad GrowthResource

8 Severence Substation Add in a new 230 kV substation by tapping the Weld Ft. St.Vrain line to service a retail customer

TBD Retail Load

9 Barnesville Substation /DCP Lucerne 2 –Barnesville 115 kV

Add in a new 115 kV Substation via a new line from DCPLucerne to the Barnesville Substation to service a retail load

TBD Retail Load

10 Box Elder Replacement Convert 44kV Box Elder Substation to a 115kV substation toservice growing loads in the area. Might tie into SWEP

TBD Load Growth

11Rosedale

332266

1010

Page 11: Public Service Company of Colorado Transmission Projects ...€¦ · 2 Nov 2010 In Service No CPCN Required 2. Midway-Waterton 345kV Transmission Project 3,4,5 Jun 2011 In Service

Current System Future System

Page 12: Public Service Company of Colorado Transmission Projects ...€¦ · 2 Nov 2010 In Service No CPCN Required 2. Midway-Waterton 345kV Transmission Project 3,4,5 Jun 2011 In Service

# Project Comments ISD* Drivers

1 Grand Jct 138/115kV Replace 50 MVA TX with 100MVA TX

2016 Reliability

2 Bluestone ValleySubstation

New 230/69 kV transformer atBluestone. New 4 mile 69 kV linefrom Bluestone to Debeque

TBD Reliability

3 Rifle–Parachute 230 kVLine

New, second 230 kV line betweenRifle and Parachute

2016 Load GrowthReliability

4 Hayden – Foidel – GorePass 230kV Loop

loop Hayden-Gore Pass 230kVline into Foidel Creek Substationcreating a Hayden-Foidel Creek230kV Line #2 and a FoidelCreek-Gore Pass 230kV line.

TBD Reliability

44

Western Slope / Mountain Area

8899

12

loop Hayden-Gore Pass 230kVline into Foidel Creek Substationcreating a Hayden-Foidel Creek230kV Line #2 and a FoidelCreek-Gore Pass 230kV line.

5 Glenwood-Rifle 69 to115kV

Replace existing Glenwood-Rifle69 kV transmission system with115 kV system

TBD Reliability

6 Gilman–Avon 115kVLine

New 10-mile 115kV line in EagleCounty for reliability and alternatesource to Holy Cross customers

2021 Reliability

7 Parachute – Cameo230kV Line

New 230 kV line from theParachute substation to Cameosubstation

TBD Reliability

8 New Castle Substation Construct a new 115 kVsubstation to service Distributionloads in New Castle

TBD Distribution

9 Wolcott Reactor Install 40 MVAR reactor atWolcott.

2017 Reliability

3322

*All project in-service dates subject to change

55

11

6677

8899

Page 13: Public Service Company of Colorado Transmission Projects ...€¦ · 2 Nov 2010 In Service No CPCN Required 2. Midway-Waterton 345kV Transmission Project 3,4,5 Jun 2011 In Service

Rifle -Parachute 230kV Project (#2)

Purpose:Serve anticipated load growth (electric-driven

compressors) in the Piceance BasinDescription20 mile 230kV lineElectrically parallel to existing 230kV line

StatusFiled CPCN in Dec 2012CPCN Granted Feb 2013ISD - 2016

13

Purpose:Serve anticipated load growth (electric-driven

compressors) in the Piceance BasinDescription20 mile 230kV lineElectrically parallel to existing 230kV line

StatusFiled CPCN in Dec 2012CPCN Granted Feb 2013ISD - 2016

Page 14: Public Service Company of Colorado Transmission Projects ...€¦ · 2 Nov 2010 In Service No CPCN Required 2. Midway-Waterton 345kV Transmission Project 3,4,5 Jun 2011 In Service

Rifle -Parachute 230kV Line #2 Location Map

14

Page 15: Public Service Company of Colorado Transmission Projects ...€¦ · 2 Nov 2010 In Service No CPCN Required 2. Midway-Waterton 345kV Transmission Project 3,4,5 Jun 2011 In Service

11

# Project Comments ISD* Drivers

1 IREA HappyCanyon

Construct a new 115 kV substationfor IREA

2016 WholesaleCustomer

South Denver/CO Springs Area

15*All project in-service dates subject to change

Page 16: Public Service Company of Colorado Transmission Projects ...€¦ · 2 Nov 2010 In Service No CPCN Required 2. Midway-Waterton 345kV Transmission Project 3,4,5 Jun 2011 In Service

PSCo Public PolicySenate Bill 07-100

►Designate “Energy Resource Zones (ERZ)”►Develop plans for the construction or expansion of

transmission facilities necessary to deliver electric powerconsistent with the timing of the development of beneficialenergy resources located in or near such zones

►Consider how transmission can be provided to encouragelocal ownership of renewable energy facilities

►Submit proposed plans, designations, and applications forcertificates of public convenience and necessity to thecommission

16

1616

►Designate “Energy Resource Zones (ERZ)”►Develop plans for the construction or expansion of

transmission facilities necessary to deliver electric powerconsistent with the timing of the development of beneficialenergy resources located in or near such zones

►Consider how transmission can be provided to encouragelocal ownership of renewable energy facilities

►Submit proposed plans, designations, and applications forcertificates of public convenience and necessity to thecommission

Page 17: Public Service Company of Colorado Transmission Projects ...€¦ · 2 Nov 2010 In Service No CPCN Required 2. Midway-Waterton 345kV Transmission Project 3,4,5 Jun 2011 In Service

Public Service Company of Colorado SB-100 projects

17

Page 18: Public Service Company of Colorado Transmission Projects ...€¦ · 2 Nov 2010 In Service No CPCN Required 2. Midway-Waterton 345kV Transmission Project 3,4,5 Jun 2011 In Service

Senate Bill 100 Project ListItem Project Zone In Service Date* Project Status

Planned

1. Missile Site 230kVSwitching Station

2 Nov 2010 In ServiceNo CPCN Required

2. Midway-Waterton 345kVTransmission Project

3,4,5 Jun 2011 In ServiceCPCN: July 2009

3. Missile Site 345kVSwitching Station

2 October 2012 In serviceCPCN: June 2010

4. Pawnee-Smoky Hill 345kVTransmission Project

1 June 2013 IN ServiceCPCN: Feb 2009

5. Pawnee-Daniels Park 345kVTransmission Project

1 2019 CPCN: April 2015

18*All project in-service dates subject to change

5. Pawnee-Daniels Park 345kVTransmission Project

1 2019 CPCN: April 2015

Conceptual

6. Lamar-Front Range 345kVTransmission Project

2, 3 TBD Studies Complete.No plans for full build-out at this time

7. Lamar-Vilas 230kVTransmission Project

3 TBD See Lamar – Front Range

8. Weld County Expansion Project 1 TBD Studies Ongoing

9. San Luis Valley 4 2022? OngoingCCPG – SLV Subcommittee

Page 19: Public Service Company of Colorado Transmission Projects ...€¦ · 2 Nov 2010 In Service No CPCN Required 2. Midway-Waterton 345kV Transmission Project 3,4,5 Jun 2011 In Service

Pawnee to Daniels Park► Cost $152 million► In-service date: 2019► Purpose: Reliability, SB

07-100;► Infrastructure: 124-mile

transmission fromPawnee Substation toDaniels Park Substationand from Smoky HillSubstation to DanielsPark Substation

► Open House Meetings inSeptember

19

► Cost $152 million► In-service date: 2019► Purpose: Reliability, SB

07-100;► Infrastructure: 124-mile

transmission fromPawnee Substation toDaniels Park Substationand from Smoky HillSubstation to DanielsPark Substation

► Open House Meetings inSeptember

Page 20: Public Service Company of Colorado Transmission Projects ...€¦ · 2 Nov 2010 In Service No CPCN Required 2. Midway-Waterton 345kV Transmission Project 3,4,5 Jun 2011 In Service

PSCo Regulatory ActivitiesRule 3206Rule 3627

PSCo Regulatory ActivitiesRule 3206Rule 3627

20

PSCo Regulatory ActivitiesRule 3206Rule 3627

PSCo Regulatory ActivitiesRule 3206Rule 3627

Zinn Photography/Courtesy of SunEdison

Page 21: Public Service Company of Colorado Transmission Projects ...€¦ · 2 Nov 2010 In Service No CPCN Required 2. Midway-Waterton 345kV Transmission Project 3,4,5 Jun 2011 In Service

CPUC Rule 3206► “Construction or Extension of Transmission Facilities”► Filed Annually – end of April► Commission Determines:

►Ordinary Course of Business►CPCN Required

► PSCo Filed Projects:►SWEP Participation►Ault – Cloverly 230/115 kV►Weld – Rosedale 230 kV►Rosedale – Milton 230 kV►Rush Creek – Missile Site 345 kV►Wolcott 40 MVAR Reactor

21

► “Construction or Extension of Transmission Facilities”► Filed Annually – end of April► Commission Determines:

►Ordinary Course of Business►CPCN Required

► PSCo Filed Projects:►SWEP Participation►Ault – Cloverly 230/115 kV►Weld – Rosedale 230 kV►Rosedale – Milton 230 kV►Rush Creek – Missile Site 345 kV►Wolcott 40 MVAR Reactor

Page 22: Public Service Company of Colorado Transmission Projects ...€¦ · 2 Nov 2010 In Service No CPCN Required 2. Midway-Waterton 345kV Transmission Project 3,4,5 Jun 2011 In Service

CPUC Rule 3627► Requires Regulated Utilities to File Transmission Report

► 10-Year Plan, 20-Year Scenario; 2-year cycle► Black Hills, Tri-State, Public Service

► Use CCPG as Forum► Proactive Stakeholder Participation► Report Filed February 2016► Proceeding Consolidated with SB07-100► Comments Received from OCC and IEA► Responses Filed April 29► ALJ Assigned to Facilitate► Expect Workshop Q2-2016► Goal: Ruling of Adequacy

22

► Requires Regulated Utilities to File Transmission Report► 10-Year Plan, 20-Year Scenario; 2-year cycle► Black Hills, Tri-State, Public Service

► Use CCPG as Forum► Proactive Stakeholder Participation► Report Filed February 2016► Proceeding Consolidated with SB07-100► Comments Received from OCC and IEA► Responses Filed April 29► ALJ Assigned to Facilitate► Expect Workshop Q2-2016► Goal: Ruling of Adequacy

Page 23: Public Service Company of Colorado Transmission Projects ...€¦ · 2 Nov 2010 In Service No CPCN Required 2. Midway-Waterton 345kV Transmission Project 3,4,5 Jun 2011 In Service

23

Page 24: Public Service Company of Colorado Transmission Projects ...€¦ · 2 Nov 2010 In Service No CPCN Required 2. Midway-Waterton 345kV Transmission Project 3,4,5 Jun 2011 In Service