salt lake city – las vegas high speed rail – alignment study student engineering associates
TRANSCRIPT
Salt Lake City – Las Vegas High Speed Rail – Alignment
StudyStudent Engineering Associates
Project Management• Project Management Approach• Major Milestones• Project Scope of Work• Cost Management Plan/Cost Baseline
Project Management Approach
• Staffing Management Plan• Communications Management Plan• Quality Management Plan
Staffing Management Plan• Principal Engineer – Dr. Steven Bartlett• Vice President – Byron Foster• Project Management Team – 4 Members• Alignment Team – 5 Members• Drainage Team – 4 Members• Environmental Team – 5 Members• Geotechnical Team – 4 Members• Structural Team – 4 Members• Utilities/Transportation Team – 3 Members
Communications Management Plan
• Meetings• Email• Informal Communication
Alejandro Medinilla
Project Manager
Dane Janak Project ManagerDanny Thompson Project Manager
Jeff Thomas Project ManagerDevin Weder Alignment Team Leader
Joe Bolton Drainage Team Leader
Joseph WellsEnvrionmental Team
LeaderKrystal Harman Geotechnical Team Leader
Eric Soto Structures Team Leader
Karlo VelezUtilities/Traffic Team
Leader
Quality Management Plan
Major MilestonesMilestone Description Date
Complete Scope of Work Document
All general project requirements are to be determined in order to assign work
2/3/2015
Complete Feasibility Study Report and Presentation
“Big Picture” items to be generally completed and submitted for presentation
3/13/2015
Complete Final Report and Presentation
A detailed look into specific “Big Picture” items to be entirely completed and submitted for presentation
4/30/2015
Scope of Work• Alignment• Environmental• Utilities & Transportation• Geotechnical• Structures• Drainage
Alignment Approach
Alignment Approach Western Union Pacific Railroad Corridor Eastern I-15 Corridor Track Layout
Cut & Fill Estimates Geometric Constraints
Estimate Surface Data Design of Horizontal Curves Design of Vertical Curves
Drainage Approach Storm Drainage
Hydrologic Analysis of Watersheds Identify Need and Location for Culverts
Irrigation Features Open Channel Flow Analysis for Existing
Channels Design of Drainage for Rail Line
Environmental Approach Sensitive Lands
Culturally Environmentally Endangered Species
Right-of-Way Identify Ownership
State Federal Private
Environmental Impact Studies
Utilities and Transportation Approach
Identify Potential Utility Interferences Utilities Fiber optics Current Easements
Identify Existing Railroad and Road Interferences Access Rights
Construction Considerations Relocation
Geotechnical Approach Identify Soil/Rock Types Develop Typical Cross Sections Identify Slope Stability Identify Need for Tunnels
Types of Soils Tunneling Methods
Preliminary Design Work for Structural Foundations
Preliminary Design for Ballast and Sub-Ballast Materials
Structural Approach Preliminary Design of Grade
Separated Track Bridges
Location Length
Type Tunnels
Type of Rock Methods
Preliminary Design of Typical Pedestrian Crossings
ScheduleID Task Name Start Finish
2 Feasibility Study Thu 1/29/15 Tue 3/10/15
3 Alignment Mon 1/19/15Tue 3/10/15
4 Rough Draft ofAlignment
Mon 1/19/15Fri 1/30/15
5 Alignment Internal Review
Mon 2/2/15 Fri 2/13/15
6 Adjustment ofAlignment
Mon 2/16/15Mon 2/23/15
7 Horizontal Alignment
Tue 2/24/15 Tue 3/10/15
8 Drainage Thu 1/29/15 Tue 3/10/15
9 Research on HSR drainage
Thu 1/29/15 Thu 2/5/15
10 Track Drainage Fri 2/6/15 Fri 2/20/15
11 ID Hydrological and OCF Characteristics
Mon 2/23/15Tue 3/10/15
12 Environmental Thu 1/29/15 Tue 3/10/15
13 Detailed Mapsand Boundaries
Thu 1/29/15 Thu 2/5/15
14 EnvironmentalImpact Statement
Fri 2/6/15 Tue 3/10/15
15 Geotech Mon 1/19/15Tue 3/10/15
16 Geo Maps (general)
Mon 1/19/15Fri 2/6/15
17 Track Drainage Mon 2/9/15 Fri 2/13/15
18 Geomaps (Detailed)
Mon 2/16/15Tue 3/10/15
19 Utilities Mon 1/19/15Tue 3/10/15
20 Existing Utilities Map
Mon 1/19/15Thu 1/29/15
21 Identification of XS
Mon 2/2/15 Fri 2/13/15
22 Specific Alignment Constraints
Mon 2/16/15Fri 2/20/15
23 Relocation Cost Estimate
Mon 2/23/15Tue 3/10/15
24 Structures Mon 2/2/15 Tue 3/10/15
25 Identification of XS
Mon 2/2/15 Fri 2/13/15
26 ID Bridge and Tunnel Type
Mon 2/16/15Tue 3/10/15
27 Project Management
Mon 1/19/15Tue 3/10/15
28 Principal Engineer
Mon 1/19/15Tue 3/10/15
29 Vice President Mon 1/19/15Tue 3/10/15
Alignment Team
Alignment Team
Alignment Team
Alignment Team
Drainage Team
Drainage Team
Drainage Team
Environmental Team
Environmental Team
Geotech Team
Geotech Team
Traffic/Utilities Team
Traffic/Utilities Team
Traffic/Utilities Team
Traffic/Utilities Team
Structures
Structures
Project Management
Principal Engineer
Vice President
S T M F T S W S T M F T S W S T M F TJan 18, '15 Feb 1, '15 Feb 15, '15 Mar 1, '15 Mar 15, '15 Mar 29, '15
Team Name Engineering Rate Student Rate
Principle Engineer Oversight $202.5/hr $81/hr
Vice President $162/hr $33/hr
Project Management $108/hr $22/hr
Alignment $81/hr $22/hr
Drainage $81/hr $22/hr
Environmental $81/hr $22/hr
Geotech $81/hr $22/hr
Structural $81/hr $22/hr
Transportation & Utilities $81/hr $22/hr
Total $397,926 $124,622
Cost Management Plan/Cost Baseline
Schedule towards Feasibility StudyTask Name Cost Work
Scope of Work Estimate $397,926.00 4,666 hrs
Alignment $77,922.00 962 hrs
East & West rough draft $7,290.00 90 hrs
Horizontal Alignment $9,720.00 120 hrs
Vertical Alignment $12,960.00 160 hrs
Finalized Alignments $9,720.00 120 hrs Drainage $40,824.00 504 hrs
Storm Drainage $6,804.00 84 hrs
Irrigation Features $6,804.00 84 hrs
Design of Drainage for Rail Line $13,608.00 168 hrs
Environmental $27,135.00 335 hrs
Right of way research $3,645.00 45 hrs
Sensitive Lands research $2,430.00 30 hrs Collection of Data $2,430.00 30 hrs
Collaboration $4,455.00 55 hrs
Geotech $57,267.00 707 hrs
Soil classification & Problematic characteristics $3,240.00 40 hrs
Research & Design of tunnels, retaining systems and foundations $4,455.00 55 hrs
Calcs & Drafts of cuts, stability analysis, and fill materials $2,025.00 25 hrs
Additional issues $4,050.00 50 hrs Project Management $60,480.00 560 hrs
Structural $67,068.00 828 hrs
Design Criteria $1,296.00 16 hrs
Structures count estimate $9,720.00 120 hrs
Revised count based on alignment changes $8,100.00 100 hrs
Final count and total cost estimate $3,240.00 40 hrs
Transportation & Utilities $58,482.00 722 hrs Research possible utility lines $2,025.00 25 hrs
Research possible railroad $2,025.00 25 hrs
Construction access $1,620.00 20 hrs
Preliminary cost estimate of utilities and crossings $2,835.00 35 hrs
Feasibility study submit $3,645.00 45 hrs
Present cost estimate of relocations for overall plan $2,430.00 30 hrs
Principle Advising $8,748.00 48 hrs