pulsar construction schedule

2
Pulsar Construction Schedule • Assembly vendor-Altron Inc loacated in Anoka, MN • QTY 2 first article • Production 43 units • PC vendor is Proto Express (placed by Altron)

Upload: branxton

Post on 05-Jan-2016

24 views

Category:

Documents


0 download

DESCRIPTION

Pulsar Construction Schedule. Assembly vendor-Altron Inc loacated in Anoka, MN QTY 2 first article Production 43 units PC vendor is Proto Express (placed by Altron). All long lead components have been purchased by The Univ of Chicago They are being shipped today - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Pulsar Construction Schedule

Pulsar Construction Schedule

• Assembly vendor-Altron Inc loacated in Anoka, MN

• QTY 2 first article

• Production 43 units

• PC vendor is Proto Express (placed by Altron)

Page 2: Pulsar Construction Schedule

All long lead components have been purchased by The Univ of Chicago

They are being shipped today

First blank boards must be tested and approved by The University of Chicago

Vendor expects to deliver first item by end of April

(HaroldMJS):

Negotiations are in progress.

Harold’s best current estimate is that after we approve the first board, the rest will come in about 3 weeks.