Rossport Solidarity Camp Observations to ABP Oral Hearing, Bellmullet, September 2010 Part 1 Contents Proper Procedure & Due Process Strategic National Importance of Corrib Gas Extensification Subsea Hardware Qualitative Risk Assessment Traffic Vibrations Part 1

Upload: vivian-pope

Post on 03-Jan-2016

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Rossport Solidarity Camp Observations to ABP Oral Hearing, Bellmullet, September 2010 Part 1 Contents Proper Procedure & Due Process Strategic National

Rossport Solidarity Camp Observationsto

ABP Oral Hearing, Bellmullet, September 2010

Part 1

Contents

Proper Procedure & Due ProcessStrategic National Importance of Corrib GasExtensificationSubsea HardwareQualitative Risk AssessmentTrafficVibrations Part 1

Page 2: Rossport Solidarity Camp Observations to ABP Oral Hearing, Bellmullet, September 2010 Part 1 Contents Proper Procedure & Due Process Strategic National

Source: An Bord Pleanála website

Page 3: Rossport Solidarity Camp Observations to ABP Oral Hearing, Bellmullet, September 2010 Part 1 Contents Proper Procedure & Due Process Strategic National

During the oral hearing we get more late information...

Improper procedure, unjust to the public

Page 4: Rossport Solidarity Camp Observations to ABP Oral Hearing, Bellmullet, September 2010 Part 1 Contents Proper Procedure & Due Process Strategic National

An Board Pleanála Code of Conduct

Page 5: Rossport Solidarity Camp Observations to ABP Oral Hearing, Bellmullet, September 2010 Part 1 Contents Proper Procedure & Due Process Strategic National

An Board Pleanála Code of Conduct

“the Corrib gas pipeline meet[s] all relevant safety standards and codes” – Bob Hanna of TAG to ABP, 20th January 2010

Page 6: Rossport Solidarity Camp Observations to ABP Oral Hearing, Bellmullet, September 2010 Part 1 Contents Proper Procedure & Due Process Strategic National

ABP letter to applicant 2nd November 2009

• “Due regard” for government policy• Considers the project as a whole

Page 7: Rossport Solidarity Camp Observations to ABP Oral Hearing, Bellmullet, September 2010 Part 1 Contents Proper Procedure & Due Process Strategic National

Strategic National Importance of Corrib Gas- Conventional Economics -

• €0.00 guaranteed state take from Corrib• SEPIL profits add to Irish GDP... But benefit Shell only• No discount buy back or any contract with the state

for supply → zero security of supply

Page 8: Rossport Solidarity Camp Observations to ABP Oral Hearing, Bellmullet, September 2010 Part 1 Contents Proper Procedure & Due Process Strategic National

Strategic National Importance of Corrib Gas- Using Accounting Principles -

• Fossil fuel reserves & mined material is Natural Capital

• Truly sustainable development must increase our renewable income

Page 9: Rossport Solidarity Camp Observations to ABP Oral Hearing, Bellmullet, September 2010 Part 1 Contents Proper Procedure & Due Process Strategic National

Extensification of Life of Project- Corporate plans -

“Commenced drilling the 18/20-G exploration well offshore Ireland, targeting a structure north of the Corrib Field. Should hydrocarbons be discovered and prove commercial, the structure would have the potential to significantly extend the life of the Corrib platform. Vermilion holds an 18.5% interest in this well.”

- Extract from Vermillion press release 9th Aug 2010

Page 10: Rossport Solidarity Camp Observations to ABP Oral Hearing, Bellmullet, September 2010 Part 1 Contents Proper Procedure & Due Process Strategic National

Subsea Installations2008 December“Sedco 711 departs the Corrib field having completed work on the Corrib wells. Four wells at the Corrib field are now completed and are ready for production at a later date. Work on the wells was carried out during the 2006, 2007 and 2008 drilling seasons.”

Sedco 711 drilling rig

http://www.shell.ie/home/content/irl/aboutshell/shell_businesses/e_and_p/corrib/about/history/

•Corrib wells heads & manifold fitted by Transocean•Subsea work was completed to original plan of development (at best)

•Not intended as pressure regulation to an MAOP of 150 bar

Page 11: Rossport Solidarity Camp Observations to ABP Oral Hearing, Bellmullet, September 2010 Part 1 Contents Proper Procedure & Due Process Strategic National

Qualitative Risk Assessment

“There are different types of qualitative risk assessment that can be carried out... the chosen method depends on the purpose and objectives of the assessment and what you are trying to achieve”

– Point 5 of Sheryl Hurst’s evidence

Page 12: Rossport Solidarity Camp Observations to ABP Oral Hearing, Bellmullet, September 2010 Part 1 Contents Proper Procedure & Due Process Strategic National

Qualitative Risk Assessment

“There are different types of qualitative risk assessment that can be carried out... the chosen method depends on the purpose and objectives of the assessment and what you are trying to achieve”

– Point 5 of Sheryl Hurst’s evidence

“One objective of the Corrib bowtie workshops was to demonstrate that the risks associated with the pipeline had been reduced to levels which were ALARP which means As Low As Reasonably Practicable”

- Point 39 of Sheryl Hurst’s evidence

Page 13: Rossport Solidarity Camp Observations to ABP Oral Hearing, Bellmullet, September 2010 Part 1 Contents Proper Procedure & Due Process Strategic National

Traffic

“HCV traffic to and from Glengad will be managed using a controlled convoy system, which was successfully used previously during the landfall construction”

- Michael Noonan, point 4.2.9 of his evidence

Page 14: Rossport Solidarity Camp Observations to ABP Oral Hearing, Bellmullet, September 2010 Part 1 Contents Proper Procedure & Due Process Strategic National

Traffic chaos on L1202

Road blockage on 18th May 2009 involving Shell HCV

Page 15: Rossport Solidarity Camp Observations to ABP Oral Hearing, Bellmullet, September 2010 Part 1 Contents Proper Procedure & Due Process Strategic National

Vibrations“These vibrations will travel through the ground as

various different waveforms dependant on the nature of the geology surrounding the TBM ”

“Groundborne vibration has the potential to be transmitted to residential and other buildings near to

the shore as feelable vibration and groundborne noise...”

– Rupert Thornley-Taylor in point 4.2 & 4.4 of his evidence

Page 16: Rossport Solidarity Camp Observations to ABP Oral Hearing, Bellmullet, September 2010 Part 1 Contents Proper Procedure & Due Process Strategic National

Vibrations“The model is deterministic... Consequently the

accuracy of the results is dependent on the correctness of the input parameters”

– Rupert Thornley-Taylor in point 4.13 of his evidence

Page 17: Rossport Solidarity Camp Observations to ABP Oral Hearing, Bellmullet, September 2010 Part 1 Contents Proper Procedure & Due Process Strategic National

Vibrations“The model is deterministic... Consequently the

accuracy of the results is dependent on the correctness of the input parameters”

– Rupert Thornley-Taylor in point 4.13 of his evidence

But the input parameters are based on the 2008 for the crossings at Glengad to Rossport & back to Aghoos...

Page 18: Rossport Solidarity Camp Observations to ABP Oral Hearing, Bellmullet, September 2010 Part 1 Contents Proper Procedure & Due Process Strategic National

Geophysical data is from 2009 route survey

Page 19: Rossport Solidarity Camp Observations to ABP Oral Hearing, Bellmullet, September 2010 Part 1 Contents Proper Procedure & Due Process Strategic National

Vibrations“The model is deterministic... Consequently the

accuracy of the results is dependent on the correctness of the input parameters”

– Rupert Thornley-Taylor in point 4.13 of his evidence

But the input parameters are based on the 2008 for the crossings at Glengad and Aghoos

So does the “garbage in, garbage out” principle apply?

Page 20: Rossport Solidarity Camp Observations to ABP Oral Hearing, Bellmullet, September 2010 Part 1 Contents Proper Procedure & Due Process Strategic National

Vibrations

“There would be no significant vibration effect even when the vibration from the TBM and temporary railway are considered in combination with vibration from construction vehicles on the highway”

– Rupert Thornley-Taylor in point 5.5 of his evidence

Page 21: Rossport Solidarity Camp Observations to ABP Oral Hearing, Bellmullet, September 2010 Part 1 Contents Proper Procedure & Due Process Strategic National

Vibrations

“There would be no significant vibration effect even when the vibration from the TBM and temporary railway are considered in combination with vibration from construction vehicles on the highway”

– Rupert Thornley-Taylor in point 5.5 of his evidence

But SEPIL 2009 haulage to Glengad on L1202 damaged walls and foundations along route

Page 22: Rossport Solidarity Camp Observations to ABP Oral Hearing, Bellmullet, September 2010 Part 1 Contents Proper Procedure & Due Process Strategic National

Rossport Solidarity Camp Observations

To

ABP Oral Hearing, Bellmullet, September 2010

End Part 1