rate impacts of various dsm program designs
DESCRIPTION
Rate Impacts of Various DSM Program Designs. Dave Lamont EEU Budget Negotiations April 10, 2006. Model Design. Based on 2004 revenues and sales Losses attributed to Sales and DSM impacts are adjusted to VELCO Base load forecast assumes no new DSM after 2008 - PowerPoint PPT PresentationTRANSCRIPT
Rate Impacts of Various DSMProgram Designs
Dave Lamont
EEU Budget Negotiations
April 10, 2006
Model Design
• Based on 2004 revenues and sales
• Losses attributed to Sales and DSM impacts are adjusted to VELCO
• Base load forecast assumes no new DSM after 2008
• Base load growth (no DSM) assumed to be 1.5%
Model Design
• 2004 Base revenues separated into VY, HQ, and IPP plus “everything else”
• Revenues are adjusted going forward for impacts of contract expirations as well as incremental market purchases and sales. “Everything else” escalated at inflation (2.5%)
• Model used ICF avoided cost study, including ICAP cost projections
Model Design
• RR includes DSM budgets for ‘06 – ’08
• Revenue requirements (RR) adjusted for T&D expenditures above base peak load
Scenarios
• Model used DSM scenarios as presented by EVT at the 12/3/2005 workshop
• A second set was developed which assumed 2008 savings levels continued through 2025 with costs escalated at inflation (2.5%)
• Savings estimates incorporated EVT decay function
• DSM costs expensed in each year
Results
• Rates increased
• Revenue requirements (including DSM costs) decreased
Base CaseBase Case: Currently Committed EVT Programs as proposed
Costs 2006 2007 2008 TOTAL Cost/ MWh
Current EEU $16.7 $17.6 $18.2 $52.5
GWh Savings 2006 2007 2008 TOTAL
Current EEU
61
71 81
213 $246.02
Rate and Bill Impacts 3 Year programs Programs continued at 2008
levels
Levelized Rate 2006 - 2015 $0.1305 Levelized Rate $0.1320
Rate Change 2006 - 2015 23.7% Rate Change 1.10%
NPV Rve Req 2006 - 2015 $5,720 NPV Rev Req $5,673
Revenue Requirement Change 41% Rev Req Change -0.81%
Scenario 1: Modest increment with current strategies, as presented at 12/1 PSB Workshop
Costs 2006 2007 2008 TOTALCost/ MWh
Current EEU $16.7 $17.6 $18.2 $52.5
Scenario 1 Increment $1.4 $3.3 $5.5 $10.1
Scenario 1 Total $18.0 $20.9 $23.7 $62.6
% Increase 8% 19% 30% 19%
GWh Savings 2006 2007 2008 TOTAL
Current EEU 61 71 81 213 $246.02
Scenario 1 Increment 6 12 26 44 $227.21
Scenario 1 Total 67 83 107 258 $242.77
% Increase 9% 17% 33% 21%
Rate and Bill Impacts 3 Year programs Programs continued at 2008 levels
Levelized Rate 2006 - 2015 $0.1307 Levelized Rate $0.1325
Rate Change from Base Case 0.10% Rate Change 1.49%
NPV Rve Req 2006 - 2015 $5,689 NPV Rev Req $5,608
Rev Req change from Base Case -0.53% Rev Req Change -1.96%
Scenario 2: Double spending in 2008, as presented at 12/1 PSB Workshop
Costs 2006 2007 2008 TOTAL Cost/ MWh
Current EEU $16.7 $17.6 $18.2 $52.5
Scenario 2 Increment $3.4 $8.8 $17.2 $29.5
Scenario 2 Total $20.1 $26.5 $35.4 $82.0
% Increase 21% 50% 95% 56%
GWh Savings 2006 2007 2008 TOTAL
Current EEU 61 71 81
213 $246.02
Scenario 2 Increment 13 34 75
122 $241.69
Scenario 2 Total 74 105 156
335 $244.44
% Increase 21% 48% 93% 57%
Rate and Bill Impacts 3 Year programs Programs continued
at 2008 levels
Levelized Rate 2006 - 2015 $0.1307 Levelized Rate $0.1332
Rate Change from Base Case 0.16% Rate Change 2.01%
NPV Rve Req 2006 - 2015 $5,681 NPV Rev Req $5,526
Rev Req change from Base Case -0.67% Rev Req Change -3.38%
Scenario 4: Implement existing contract spending and strategies with current funding, PLUS as much additional cost-effective investment over next 3 years w/o policy constraints
Costs 2006 2007 2008 TOTAL Cost/ MWh
Current EEU $16.7 $17.6 $18.2 $52.5
Scenario 4 Increment $20.8 $61.3 $88.1 $170.1
Scenario 4 Total $37.4 $78.9 $106.3 $222.6
% Increase 125% 348% 484% 324%
GWh Savings 2006 2007 2008 TOTAL
Current EEU 61 71 81 213 $246.02
Scenario 4 Increment 36 105 147 288 $591.21
Scenario 4 Total 97 176 228 501 $444.26
% Increase 59% 148% 181% 135%
Rate and Bill Impacts 3 Year programs Programs continued at 2008 levels
Levelized Rate 2006 - 2015 $0.1332 Levelized Rate $0.1439
Rate Change from Base Case 2.07% Rate Change 10.24%
NPV Rve Req 2006 - 2015 $5,706 NPV Rev Req $5,744
Rev Req change from Base Case -0.24% Rev Req Change 0.43%
Scenario 5: Ramp up to annual spending of $52.5 million (three times current level) in 2008; Maintain current policies for up to 2 times spending, then unconstrained.
Costs 2006 2007 2008 TOTAL Cost/ MWh
Current EEU $16.7 $17.6 $18.2 $52.5
Scenario 5 Increment $3.4 $13.9 $34.3 $51.6
Scenario 5 Total $20.1 $31.5 $52.5 $104.1
% Increase 21% 79% 188% 98%
GWh Savings 2006 2007 2008 TOTAL
Current EEU 61 71 81 213 $246.02
Scenario 5 Increment 13 75 214 301 $171.07
Scenario 5 Total 74 146 295 515 $202.13
% Increase 21% 105% 264% 141%
Rate and Bill Impacts 3 Year programs Programs continued at 2008
levels
Levelized Rate 2006 - 2015 $0.1311 Levelized Rate $0.1356
Rate Change from Base Case 0.44% Rate Change 3.88%
NPV Rve Req 2006 - 2015 $5,673 NPV Rev Req $5,533
Rev Req change from Base Case -0.81% Rev Req Change -3.25%