richard beaumont bam

31
Building Information Modelling (BIM) Leeds Arena – Case Study

Upload: darrylbcamp

Post on 06-May-2015

585 views

Category:

Business


1 download

DESCRIPTION

Richard Beaumont, BAM - Leeds Arena Case Study

TRANSCRIPT

Page 1: Richard beaumont bam

Building Information Modelling (BIM)

Leeds Arena – Case Study

Page 2: Richard beaumont bam

Leeds Arena – BIM Time-line

April 2010

Appointed Preferred Bidder

Design Currently 2D

No BIM Requirement

April 2010 to March 2011

Tender Second Stage

Design starting to be developed in 3D

2D Design still being under taken

No BIM Requirement

March 2011

Contract signed

No BIM Requirement

April 2011

BAM Decision to trial BIM on Leeds Arena

Page 3: Richard beaumont bam

- Fabrication Model

Arup M.E.P

Revit 3D

Arup –

Structures –

Revit 3D

Arup 3D Civil

Populous – Rhino

3D & Microstation

2D

Steel – FEL –

Telka 3D M&E – Rotary –

CAD Duct 3D

Precast –

Creagh –

Tekla 3D

Glazing

Contractor 2D

Other design

subcontractors

3D & 2D

• Lifts

• Escalators

• Metalwork

• etc

Envelope –

Lakesmere –

3D DWG

Design Data Model

BAM model co-ordination

Page 4: Richard beaumont bam

Design Data Model – By Design Consultants

Page 5: Richard beaumont bam

Fabrication Model – Co-ordination of subcontractor & Design

Consultants

Page 6: Richard beaumont bam

Leeds Arena Model

Page 7: Richard beaumont bam

Populous Secondary Steel Model FEL Steel Model

Combined Model Lakesmere Stub Model

Example of Supply Chain Design Coordination

Page 8: Richard beaumont bam

Clash in design data model Co-ordinated in Fabrication model

Page 9: Richard beaumont bam

Clash in Fabrication model Co-ordinated in Fabrication model

Page 10: Richard beaumont bam

Repositioning of ductwork around

steelwork

Page 11: Richard beaumont bam

Temporary Propping to Wing Wall Edge Protection to Metal Deck Areas

Handrail locations for temporary and Permanent Schemes High Level Duct, Gantry & Steel Coordination

Zero Harm by design

Page 12: Richard beaumont bam

Building Information Modelling (BIM)

Planning

Page 13: Richard beaumont bam

Initial Concrete roof and external Cladding Sequencing

Precast Wall Slabs

Roof decking erection

Roof Truss erection

Page 14: Richard beaumont bam

4D Planning

Page 15: Richard beaumont bam

Logistics;- Precast and Structural Steel

Precast

Steel

Steel

Precast

Steel

Page 16: Richard beaumont bam

4D Planning

Page 17: Richard beaumont bam

Progress monitoring

Page 18: Richard beaumont bam

Planned (Target Programme)

Page 19: Richard beaumont bam

Actual

Page 20: Richard beaumont bam

Planned (Target Programme) v Actual

Page 21: Richard beaumont bam

Actual

Planned (Target programme) v Actual

Planned (Target Programme)

Page 22: Richard beaumont bam

Work package coordination

Page 23: Richard beaumont bam

From the 3D Model it is clear that we need to remove steel to allow the unit to be erected in place

Steel highlighted in Blue is to be left out during Steel erection

ESCALATOR LOCATION

Installation Methodology

Page 24: Richard beaumont bam

Escalator lifted into position from ground floor by means of A frames supported on existing structural steel above

Installation Methodology

Page 25: Richard beaumont bam
Page 26: Richard beaumont bam

Building Information Modelling (BIM)

Quantities

Page 27: Richard beaumont bam

Revit Concrete quantity checks

Steel quantity Checks with Solibri

Page 28: Richard beaumont bam

Building Information Modelling (BIM)

What next

Page 29: Richard beaumont bam

Efficient Cost Planning & Procurement

• Quick measures from models

• Cost plans

• Direct take offs

Page 30: Richard beaumont bam

Handover & Aftercare

• Snagging & Handover

• O&M Manuals

• Field BIM

• Defects management

• Lifecycle

Page 31: Richard beaumont bam