pueblo chemical agent-destruction pilot plant explosive destruction system (pcapp eds) project...
Upload: program-executive-office-assembled-chemical-weapons-alternatives-peo-acwa
Post on 16-Jul-2015
118 views
TRANSCRIPT
Pueblo Chemical Agent-Destruction Pilot
Plant Explosive Destruction System
(PCAPP EDS)
Project Update
30 October 2013
“Distribution Statement A: Approved for
public release; Distribution is unlimited”
UNCLASSIFIED
Presented to:
Pueblo Chemical Depot (PCD) Citizens’ Advisory Commission (CAC)
Presented by:
Mr. Steven Bird
PCAPP EDS Project Lead
Joint Project Manager-Elimination (Provisional) (JPM-E (P))
Provide the Pueblo Chemical Depot (PCD) Citizens’ Advisory
Commission (CAC) with an update on the current status of
the construction contracting and planning effort supporting
Pueblo Chemical Agent-Destruction Pilot Plant Explosive
Destruction System (PCAPP EDS) Project
Objective
EDS Phase 2
MissionTo destroy an estimated 1,366 over packed leakers, DOT cylinders,
estimated rejects and leakers, and contaminated bursters identified
by the ACWA Program in a safe and efficient manner that is
protective of human health (workers and residents) and the
environment
Overview of PCAPP EDS
Operators place
the item in the
munition holder.
Linear-shaped charges are
attached along the munition body
and the item is placed in the
munition holder (up to 6 pack).
Operators slide the
munition holder into the
vessel.
Operators remotely detonate the
linear shaped charges to access
the munition body and destroy
explosives.
Once neutralization chemicals are
added, the vessel is heated with steam
and rotated to mix the contents. A
liquid sample is collected to verify
treatment goal ( less than 50 ppm) has
been met prior to draining.
The vessel is closed and
sealed.
Next water rinse is added, steam
heated, rotated, and drained. An air
sample is collected to verify treatment
goal has been met prior to opening
door and removing scrap metal.
PCAPP EDS Process Summary
Forecasted Items to be Destroyed
Overview of PCAPP EDS
Item Rejects LeakersKnown
OverpacksContaminated Total
155mm 59 114 197 0 370
105mm 391 58 264 0 713
4.2” Mortar 89 15 88 0 192
DOT
Cylinders
9 0 2 0 11
Bursters 0 0 0 80 80
Total 548 187 551 80 1,366
• Operations will be campaigned starting with over packed items and DOT cylinders,
followed by 155mm projectiles, 105 mm projectiles, and 4.2” mortars and
contaminated bursters
• A temporary closure of the PCAPP EDS site is planned between each campaign
Site Construction - Contractor
• Corps of Engineers (COE), Huntsville received approval from Small
Business Administration on 30 August 2013 to move forward with
8/(a)/Native American contractor
• The contractor, Komada LLC, based in Colorado Springs, CO, has a
strong local presence and a good relationship with state regulatory
bodies
• The design partner, Merrick & Company, based in Denver, CO, has
done chemical demilitarization work for Huntsville in the past
• Past performance ratings have been in the outstanding range
PCAPP EDS Contracting Status
Construction Schedule
• Initial proposal received: October 16, 2013
• Projected Contract Award Date: October 28, 2013
• Projected Design Start: November 2013
• Projected Design Complete: February 2014
• Projected Construction Start: February 2014
• Projected Construction Complete: July 2014
• Beneficial Occupancy Date (BOD): July 2014
• Projected Final As-Built Drawings/3rd Party Certification: August 8,
2014
Site Construction – Major Components
• EDS Trailers – P2R and P2A
• Environmental Enclosures – Each with support equipment
• Explosives Storage Magazines – Store donor explosives
• Air Monitoring Trailers – Hold air monitoring instruments
• Command Post Modular Facility (outside Chemical Limited Area (CLA))
• Treaty Trailer Modular Facility (outside CLA)
• Crew Change House Modular Facility
• Laboratory Facility
• Entry Control Facility (personnel and vehicular)
• Emergency site back up generator
• On-site munition storage (existing ammunition igloo)
• On-site warehouse (existing ammunition igloo)
• Connection to G-block CLA
Site Construction – Command Post
OFFICE
1
CP 3CP 2
REF REF
KITCHEN
BREAK ROOM
PROJECTION
SCREEN
WORK STATIONS
CONFERENCE
ROOM
CP 1
RECORDS
STORAGE
ROOM
JANITORMEN’S
ROOMLADIES’
ROOM
ELEC/
SERVER ROOM
OFFICE
2
OFFICE
3
OFFICE
4
NSF
OFFICE
COMMAND POST
QUADRUPLE WIDE, 64’ X 64’
Scale
10’
64’
64’
Plan TableBook
Shelf
Book
ShelfPlan TableBook
Shelf
Book
ShelfPlan TableBook
Shelf
Book
Shelf
Site Construction – Change House
REF REFICE
MACH
SHWR
SHWR
SHWR
ELEC
BE
NC
H
JANITOR’S
CLOSET
SHWR
SHWR
MEN’S
ROOM
MEN’S
LOCKERS
LADIES’
ROOM
PPE
DRESSOUT
ROOM
WOMEN’S
LOCKERS
LOCKERS
CHANGE HOUSE
TRIPLE WIDE, 64’ X 48’
Scale
10’
64’
48’
BE
NC
H
BE
NC
H
WORK STATIONS
PCAPP EDS Use of Existing Igloos
Igloo Refurbishment and Upgrade
• Igloos H1101, H1102, H1103 refurbished/upgraded to support PCAPP EDS
• Upgrades include:
‒ Apron extensions (H1102 and H1103)
‒ Igloo Containment System (Igloo H1102 only)
‒ Repair of magazine membrane
‒ Adding earthen cover
‒ Repairing Lightning Protection System
‒ Repairing vent system
‒ Installing fusible links
‒ Stenciling magazine numbers
‒ Epoxy coating (H1102 and H1103)
For Information on the Joint Project Manager for Elimination (Provisional)
Mr. Steven Bird
Operations Directorate
PCAPP EDS Project Lead, JPM-E (P)
Phone - 410.436.4577