rate impacts of various dsm program designs

11
Rate Impacts of Various DSM Program Designs Dave Lamont EEU Budget Negotiations April 10, 2006

Upload: cassidy-rosales

Post on 30-Dec-2015

49 views

Category:

Documents


4 download

DESCRIPTION

Rate Impacts of Various DSM Program Designs. Dave Lamont EEU Budget Negotiations April 10, 2006. Model Design. Based on 2004 revenues and sales Losses attributed to Sales and DSM impacts are adjusted to VELCO Base load forecast assumes no new DSM after 2008 - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Rate Impacts of Various DSM Program Designs

Rate Impacts of Various DSMProgram Designs

Dave Lamont

EEU Budget Negotiations

April 10, 2006

Page 2: Rate Impacts of Various DSM Program Designs

Model Design

• Based on 2004 revenues and sales

• Losses attributed to Sales and DSM impacts are adjusted to VELCO

• Base load forecast assumes no new DSM after 2008

• Base load growth (no DSM) assumed to be 1.5%

Page 3: Rate Impacts of Various DSM Program Designs

Model Design

• 2004 Base revenues separated into VY, HQ, and IPP plus “everything else”

• Revenues are adjusted going forward for impacts of contract expirations as well as incremental market purchases and sales. “Everything else” escalated at inflation (2.5%)

• Model used ICF avoided cost study, including ICAP cost projections

Page 4: Rate Impacts of Various DSM Program Designs

Model Design

• RR includes DSM budgets for ‘06 – ’08

• Revenue requirements (RR) adjusted for T&D expenditures above base peak load

Page 5: Rate Impacts of Various DSM Program Designs

Scenarios

• Model used DSM scenarios as presented by EVT at the 12/3/2005 workshop

• A second set was developed which assumed 2008 savings levels continued through 2025 with costs escalated at inflation (2.5%)

• Savings estimates incorporated EVT decay function

• DSM costs expensed in each year

Page 6: Rate Impacts of Various DSM Program Designs

Results

• Rates increased

• Revenue requirements (including DSM costs) decreased

Page 7: Rate Impacts of Various DSM Program Designs

Base CaseBase Case: Currently Committed EVT Programs as proposed    

Costs 2006 2007 2008 TOTAL Cost/ MWh

Current EEU $16.7 $17.6 $18.2 $52.5  

GWh Savings 2006 2007 2008 TOTAL  

Current EEU

61

71 81

213 $246.02

Rate and Bill Impacts 3 Year programs  Programs continued at 2008

levels    

Levelized Rate 2006 - 2015 $0.1305   Levelized Rate $0.1320  

Rate Change 2006 - 2015 23.7% Rate Change 1.10%  

NPV Rve Req 2006 - 2015 $5,720 NPV Rev Req $5,673  

Revenue Requirement Change 41%   Rev Req Change -0.81%  

Page 8: Rate Impacts of Various DSM Program Designs

Scenario 1: Modest increment with current strategies, as presented at 12/1 PSB Workshop

Costs 2006 2007 2008 TOTALCost/ MWh

Current EEU $16.7 $17.6 $18.2 $52.5  

Scenario 1 Increment $1.4 $3.3 $5.5 $10.1  

Scenario 1 Total $18.0 $20.9 $23.7 $62.6  

% Increase 8% 19% 30% 19%  

     

GWh Savings 2006 2007 2008 TOTAL  

Current EEU 61 71 81 213 $246.02

Scenario 1 Increment 6 12 26 44 $227.21

Scenario 1 Total 67 83 107 258 $242.77

% Increase 9% 17% 33% 21%  

   

Rate and Bill Impacts 3 Year programs   Programs continued at 2008 levels    

Levelized Rate 2006 - 2015 $0.1307 Levelized Rate $0.1325  

Rate Change from Base Case 0.10% Rate Change 1.49%  

NPV Rve Req 2006 - 2015 $5,689 NPV Rev Req $5,608  

Rev Req change from Base Case -0.53%   Rev Req Change -1.96%  

Page 9: Rate Impacts of Various DSM Program Designs

Scenario 2: Double spending in 2008, as presented at 12/1 PSB Workshop  

Costs 2006 2007 2008 TOTAL Cost/ MWh

Current EEU $16.7 $17.6 $18.2 $52.5  

Scenario 2 Increment $3.4 $8.8 $17.2 $29.5  

Scenario 2 Total $20.1 $26.5 $35.4 $82.0  

% Increase 21% 50% 95% 56%  

     

GWh Savings 2006 2007 2008 TOTAL  

Current EEU 61 71 81

213 $246.02

Scenario 2 Increment 13 34 75

122 $241.69

Scenario 2 Total 74 105 156

335 $244.44

% Increase 21% 48% 93% 57%  

   

Rate and Bill Impacts 3 Year programs  Programs continued

at 2008 levels    

Levelized Rate 2006 - 2015 $0.1307 Levelized Rate $0.1332  

Rate Change from Base Case 0.16% Rate Change 2.01%  

NPV Rve Req 2006 - 2015 $5,681 NPV Rev Req $5,526  

Rev Req change from Base Case -0.67%   Rev Req Change -3.38%  

Page 10: Rate Impacts of Various DSM Program Designs

Scenario 4: Implement existing contract spending and strategies with current funding, PLUS as much additional cost-effective investment over next 3 years w/o policy constraints  

Costs 2006 2007 2008 TOTAL Cost/ MWh

Current EEU $16.7 $17.6 $18.2 $52.5  

Scenario 4 Increment $20.8 $61.3 $88.1 $170.1  

Scenario 4 Total $37.4 $78.9 $106.3 $222.6  

% Increase 125% 348% 484% 324%  

     

GWh Savings 2006 2007 2008 TOTAL  

Current EEU 61 71 81 213 $246.02

Scenario 4 Increment 36 105 147 288 $591.21

Scenario 4 Total 97 176 228 501 $444.26

% Increase 59% 148% 181% 135%  

   

Rate and Bill Impacts 3 Year programs   Programs continued at 2008 levels    

Levelized Rate 2006 - 2015 $0.1332 Levelized Rate $0.1439  

Rate Change from Base Case 2.07% Rate Change 10.24%  

NPV Rve Req 2006 - 2015 $5,706 NPV Rev Req $5,744  

Rev Req change from Base Case -0.24%   Rev Req Change 0.43%  

Page 11: Rate Impacts of Various DSM Program Designs

Scenario 5: Ramp up to annual spending of $52.5 million (three times current level) in 2008; Maintain current policies for up to 2 times spending, then unconstrained.  

Costs 2006 2007 2008 TOTAL Cost/ MWh

Current EEU $16.7 $17.6 $18.2 $52.5  

Scenario 5 Increment $3.4 $13.9 $34.3 $51.6  

Scenario 5 Total $20.1 $31.5 $52.5 $104.1  

% Increase 21% 79% 188% 98%  

   

GWh Savings 2006 2007 2008 TOTAL  

Current EEU 61 71 81 213 $246.02

Scenario 5 Increment 13 75 214 301 $171.07

Scenario 5 Total 74 146 295 515 $202.13

% Increase 21% 105% 264% 141%  

 

Rate and Bill Impacts 3 Year programs  Programs continued at 2008

levels    

Levelized Rate 2006 - 2015 $0.1311 Levelized Rate $0.1356  

Rate Change from Base Case 0.44% Rate Change 3.88%  

NPV Rve Req 2006 - 2015 $5,673 NPV Rev Req $5,533  

Rev Req change from Base Case -0.81%   Rev Req Change -3.25%