rfp 300009943.addendum iii -...
TRANSCRIPT
April 30, 2018
ADDENDUM III
TO: ALL POTENTIAL PROPOSERS
RE: RFP #: 3000009943, Mid-Barataria Sediment Diversion (BA-0153) Independent Cost Estimator (ICE) Contractor
PROPOSAL DUE DATE: MAY 10, 2018 @ 3:00PM
This addendum and associated attachment shall be considered part of the RFP. The revisions and additions in this addendum supersede the requirements in the advertised RFP.
I. QUESTIONS AND ANSWERS
1. Q. My request is to forward the pre-conference document and the sign-in sheet? A. See attached.
2. Q. If a company was to participate as a part of an ORT or as ICE Contractor for the
CPRA Mid Basin Sediment Diversion Project, would that same company also be allowed to participate in the construction efforts under the future CMAR teams for the various projects?
A. A firm on the ICE Contractor Team for Mid-Barataria would not be able to participate on the Design Team or CMAR Team for Mid-Barataria Sediment Diversion Project. A firm would be able to participate on the Design Team, ICE Contractor Team, or CMAR Team for Mid-Breton Sediment Diversion Project.
3. Q. Please Consider removing the following Mandatory Qualification listed in 1.8.1.
E. Mechanical Estimator: The Mechanical Estimator shall have at least 10 years of hard bid mechanical estimating experience. The Mechanical Estimator shall have a degree in Mechanical Engineering. The Mechanical Estimator may be a staff member of either the prime or a subcontractor.
F. Electrical Estimator: The Electrical Estimator shall have at least 10 years of hard bid electrical estimating experience. The Electrical Estimator shall have a degree in Electrical Engineering. The Electrical Estimator may be a staff member of either the prime or a subcontractor.
2
For the following reasons:
a. It is our experience and recommendation that these positions are not necessary and will add costs to the program. These scopes will be subcontracted by the CMAR and this work will go through a competitive process that will receive multiple quotes.
b. These positions were not identified as a mandatory requirement in the CMAR’s RFQ. An ICE estimator with a General Contracting background will be able to understand the level of coordination necessary for these disciplines in order to complete their work, and any potential coordination costs associated with the individual subcontractor quotes.
c. If the CMAR does want to take on this scope, quotes can still be solicited from subcontractors to check the costs. Some agencies require Prime CMAR Contractors to attain competitive quotes, and this could be instituted if necessary.
d. The Prime CMAR is bound to perform between 30% to 70% of the work. The Electrical and Mechanical work will be a good opportunities for subcontracted work.
e. The requirement for a degree in Electrical and Mechanical Engineering and 10 years of hard estimating experience will be hard to come by. The estimating experience comes from a history of managing this work from a contractors background. This could be adjusted to “Construction Management, Civil Engineering or in a related field” as with your other mandatory qualified fields.
f. If necessary, these positions could be captured as “Lead Discipline Estimators” as identified in the CMAR RFQ. This would show depth of team if needed in order to meet certain contract deadlines.
A. After further review of the mandatory qualifications, it is in CPRA’s best interest to move all qualifications to Section 1.8.2, Desirable Qualifications. The Mechanical and Electrical Estimator positions will be included under Section 1.8.2, Desirable Qualifications. See Section II of this Addendum.
4. Q. Paragraph 1.9.1 D lists: “Evidence of a thorough working knowledge of and the technical expertise necessary to use commercial off-the shelf (OTS) software, to include Sage Timberline®, MC2® and US Cost Success®.”, but omits HCSS from the list. HCSS is listed as a requirement in 1.8.1. Please include HCSS in the list of acceptable estimating software packages.
A. HCSS is an acceptable commercial OTS cost estimating software. See Section II of this Addendum.
3
5. Q. Please Consider removing the following Mandatory Qualification listed in 1.8.1. G. Purchaser: The Purchaser shall have at least 5 years of experience purchasing, preferably public sector procurement, or related work. The Purchaser shall have a degree in Accounting, Finance, or in a related field. The Purchaser shall have knowledge of large scale purchasing methods as well as federal, state and local purchasing laws and shall be proficient in word processing, excel, database and presentation software. The Purchaser may be a staff member of either the prime or a subcontractor. For the following reasons: a. It is our experience and recommendation that this position is not necessary and will add costs to the program. b. The CMAR Contractor is required to submit a Procurement Plan which should be tied to a competitive process. The ICE will be involved in an audit of the selection process in order to validate that CPRA is receiving good value. c. The ICE historically has a hard time getting quotes on projects when the vendors learn that there is no opportunity for them to receive work when they submit quotes. All quotes received by the CMAR should be shared with the team. d. Estimators need to be involved in the selection process as all quotes received will be qualified with inclusions and exclusions. The estimators will need to adjust their estimates based on the individual quotes. e. The Purchaser would serve as a middle man and is unnecessary to the process.
A. After further review of the mandatory qualifications, it is in CPRA’s best interest to move all qualifications to Section 1.8.2, Desirable Qualifications. The Purchaser will be included under Section 1.8.2, Desirable Qualifications. See Section II of this Addendum.
6. Q. Would the CPRA delay the selection of the ICE Contractor until CMAR Contractor is selected?
A. No.
7. Q. Can a firm submit on the ICE Contractor RFQ as Prime without disqualifying a CMAR Contractor if also on their team?
A. A firm may submit a proposal to serve as the ICE Contractor under this RFP without disqualifying a prospective CMAR Contractor team from consideration.
8. Q. Can a firm submit on the ICE Contractor RFQ as a SubConsultant without disqualifying a CMAR Contractor if also on their team?
A. A firm may be listed as a sub-consultant to an ICE Contractor under this RFP without disqualifying a prospective CMAR Contractor team from consideration.
9. Q. Can a firm submit on the ICE Contractor RFQ with the understanding that should their CMAR Contractor be selected, the ICE RFQ Submittal would be considered non-responsive? This would be noted in bold text in the cover letter.
4
A. The selected prime from the ICE solicitation cannot be a subcontractor on the selected CMAR team. Should a proposer be selected for the ICE solicitation and is a subcontractor on the CMAR team, the State will award to the next highest-ranked proposer on the ICE solicitation.
10. Q. The RFP does not state a certain “standard form” to use for the proposal submittal. Should the Prime Consultant use the CPRA 24-102 and have each Subconsultant complete their own to incorporate?
A. Though this form is not contained in this RFP, the Proposer may utilize CPRA Form 24-102 as part of their proposal submittal.
11. Q. Should the Prime consultant incorporate the SubConsultant information into a single team proposal submittal in consultant’s chosen format?
A. Section 1.11 states Proposers are encouraged to submit proposals in a concise, orderly fashion that includes complete, appropriate comment, documentation, and submittals to address the RFP requirements.
12. Q. Is it possible to substitute professional certifications (such as Certified Cost Professional (CCP) from AACEI) for degrees in any of the estimator categories? Would the lack of a degree by a proposed Estimator result in points deducted in the evaluation/or would this be considered a disqualifying criteria?
A. After further review of the mandatory qualifications, it is in CPRA’s best interest to move all qualifications to Section 1.8.2, Desirable Qualifications; therefore, it is possible to substitute professional certifications for degrees in any of the estimator categories.
13. Q. Are there any page restrictions or limitations, other than 3 pages per resumes? Any page size restrictions?
A. No. Section 1.11 states Proposers are encouraged to submit proposals in a concise, orderly fashion that includes complete, appropriate comment, documentation, and submittals to address the RFP requirements.
14. Q. Can one staff member fulfill multiple roles? I.e. can an individual staff member be proposed to fill both Mechanical & Electrical Estimator positions?
A. Yes.
5
II. RFP REVISIONS
Section 1.8 Qualifications for Proposer. Delete Section 1.8 in its entirety and replace with the following:
1.8 Staff Requirements and Qualifications for Proposer
1.8.1 Staff Requirements
The Proposer shall provide the following staff positions: Principal Project Manager Lead Estimator Structural Estimator Civil Estimator Mechanical Estimator Electrical Estimator Purchaser Project Assistant
One hourly rate for each staff position shall be provided (see Attachment II, Required Rate Schedule in the RFP).
1.8.2 Desirable Qualifications
The Proposer’s staff should meet the following qualifications:
A. Project Manager: The Project Manager should have at least 10 years of experience managing Heavy Civil projects. The Project Manager should have a degree in Construction Management, Civil Engineering or in a related field. The Project Manager should have experience in Field Operations Management and Estimating from a Contractor’s Perspective. It is preferred that the Project Manager have experience with alternative delivery (Design-Build, CMAR) project and have experience in management of relevant project such as large hydraulic projects. The Project Manager should be a staff member of the prime contractor.
B. Lead Estimator: The Lead Estimator should have at least 20 years of hard bid
general estimating experience, of which 10 years of experience should have been as the lead estimator. The Lead Estimator should have a degree in Construction Management, Civil Engineering or in a related field. The Lead Estimator should be proficient in HCSS Heavy Bid Estimating Software, Agtek Software or similar. It is preferred that the Lead Estimator have experience with alternative delivery (Design-Build, CMAR) project and have experience as the lead estimator of relevant project such as large hydraulic projects. The Lead Estimator should be a staff member of the prime contractor.
6
C. Structural Estimator: The Structural Estimator should have at least 15 years of hard bid in heavy civil structural estimating experience. The Structural Estimator should have a degree in Construction Management, Civil Engineering, Structural Engineering or in a related field. The Structural Estimator should have extensive knowledge of construction means and methods, costs and engineering principles. The Structural Estimator may be a staff member of either the prime or a subcontractor.
D. Civil Estimator: The Civil Estimator should have at least 15 years of hard bid
in heavy civil structural estimating experience. The Civil Estimator should have a degree in Construction Management, Civil Engineering, or Structural Engineering or in a related field. The Civil Estimator should have extensive knowledge of construction means and methods, costs and engineering principles. The Civil Estimator should be proficient in HCSS Heavy Bid Estimating Software, Agtek Software or similar. The Civil Estimator may be a staff member of either the prime or a subcontractor.
E. Project Assistant: The Project Assistant should have experience in the preparation of a wide range of written material (technical reports, presentations, etc.) for dissemination to technical and non-technical audiences.
F. Principal – Duties include, but are not limited to, responsibility for overall
quality management of effort performed under this contract; resolve potential contractual communicated by CPRA.
G. Mechanical Estimator: The Mechanical Estimator should have at least 10 years
of hard bid mechanical estimating experience. The Mechanical Estimator should have a degree in Mechanical Engineering. The Mechanical Estimator may be a staff member of either the prime or a subcontractor.
H. Electrical Estimator: The Electrical Estimator should have at least 10 years of
hard bid electrical estimating experience. The Electrical Estimator should have a degree in Electrical Engineering. The Electrical Estimator may be a staff member of either the prime or a subcontractor.
I. Purchaser: The Purchaser should have at least 5 years of experience purchasing,
preferably public-sector procurement, or related work. The Purchaser should have a degree in Accounting, Finance, or in a related field. The Purchaser should have knowledge of large scale purchasing methods as well as federal, state and local purchasing laws and should be proficient in word processing, excel, database and presentation software. The Purchaser may be a staff member of either the prime or a subcontractor.
7
Section 1.9.1, Section D, Company Background and Experience.
Delete the fourth bullet in its entirety and replace with the following: Evidence of a thorough working knowledge of and the technical expertise necessary to use
commercial off-the shelf (OTS) software, to include Sage Timberline®, MC2®, HCSS, and US Cost Success®.
Section 1.29 Contract Award and Execution
The following language is being added: CPRA encourages all interested firms to submit a proposal on the ICE solicitation whether or not they have submitted as a subcontractor on a team for the CMAR solicitation. The scope of services requires the selected team to perform independent reviews on items such as costs estimates and construction scheduling submitted by the CMAR Team, which is being selected under a separate solicitation. Therefore, the selected prime from the ICE solicitation cannot be a subcontractor on the selected CMAR team. Should a proposer be selected for the ICE solicitation and is a subcontractor on the CMAR team, the State will award to the next highest-ranked proposer on the ICE solicitation. Attachments: Pre-Proposal Conference Presentation
Pre-Proposal Conference Sign-In Sheet
Rud
y Si
mon
eaux
| A
pril
12, 2
018
MID
-BA
RAT
AR
IASE
DIM
ENT
DIV
ERSI
ON
ICE
PRE-
SUBM
ITTA
L M
EETI
NG
•M
id-B
arat
aria
Sedi
men
t Div
ersi
on P
roje
ct
•O
verv
iew
of C
MAR
Proj
ect D
eliv
ery
Met
hod
•IC
E Sc
ope
of S
ervi
ces
•IC
E R
FP
•Q
uest
ions
2
OVE
RVIE
W
CPR
A | B
A-01
53 IC
E PR
E-SU
BMIT
TAL
MEE
TIN
G
•R
iver
Inle
t and
Div
ersi
on C
ontro
l Stru
ctur
e•
Con
veya
nce
Cha
nnel
•G
ated
“Bac
k” S
truct
ure
(thro
ugh
exis
ting
NO
V le
vee)
•O
utfa
ll C
hann
el•
Dra
inag
e Im
prov
emen
ts•
LA-2
3 H
ighw
ay R
ealig
nmen
t/Brid
ge•
NO
GC
Rai
lroad
Brid
ge•
Util
ity R
eloc
atio
ns•
Dre
dge
Mat
eria
l Pla
cem
ent
4
MID
-BA
RAT
AR
IA S
EDIM
ENT
DIV
ERSI
ON
PRO
JEC
T FE
ATU
RES
CPR
A | B
A-01
53 IC
E PR
E-SU
BMIT
TAL
MEE
TIN
G
MID
-BA
RAT
AR
IA S
EDIM
ENT
DIV
ERSI
ON
PRO
JEC
T LO
CAT
ION
5C
PRA
| BA-
0153
ICE
PRE-
SUBM
ITTA
L M
EETI
NG
•R
SIQ
: Ap
ril 2
017
–Ju
ly 2
017
•AE
CO
M s
elec
ted
in J
uly
2017
•AE
CO
M c
ontra
cted
in O
ctob
er 2
017
•Ba
sis
of D
esig
n (1
5%) m
ilest
one
targ
eted
for 3
rdQ
TR o
f 20
18
6
ENG
INEE
RIN
G A
ND
DES
IGN
CPR
A | B
A-01
53 IC
E PR
E-SU
BMIT
TAL
MEE
TIN
G
•Pr
ojec
t Man
agem
ent P
lan
•Te
chni
cal R
epor
t Pla
nnin
g (m
odel
ling,
dat
a ga
ps, d
ata
colle
ctio
n, m
onito
ring,
des
ign
crite
ria)
•En
gine
erin
g Al
tern
ativ
es:
-In
take
(stru
ctur
e ty
pe, s
ill el
evat
ion,
con
stru
ctio
n m
etho
d)
-C
onve
yanc
e C
hann
el (g
eom
etry
, lin
ing,
tran
sitio
n)
-O
utfa
ll (n
eces
sity
of “
back
” stru
ctur
e)
-Au
xilia
ry F
eatu
res
(hig
hway
, brid
ge, p
ump
stat
ion,
sip
hon)
•Ba
sis
of D
esig
n (1
5%) m
ilest
one
targ
eted
for 3
rd Q
TR o
f 20
187
ENG
INEE
RIN
G A
ND
DES
IGN
Cur
rent
Act
iviti
es:
CPR
A | B
A-01
53 IC
E PR
E-SU
BMIT
TAL
MEE
TIN
G
•R
SIQ
: N
ovem
ber 2
017
–M
arch
201
8
•Fo
ur S
tate
men
ts o
f Qua
lific
atio
ns (S
OQ
s) re
ceiv
ed a
nd
unde
r eva
luat
ion.
•Se
lect
ion
antic
ipat
ed in
Jun
e 20
18.
8
CM
AR
CO
NTR
AC
TOR
CPR
A | B
A-01
53 IC
E PR
E-SU
BMIT
TAL
MEE
TIN
G
9
PRO
JEC
T SC
HED
ULE
Mile
ston
eM
onth
/Yea
rIC
E C
ontra
ctor
NTP
July
201
8
CM
ARC
ontra
ctor
NTP
Augu
st 2
018
15%
(BO
D) D
esig
n D
eliv
erab
leSe
ptem
ber 2
018
30%
Des
ign
Del
iver
able
Mar
ch 2
019
60%
Des
ign
Del
iver
able
Janu
ary
2020
90%
Des
ign
Del
iver
able
Augu
st 2
020
100%
Des
ign
Del
iver
able
Nov
embe
r 202
0
Con
stru
ctio
n St
art
July
202
1
Con
stru
ctio
n En
dFe
brua
ry 2
026
CPR
A | B
A-01
53 IC
E PR
E-SU
BMIT
TAL
MEE
TIN
G
•Pe
rmit
subm
itted
to U
SAC
E in
Jun
e 20
16•
EIS
bega
n in
ear
ly 2
017
•Sc
opin
g M
eetin
gs (J
uly
20, 2
5, 2
7)-
Atte
ndan
ce ra
nged
from
70-
130
peop
le
•EI
S Sc
opin
g Pe
riod
Clo
sed
Sept
embe
r 5, 2
017
-O
ver 8
00 C
omm
ents
-O
ver 5
00 In
divi
dual
(For
m) L
ette
rs
-O
ver 1
00 C
omm
ents
from
out
side
of L
ouis
iana
-O
ver 4
0 “a
ffilia
tions
” with
in c
omm
ents
10
EIS/
PER
MIT
TIN
G
CPR
A | B
A-01
53 IC
E PR
E-SU
BMIT
TAL
MEE
TIN
G
•N
RD
Bar
atar
iaBa
sin
Stra
tegi
c R
esto
ratio
n Pl
an P
hase
I-
Und
erw
ay
•EI
S Al
tern
ativ
e An
alys
es C
hapt
er-
Und
erw
ay
•EI
S Ex
istin
g an
d H
isto
ric C
ondi
tions
Cha
pter
(por
tion)
-U
nder
way
11
EIS/
PER
MIT
TIN
G
CPR
A | B
A-01
53 IC
E PR
E-SU
BMIT
TAL
MEE
TIN
G
OVE
RVIE
W O
F C
MA
RPR
OJE
CT
DEL
IVER
Y M
ETH
OD
14C
PRA
| BA-
0153
ICE
PRE-
SUBM
ITTA
L M
EETI
NG
AD
VAN
TAG
ES O
F C
MA
R
•Le
gisl
atio
n ha
s be
en e
stab
lishe
d fo
r pol
icie
s/pr
oced
ures
an
d pr
otec
tion
agai
nst l
egal
cha
lleng
es (R
S 38
:222
5.2.
4)•
Prov
ides
con
tract
or‐le
d es
timat
es e
arlie
r and
allo
ws
scop
e re
visi
on d
urin
g de
sign
to m
eet p
roje
ct b
udge
t•
Can
redu
ce o
vera
ll pr
ojec
t ris
ks a
nd c
ontin
genc
y; a
lso
may
redu
ce d
esig
n m
isun
ders
tand
ings
and
cha
nge
orde
rs•
Mor
e su
itabl
e fo
r the
USA
CE/
NEP
A pe
rmitt
ing
and
regu
lato
ry p
roce
ss th
an a
ny fo
rm o
f Des
ign-
Build
•W
idel
y ac
cept
ed b
y bo
th e
ngin
eerin
g an
d co
nstru
ctio
n in
dust
ry
17C
PRA
| BA-
0153
ICE
PRE-
SUBM
ITTA
L M
EETI
NG
18
30%
Des
ign
Com
plet
ion
BO
D (1
5%)
Com
plet
ion
Typi
cal S
ched
ule
60%
Des
ign
Com
plet
ion
90%
Des
ign
Com
plet
ion
GM
P
CMAR
CM
AR
INTE
GR
ATIO
NR
S 38
:222
5.2.
4 ICE
CPR
A | B
A-01
53 IC
E PR
E-SU
BMIT
TAL
MEE
TIN
G
19
30%
Des
ign
Com
plet
ion
BO
D (1
5%)
Com
plet
ion
MBS
D S
ched
ule
60%
Des
ign
Com
plet
ion
90%
Des
ign
Com
plet
ion
GM
P
CMAR
CM
AR
INTE
GR
ATIO
NM
ID-B
AR
ATA
RIA
TEA
M
ICE
CPR
A | B
A-01
53 IC
E PR
E-SU
BMIT
TAL
MEE
TIN
G
21
SCO
PE O
F SE
RVIC
ES
Part
III: I
ndep
ende
nt C
ost E
stim
ator
Sco
pe o
f Ser
vice
s-
Sect
ion
3.1
Gen
eral
Adm
inis
tratio
n an
d C
oord
inat
ion
-Se
ctio
n 3.
2 C
ost E
stim
ates
-Se
ctio
n 3.
3 C
onst
ruct
abilit
y R
evie
w, S
ched
ule
Rev
iew,
and
Va
lue
Engi
neer
ing
CPR
A | B
A-01
53 IC
E PR
E-SU
BMIT
TAL
MEE
TIN
G
22
SCO
PE O
F SE
RVIC
ES
CPR
A | P
RE-
EVAL
UAT
ION
MEE
TIN
G
Basi
s of
Des
ign
(15%
) Mile
ston
e•
Rev
iew
Des
ign
Team
’s B
OD
est
imat
e an
d pr
ovid
e fe
edba
ck o
n th
e ad
equa
cy o
f the
cur
rent
pro
ject
bud
get.
•C
olla
bora
te w
ith D
esig
n Te
am, C
MAR
Con
tract
or, a
nd
CPR
A to
:-
Esta
blis
h ba
selin
e pr
oduc
tion
rate
ass
umpt
ions
and
st
anda
rds
for f
orm
ulat
ion
of fu
ture
cos
t est
imat
es a
nd
sche
dule
est
imat
es;
-D
evel
op a
nd a
lign
the
wor
k br
eakd
own
stru
ctur
e (W
BS)
whi
ch w
ill be
car
ried
forw
ard
for f
utur
e co
st e
stim
ates
; and
-D
evel
op th
e fo
rmat
for t
he p
rogr
essi
ve e
stim
ates
.
CPR
A | B
A-01
53 IC
E PR
E-SU
BMIT
TAL
MEE
TIN
G
23
SCO
PE O
F SE
RVIC
ES
CPR
A | P
RE-
EVAL
UAT
ION
MEE
TIN
G
30%
, 60%
and
90%
Des
ign
Mile
ston
es•
Inde
pend
ently
prep
are
a de
taile
d co
st e
stim
ate
and
a Ba
sis
of E
stim
ate
Rep
ort.
•Pr
oduc
e an
Est
imat
e Va
rianc
e R
epor
t com
parin
g th
e co
st
estim
ates
pre
pare
d by
the
Des
ign
Team
and
CM
ARC
ontra
ctor
with
the
one
prep
ared
by
the
ICE
Con
tract
or.
•Be
pre
pare
d to
ass
ist C
PRA
in e
stim
ate
reco
ncilia
tion.
CPR
A | B
A-01
53 IC
E PR
E-SU
BMIT
TAL
MEE
TIN
G
24
SCO
PE O
F SE
RVIC
ES
CPR
A | P
RE-
EVAL
UAT
ION
MEE
TIN
G
Opt
iona
l Tas
ks•
GM
PR
evie
w. T
he C
MAR
Con
tract
or w
ill su
bmit
a G
uara
ntee
d M
axim
um P
rice
(GM
P) to
CPR
A af
ter t
he
90%
mile
ston
e. T
he IC
E C
ontra
ctor
may
be
task
ed b
y C
PRA
to p
rovi
de in
depe
nden
t est
imat
ing
supp
ort d
urin
g th
e pr
oces
s of
GM
Pre
view
and
neg
otia
tion.
•C
ost E
stim
atin
g Su
ppor
t Dur
ing
Con
stru
ctio
n. T
he IC
E C
ontra
ctor
may
be
task
ed b
y C
PRA
to p
rovi
de
inde
pend
ent e
stim
atin
g to
sup
port
a co
st re
ason
able
ness
an
alys
is o
f any
wor
k pe
rform
ed o
r pro
pose
d an
d/or
the
nego
tiatio
n of
any
pro
pose
d ad
just
men
t to
the
GM
P.
CPR
A | B
A-01
53 IC
E PR
E-SU
BMIT
TAL
MEE
TIN
G
25
SCO
PE O
F SE
RVIC
ES
CPR
A | P
RE-
EVAL
UAT
ION
MEE
TIN
G
Con
stru
ctab
ility
Rev
iew,
Sch
edul
e R
evie
w a
nd V
alue
En
gine
erin
g•
The
ICE
Con
tract
or w
ill no
t be
task
ed w
ith a
full,
in
depe
nden
t con
stru
ctab
ility,
sch
edul
e or
val
ue
engi
neer
ing
revi
ew.
•H
owev
er, t
he IC
E C
ontra
ctor
may
be
aske
d to
pro
vide
in
put o
n ris
ks a
ssoc
iate
d w
ith th
e co
nstru
ctio
n an
d pr
opos
al o
f any
con
stru
ctab
ility
or v
alue
eng
inee
ring
or
sche
dulin
g co
mm
ents
that
are
evi
dent
dur
ing
the
cour
se
of th
e es
timat
ing
wor
k.
CPR
A | B
A-01
53 IC
E PR
E-SU
BMIT
TAL
MEE
TIN
G
26
SCO
PE O
F SE
RVIC
ES
CPR
A | P
RE-
EVAL
UAT
ION
MEE
TIN
G
Sect
ion
3.4:
Del
iver
able
s•
Cos
t Est
imat
e us
ing
com
mer
cial
off-
the-
shel
f (O
TS)
estim
atin
g so
ftwar
e.
•Ba
sis
of E
stim
ate
Rep
ort.
•Es
timat
e Va
rianc
e R
epor
t-
Doc
umen
t any
sig
nific
ant d
iffer
ence
s be
twee
n th
e co
st
estim
ates
pro
duce
d by
the
Des
ign
Team
, CM
ARC
ontra
ctor
, an
d IC
E C
ontra
ctor
;
-N
arra
tive
and
char
t sho
win
g th
e m
ajor
cos
t cha
nges
and
ex
plai
ning
the
reas
ons
for t
he c
hang
es.
-Pr
epar
ed p
er A
STM
E18
04, “
Stan
dard
Pra
ctic
e fo
r Per
form
ing
and
Rep
ortin
g C
ost A
naly
sis
durin
g th
e D
esig
n Ph
ase
of a
Pr
ojec
t”C
PRA
| BA-
0153
ICE
PRE-
SUBM
ITTA
L M
EETI
NG
28
•R
FP p
acka
ge w
as is
sued
on
April
4, 2
018
and
incl
udes
the
follo
win
g:-
RFP
Sol
icita
tion
Doc
umen
t•
Part
I: A
dmin
istra
tive
and
Gen
eral
Info
rmat
ion
•Pa
rt II:
Int
rodu
ctio
n an
d Ba
ckgr
ound
•Pa
rt III
: Sc
ope
of S
ervi
ces
•Pa
rt IV
: Ev
alua
tion
•At
tach
men
ts:
-C
ertif
icat
ion
Stat
emen
t
-R
equi
red
Rat
e Sc
hedu
le
-Sa
mpl
e C
ontra
ct
-El
ectro
nic
Vend
or P
aym
ent S
olut
ion
REQ
UES
T FO
R P
RO
POSA
LS
CPR
A | B
A-01
53 IC
E PR
E-SU
BMIT
TAL
MEE
TIN
G
29
•Pa
rt I,
Sect
ion
1.6:
Sch
edul
e of
Eve
nts
Adv
ertis
emen
tPer
iod
Apr
il 4,
201
8–M
ay 8
, 201
8Pr
e-Su
bmitt
alM
eetin
gAp
ril 1
2, 2
018
Dea
dlin
efo
rQue
stio
nsAp
ril 2
0, 2
018
CPR
AR
espo
nses
toQ
uest
ions
April
25,
201
8Pr
opos
als
Due
May
8, 2
018
Sele
ctio
nC
omm
ittee
Rev
iew
May
8, 2
018
–Ju
ne 4
, 201
8An
noun
cem
ento
fSel
ecte
dIC
EC
ontra
ctor
June
5,2
018
Con
tract
ing/
Neg
otia
tion/
Awar
dPe
riod
June
5, 2
018
–Ju
ly 3
, 201
8Ta
rget
Not
ice
toPr
ocee
dJu
ly 3
, 201
8
REQ
UES
T FO
R P
RO
POSA
LS
CPR
A | B
A-01
53 IC
E PR
E-SU
BMIT
TAL
MEE
TIN
G
30
•Pa
rt I,
Sect
ion
1.8:
Qua
lific
atio
ns:
-Pr
ojec
t Man
ager
-Le
ad E
stim
ator
-St
ruct
ural
Est
imat
or
-C
ivil
Estim
ator
-M
echa
nica
l Est
imat
or
-El
ectri
cal E
stim
ator
-Pu
rcha
ser
REQ
UES
T FO
R P
RO
POSA
LS
CPR
A | B
A-01
53 IC
E PR
E-SU
BMIT
TAL
MEE
TIN
G
31
•Pa
rt I,
Sect
ion
1.9:
Pro
posa
l Res
pons
e Fo
rmat
:-
Volu
me
I -Te
chni
cal P
ropo
sal a
nd C
ost R
ates
•C
over
Let
ter,
Tabl
e of
Con
tent
s, a
nd E
xecu
tive
Sum
mar
y
•C
ompa
ny B
ackg
roun
d an
d Ex
perie
nce
•Ap
proa
ch a
nd M
etho
dolo
gy
•Pr
opos
ed S
taff
Qua
lific
atio
ns
•Pa
rtici
patio
n of
Vet
eran
Initi
ativ
e an
d H
udso
n In
itiat
ive
smal
l en
trepr
eneu
rshi
ps
•C
ost P
ropo
sal
•C
ertif
icat
ion
Stat
emen
t, Su
bcon
tract
ors,
and
Insu
ranc
e
-Vo
lum
e II
–Fi
nanc
ial I
nfor
mat
ion
REQ
UES
T FO
R P
RO
POSA
LS
CPR
A | B
A-01
53 IC
E PR
E-SU
BMIT
TAL
MEE
TIN
G
32
•Pa
rt IV
: Ev
alua
tion:
-R
elev
ant C
ompa
ny B
ackg
roun
d an
d Ex
perie
nce
-20
poin
ts
-St
aff Q
ualif
icat
ions
of I
ndiv
idua
ls A
ssig
ned
the
Proj
ect-
25 p
oint
s
-Ap
proa
ch a
nd M
etho
dolo
gy/S
cope
of S
ervi
ces
-20
poin
ts
-H
udso
n/Ve
tera
n Sm
all E
ntre
pren
eurs
hip
Prog
ram
-10
poi
nts
-C
ost -
25 p
oint
s
REQ
UES
T FO
R P
RO
POSA
LS
CPR
A | B
A-01
53 IC
E PR
E-SU
BMIT
TAL
MEE
TIN
G
Rud
y Si
mon
eaux
| A
pril
12, 2
018
ANY
QU
ESTI
ON
S?
THA
NK
YO
U
33C
PRA
| BA-
0153
ICE
PRE-
SUBM
ITTA
L M
EETI
NG