runways uk – dr jock lowe. 1.is extra capacity needed? commission report – yes 2.where should...
TRANSCRIPT
1. Is extra capacity needed?Commission Report – Yes
2. Where should that capacity be?Commission Report – Emphatic Recommendation; Heathrow
Three Big Questions
2
• Great research• Wide consultation • Comprehensive report• Not truly iterative
But….
Commission Process
3
• National Issue – We have to solve itProbably by using less diesel vehicles• Local Issue – Mitigation using Road
Planning etc.
Emissions A Big Little Problem
5
• Reduction by alternating flightpaths not runways- otherwise, why not build 4 runways but use the capacity of 3• Limit overall capacity until noise
targets met
NoiseMust Get Better
6
• Northwest and Extended Runway Options have the same max capacity• Contradiction by valuing 40,000 slots
but then ruling out 4th Runway• Limit set by Government, could be
650,000 to 750,000• £3bn - £5bn lower costs
First But… Capacity & Cost
8
• Easier Air Space Management• Second Taxiway could be Standby
Runway• More land is available if necessary for
taxiways, stands and parking• Peripheral developments outside the
boundary
Third But… Resilience
10
• Extended Runway construction easily phased- Release capacity when targets met• No villages destroyed• No waste plant to relocate
Fourth But… Construction
11