pueblo chemical agent-destruction pilot plant explosive destruction system (pcapp eds) project...

18
Pueblo Chemical Agent-Destruction Pilot Plant Explosive Destruction System (PCAPP EDS) Project Update 30 October 2013 “Distribution Statement A: Approved for public release; Distribution is unlimited” UNCLASSIFIED Presented to: Pueblo Chemical Depot (PCD) Citizens’ Advisory Commission (CAC) Presented by: Mr. Steven Bird PCAPP EDS Project Lead Joint Project Manager-Elimination (Provisional) (JPM-E (P))

TRANSCRIPT

Pueblo Chemical Agent-Destruction Pilot

Plant Explosive Destruction System

(PCAPP EDS)

Project Update

30 October 2013

“Distribution Statement A: Approved for

public release; Distribution is unlimited”

UNCLASSIFIED

Presented to:

Pueblo Chemical Depot (PCD) Citizens’ Advisory Commission (CAC)

Presented by:

Mr. Steven Bird

PCAPP EDS Project Lead

Joint Project Manager-Elimination (Provisional) (JPM-E (P))

Provide the Pueblo Chemical Depot (PCD) Citizens’ Advisory

Commission (CAC) with an update on the current status of

the construction contracting and planning effort supporting

Pueblo Chemical Agent-Destruction Pilot Plant Explosive

Destruction System (PCAPP EDS) Project

Objective

EDS Phase 2

MissionTo destroy an estimated 1,366 over packed leakers, DOT cylinders,

estimated rejects and leakers, and contaminated bursters identified

by the ACWA Program in a safe and efficient manner that is

protective of human health (workers and residents) and the

environment

Overview of PCAPP EDS

Operators place

the item in the

munition holder.

Linear-shaped charges are

attached along the munition body

and the item is placed in the

munition holder (up to 6 pack).

Operators slide the

munition holder into the

vessel.

Operators remotely detonate the

linear shaped charges to access

the munition body and destroy

explosives.

Once neutralization chemicals are

added, the vessel is heated with steam

and rotated to mix the contents. A

liquid sample is collected to verify

treatment goal ( less than 50 ppm) has

been met prior to draining.

The vessel is closed and

sealed.

Next water rinse is added, steam

heated, rotated, and drained. An air

sample is collected to verify treatment

goal has been met prior to opening

door and removing scrap metal.

PCAPP EDS Process Summary

Forecasted Items to be Destroyed

Overview of PCAPP EDS

Item Rejects LeakersKnown

OverpacksContaminated Total

155mm 59 114 197 0 370

105mm 391 58 264 0 713

4.2” Mortar 89 15 88 0 192

DOT

Cylinders

9 0 2 0 11

Bursters 0 0 0 80 80

Total 548 187 551 80 1,366

• Operations will be campaigned starting with over packed items and DOT cylinders,

followed by 155mm projectiles, 105 mm projectiles, and 4.2” mortars and

contaminated bursters

• A temporary closure of the PCAPP EDS site is planned between each campaign

Site Construction - Contractor

• Corps of Engineers (COE), Huntsville received approval from Small

Business Administration on 30 August 2013 to move forward with

8/(a)/Native American contractor

• The contractor, Komada LLC, based in Colorado Springs, CO, has a

strong local presence and a good relationship with state regulatory

bodies

• The design partner, Merrick & Company, based in Denver, CO, has

done chemical demilitarization work for Huntsville in the past

• Past performance ratings have been in the outstanding range

PCAPP EDS Contracting Status

Construction Schedule

• Initial proposal received: October 16, 2013

• Projected Contract Award Date: October 28, 2013

• Projected Design Start: November 2013

• Projected Design Complete: February 2014

• Projected Construction Start: February 2014

• Projected Construction Complete: July 2014

• Beneficial Occupancy Date (BOD): July 2014

• Projected Final As-Built Drawings/3rd Party Certification: August 8,

2014

Site Construction – Major Components

• EDS Trailers – P2R and P2A

• Environmental Enclosures – Each with support equipment

• Explosives Storage Magazines – Store donor explosives

• Air Monitoring Trailers – Hold air monitoring instruments

• Command Post Modular Facility (outside Chemical Limited Area (CLA))

• Treaty Trailer Modular Facility (outside CLA)

• Crew Change House Modular Facility

• Laboratory Facility

• Entry Control Facility (personnel and vehicular)

• Emergency site back up generator

• On-site munition storage (existing ammunition igloo)

• On-site warehouse (existing ammunition igloo)

• Connection to G-block CLA

Overview of PCAPP EDS

Site Location

Site Construction Concrete Pad Diagram

Site Construction Concrete Pad Close Up

Site Construction – Command Post

OFFICE

1

CP 3CP 2

REF REF

KITCHEN

BREAK ROOM

PROJECTION

SCREEN

WORK STATIONS

CONFERENCE

ROOM

CP 1

RECORDS

STORAGE

ROOM

JANITORMEN’S

ROOMLADIES’

ROOM

ELEC/

SERVER ROOM

OFFICE

2

OFFICE

3

OFFICE

4

NSF

OFFICE

COMMAND POST

QUADRUPLE WIDE, 64’ X 64’

Scale

10’

64’

64’

Plan TableBook

Shelf

Book

ShelfPlan TableBook

Shelf

Book

ShelfPlan TableBook

Shelf

Book

Shelf

Site Construction – Change House

REF REFICE

MACH

SHWR

SHWR

SHWR

ELEC

BE

NC

H

JANITOR’S

CLOSET

SHWR

SHWR

MEN’S

ROOM

MEN’S

LOCKERS

LADIES’

ROOM

PPE

DRESSOUT

ROOM

WOMEN’S

LOCKERS

LOCKERS

CHANGE HOUSE

TRIPLE WIDE, 64’ X 48’

Scale

10’

64’

48’

BE

NC

H

BE

NC

H

WORK STATIONS

Site Construction – Treaty Trailer

PCAPP EDS Chemical Laboratory

Mobile Chemical Laboratory Structure

PCAPP EDS Use of Existing Igloos

Igloo Refurbishment and Upgrade

• Igloos H1101, H1102, H1103 refurbished/upgraded to support PCAPP EDS

• Upgrades include:

‒ Apron extensions (H1102 and H1103)

‒ Igloo Containment System (Igloo H1102 only)

‒ Repair of magazine membrane

‒ Adding earthen cover

‒ Repairing Lightning Protection System

‒ Repairing vent system

‒ Installing fusible links

‒ Stenciling magazine numbers

‒ Epoxy coating (H1102 and H1103)

Questions?

For Information on the Joint Project Manager for Elimination (Provisional)

Mr. Steven Bird

Operations Directorate

PCAPP EDS Project Lead, JPM-E (P)

Phone - 410.436.4577

[email protected]