response and remediation program update

20
Date #, 2009 Presenter Name Response and Remediation Program Update April 16, 2013 Derrick Williams, Program Manager

Upload: deo

Post on 19-Mar-2016

54 views

Category:

Documents


2 download

DESCRIPTION

Response and Remediation Program Update. April 16, 2013Derrick Williams, Program Manager. Response and Remediation Program. Hazardous Site Response Program Voluntary Remediation Program Brownfields Program CERCLA PA/SI Team. Legislative Update. SB176 – Recommended to Study Committee - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Response and Remediation Program Update

Date #, 2009 Presenter Name

Response and Remediation Program Update

April 16, 2013 Derrick Williams, Program Manager

Page 2: Response and Remediation Program Update

Georgia Department of Natural Resources

•Hazardous Site Response Program

•Voluntary Remediation Program

•Brownfields Program

•CERCLA PA/SI Team

Response and Remediation Program

Page 3: Response and Remediation Program Update

Georgia Department of Natural Resources

• SB176 – Recommended to Study Committee

• HB276 – Reauthorized SW/HW Fees

Legislative Update

Page 4: Response and Remediation Program Update

Georgia Department of Natural Resources

• Fees/fines Collected $13,615,384

• Fees Appropriated $2,939,882

• Local Gov Reimbursement $1,622,178

FY12 HSRA Funding

Page 5: Response and Remediation Program Update

Georgia Department of Natural Resources

HSI Data

Page 6: Response and Remediation Program Update

Georgia Department of Natural Resources

Hazardous Site Inventory• 554 total HSI sites

• 297 active sites with responsible parties identified– 199 cleanups in progress

– 67 investigations in progress

– 31 no action taken (due to lack of resources)

• 124 local gov. solid waste landfills

• 70 RCRA permitted sites (hazardous waste)

• 63 orphan sites

6

Page 7: Response and Remediation Program Update

Georgia Department of Natural Resources

• $5,000 per application

• Invoicing $75/hour for EPD overview

• $431,550 collected to date

VRP Application Review Fees

Page 8: Response and Remediation Program Update

Georgia Department of Natural Resources

VRP Growth

Page 9: Response and Remediation Program Update

Georgia Department of Natural Resources

VRP Applications

•65 Applications received

•53 Applications approved

•8 Applications under review

•4 Applications withdrawn

•4 Properties delisted

Page 10: Response and Remediation Program Update

Georgia Department of Natural Resources

VRP Program Results

• 8 participants have stopped active groundwater corrective action

• 28 participants have or propose UECs to restrict groundwater use

• 2 participants propose active groundwater corrective action

Page 11: Response and Remediation Program Update

Georgia Department of Natural Resources

VRP Program Refinement

• Develop application checklist

• Application reviews completed in < 90 days

• All VRP applications handled by VRP Program

• Limit financial assurance to cost of long-term care of exposure controls

Page 12: Response and Remediation Program Update

Georgia Department of Natural Resources

Federal Brownfields Funding

Page 13: Response and Remediation Program Update

Georgia Department of Natural Resources

• $3,000 per application

• $1,359,000 collected to date

• VRP Escrow Account Act passed in 2010

• Allows retention and use of application fees by Brownfields Program

Brownfields Application Review Fees

Page 14: Response and Remediation Program Update

Georgia Department of Natural Resources

Brownfields Fees

Page 15: Response and Remediation Program Update

Georgia Department of Natural Resources

Brownfields Applications

Page 16: Response and Remediation Program Update

Georgia Department of Natural Resources

Brownfields Application Types

455 Applications to date

Page 17: Response and Remediation Program Update

Georgia Department of Natural Resources

Brownfield Application Status

Page 18: Response and Remediation Program Update

Georgia Department of Natural Resources

Brownfields Program Results

• >450 Brownfields applications received to date

• 5,500 acres undergoing voluntary cleanup

• Millions of dollars invested in cleanup with minimal expense to taxpayers

• Billion+ dollars statewide being invested in properties that were blighted or underutilized

Page 19: Response and Remediation Program Update

Georgia Department of Natural Resources

• 262 final LOLs issued

• 2,524 acres certified in compliance with RRS

• 772,962 tons of contaminated soil remediated

Brownfields Completed

Page 20: Response and Remediation Program Update

Georgia Department of Natural Resources

Contact Information

Derrick Williams - ManagerResponse and Remediation Program

[email protected]